Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
EXECUTIVE SUMMARY
1.1. Identification of Project:
Sardar Vallabhbhai Patel International Airport (SVPIA) (IATA: AMD, ICAO: VAAH) is an
international airport serving the cities of Ahmedabad and Gandhinagar in Gujarat, India. It
is named after Sardar Vallabhbhai Patel, the 1st Deputy Prime Minister of India.
In fiscal year 2017-18, it handled about 9.2 million passengers making it the eighth-busiest
airport in terms of passenger traffic in India. The airport is an operating hub for Air Odisha
and Blue Dart Aviation. The airport also serves as a focus city for Air India, GoAir, IndiGo
and Jet Airways.
As part of the airport modernization process, the AAI proposed to construct a new air
traffic control (ATC) tower cum technical block. The same will be done due to operational
requirement as approach funnel of runway (23) is not clearly visible from existing ATC
Tower
The area earmarked for the proposed construction is about 9840.00 m2 within the existing
airport premises. There is no additional requirement of land for the proposed construction
works. The construction work will be done in the land abutting the existing airport. Thus,
the same requires prior Environmental Clearance under the provisions of EIA Notification,
2006 and subsequent amendments. The same shall be categorized under item 7 (a) of
Schedule - Gazette Notification as Category A project.
1.2. Project Brief:
The project involves construction of new ATC tower cum technical block. The old ATC
building will be dismantled. The total area of the existing SVPI airport is 928.59 acres,
while the area earmarked for the proposed construction is 9840 sq. m. The details of the
proposed building are summarized as under:
Table 1.1: Project summary for new ATC tower cum technical block
S No. Description Details
1. Project cost Rs. 166.47 Cr.
2. Location Latitude: 23° 04' 42.44" N
Longitude: 72° 37' 12.15" E
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
3. ARP coordinates Latitude : 23° 04' 16.28" N
Longitude : 72° 37' 35.15" E
4. Plot area 9840 sq. m.
5. Ground Coverage (achieved) 1512.25 sq. m.
6. Total Built Up Area (including
Headroom & core of Tower)
10520.5 sq. m.
7. Green Area 3338.5 sq. m. (33.92 %)
8. Road and Open Area (excluding surface
parking area)
3466.65 sq. m.
9. Surface parking Area 1522.595 sq. m. (32 Cars & 64 Scooters)
10. No. of Floors 15
11. Height of Tower 72.4 m
12. Population {Staff (ATC cum Technical
Block)
125 Persons (Peak)
13. Water demand 12 KLD (Domestic)
14. Power requirement 1000 KW
Source: 132 kV GSS of Torrent Power
15. Back up source 750 kVA (2 nos.)
16. Solid waste generation 57 kg/day
Table 1.2: Existing Airport Data
S.
no Particulars Details Particulars Details
A. General Information
1. Airport Owner/Operator Airports Authority of India
2. State Gujarat
3. Location Hansol, Ahmedabad. Gujarat
4. Latitude & Longitude of Aerodrome
Reference Point (ARP–WGS 84)
23°04'16.28"N 72°37'35.15"E
5. Suitability Code E Aircraft
6. Aircraft operations
(Scheduled/Non-scheduled)
Destination:
Domestic: Delhi, Kolkata, Mumbai, Chennai, Goa, Pune, Hyderabad, Bangalore, Jaipur, Indore, Bhopal International: Singapore, Abu Dhabi, Muscat, Dubai, Sharjah, Doha, Kuwait, London, Newark
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Operators :
Domestic: Air India, Air Vistara, Jet Airways, Spice jet, Go Air, Indigo, Air Costa, Jet Lite International: Air Arabia, Emirates, Spice jet, Fly Dubai, Jet Airways, Etihad, Singapore, Qatar, Air India Frequency :
Domestic : 124 per day International : 24 per day
7. Other Airports in the vicinity
(within 150 Km radius)
Vadodara Airport : 100.00 km towards SE
B. Airport land area & utilization
1. Total land area (Acres) 928.59 Acres
C. Aerodrome Data (Air side)
1. Aerodrome elevation / Reference Temperature
57.5 m /42°C
2. Aerodrome Reference Code (ARC) 4E
3. Aerodrome traffic density Medium
4. Type of traffic permitted VFR/IFR (with night operation)
5. Aerodrome rescue & fire fighting category (ARFF)
Cat-IX
D. Runway
1. Runway operations 05/23
2. Runway Dimension 3505 m x 45 m
3. Runway strip dimension 3625 m x 150 m
4. Runway Strength (PCN) Rigid Portion - 83/R/B/W/T Flexible / Composite portion ---94/F/B/W/T
5. Runway surface Flexible Pavement
6. Runway shoulder 10.5 M
7. Runway End Safety area (RESA) 90 m x 90 m at both end of runway
E Terminal Building
1. Area Domestic Side: 31000 sq.m International Side: 39000 sq.m
2. PEAK HOUR CAPACITY (PHP) DEPARTURE/ARRIVAL/TRANSIT PAX
Domestic: 1600
International: 1400
3. Car Parking Area Domestic: 10786.55 Sq.m
International: 17621.59 Sq.m
F. Apron Details
1. Dimension Apron 1: 750 m x 200 m
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Apron 2: 363 m x 135 m
2. Capacity Apron 1- 24 (Code A & B: 12, Code C :7, D & E : 5) Apron 2- 06 (Code C: 2 and Code D & E: 4)
3. PCN
APRON-1 Bay 1 to 7 88/R/A/W/T Bays 8 to 12 59/R/A/W/T Bays 13 82/R/A/W/T Bay 14 to 21 98/R/B/W/T Bay 22 to 24 59/R/A/W/T APRON-2 Bay 31 to 36 63/R/B/W/T
G Taxiway Details
1. Width Taxiways Length (m)
Width (m)
Surface Type
Strength
ALPHA 308.45 23 Rigid (Concrete)
72/R/B/W/T
BRAVO 337 23 Flexible (Asphalt)
58/R/B/W/T (Rigid ) 101/F/B/W/T (Flexible)
CHARLIE 297 23 Rigid (Concrete)
77/R/B/W/T
DELTA 320 23 Rigid (Concrete)
84/R/B/W/T
FOXTROT 262 23 Rigid (Concrete)
---
GOLF 152.25 23 Rigid (Concrete)
65/R/B/W/T
HOTEL 152.25 23 Rigid (Concrete)
65/R/B/W/T
2. PARALLEL TWY (Width/Strength)
Taxiways Length (m)
Width (m)
Surface Type
Strength
PAPA 1455.60
23
Rigid (Concrete)
Between TWY B & TWY C) 84/R/B/W/T (Between TWY A & TWY B) 81/R/B/W
3. Shoulder All Twy having shoulders of 10.5 m each side
H. Navigation Aids
1. DVOR Available
2. PAPI PAPI for both ends have been installed to accommodate Cat-E Aircraft; Glide Angle Rwy 05 - 3 degree / Rwy 23 – 3 degree
I AAI Staff Accommodation
Residential Colony Type of Quarters Available Quarters
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
TYPE I (A) 3 TYPE II (A) 33 TYPEIII (B) 42 TYPEIV (C) 13 TYPEV (D) 6 TYPEVI (E) 1 TOTAL 98
CISF Barrack Accommodation 2 Male barrack accommodation 1 Female barrack accommodation
J. Other Facilities
1. Instrumental Landing system Available
2. Runway Light Facilities Available
3. Approach Lighting System (ALS) Runway 05- SALS Runway 23- Abridged Cat - I Approach Lights (Length 750 m)
H. Solar Panels
1. Area for Solar panels 12 acres in front of Radar in ops area
********************
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
INTRODUCTION OF THE PROJECT
2.1 Identification of Project and Project Proponent Ahmedabad district is located in the central Gujarat. Ahmedabad is the largest city in
Gujarat and seventh largest urban agglomeration in India located on the banks of the
Sabarmati River, 30 km from the state capital Gandhinagar. Ahmedabad is an industrial
hub for textiles and was popularly known as the ‘Manchester of India’.
Sardar Vallabhbhai Patel International Airport (S.V.P.I.) is spread over an area of 928.59
acres. Presently 774 acres of land has been used on airside (operational area) while 142.93
acres earmarked on city side (in use 45 acres + future development 97.93 acres). Airports
Authority of India (AAI) proposes to construct new ATC Tower cum Technical Block at
S.V.P.I. at an area of 9840.00 m2 (2.43 Acres).
The proposal is to construct new ATC Tower cum Technical Block at S.V.P.I. Airport,
Ahmedabad to make approach funnel of runway (23) visible, as from existing ATC Tower
cum Technical Block approach funnel (23) is not clearly visible.
Airports Authority of India (AAI) was constituted by an Act of Parliament and came into
being on 1st April 1995. AAI under the Ministry of Civil Aviation is responsible for
creating, upgrading, maintaining and managing civil aviation infrastructure in India.
Airports Authority of India (AAI).
AAI is planning to take up the works of construction of new ATC Tower and other allied
works. The proposed construction of new ATC tower cum Technical Block of Airport is
categorized under item 7 (a) of Schedule - Gazette Notification dated Sept. 14th, 2006 and
its subsequent amendment thereafter.
The existing facility & other details are as follows:
S.N. Particulars Details Particulars Details
A. General Information
1. Airport Owner/Operator Airports Authority of India
2. State Gujarat
3. Location Hansol, Ahmedabad. Gujarat
4. Latitude & Longitude of 23°04'16.28"N 72°37'35.15"E
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Aerodrome Reference Point
(ARP–WGS 84)
5. Suitability Code E Aircraft
6. Aircraft operations
(Scheduled/Non-scheduled)
Destination:
Domestic: Delhi, Kolkata, Mumbai, Chennai, Goa, Pune, Hyderabad, Bangalore, Jaipur, Indore, Bhopal International: Singapore, Abu Dhabi, Muscat, Dubai, Sharjah,
Doha, Kuwait, London, Newark
Operators :
Domestic: Air India, Air Vistara, Jet Airways, Spice jet, Go Air, Indigo, Air Costa, Jet Lite International: Air Arabia, Emirates, Spice jet, Fly Dubai, Jet
Airways, Etihad, Singapore, Qatar, Air India
Frequency :
Domestic : 124 per day International : 24 per day
7. Other Airports in the vicinity
(within 150 Km radius)
Vadodara Airport : 100.00 km towards SE
B. Airport land area & utilization
1. Total land area (Acres) 928.59 Acres
C. Aerodrome Data (Air side)
1. Aerodrome elevation / Reference Temperature
57.5 m /42°C
2. Aerodrome Reference Code (ARC)
4E
3. Aerodrome traffic density Medium
4. Type of traffic permitted VFR/IFR (with night operation)
5. Aerodrome rescue & fire fighting category (ARFF)
Cat-IX
D. Runway
1. Runway operations 05/23
2. Runway Dimension 3505 m x 45 m
3. Runway strip dimension 3625 m x 150 m
4. Runway Strength (PCN) Rigid Portion - 83/R/B/W/T Flexible / Composite portion ---94/F/B/W/T
5. Runway surface Flexible Pavement
6. Runway shoulder 10.5 M
7. Runway End Safety area (RESA) 90 m x 90 m at both end of runway
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
E Terminal Building
1. Area Domestic Side: 31000 sq.m International Side: 39000 sq.m
2. PEAK HOUR CAPACITY (PHP) DEPARTURE/ARRIVAL/TRANSIT PAX
Domestic: 1600
International: 1400
3. Car Parking Area Domestic: 10786.55 Sq.m
International: 17621.59 Sq.m
F. Apron Details
1. Dimension Apron 1: 750 m x 200 m Apron 2: 363 m x 135 m
2. Capacity Apron 1- 24 (Code A & B: 12, Code C :7, D & E : 5) Apron 2- 06 (Code C: 2 and Code D & E: 4)
3. PCN
APRON-1 Bay 1 to 7 88/R/A/W/T Bays 8 to 12 59/R/A/W/T Bays 13 82/R/A/W/T Bay 14 to 21 98/R/B/W/T Bay 22 to 24 59/R/A/W/T APRON-2 Bay 31 to 36 63/R/B/W/T
G Taxiway Details
1. Width Taxiways Length (m)
Width (m)
Surface Type
Strength
ALPHA 308.45 23 Rigid (Concrete)
72/R/B/W/T
BRAVO 337 23 Flexible (Asphalt)
58/R/B/W/T (Rigid ) 101/F/B/W/T (Flexible)
CHARLIE 297 23 Rigid (Concrete)
77/R/B/W/T
DELTA 320 23 Rigid (Concrete)
84/R/B/W/T
FOXTROT 262 23 Rigid (Concrete)
---
GOLF 152.25 23 Rigid (Concrete)
65/R/B/W/T
HOTEL 152.25 23 Rigid (Concrete)
65/R/B/W/T
2. PARALLEL TWY (Width/Strength)
Taxiways Length (m)
Width (m)
Surface Type
Strength
PAPA 1455.60
23
Rigid (Concrete)
Between TWY B & TWY C) 84/R/B/W/T (Between TWY A & TWY B) 81/R/B/W
3. Shoulder All Twy having shoulders of 10.5 m each side
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
H. Navigation Aids
1. DVOR Available
2. PAPI PAPI for both ends have been installed to accommodate Cat-E Aircraft; Glide Angle Rwy 05 - 3 degree / Rwy 23 – 3 degree
I AAI Staff Accommodation
Residential Colony Type of Quarters Numbers TYPE I (A) 3 TYPE II (A) 33 TYPEIII (B) 42 TYPEIV (C) 13 TYPEV (D) 6 TYPEVI (E) 1 TOTAL 98
CISF Barrack Accommodation 2 Male barrack accommodation 1 Female barrack accommodation
J. Other Facilities
1. Instrumental Landing system Available
2. Runway Light Facilities Available
3. Approach Lighting System (ALS) Runway 05- SALS Runway 23- Abridged Cat - I Approach Lights (Length 750 m)
H. Solar Panels
1. Area for Solar panels 12 Acres in front of Radar in ops area
2.2 Brief Description of Nature of the Project AAI is planning to construct ATC Tower cum Technical Block at S.V.P.I. Airport,
Ahmedabad due to operational requirement as approach funnel of runway (23) is not
visible.
Type of project: The proposed expansion of Airport is categorized as category A under item 7 (a) of
Schedule - Gazette Notification dated Sept. 14th, 2006 and its subsequent amendment for
preparation of Environment Impact Assessment study and Environment Management
Plan. However general condition is not applicable to this project. This project is
independent and is not linked with other project which may attract directly or indirectly
any provisions of schedule of EIA notification 2006 amended to date.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
2.3 Need for the project & its Importance The ATC Tower controls all movements such as takeoff, landing and ground traffic. The
Purpose of ATC Tower is to prevent collisions, organize and expedite the flow of air
traffic, and provide information and other support for pilots. ATC provides services to all
private, military, and commercial aircraft operating within its airspace.
The existing ATC Tower cum Technical Block needs to relocate due to operational
requirement as approach funnel of runway (23) is not clearly visible. To meet the proper
and smooth movement of Aircrafts at the S.V.P.I. Airport, Ahmedabad it is required to
relocate the ATC Tower cum Technical Block.
Improvements in connectivity will effectively contribute to the economic performance of
the wider economy through enhancing its overall level of productivity. Table 1.1 shows
the quantum of passengers handled at SVPI airports in last few years:
Table 1-1: Passenger Handled at Major Airports in India (in millions)
S. N. Particulars 2014-15 (FY) 2015-16 (FY) 2016-17 (FY) 2017-18 (FY)
Dom Inlt. Dom Inlt. Dom Inlt. Dom Inlt.
1. Aircraft Movement 41529 41529 43697 10416 38762 12345 49987 13142
2. Passenger 3571559 3571559 6483641 1568535 7323471 1785909 5619373 1850954
3. Cargo (in tones) 35932 35932 44317 23457 45552 31050 50367 41266
Source: Airports Authority of India, APAO, New Delhi
2.4 Demand Supply Gap
The existing ATC Tower cum Technical Block needs to relocate due to operational
requirement as approach funnel of runway (23) is not clearly visible. To meet the proper
and smooth movement of Aircrafts at the S.V.P.I. Airport, Ahmedabad it is required to
relocate the ATC Tower cum Technical Block.
2.5 Imports vs. Indigenous production
Not Applicable as the project is construction of new ATC tower cum Technical Block at
SVPI Airport, Ahmedabad.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
2.6 Export Possibility
Not Applicable as the project is construction of new ATC tower cum Technical Block at
SVPI Airport, Ahmedabad.
2.7 Domestic/ export Markets
Not Applicable as the project is construction of new ATC tower cum Technical Block at SVPI Airport, Ahmedabad.
2.8 Employment Generation (Direct and Indirect) due to the project
The proposed project will provide direct employment during construction & operation
phase. Local workers will be hired from the nearby areas during construction
phase/workers will be sourced by construction contractor. During operation phase
employees from existing ATC Tower will be shifted in new ATC Tower cum Technical
Block.
*********
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
PROJECT DESCRIPTION
3.1 Type of Project: AAI is planning to construct ATC Tower cum Technical Block at S.V.P.I. Airport,
Ahmedabad due to operational requirement as approach funnel of runway (23) is not
visible.
Project falls under Category “A”, under schedule ‘7(a)’ of EIA Notification dated 14th
September, 2006 & amendment made thereafter.
3.2 Location:
The project is situated at Hansol, Ahmedabad, Gujarat. The airports reference point is
located at latitude 23°04'16.28"N and longitude 72°37'35.15"E. The Google map is
given in Figure.
Figure: Google Map
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
S.V.P.I. Airport Environmental Setting: S. No Particulars Details
1. Present Land use at Airport Industrial Commercial
2. Nearest Highway/Major Road • NH-8: 5.5 km towards NE
• NH-8C: 12.0 km towards NNW
• NH-59: 1.7 km towards SE
• NH-228: 13.88 km towards SSW
• SH-41: 4.1 km towards W
3. Nearest Railway Station Ahmedabad Railway Station : 6.8 km towards sw
4. Nearest Town/village • Ahmedabad (As the proposed project site lies within
S.V.P.I. Airport, Ahmedabad).
5. Major Water Bodies • Sabarmati River : 1.5 km towards N
• Khairicut Canal : 3.0 km towards E
• Narmada Main Canal : 5.2 km towards N
• Bera Nala : 6.5 km towards NE
• Kankariya Talav : 8.3 km towards SSW
• Khari Nadi : 8.7 km towards E
• Chandola Talav : 10.7 km towards SSW
• Vaheva Nadi : 11.6 km towards S
6. Seismic Zone Zone III (Moderate Seismic Hazard)
3.3 Details of alternative site:
The proposed project involves construction of new ATC Building cum Technical Block
at S.V.P.I. Airport Ahmedabad. The construction work will be done in the land abutting
the existing airport. Hence, no alternative sites were examined.
3.4 Size or magnitude of operation: S.V.P.I. Airport is spread over an area of 928.59 acres. Presently 774 acres of land has
been used on airside (operational area) while 142.93 acres earmarked on city side (in use
45 acres + future development 97.93 acres). Airports Authority of India (AAI) proposes
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
to construct new ATC Tower cum Technical Block at S.V.P.I. at an area of 9840.00 m2
(2.43 Acres) out of which 1512.25 m2 shall be utilized as ground coverage. The total
Built up area envisaged for the proposed tower 10520.5 m2.
Details of proposed Facility are as under:
S No. Description Details
1. Coordinates (ATC Tower) Latitude: 23° 04' 42.44" N
Longitude: 72° 37' 12.15" E
2. ARP coordinates Latitude : 23° 04' 16.28" N
Longitude : 72° 37' 35.15" E
3. Plot area 9840 sq. m.
4. Ground Coverage (achieved) 1512.25 sq. m.
5. Total Built Up Area (including
Headroom & core of Tower)
10520.5 sq. m.
6. Green Area 3338.5 sq. m. (33.92 %)
7. Road and Open Area (excluding surface
parking area)
3466.65 sq. m.
8. Surface parking Area 1522.595 sq. m. (32 Cars & 64 Scooters)
9. No. of Floors 15
10. Height of Tower 72.4 m
11. Population {Staff (ATC cum Technical
Block)}
125 Persons (Peak)
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Fig: Layout Plan of New ATC Tower cum Technical Block
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Fig: Master Plan of SVPI Airport, Ahmedabad
3.5 Raw Material required (Quantity & Source), Product & Mode of Transport: Airport being a service industry doesn’t process any raw material or deal in production
of products. The proposed project is construction of new ATC tower cum Technical
Bock which requires general construction materials viz. sand, aggregates, bricks, etc.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
will be used for infrastructure (roads, service areas, ATC tower) development. The raw
materials will be procured from nearby markets as per requirements and transportation
facilities will be provided by construction contractor.
3.6 Resource optimization/recycling & Reuse envisaged in the Project: 1. Use of fly ash will be considered as a part of resource optimization, recycling & reuse as per
engineering and operational requirements.
2. During construction phase, material will be used as per requirements with the focus of resources
conservation.
3. During operational phase, the input resources such as Drinking Water, Energy & Fuels will be
used as per requirements with the focus of resources conservation & resource
Optimizations.
4. During operation Municipal wastes will be managed as per MSW Rules, 2016; two bin systems
will be followed. All the recyclable wastes collected will be recycled by the service provider and
biological wastes will be composted away from the airport by municipal authorized facilities.
5. ISO 50001- Energy Management System is in place, energy conservation, energy efficiency will
be considered as a part of resources conservation & resource optimizations.
6. Use of renewable energy and capacity enhancement will be considered for energy resource
optimization.
3.7 Availability of Water, Energy / Power Requirement & Source:
3.7.1 Population :
S. No. Population Details
1. Staff ( Control Tower cum Technical Block) Peak Intensity 125
2. Visitors 50
3.7.2 Water requirement:
The daily consumption of water for new ATC tower cum Technical Block during
operation phase for domestic use will be about 12 KLD out of which 7 KLD will be fresh
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
water and 5 KLD will be recycled/treated water. The water requirement for Landscaping,
HVAC & DG cooling will be about 32 KLD (treated water). The water will be met
through Ahmedabad Municipal Corporation (AMC) water supply. The details of water
requirement and wastewater generation for operation phase are as follows:
A. Construction phase:
Domestic Water
Domestic water during construction phase for approx 100 nos. of workers will be 5
KLD, which will be met through the construction contractor / from the supply line of
AMC as specified in the contract award.
The potable water supplied for construction workers will be treated to meet the potable
water specification by the contractor as per AMC water quality norms / IS10500.
Domestic wastewater will be generated, collected and retained in the bio toilets provided
by construction contractor.
B. Operational Phase:
S. No.
Particulars Population* Fresh water
demand
Treated water Demand
Total water Demand
1. Staff’s 125 @40 LPCD: 5 KLD @30 LPCD: 4 KLD 9 KLD
2. Visitors 50 @25 LPCD: 2 KLD @20 LPCD: 1 KLD 3 KLD
3. Landscape @5L/m2 17 KLD 17 KLD
4. HVAC & DG cooling 50 KL One Time Requirement
and 15 KLD Daily requirement
15 KLD 15 KLD
Total 7 KLD 37 KLD 44 KLD
Source: NBC 2016 *Maximum Footfall
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Water Balance
Fresh water
7 KLD
Staff’s5 KLD
STP treated
water
37 KLD
6 KLD
Waste water
S
T
P
Capacity
10 KLD
Sludge &
evaporation
losses
1 KLD
Recycled/ reused for flushing, landscaping
Daily water demand: 44 KLD {7 KLD (fresh) + 37 KLD (recycled/ reused water)}
HVAC & DG Cooling 50 KL
4 KLD
Visitors -2 KLD
Landscape17 KLD
2 KLD
5 KLDFlushing 5 KLD
Treated water from AMC
32 KLD
35 KLD Re-circulated
15 KLD
5 KLD
3.7.3 Power Demand
The total proposed load for ATC tower cum Technical Block at S.V.P.I. Airport,
Ahmedabad is 1000 KW. The power supply shall be drawn from existing 132 kV GSS of
Torrent Power.
There will be power backup through DG sets of capacity of 750 kVA (2 nos.) used in
case of power cut or failure. DG set will be provided with an effective safe stack height
for proper dispersion of pollutants that will keep the emissions within the permissible
limit. The fuel requirement will be about 240 lit/hr of HSD (as and when used).
3.7.4 STORM WATER MANAGEMENT:
Construction phase
Contaminant Sources Impact Mitigation Sediment & Floatables
Streets, lawns, driveways, roads, construction
During construction, sediment fencing or other erosion control devices will be used to mitigate the short-term
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
activities, adverse impacts of sedimentation.
Oil & Grease Roads, driveways, parking lots etc.
Oil & Grease trap will be provided to remove oil & grease, suspended matter, and ensure the quality of water.
Storm water control and rain water harvesting will be done as per the standards laid
down by CGWA & BIS. Following measure will be adopted for the same:
Construction Sequencing: Construction sequencing (involves disturbing only part of a
site at a time to prevent erosion from dormant parts) has been done at site. Grading
activities and construction are completed and soils are effectively stabilized on one part
of the site before grading and construction commence at another part.
Compost Blankets: A compost blanket is a layer of loosely applied composted material
placed on the soil in disturbed areas to reduce storm water runoff and erosion. This
material fills in small rills and voids to limit channelized flow, provides a more
permeable surface to facilitate storm water infiltration, and promotes re-vegetation.
Post Construction Phase:
a. Design:
For good design of rainwater harvesting, following points are to be kept under
consideration:
• Ideal location with good ground slope.
• The location has adequate subsurface permeability of the aquifer to accommodate
maximum recharge of rainwater through injection well.
• Rate of filtration should exceed average rainfall intensity.
• Clogging of filtration media should be cleaned periodically.
• Ground water pollution does not take place.
b. Baseline:
The average annual rainfall (based on last 5 years rainfall data) at Ahmedabad station is
623 mm.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Rain Fall Data (last 5 years):
S. No. Year Annual Average Rainfall
1 2017 734.5
2 2016 436.1
3 2015 315.7
4 2014 698.2
5 2013 929
Total 3113.5 say 3114
Average 622.8 say 623
Source: IMD, Ahmedabad
c. Calculation of No. of RWH Structures:
The rain water harvesting structures are calculated on the basis of peak intensity of
rainfall recorded as 40 mm/hr considering 15 minutes of peak rainfall. The same has
been done to avoid flooding of the area.
S.
No
Type of
Structure/ Surface
Area [A]
(sq. m.)
Run off
Coefficient
[C]
Intensity
of rainfall
(m/hour) [I]
Total Recharge
[Q = CIA]
(m3/hr)
1. Roof Top 1512.25 0.9 0.04 54.441
2. Landscape 3338.5 0.3 0.04 40.062
3. Road &Paved area 4989.25 0.75 0.04 149.677
Grand Total (1-3) 9840 244.18
Total Rain Water Flow : 244.18 m3/hr
Considering 15 minutes of peak rainfall,
Runoff volume : 61.04 m3/hr
Volume of each pit : 27 m3 (3 m x 3 m x 3 m)
Total no. of rain water harvesting pits required
: Total run-off volume/volume of each pit
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
: 61.04/27
: 2.26 say 2 nos.
Therefore, 2 Nos. rain Water Harvesting pit of size 3 m length x 3 m width x 3 m depth with
PVC slotted pipe upto minimum depth of 30 m.
d. Design of Rain Water Harvesting Structure:
The dimensional parameters of Desilting/Settlement chamber would be 3 m (length) x 3
m (width) x 1.30 (depth). In Desilting chamber, 0.30 m depth below outflow is kept for
silt deposition. The filtration tank dimension would be 3 m (length) x 3 m (width) x 1 m
(depth) with 0.15 m dia recharge well of 30 m depth depending upon the formation for
recharge in aquifer through vadose zone.
e. Calculation of annual recharge:
S.
No
Type of
Structure/ Surface
Area [A]
(sq. m.)
Run off
Coefficient
[C]
Intensity
of rainfall [I]
(m/annum)
Total Recharge
[Q= CIA]
(m3/ annum)
1. Roof Top 1512.25 0.9 0.623 847.91
2. Landscape 3338.5 0.3 0.623 623.96
3. Paved area 4989.25 0.75 0.623 2331.22
Grand Total (1-3) 9840 3803.09
Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting
structure would be 3803.09 m3/ annum.
3.8 Waste Generation & Management Solid Waste management:
Solid waste generated from the airport mainly comprises of food waste and garbage
waste. Further, small quantities of sludge from STP and other waste are being generated.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
The solid waste generated will be first segregated as plastic, glass, paper, and other waste
separately and disposed off as per applicable Rules.
Solid Waste Calculation:
Particulars Population Basis Quantity of waste generated (in kg/day)
Staffs 125 @0.40 kg/day 50
Visitors 50 @0.12 kg/day 6
Landscaping 0.824 acres @0.2kg/acre/day 0.16
Total 56.16 Say 57 kg/day *Source: NBC 2016
Break Up of Residential Solid Waste:-
Particulars Quantity (kg/day) % Percentage
Biodegradable 27 47.43
Paper 5 8.13
Plastic/rubber 5 9.22
Metal 1 0.5
Glass 1 1.01
Rags 2 4.49
Other 2 4.02
Inerts 14 25.16
Total 57 100
Source: Municipal Solid Waste Management Manual-Part-II, CPHEEEO, MOUD, 2016
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
Bins Particulars Treatment Disposal Green Compostable waste Collected in green colored bins and sent
to the OWC Will be sent to municipality disposal site
White Dry/ recyclable waste:
No in-situ treatment. Collected in white colored bins and sent to solid waste collection point. Segregated waste will be
handed over to authorized waste pickers or waste collectors.
Black Other waste/ Domestic hazardous waste
No in-situ treatment. Collected in Black colored bins and sent to solid waste collection point
Source: Municipal Solid Waste Management Manual, CPHEEEO, MOUD, 2016
Waste water treatment & management:
During operation phase, wastewater generated from ATC Tower cum Technical Block will
be treated in Sewage Treatment Plant (STP) comprising primary, secondary and tertiary
treatment facilities.
3.9 Schematic representations of the Feasibility drawing which give information of
EIA purpose:
As per the EIA notification dated 14th September, 2006, it is mandatory for the proposed
activity to get Environmental Clearance (EC) before setting up any project or
expansion/modernization of any project. The detailed chart delineating the process is
given below:
Environmental Impact Assessment (EIA) is a well planned process to predict the
environmental consequences of any kind of development, which is a result of human
activities and to suggest appropriate measures in order to reduce adverse effects and also
to augment positive effects. The EIA procures a rational and ethical approach for
sustainable development. However, it is more scientific process because it not only tells
the past, present and the future consequences of on-going developments, but also
predicts the future events which are likely to change due to various reasons.
In terms of the EIA notification of the MoE&F dated 14th September 2006, the generic
structure of EIA documents shall be as under:-
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
• Introduction
• Project Description
• Analysis of Alternatives (Technology & Site)
• Description of the Environment
• Anticipated Environmental Impact & mitigation Measures
• Environmental Monitoring Programme
• Additional studies
• Project benefits
• Environmental Cost benefits Analysis
• EMP
• Summary & Conclusion
• Disclosure of Consultant Engaged
*************
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
SITE ANALYSIS
4.1 Connectivity: S.V.P.I. Airport is an international airport serving the cities of Ahmedabad and
Gandhinagar in Gujarat, India. The airport is located in Hansol, 9 km (5.6 mi) north of
central Ahmedabad.
Particular Details
Nearest Highway/Major Road, • NH-8: 5.5 km towards NE
• NH-8C: 12.0 km towards NNW
• NH-59: 1.7 km towards SE
• NH-228: 13.88 km towards SSW
• SH-41: 4.1 km towards W
Railway Station Ahmedabad Railway Station : 6.8 km towards sw
Public Transport
Plenty of tourist buses, taxis and luxury coaches are available
to and from important cities of the state and that of the
country.
4.2 Land Form, Land Use & Land Ownership
Presently, the airport is situated on 928.59 acres of land and the airport was set up in
1937, while international operations began on 26/01/1991 and currently operates about
148 flights per month. Currently, 774 acres of land is available on airside and 142.93 acres
of land is available on city side (45 acres present in use & 97.93 acres for future development).
The land ownership of 928.59 acres is reserved with Airport Authority of India.
4.3 Topography
Geomorphologically the district can be divided into two zones, the major portion of it
forms a flat planar topography except for a few rocky features in the extreme southern
portion.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
22
Source: http://en-in.topographic-map.com/places/Ahmedabad-7809992 Fig: Topographical Map of S.V.P.I. Airport, Ahmedabad
4.4 Existing Land use Pattern The land use pattern of the existing airport remains same. The additional construction
of new ATC tower will be converted into industrial commercial category.
4.5 Existing Infrastructure of Site
Existing infrastructure details are given in Section-2.1.
4.6 Soil Classification The soils in the district can broadly be classified as: they are Black soils, Goradu
soils, Kyari soils & Rocky soils. Alluvial sandy loam to sandy clay soils are found in
the Kheda, Gandhinagar, Ahmadabad and Mehsana district and the western part of the
Vadodara district. These soils are the most productive soils in the state and contains
fairly good amount of potassium. (Source:- Ground Water Brochure Ahmedabad
District Gujarat & http://www.gujenvis.nic.in/PDF/soil.pdf)
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
4.7 Climate Data from Secondary Sources The climate of the district is characterized by hot summer and general dryness except
during the southwest monsoon seasons. The year can be divided into four seasons.
The period from March to May is the hot season (summer) followed by southwest
monsoon from June to September. October and November constitute the post-
monsoon or retreating monsoon season. The cold season (winter) starts from
December and ends in February. The mean maximum temperature ranges between
28.4ºC during January to 41.8ºC during May and the mean minimum temperatures
vary between 11.7ºC during January and 27ºC during June. Long-term average annual
rainfall recorded by IMD station at Ahmedabad is 799.6 mm. Most of the rainfall
(about 766 mm) is received from south-west monsoon between June to September.
(Source: Ground Water Brochure Ahmedabad District Gujarat).
4.8 Social Infrastructure Available The existing social infrastructure in the Shillong which is located at about 10 km from
the airport are:
Hospital with ambulance;
Banks;
Post office;
Bus station;
Fire station;
Secondary school;
Police station;
Shopping complex;
Sports infrastructure (Stadium & Camps etc);
Community halls;
Cinema halls; and
Primary health care centers
**************
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd. EIA Coordinator 24
Airports Authority of India
Authorized Signatory
PLANNING BRIEF
5.1 Planning Concept This is a planned airport development project to cater aviation demand as per Master Plan.
The construction of new ATC building cum Technical block is proposed. Other facilities such
as power, transportation and communication, social infrastructure facilities are already
available at project site as the proposed project lies within S.V.P.I. Airport, Ahmedabad.
5.2 Population Projection The general public at S.V.P.I airport, Ahmedabad will not be having any impact as this
building is to be used by only staff of existing ATC office.
5.3 Land use planning Land use has been categorized based on the following functional groups:
Airfield Dependent: Land uses with the highest location and area priority include those that
are fully within the airfield, or overlapping the airside-landside boundary.
Airport Supporting: Land uses with functional priority include those that are required for
the airport to function. Their location may be on the airside or landside but preferably within
the airport boundary.
Commercial: Land uses that are fully provide non-aviation revenues. These uses have
flexibility of location but should not interfere with the functional operation of Airfield
Dependent or Airport Supporting Land Uses.
Infrastructure & Open Space: These land use areas are determined by the needs of all the
land uses above. Since supporting infrastructure must be within the development areas the
first three groups determine the area required for this group. Open space includes those areas
remaining which cannot be developed.
5.4 Assessment of Infrastructure Demand (Physical & Social) Social Demand
On the basis of the preliminary site visit, the infrastructure demand in the nearby area is
assessed on the basis of need and priority:
The assessment will be identified in the socio economic survey, after the grant of TOR and
will be submitted at the time of final presentation regarding Environmental Clearance.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd. EIA Coordinator 25
Airports Authority of India
Authorized Signatory
Physical infrastructure Physical infrastructure is an important aspect of the site. It determines the quality of life to a
large extent. Physical infrastructure deals with:
• Water supply
• Electricity
• Waste management & treatment
Water supply The daily consumption of water for new ATC tower cum Technical Block during operation
phase for domestic use will be about 12 KLD out of which 7 KLD will be fresh water and 5
KLD will be recycled/treated water. The water requirement for Landscaping, HVAC & DG
cooling will be about 32 KLD (treated water). The water will be met through AMC water
supply.
Electricity
The total proposed load for ATC tower cum Technical Block at S.V.P.I. Airport, Ahmedabad
is 1000 KW. The power supply shall be drawn from existing 132 kV GSS of Torrent Power.
There will be power backup through DG sets of capacity of 750 kVA (2 nos.) used in case of
power cut or failure. DG set will be provided with an effective safe stack height for proper
dispersion of pollutants that will keep the emissions within the permissible limit. The fuel
requirement will be about 240 lit/hr of HSD (as and when used).
Solid Waste management:
Solid waste generated from the airport mainly comprises of food waste and garbage waste.
Further, small quantities of sludge from STP and other waste are being generated. Collection
and handling of domestic solid waste is being done in line with the provisions of the Solid
Waste Management Rules 2016. Waste water treatment & management:
During operation phase, wastewater generated from ATC Tower cum Technical Block will
be treated in Sewage Treatment Plant (STP) comprising primary, secondary and tertiary
treatment facilities.
*********
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
PROPOSED INFRASTRUCTURE
6.1 Industrial Area (processing area) S.V.P.I. Airport is spread over an area of 928.59 acres. Presently 774 acres of land has been
used on airside (operational area) while 142.93 acres earmarked on city side (in use 45 acres +
future development 97.93 acres). Airports Authority of India (AAI) proposes to construct new
ATC Tower cum Technical Block at S.V.P.I. at an area of 9840.00 m2 (2.43 Acres) out of
which 1512.25 m2 shall be utilized as ground coverage. The total built up area envisaged for
the proposed tower 10520.5 m2.
The Brief details are as under:
S No. Description Details
1. Project cost Rs. 166.47 Cr.
2. Location Latitude: 23° 04' 42.44" N
Longitude: 72° 37' 12.15" E
3. ARP coordinates Latitude : 23° 04' 16.28" N
Longitude : 72° 37' 35.15" E
4. Plot area 9840 sq. m.
5. Ground Coverage (achieved) 1512.25 sq. m.
6. Total Built Up Area (including
Headroom & core of Tower)
10520.5 sq. m.
7. Green Area 3338.5 sq. m. (33.92 %)
8. Road and Open Area (excluding surface
parking area)
3466.65 sq. m.
9. Surface parking Area 1522.595 sq. m.
10. No. of Floors 15
11. Height of Tower 72.4 m
12. Population {Staff (ATC cum Technical
Block)
125 Persons (Peak)
13. Water demand 12 KLD (domestic)
6.2 Residential Area (non-processing area) Not Applicable as the project is construction of new ATC tower cum Technical Block at
SVPI Airport, Ahmedabad.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
6.3 Green Belt Approximately 33.92 % of the total project area will be under green belt and plantation.
Entire landscaping is irrigated with treated waste water having drip irrigation and automatic
water efficient water dispensing system.
6.4 Social Infrastructure The proposed infrastructure will be identified in the socio-economic survey, after the grant of
ToR and will be submitted at the time of final presentation regarding Environmental
Clearance.
6.5 Connectivity S.V.P.I. Airport is an international airport serving the cities of Ahmedabad and Gandhinagar
in Gujarat, India. The airport is located in Hansol, 9 km (5.6 mi) north of central Ahmedabad.
The connectivity details are as below:
Particular Details
Nearest Highway/Major Road, • NH-8: 5.5 km towards NE
• NH-8C: 12.0 km towards NNW
• NH-59: 1.7 km towards SE
• NH-228: 13.88 km towards SSW
• SH-41: 4.1 km towards W
Railway Station Ahmedabad Railway Station : 6.8 km towards SW
Public Transport
Plenty of tourist buses, taxis and luxury coaches are available
to and from important cities of the state and that of the
country.
6.6 Drinking Water Management (Source & Supply of Water) The daily consumption of water for new ATC tower cum Technical Block during
operation phase for domestic use will be about 12 KLD out of which 7 KLD will be fresh
water and 5 KLD will be recycled/treated water. The water requirement for Landscaping,
HVAC & DG cooling will be about 32 KLD (treated water). The water will be met
through by AMC water supply.
6.7 Sewerage System For the treatment of domestic sewerage, STP will be installed in the project site.
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
6.8 Industrial Waste Management No Industrial waste will be generated from the project.
6.9 Solid waste Management Solid waste generated from the airport mainly comprises of food waste and garbage waste.
Further, small quantities of sludge from STP and other waste are being generated. Collection
and handling of domestic solid waste is being done in line with the provisions of the Solid
Waste Management Rules 2016.
6.10 Waste water treatment & management During operation phase, wastewater generated from ATC Tower cum Technical Block will
be treated in Sewage Treatment Plant (STP) comprising primary, secondary and tertiary
treatment facilities. The treated wastewater from the STP will be used for flushing.
6.11 Power Requirement & Supply/ Source The total proposed load for ATC tower cum Technical Block at S.V.P.I. Airport, Ahmedabad
is 1000 KW. The power supply shall be drawn from existing 132 kV GSS of Torrent Power.
There will be power backup through DG sets of capacity of 750 kVA (2 nos.) used in case of
power cut or failure. DG set will be provided with an effective safe stack height for proper
dispersion of pollutants that will keep the emissions within the permissible limit. The fuel
requirement will be about 240 lit/hr of HSD (as and when used).
**************
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
REHABILITATION & RESETTLEMENT (R&R) PLAN
7.1. Rehabilitation & Resettlement (R&R) Plan
Introduction:
Airport Authority of India (AAI) proposes to construct new ATC Tower cum Technical
Block as the approach funnel of runway (23) is out of visual coverage from existing ATC
Tower. S.V.P.I. Airport is spread over an area of 928.59 acres. Presently 774 acres of land
has been used on airside (operational area) while 142.93 acres earmarked on city side (in use
45 acres + future development 97.93 acres). Airports Authority of India (AAI) proposes to
construct new ATC Tower cum Technical Block at S.V.P.I. at an area of 9840.00 m2 (2.43
Acres) out of which 1512.25 m2 shall be utilized as ground coverage. The total Built up area
envisaged for the proposed tower 10520.5 m2. The land ownership of 928.59 acres is reserved
with Airport Authority of India.
Therefore Rehabilitation and Resettlement (R&R) is not applicable for proposed project.
************
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
PROJECT SCHEDULE & COST ESTIMATES
8.1. Project Schedule & Cost Estimates Estimated cost of work for the construction of new ATC Tower cum Technical Block &
allied works is worked out to be Rs. 166.47 Crores.
*************
Project : Construction of New ATC Tower cum Technical Block at S.V.P.I Airport, Ahmedabad PFR
Promoter : Airports Authority of India
Gaurang Environmental Solutions Pvt. Ltd.
EIA Coordinator
Airports Authority of India
Authorized Signatory
ANALYSIS OF PROPOSAL
9.1. Analysis of the Proposal The present proposal of construction of new ATC tower cum Technical Block will
help to meet the proper and smooth movement of Aircrafts at the S.V.P.I. Airport,
Ahmedabad. Improvements in connectivity will effectively contribute to the economic
performance of the wider economy through enhancing its overall level of productivity. The
project will boast economic growth benefitting the whole region through the
generation of both direct and indirect economic value. Airport operations will have a
considerable economic and social impact in surrounding regions.
These benefits extend far beyond the direct effect of an airport’s operation on its
community development to the wider benefits that air service accessibility brings to
business interests and to consumers. The construction and operation of airport will
generate direct employment opportunity, indirectly contributed jobs through supply
chain, enhance induced impact through tourism. Thus the project will prove beneficial
to the area.
. *********