evms london olympics 2012_david_birch
TRANSCRIPT
-
7/27/2019 EVMS London Olympics 2012_David_Birch
1/27
Olympic Delivery Authority*
Earned Value in the London 2012 Programme
9 June 2009
*Prepared by CLM Delivery Partner Limited
-
7/27/2019 EVMS London Olympics 2012_David_Birch
2/27
2
What well cover today
The Programme
The Challenges
The Structure
How we implemented
How is it working
Lessons Learned
Q & A, and your thoughts
-
7/27/2019 EVMS London Olympics 2012_David_Birch
3/27
3
The Programme
The Olympic Park
Site Preparation and Infrastructure
Venues
International Broadcast Centre and
Main Press Centre
Olympic Village
Parkwide Projects (Including
Logistics & Security)
Off Park Venues
Transport
Programme Management
-
7/27/2019 EVMS London Olympics 2012_David_Birch
4/27
4
-
7/27/2019 EVMS London Olympics 2012_David_Birch
5/27
5
-
7/27/2019 EVMS London Olympics 2012_David_Birch
6/27
6
-
7/27/2019 EVMS London Olympics 2012_David_Birch
7/27
7
The Beginning
-
7/27/2019 EVMS London Olympics 2012_David_Birch
8/27
8
How its working
April 2009
Nov 2008
-
7/27/2019 EVMS London Olympics 2012_David_Birch
9/27
9
Some Programme Statistics
9,000 construction workforce on the Olympic Park site at peak
Demolition of more than 220 buildings
1.5 million cubic metres of soil excavated (enough to fill more than 7
Wembley Stadiums), cleaned where necessary and re-used on Park
Two 6km tunnels and 200km of underground cabling installed
2.5km of railway sidings being decommissioned and cleared from the
centre of the Olympic ParkMore than 30 new bridges spanning rivers and railway lines
2,400 number of piles forming the foundation of the Aquatics Centre
12,000 tonnes of steel contained in the Olympic Stadium the same
weight as 1,558 double-decker buses
Current ODA Budget 7.47bn % complete = 36%
Programme Budget 9.33bn SPI=1.0 CPI=1.1
-
7/27/2019 EVMS London Olympics 2012_David_Birch
10/27
10
The ChallengesA stable but flexible Programme WBS
One data collection structure
Earned Value as the common means of reporting progress over a
diverse programme of projects
Various funding sources and strict budgetary governance
Identification and integration of project interfaces
One week to turn around month end programme results
Programme completion date FIXED
-
7/27/2019 EVMS London Olympics 2012_David_Birch
11/27
11
The Structure - Performance Measurement and Commercial Management
CLM Level 1 Schedule
CLM Level 2 Schedule
Production
Database
Tier 1 Contractor Schedules
Labour (hours and cost)
Equipment
Materials
Supplies
Contracted Services
Transport and Travel
Other
External
DatrabaseResources &
NEC Activity List
Schedule Performance
& Cost Performance
Reports etc.
Detailed EV
and %Complete
Reviewed by
CLM - Summary
Submitted
Actual Cost
(via CLMCert)
COBRA
Earned
Value
Actual
Cost
ODA
Finance(Oracle)
-
7/27/2019 EVMS London Olympics 2012_David_Birch
12/27
Reporting Cycle
-
7/27/2019 EVMS London Olympics 2012_David_Birch
13/27
13
Implementation The System
Industry Standard systems selected and integrated Primavera P6
COBRA Super users for support and training
Robust and reliable IT infrastructure
Started with the WBS & WBS dictionary
Structured approach to breaking down work Allows roll-up from Contractor through project to programme level detail
Ensured use of one coding structure for collection of data to control
schedule and cost baselines
Scope Description, Definition, and Process Flow Diagrams
Created a fit to organisation needs and operations Essential activities were to document and agree (particularly interfaces)
Baseline document issued defining Scope and Budgets
-
7/27/2019 EVMS London Olympics 2012_David_Birch
14/27
14
Implementation Documentation
Procedures Contain mandatory minimums Are fit for purpose
Allow for flexibility at working levels
Capture best practices and lessons learned
Instructions and Guidelines Detailed clarification and guidance
Include worked examples and templates
Training Based on procedures, instructions and guidelines
Mixture of online and interactive resources
Sharing of experiences and lessons learned
-
7/27/2019 EVMS London Olympics 2012_David_Birch
15/27
15
Implementation - Assurance
Monthly Project and Programme reviews
Themed Project and Programme audits (focus on key
processes and/or identified areas of identified weakness)
Progressive collection of lessons learned
Implementation of necessary adjustments to workprocesses from findings
-
7/27/2019 EVMS London Olympics 2012_David_Birch
16/27
16
Implementation The Challenges
People
Appropriate levels of experience in team members
Clear Roles, Responsibilities and Job descriptions
Attention to team mix and team dynamics
Clear team and personal objectives
Incentives for excellent performance
Communications
Clarity of verbal and written briefings and instructions
Multi-level communications driving understanding
Systems
Team and Contractor Training on system set-up and use
-
7/27/2019 EVMS London Olympics 2012_David_Birch
17/27
17
How its working (Recording & Reporting Earned Value)
Quantified Activity Schedule
Records baseline construction quantities and
cumulative progress.
E.g.
# of piles / rakers / seats
m
3
of concreteTonnes of Steel
Tier 1 Contractor Detailed
Schedule
%
Complete
% complete applied against the budget to
calculate Earned Value
-
7/27/2019 EVMS London Olympics 2012_David_Birch
18/27
18
How its working (Recording & Reporting Earned Value)
Tier 1 Contractor Detailed
Schedule
% complete applied against the budget to
calculate Earned Value
-
7/27/2019 EVMS London Olympics 2012_David_Birch
19/27
19
How its working (Recording & Reporting Earned Value)
Tier 1 Contractor Detailed
Schedule
% complete applied against the budget to
calculate Earned Value
Tier 1 Contractor SummarySchedule
rolls
up
CLM Level 2 Schedule
aligns
with
-
7/27/2019 EVMS London Olympics 2012_David_Birch
20/27
20
How its working (Recording & Reporting Earned Value)
CLM Level 2 Schedule
-
7/27/2019 EVMS London Olympics 2012_David_Birch
21/27
21
How its working (Recording & Reporting Earned Value)
CLM Level 2 Schedule
Project Analysis
Monthly Reporting
-
7/27/2019 EVMS London Olympics 2012_David_Birch
22/27
22
Benefits of EV on London 2012
Disciplined approach to measuring performance against a plan
Powerful tool for establishing Trends and giving early warnings
Enabler for Risk identification & implementation of successful
mitigation action plans
Facilitates effective forecasting
Allows roll-up of performance data to programme levels
2% 2% 2%
-
Planned Earned Actual SV () SV (%) CV () CV (%) SPI CPI
Current Period: 1,160 1,160 1,063 0 0.0% 97 9.1% 1.00 1.09
Cumulative: 3,537 3,537 3,313 0 0.0% 224 6.8% 1.00 1.07
Forecast end FY: 3,615 - 3,396
Budget AFC VAC () VAC (%) Committed Remaining Spent % Spent % Complete
At Completion: 220,000 220,000 0 0% 0 220,000 3,313 2% 2%
Budget Item
- Planned Earned Actual SPI CPI BAC AFC VAC
- - Design TBC TBC TBC TBC #VALUE! #VALUE! 13,161 TBC TBC
- - Construction TBC TBC TBC TBC #VALUE! #VALUE! 167,029 TBC TBC
- - ODA Operational TBC TBC TBC TBC #VALUE! #VALUE! - TBC TBC
Delivery Partner TBC TBC TBC TBC #VALUE! #VALUE! 490 TBC TBC
Other TBC TBC TBC TBC #VALUE! #VALUE! 4,320 TBC TBC
TOTAL 2% 3,537 3,537 3,313 1.00 1.07 185,000 185,000 0
- - - - -
- - - - -
- - - - -
- - - -
- - - - -
. .
, .
- .
SCHEDULE / COST PERF. INDEX
-
-
-
-
I
.
.
- ,
,
.
-
-
PROJECT PERFORMANCE / EARNED VALUE
COMMERCIALPlanned %
Complete
Actual %
CompleteActual % Spent
-
-
:
I .
I
,
.
-
-
-
-
.
.
COST SUMMARY
COST DETAIL
% CompleteCumulative At Completion
-
-
-
-
-
-
-
-
-
-
-
-I
0
1,000
2,000
3,000
4,000
5,000
6,000
0
50000000
100000000
150000000
200000000
250000000
Apr-
07
M
ay-
07
Jun-
07
Jul-
07
A
ug-
07
S
ep-
07
Oct-
07
Nov-
07
D
ec-
07
Jan-
08
F
eb-
08
M
ar-
08
0
1,000
2,000
3,000
4,000
5,000
Apr-0
7
May-
07
Jun-
07
Jul-0
7
Aug-
07
Sep-
07
Oct-0
7
Nov-
07
Dec-0
7
Jan-
08
Feb-
08
Mar-0
8
Baseline Budget Earned Value Actual Costs
0.50
0.70
0.90
1.10
1.30
1.50
1.70
1.90
2.10
2.30
Sep-
07
Oct-
07
Nov-
07
Dec-
07
Jan-
08
Feb-
08
Mar
-08
SPI CPI
-
7/27/2019 EVMS London Olympics 2012_David_Birch
23/27
23
Lessons Learned
Dont assume your way of doing things is better, or that it is the
only way
Dont assume employees have all the needed skills
Dont assume that mgmt understand what you are trying to
accomplish
Provide right level of training, including:Customers and stakeholders organisations
Early intervention and training of Contractors team
Establish clear roles and responsibilities, and keep checking
-
7/27/2019 EVMS London Olympics 2012_David_Birch
24/27
24
Lessons Learned
Everyone must work within the WBS structure
Cost collection system fully keyed in by coding
Contractors keyed in at lower levels
Spend the time and resources to get your baseline right it will
minimise heartache down the road
Services and Operations run on Level of Effort, performance
measured with KPIs or other metrics
-
7/27/2019 EVMS London Olympics 2012_David_Birch
25/27
25
Last thoughts
Always try to influence the desired behaviour or decisions,
avoid telling individual or teams what to do
Be careful how and what you set as expectations, you can
always increase them (and make everyone happy)
Above all Keep i t s imple
Good luck, and start thinking of EV as a management tool, it ismuch more than just a reporting method!
-
7/27/2019 EVMS London Olympics 2012_David_Birch
26/27
26
THANK YOU for letting me be part of YOUR morning!!
Your Questions
Your Thoughts
Your Comments
-
7/27/2019 EVMS London Olympics 2012_David_Birch
27/27
27The official Emblem of the London Organising Committee of the Olympic Games
and Paralympic Games Ltd is protected by copyright. London Organising Committee
of the Olympic Games and Paralympic Games Ltd 2007. All rights reserved.
Thank youThank you