    Olympic Delivery Authority*

    Earned Value in the London 2012 Programme

    9 June 2009

    *Prepared by CLM Delivery Partner Limited

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    2/27

    2

    What well cover today

    The Programme

    The Challenges

    The Structure

    How we implemented

    How is it working

    Lessons Learned

    Q & A, and your thoughts

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    3/27

    3

    The Programme

    The Olympic Park

    Site Preparation and Infrastructure

    Venues

    International Broadcast Centre and

    Main Press Centre

    Olympic Village

    Parkwide Projects (Including

    Logistics & Security)

    Off Park Venues

    Transport

    Programme Management

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    4/27

    4

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    5/27

    5

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    6/27

    6

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    7/27

    7

    The Beginning

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    8/27

    8

    How its working

    April 2009

    Nov 2008

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    9/27

    9

    Some Programme Statistics

    9,000 construction workforce on the Olympic Park site at peak

    Demolition of more than 220 buildings

    1.5 million cubic metres of soil excavated (enough to fill more than 7

    Wembley Stadiums), cleaned where necessary and re-used on Park

    Two 6km tunnels and 200km of underground cabling installed

    2.5km of railway sidings being decommissioned and cleared from the

    centre of the Olympic ParkMore than 30 new bridges spanning rivers and railway lines

    2,400 number of piles forming the foundation of the Aquatics Centre

    12,000 tonnes of steel contained in the Olympic Stadium the same

    weight as 1,558 double-decker buses

    Current ODA Budget 7.47bn % complete = 36%

    Programme Budget 9.33bn SPI=1.0 CPI=1.1

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    10/27

    10

    The ChallengesA stable but flexible Programme WBS

    One data collection structure

    Earned Value as the common means of reporting progress over a

    diverse programme of projects

    Various funding sources and strict budgetary governance

    Identification and integration of project interfaces

    One week to turn around month end programme results

    Programme completion date FIXED

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    11/27

    11

    The Structure - Performance Measurement and Commercial Management

    CLM Level 1 Schedule

    CLM Level 2 Schedule

    Production

    Database

    Tier 1 Contractor Schedules

    Labour (hours and cost)

    Equipment

    Materials

    Supplies

    Contracted Services

    Transport and Travel

    Other

    External

    DatrabaseResources &

    NEC Activity List

    Schedule Performance

    & Cost Performance

    Reports etc.

    Detailed EV

    and %Complete

    Reviewed by

    CLM - Summary

    Submitted

    Actual Cost

    (via CLMCert)

    COBRA

    Earned

    Value

    Actual

    Cost

    ODA

    Finance(Oracle)

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    12/27

    Reporting Cycle

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    13/27

    13

    Implementation The System

    Industry Standard systems selected and integrated Primavera P6

    COBRA Super users for support and training

    Robust and reliable IT infrastructure

    Started with the WBS & WBS dictionary

    Structured approach to breaking down work Allows roll-up from Contractor through project to programme level detail

    Ensured use of one coding structure for collection of data to control

    schedule and cost baselines

    Scope Description, Definition, and Process Flow Diagrams

    Created a fit to organisation needs and operations Essential activities were to document and agree (particularly interfaces)

    Baseline document issued defining Scope and Budgets

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    14/27

    14

    Implementation Documentation

    Procedures Contain mandatory minimums Are fit for purpose

    Allow for flexibility at working levels

    Capture best practices and lessons learned

    Instructions and Guidelines Detailed clarification and guidance

    Include worked examples and templates

    Training Based on procedures, instructions and guidelines

    Mixture of online and interactive resources

    Sharing of experiences and lessons learned

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    15/27

    15

    Implementation - Assurance

    Monthly Project and Programme reviews

    Themed Project and Programme audits (focus on key

    processes and/or identified areas of identified weakness)

    Progressive collection of lessons learned

    Implementation of necessary adjustments to workprocesses from findings

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    16/27

    16

    Implementation The Challenges

    People

    Appropriate levels of experience in team members

    Clear Roles, Responsibilities and Job descriptions

    Attention to team mix and team dynamics

    Clear team and personal objectives

    Incentives for excellent performance

    Communications

    Clarity of verbal and written briefings and instructions

    Multi-level communications driving understanding

    Systems

    Team and Contractor Training on system set-up and use

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    17/27

    17

    How its working (Recording & Reporting Earned Value)

    Quantified Activity Schedule

    Records baseline construction quantities and

    cumulative progress.

    E.g.

    # of piles / rakers / seats

    m

    3

    of concreteTonnes of Steel

    Tier 1 Contractor Detailed

    Schedule

    %

    Complete

    % complete applied against the budget to

    calculate Earned Value

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    18/27

    18

    How its working (Recording & Reporting Earned Value)

    Tier 1 Contractor Detailed

    Schedule

    % complete applied against the budget to

    calculate Earned Value

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    19/27

    19

    How its working (Recording & Reporting Earned Value)

    Tier 1 Contractor Detailed

    Schedule

    % complete applied against the budget to

    calculate Earned Value

    Tier 1 Contractor SummarySchedule

    rolls

    up

    CLM Level 2 Schedule

    aligns

    with

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    20/27

    20

    How its working (Recording & Reporting Earned Value)

    CLM Level 2 Schedule

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    21/27

    21

    How its working (Recording & Reporting Earned Value)

    CLM Level 2 Schedule

    Project Analysis

    Monthly Reporting

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    22/27

    22

    Benefits of EV on London 2012

    Disciplined approach to measuring performance against a plan

    Powerful tool for establishing Trends and giving early warnings

    Enabler for Risk identification & implementation of successful

    mitigation action plans

    Facilitates effective forecasting

    Allows roll-up of performance data to programme levels

    2% 2% 2%

    -

    Planned Earned Actual SV () SV (%) CV () CV (%) SPI CPI

    Current Period: 1,160 1,160 1,063 0 0.0% 97 9.1% 1.00 1.09

    Cumulative: 3,537 3,537 3,313 0 0.0% 224 6.8% 1.00 1.07

    Forecast end FY: 3,615 - 3,396

    Budget AFC VAC () VAC (%) Committed Remaining Spent % Spent % Complete

    At Completion: 220,000 220,000 0 0% 0 220,000 3,313 2% 2%

    Budget Item

    - Planned Earned Actual SPI CPI BAC AFC VAC

    - - Design TBC TBC TBC TBC #VALUE! #VALUE! 13,161 TBC TBC

    - - Construction TBC TBC TBC TBC #VALUE! #VALUE! 167,029 TBC TBC

    - - ODA Operational TBC TBC TBC TBC #VALUE! #VALUE! - TBC TBC

    Delivery Partner TBC TBC TBC TBC #VALUE! #VALUE! 490 TBC TBC

    Other TBC TBC TBC TBC #VALUE! #VALUE! 4,320 TBC TBC

    TOTAL 2% 3,537 3,537 3,313 1.00 1.07 185,000 185,000 0

    - - - - -

    - - - - -

    - - - - -

    - - - -

    - - - - -

    . .

    , .

    - .

    SCHEDULE / COST PERF. INDEX

    -

    -

    -

    -

    I

    .

    .

    - ,

    ,

    .

    -

    -

    PROJECT PERFORMANCE / EARNED VALUE

    COMMERCIALPlanned %

    Complete

    Actual %

    CompleteActual % Spent

    -

    -

    :

    I .

    I

    ,

    .

    -

    -

    -

    -

    .

    .

    COST SUMMARY

    COST DETAIL

    % CompleteCumulative At Completion

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -I

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    0

    50000000

    100000000

    150000000

    200000000

    250000000

    Apr-

    07

    M

    ay-

    07

    Jun-

    07

    Jul-

    07

    A

    ug-

    07

    S

    ep-

    07

    Oct-

    07

    Nov-

    07

    D

    ec-

    07

    Jan-

    08

    F

    eb-

    08

    M

    ar-

    08

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    Apr-0

    7

    May-

    07

    Jun-

    07

    Jul-0

    7

    Aug-

    07

    Sep-

    07

    Oct-0

    7

    Nov-

    07

    Dec-0

    7

    Jan-

    08

    Feb-

    08

    Mar-0

    8

    Baseline Budget Earned Value Actual Costs

    0.50

    0.70

    0.90

    1.10

    1.30

    1.50

    1.70

    1.90

    2.10

    2.30

    Sep-

    07

    Oct-

    07

    Nov-

    07

    Dec-

    07

    Jan-

    08

    Feb-

    08

    Mar

    -08

    SPI CPI

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    23/27

    23

    Lessons Learned

    Dont assume your way of doing things is better, or that it is the

    only way

    Dont assume employees have all the needed skills

    Dont assume that mgmt understand what you are trying to

    accomplish

    Provide right level of training, including:Customers and stakeholders organisations

    Early intervention and training of Contractors team

    Establish clear roles and responsibilities, and keep checking

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    24/27

    24

    Lessons Learned

    Everyone must work within the WBS structure

    Cost collection system fully keyed in by coding

    Contractors keyed in at lower levels

    Spend the time and resources to get your baseline right it will

    minimise heartache down the road

    Services and Operations run on Level of Effort, performance

    measured with KPIs or other metrics

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    25/27

    25

    Last thoughts

    Always try to influence the desired behaviour or decisions,

    avoid telling individual or teams what to do

    Be careful how and what you set as expectations, you can

    always increase them (and make everyone happy)

    Above all Keep i t s imple

    Good luck, and start thinking of EV as a management tool, it ismuch more than just a reporting method!

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    26/27

    26

    THANK YOU for letting me be part of YOUR morning!!

    Your Questions

    Your Thoughts

    Your Comments

  • 7/27/2019 EVMS London Olympics 2012_David_Birch

    27/27

    27The official Emblem of the London Organising Committee of the Olympic Games