FREMONT UNIFIED S C H O O L D I S T R I C T
Lila Bringhurst Elementary School
Construction Update
as prepared by fB2 Solutions
Board of Education Meeting
October 24, 2018
2
Home of the Blazers
3
Project Statistics
• Number of Buildings - 4
• Total Square Footage – 99,000 sq ft
• Number of Classrooms - 45
• Enrollment Capacity – 1100
• Project Budget - $54,525,492
• Projected Completion
Date – March 7, 2019
• Status of Park –Construction underway
as of October 8, 2018.
Park expected to be
completed in April 2019
4
Project Information
• First new school for the FUSD in 25 years
• Innovative architectural design that compliments surrounding subdivision activity
• Joint Use Park serves students each weekday, community nights, weekends and holidays
• Construction started 9/11/17
• 18 rain days allowed to date
• All building skeletons erected and finishes underway
• Project well under budget – Less than .05% in change orders to date
• Hybrid project under the State Facilities Program – App filed with the State Allocation
Board; Project waiting for funding allocation, anticipated no sooner than 2022
5
Site Layout
6
Elevation View – Buildings B &C
7
Panoramic FlyoverBringhurst Elementary SchoolSeptember 28, 2018
https://shared.traceair.net/lennar/innovation-village/2018-09-28/output/pano/pano2/index.html