EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 1
Project Summary
*The Campus Construction Map PDF is linked to each map identification number, click the number on the map to view the corresponding project summary.
■ Map Identification No: 1 Project Name: Evanston Water Treatment Plant Upgrade Project Scope: Install new water filtration equipment
Project Highlights: Potential for disrupted traffic patterns based upon crane
activity on Lincoln Avenue
Important Dates: Project starts in early April and will continue to end of May. It will resume in early September and continue until late November.
Contact Information: All inquires to be directed to City of Evanston 847.328.2100
■ Map Identification No: 2 Project Name: SPAC Pool Interior Project Scope: Restoration of pool area which includes structural, tile,
and plumbing repairs. In the process we will replace interior deteriorating doors and hardware.
Project Highlights: Improved pool surface and deck
Important Dates: Start date July 22nd occupancy date September 9th
Contact Information: Paul Zack
[email protected] 847.815.4714
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 2
■ Map Identification No: 3 Project Name: Patten Gym Exterior Façade Repairs Project Scope: Renovating structural steel and façade in and around
gymnasium Project Highlights: Historic preservation
Important Dates: June 20, 2011 – fall quarter
Contact Information: Dave Grosskopf
Cell: 847.815.1601 [email protected]
■ Map Identification No: 4 Project Name: Gergle/Rader Lab in Francis Searle Project Scope: Minor internal remodeling
Project Highlights: To provide a functional space for new research.
Important Dates: Start date yet to be confirmed
Contact Information: Andrew McGonigle Cell: 847.815.4738 [email protected]
■ Map Identification No: 5 Project Name: Cook Project Scope: Misc Interior Lab Projects
Project Highlights: None
Important Dates: Schedule to be determined
Contact Information: Kit Ramos
Cell: 847.815.4718 [email protected]
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 3
■ Map Identification No: 6 Project Name: Seeley G. Mudd Library Curtain Wall Repairs Project Scope: Remove and replace specified vision glass
Project Highlights: Replace deteriorating glass
Important Dates: Start construction May 23, project completion at the end
of July
Contact Information: Paul Zack Cell: 847.815.4714 [email protected]
■ Map Identification No: 7 Project Name: Mudd Library Collaboration Space 2nd Floor Interior
Remodeling
Project Scope: 2nd floor interior renovation, new carpet, ceilings, lighting, and furniture
Project Highlights: None
Important Dates: Construction to start June 20th, project completion before September 1st
Contact Information: Elena Romero Jensen Cell: 847.815.7875 [email protected]
■ ■ Map Identification No: 8 Project Name: Tech Infill B/C Wing Project Scope: Construct a 50,000 gross square foot, 6 story addition to
the Tech Institute.
Project Highlights: 3 story atrium
Important Dates: Tech Drive will be closed until August 2012
Contact Information: Quentin Bruhn Cell No. 847-815-4728
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 4
■ Map Identification No: 9 Project Name: Tech Infill F-wing Renovations Project Scope: Reconfigure Tech-1 F-wing Physics faculty and staff
offices
Project Highlights: New Physics department offices
Important Dates: Scope and schedule to be determined
Contact Information: Robert Carlton 847.815.4744 [email protected]
■ Map Identification No: 10 Project Name: Tech Infill F/G wing Project Scope: Construct a 50,000 gross square foot, 6 story addition to
the Tech Institute.
Project Highlights: 3 story atrium and chip fabrication clean room
Important Dates: Tech Drive will be closed until August 2012
Contact Information: Quentin Bruhn Cell No. 847-815-4728 [email protected]
■ Map Identification No: 11
Project Name: North Campus Chilled Water Lines Project Scope: New underground infrastructure including 30 inch chilled
water supply and return piping will be installed from the Central Utility Plant running northeast past Cook Hall and terminating north of Mudd Library. The project is also planned to include new steam and condensate lines.
Project Highlights: These new utilities are planned to serve current and future north campus development.
Important Dates: The project is scheduled to start immediately after Commencement, June 20th, 2011 and to be completed by March 2013.
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 5
The Campus Drive road closure near Pancoe designated by the area shown on the Construction Map is anticipated to be closed from June 20th, 2011 through March 2012.
More construction impact updates to follow as project progresses.
Contact Information: Kory Burton Cell: 847.815.4746 [email protected]
■ Map Identification No: 12 Project Name: Allen Center Atrium Renovation Project Scope: Meeting Room Windows above east atrium and east
elevation façade repairs
Project Highlights: Completion of barrier wall system for east atrium renovations
Important Dates: April 24th – May 25th
Contact Information: Dave Grosskopf 847.815.1601 [email protected]
■ Map Identification No: 13 Project Name: Silverman Hall Cryo EM Lab Project Scope: Renovate a 600 square foot lab for a Cryo Electron
Microscope.
Project Highlights: The space will be humidity minimized, vibration controlled, EM shielded, air flow minimized and sound controlled.
Important Dates: The construction work will complete about 10 June. The microscope will take two months to build.
Contact Information: Quentin Bruhn Cell: 847-815-4728 [email protected]
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 6
■ Map Identification No: 14 Project Name: North Campus Chilled Water Lines Project Scope: New underground infrastructure including 30 inch chilled
water supply and return piping will be installed from the Central Utility Plant running northeast past Cook Hall and terminating north of Mudd Library. The project is also planned to include new steam and condensate lines.
Project Highlights: These new utilities are planned to serve current and future north campus development.
Important Dates: The project is scheduled to start immediately after Commencement, June 20th, 2011 and to be completed by March 2013.
The parking lot west of the Allen Center is planned to be closed for the duration of the project, and is being planned by another project to be converted to a more pedestrian friendly space.
More construction impact updates to follow as project progresses.
Contact Information: Kory Burton Cell: 847.815.4746 [email protected]
■ Map Identification No: 15 Project Name: Central Utility Plant to Norris Underground Steam Piping
Replacement Project Scope: Replace underground steam and condensate piping Project Highlights: Street east of Central Utility Plant will be closed for about
two months. The cooling pond water level will be lowered as part of the project.
Important Dates: This project is scheduled to start June 20th, completed
by Labor Day 2011. Contact Information: Karl Wolff Cell: 847.815.4679 [email protected]
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 7
■ ■ Map Identification No: 16 Project Name: Norris Replace Chilled Water Coil Sections S8/9
Project Scope: Replace chilled water coil section in air handling unit
S8/9, condensate pumps, and doors for air handling units.
Project Highlights: North Side of Norris will be used for one day to lift
equipment to roof.
Important Dates: Fan coil section will be lifted in October/November to roof; other work will be done this summer
Contact Information: Karl Wolff Cell: 847.815.4679 [email protected]
■ Map Identification No: 17
Project Name: Swift Annenberg Utility Tunnel Replacement Project Scope: Replacement of tunnel
Project Highlights: Temporary lane closure
Important Dates: Schedule to be determined Contact Information: Paul Zack
Cell: 847.815.4714 [email protected]
■ ■ Map Identification No: 18 Project Name: Swift Hall & Cresap Project Scope: Swift Hall Window Repairs, Green house roof enclosure
Project Highlights: Historic Preservation
Important Dates: June 20th – fall quarter
Contact Information: Charles Davidson
Cell: 847.815.9367 [email protected]
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 8
■ Map Identification No: 19 Project Name: Internal Service Road Reorganization Project Scope: Construction of new service road to accommodate
Evanston fire trucks in conjunction with the new traffic lights installed at the Garrett Parking lot
Project Highlights: New roadway construction and surrounding landscaping, will provide more green space around Kellogg and Lunt
Important Dates: Starts immediately after commencement and finishes prior to student return in the fall
Contact Information: Andrew McGonigle Cell: 847.815.4738
■ ■ Map Identification No: 20 Project Name: Garrett Traffic Lights Project Scope: Installation of new set traffic lights and reconfiguration of
Entrance C, commonly know as the Garret Parking Lot to provide a safer pedestrian/vehicle crossing point. A new left turn only lane will be installed on the parking lot side to enable a smoother traffic flow. Pedestrian countdown signals will be installed as part of the project and a new designated crosswalk installed to improved pedestrian safety when crossing Sheridan Road.
Project Highlights: The new entrance will be configured on the existing north driveway. The south driveway will remain open during construction but be two way, single lane traffic. Once the new entrance is completed, the south entrance will be closed and regraded and landscaped.
Important Dates: The project is scheduled to start immediately after commencement, June 20th, 2011 and be completed by Labor Day of 2011
Contact Information: Andrew McGonigle Cell: 847.815.4738
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 9
■ Map Identification No: 21 Project Name: Interior Renovation of 1918 and 1922 Sheridan Project Scope: 1st floor carpet, furniture, bathroom renovation, and
lighting
Project Highlights: None
Important Dates: June 20th – September 1st
Contact Information: Elena Romero Jensen Cell: 847.815.7875 [email protected]
■ ■ Map Identification No: 22 Project Name: Foster Walker Miscellaneous Projects Project Scope: Roof replacement, switchgear refurbishment, fan coil
replacement, upgrade fire alarm Project Highlights: West Courtyard will be used for staging area
Important Dates: June 20th – fall quarter
Contact Information: Rob Wikstom Cell: 847.863.2907 [email protected]
■ Map Identification No: 23 Project Name: Scott Hall Project Scope: Exterior Façade Exploratory work and window mock up
Project Highlights: Historic Preservation
Important Dates: June 20th – fall quarter
Contact Information: Dave Grosskopf
Cell: 847.815.1601 [email protected]
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 10
■ ■ Map Identification No: 24
Project Name: Alice Millar to Underground Storage Underground Steam Piping Replacement
Project Scope: Replace underground steam and condensate piping.
Project Highlights: The south entrance of Harris and west entrance of
Fairchild West are within the construction area and can not be used.
Important Dates: This project is scheduled to start July 5th and to be completed by Labor Day
Contact Information: Karl Wolff Cell: 847.815.4679 [email protected]
■ ■ Map Identification No: 25 Project Name: 1856 Orrington Project Scope: Interior Renovation and external site work
Project Highlights: Total building systems replacement, ADA ramp
Important Dates: Demolition start April 7, completion August 31, 2011
Contact Information: Steve Matz Cell: 847.406.9038 [email protected]
■ ■ Map Identification No: 26 Project Name: Allison Hall Residential Community Project Scope: Internal remodeling, mainly on the 1st floor to upgrading
the building to Residential community status.
Project Highlights: New lounge, seminar room with Faculty and Area Coordinator Apartments. New finishes on upper floors. The northern portion of the 619 Clarke Street parking lot will be used as a staging area for the project.
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 11
Important Dates: Starts immediately after commencement and to be completed before students return in September.
Contact Information: Steve Matz Cell: 847.815.9038 [email protected]
■ Map Identification No: 27 Project Name: Crown Driveway Replacement Project Scope: Parking lot repairs Project Highlights: One lane traffic
Important Dates: Weekend project mid-June dates to be determined
Contact Information: Paul Zack
Cell: 847.815.4714 [email protected]
■ Map Identification No: 28 Project Name: 1835 Hinman Avenue, dormitory upgrade Project Scope: To construct a new staff apartment on the 1st floor, east
wing
Project Highlights: A new staff apartment similar in content to those in Elder and Allison Halls
Important Dates: Project start summer 2011 and complete fall 2011
Contact Information: Andrew McGonigle Cell: 847.815.4738
■ Map Identification No: 29 Project Name: Sheridan Road/Forest Avenue Rehabilitation Project Project Scope: The improvement of Sheridan Road from South
Boulevard to Isabella Street. It also includes a segment of Forest Avenue from Main Street just south of Church Street, and the segments of Burnham Place and Main Street between Sheridan Road and Forest Avenue.
EVANSTON CAMPUS CONSTRUCTION MAP 2011
REVISED 6.2.2011 12
Project Highlights: “Local Access Only” will be maintained to the Northwestern University South Campus Drive. Construction zone “No Parking” at any time restrictions will be in effect for the duration of the project. To get to South Campus Drive follow the local access only signs.
Important Dates: Stage 5 construction will begin the week of April 4th with completion anticipated mid August 2011.
Contact Information: Sat Nager 847.886.2967
For more information: http://www.cityofevanston.org/assets/Sheridan‐Road‐Project‐Newsletter‐April‐2011.pdf