Excelsior Gateway Beautification Project: Ever Upward
Nicole Agbayani, Corridor Manager, Excelsior Action Group
Jack Laws, Principal, Structural Design Engineers Jason Gilmore, Artist, mosaic design
January 17, 2013
Project Background
Sculpture Proportions
Before After
Structural Properties
Structural Properties
Structural Properties
Structural Properties
Mosaic Column Design
Materials Samples & Mosaic Mock-Up
Project Support
Ed Reiskin, SFMTA Director of Transportation
John Avalos, District 11 Supervisor
Project Support
Beth Rubenstein, Executive Director Out of Site Youth Arts Center
Dan Weaver, Chair, Geneva Car Barn and Powerhouse Board of Directors
Project Timeline
• Jan 17, 2013 – Presentation to SFAC VAC
• Mar 4, 2013 – Acquire DPW permit ( 6 weeks)
• Mar 4, 2013 – Isis begins template drawings (1 – 2 weeks)
• Mar 11, 2013 – Jack begins mechanical drawings (1 week)
• Mar 18, 2013 – Old Iron Works begins fabrication (1-2 months)
• Apr 22, 2013 – Trench footing and pour column (1 – 2 weeks)
• Apr 29, 2013 – Column curing complete (1 week)
• Apr 29 – May 6, 2013 – Old Iron Works installs metalwork on column (1-2 days)
• May – Jun, 2013 – Mosaic installation
Thank You!