facilities modernization program funded by measure b project report
DESCRIPTION
Facilities Modernization Program Funded by Measure B Project Report. November 21, 2011. PROJECT PROGRESS REPORT Child Development Center. LAS POSITAS COLLEGE November 21, 2011. Project Team: Architect : Beverly Prior Architects Construction Manager : Parsons Brinckerhoff - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Facilities Modernization Program Funded by Measure B Project Report](https://reader035.vdocuments.mx/reader035/viewer/2022062323/568160bf550346895dcfe54c/html5/thumbnails/1.jpg)
Facilities Modernization ProgramFunded by Measure B
Project Report
November 21, 2011
![Page 2: Facilities Modernization Program Funded by Measure B Project Report](https://reader035.vdocuments.mx/reader035/viewer/2022062323/568160bf550346895dcfe54c/html5/thumbnails/2.jpg)
PROJECT PROGRESS REPORTChild Development Center
Project Team: Architect: Beverly Prior ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction Associates
Project Update:• Project is complete.• Project is in Warranty Period.
Occupancy Spring 2011
LAS POSITAS COLLEGENovember 21, 2011
![Page 3: Facilities Modernization Program Funded by Measure B Project Report](https://reader035.vdocuments.mx/reader035/viewer/2022062323/568160bf550346895dcfe54c/html5/thumbnails/3.jpg)
PROJECT PROGRESS REPORTPE Phase III (Outside Loop Road)
Project Team: Architect: WLC Architects / Carducci Landscape ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction
Project Update:• Project is complete.• We are in Warranty Period.• DSA Closeout is in progress.
Occupancy: 04/2011
LAS POSITAS COLLEGENovember 21, 2011
![Page 4: Facilities Modernization Program Funded by Measure B Project Report](https://reader035.vdocuments.mx/reader035/viewer/2022062323/568160bf550346895dcfe54c/html5/thumbnails/4.jpg)
PROJECT PROGRESS REPORTScience Building, Phase II
Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc
Project Update:• Interior/Exterior framing on first and second floors are being completed.• Exterior insulation is being installed. • Plumbing installation is continuing on first and second floors.• Electrical and Data installation is continuing at first and second floors.• Roofing on High Roof is complete, Low roof is 85% complete.• Storefront installation will start week of Nov 28, 2011.
Occupancy: 09/2012
LAS POSITAS COLLEGENovember 21, 2011
![Page 5: Facilities Modernization Program Funded by Measure B Project Report](https://reader035.vdocuments.mx/reader035/viewer/2022062323/568160bf550346895dcfe54c/html5/thumbnails/5.jpg)
PROJECT PROGRESS REPORTStudent Services & Central Administration
Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction
Project Update:• GFRC installation erection complete, plumbing and lining remain.• Mechanical, Electrical, Plumbing rough in continues.• Interior wall partitions underway, exterior framing 50% complete.
Occupancy: Spring 2013
LAS POSITAS COLLEGENovember 21, 2011
![Page 6: Facilities Modernization Program Funded by Measure B Project Report](https://reader035.vdocuments.mx/reader035/viewer/2022062323/568160bf550346895dcfe54c/html5/thumbnails/6.jpg)
PROJECT PROGRESS REPORTCampus Boulevard Phase I-III
Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: TBD
Project Update:• 100% Design review completed, final design schedule for December 2011.
Design Re-Start: 04/2011DSA Permit Approval: 02/2012Construction Start: 03/2012Occupancy: TBD
LAS POSITAS COLLEGENovember 21, 2011
![Page 7: Facilities Modernization Program Funded by Measure B Project Report](https://reader035.vdocuments.mx/reader035/viewer/2022062323/568160bf550346895dcfe54c/html5/thumbnails/7.jpg)
PROJECT PROGRESS REPORTPhotovoltaic System Phase II
Project Team: Design Build Contractor: Cupertino Electric Inc.Construction Manager: Parsons Brinckerhoff
Project Update:• Fencing Completed.• Racking System completed and ready for Array installation.• PV Arrays installation will start week of November 28, 2011.• Inverters and Transformer install Mid December 2011.
Occupancy: January 2012
LAS POSITAS COLLEGENovember 21, 2011