Client: Evergreen Community Power Locaon: Reading, Pennsylvania Compleon Date: August 2009 Project Summary: ESI performed the balance of the plant engineering for the complete new installation of a circulating fluidized bed boiler system firing biomass to make both power and process steam for sale across the fence to an adjacent Paper Mill. The project included the installation of a 325,000 pph circulating fluidized bed boiler and a nominal 30 MW steam turbine generator. The facility design included complete scope of supply for the material handling, ash handling, waterside auxiliaries, water treatment, air quality control systems, and electrical and piping tie-ins. ESI developed the purchase orders for all auxiliary equipment and bid packages to scope their installation. In addition to the engineering, ESI was the construction manager and scheduler for the project. 30 MW Wood-Fired Cogeneration Facility EVERGREEN COMMUNITY POWER Design/Build Engineers & Contractors, Specialist in Steam and Cogeneration Systems ESI Inc. of Tennessee 770.427.6200

Upload: others

Post on 11-Dec-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EVERGREEN COMMUNITY POWER...included complete scope of supply for the material handling, ash handling, waterside auxiliaries, water treatment, air quality control systems, and electrical

Client:Evergreen Community PowerLocation: Reading, PennsylvaniaCompletion Date:August 2009

Project Summary:ESI performed the balance of the plant engineering for the complete new installation of a circulating fluidized bed boiler system firing biomass to make both power and process steam for sale across the fence to an adjacent Paper Mill. The project included the installation of a 325,000 pph circulating fluidized bed boiler and a nominal 30 MW steam turbine generator. The facility design included complete scope of supply for the material handling, ash handling, waterside auxiliaries, water treatment, air quality control systems, and electrical and piping tie-ins. ESI developed the purchase orders for all auxiliary equipment and bid packages to scope their installation. In addition to the engineering, ESI was the construction manager and scheduler for the project.

30 MW Wood-Fired Cogeneration Facility

EVERGREEN COMMUNITY POWER

Design/Build Engineers & Contractors, Specialist in Steam and Cogeneration SystemsESI Inc. of Tennessee 770.427.6200