european green cars initiative projects helios proposal paper (july 2012)
DESCRIPTION
European Green Cars Initiative Projects- Helios Presentation with the objectives of Evaluate the performances of 4 positive electrode (NCA, LMO blend, LFP & NMC/ Graphite anode) Comparative assessment of Performance (12- 15 months cycling tests) life, cost, recycling and safety characteristicsTRANSCRIPT
F DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
PROPRIETE RENAULT
High Energy Lithium-Ion Storage Solutions
Frédérique DEL CORSO
Project coordinator - RENAULT SAS
ac
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Project presentation
Project full title: High Energy Lithium-Ion Storage SolutionsCoordinator: Frédérique DELCORSO (Renault)
Partners:
Starting Date: Nov 2009Ending Date: oct 2012 � amendment to oct 2013
Budget Total/Funding: 4,17 MEUR / 2,77 MEURHome page : http://www.helios-eu.org/
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
UU
RWTH-ISEA & IME2 Universities
ENEA
CEA
INERIS
CNRS - LRCS
ZSWAIT
6Research Institutes
JCHaR
Umicore
SAFT
EDF
4 Industries
PCA
Renault
Volvo
Ford
Adam Opel AG
CRF
6 OEM
HELIOS consortium : 18 partners from 6 member states
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Motivation
� Understand the causes of ageing mechanisms (cycling and post-mortem analysis) among 4 chemistries :
� NCA (LiNiCoAl)/ C-Graphite (SAFT –reference)
� LFP (LiFePO4) / C-Graphite
� LMO blend (LiMn2O4-NCA) / C-Graphite
� NMC (LiNiMnCo) / C-Graphite
for EV (electric vehicle),
HEV (Hybrid EV) &
PHEV (Plug-in EV) applications .
NCA : Lithium Nickel Cobalt AluminiumNMC : Lithium Nickel Manganese Cobalt LMO : Lithium Manganese spinel LFP : Lithium Iron Phosphate
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Objectives
� Evaluate the performances of 4 positive electrode ( NCA, LMO blend, LFP & NMC/ Graphite anode)
� Manufacturing 280 large cell formats (~40 Ah) – 70 per technology
� Propose safety & life test procedures for High Energy battery cells used in European context
� Comparative assessment of Performance (12- 15 monthscycling tests) life, cost, recycling and safety characteristics
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
WORK PACKAGE structure
WP5 : Electrical Characterisation of
HE cells (cycling, calendar) (EDF)
WP
8 :
Re
cycl
ing
Fe
asi
bil
ity
Stu
dy
(RW
TH
-IM
E)
WP
7 :
Eco
no
mic
al
Ass
ess
me
nt
(PS
A)
WP 6 : Safety tests
(INERIS)
WP1 : Management / Coordination (RENAULT)WP1 : Management / Coordination (RENAULT)
WP 2 : Ageing
review,
charactrerisation
and interpretation
of results (LRCS)
WP 3 : Specifications and
testing procedures
(OPEL)
WP 4 : Manufacturing of
High Energy Cell
(SAFT)
START
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Main results : WP2 (Ageing analysis, post mortem analysis)
� 2.1Bibliographic review on ageing mechanisms� Graphites
� Positive Electrodes
� Electrolyte ageing
� interfaces, characterization techniques
� 2.2 Post-mortem analysis : initial , intermediate (6 mo nths) & final characterization of electrode materials (SEM, Electrochemical measurement, XRD, DSC, Mass spectrometry, XPS )
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Main results : WP3 (Cell specification and test procedures )
� 3.1 - Target specification for a High Energy cell sui ted for EV, PHEV and/or HEV-APU applications
� 3.2 - Performance, ageing and cycling test procedure ���� inputs for WP5
� 3.3 -safety test procedures (mechanical, electrical and thermal abuseconditions) ���� inputs for WP6
� 3.4 : coordination with ISO, VDA & USABC.
���� activities achieved end of october 2012
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Main results : WP4 (High energy cell manufacture )
� 4.1 : Material selection for NMC, LFP, LMO
� 4.2 : Build of small sample cells (4/5 A), 12 cells per technology
� 4.3: up-scale study
� 4.4 : Manufacture and delivery of large cells (~40 Ah) to test institutes : 70 cells per technology
Delivery delayed : 10-12 months
All the activities have been performed � WP4 « closed »
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Main results : WP5 (Electrical performance testing)
� Cycling tests (15 months):� EV type profile : SOC 100% - 20% Imax ~1.25C (50A) @30 – 45°C
� PHEV type profile : SOC 95-25% Imax ~ 5C (200A) @ 30- 45°C
� Calendar tests (12-15 months) : storage at 45 – 60°C , 100%SOC
� Different Characterisation tests :� Complete Characterisation every 6 months,� Quick Characterisation : every 6 weeks
� Already 6- 14 months of tests performed
Helios Resumé EV Cycling Profile B 30°C 80%DOD
60
65
70
75
80
85
90
95
100
0 100 200 300 400 500 600 700 800 900 1000 1100 1200100% Cycles nom
(accumulated discharge capacity of 80%DOD cycles di vided by nominal capacity)
SO
Hac
t in
%
NCA 12 NCA 09 NCA 05 NCA 01 LMO 03 LMO 04 LMO 05 LMO 08
NMC 11 NMC 06 NMC 03 NMC 09 LFP 07 LFP 09 LFP 08 LFP 10
LMO
NMC
LFP
NCA cycle week 44
LFP
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Main results : WP6 (Safety and abuse testing )
� 6.1 bibliographical study of thermal ‘runaway’ mech anisms in lithium battery systems,
� 6.2 : Definition of safety test recommendations, ba sed on WP3 specifications
� 6.3 Thermal stability tests on 0.5 Ah cells� 6.4 : Safety tests on 40 Ah cells (running)
o Controlled crush (Radial and axial )o Penetration (nail)o Thermal stability (ARC)o Simulated Fuel Fire (Beginning of Life)o Elevated temperature Storage (2 months) @ SoC = 20, 50%o Rapid charge / dischargeo Thermal Shock Cycling (from -40 °°°°C / + 75 °°°° C)o Overchargeo Short circuito Over discharge
Crush test(radial)
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Main results : WP7 (Economical assessment)
� 7.1 : Cost assessment for Active materials
� 7.2 : Cost assessment for cells
� 7.3 : extrapolation to the pack level cost
According 3 levels of annual manufacturing volumes :- Low quantity : cells quantity equivalent to 50 000 veh / year (41 Ah),
- Mid quantity : cells quantity equivalent to 100 000 / year (41 Ah),
- High quantity : cells quantity equivalent to 200 000 / year (41 Ah).
���� activities achieved end of october 2012
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Main results : WP8 (Recycling assessment )
� 8.1 : Study of the potentially most appropriate pro cesses, involving a range of techniques from the least costly but yie lding the lowest quantity of recycled material up to the most expens ive process (cell de-activation + mechanical separation+ agglomeratio n before pyro-metallurgical or hydro-metallurgical treatment), yi elding the most usable material.
� 8.2 at cell level
� 8.3 extrapolation to pack level+ Life Cycle Analysi s
� ���� activities achieved end of october 2012.
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Milestone plan
* Delay of 9 -12 months to deliver cells according the technologies (selection of materials longer than expected, delay of raw materials supply from Japan, change of production site for LFP…)* Problem of process for LMO (only 50 cells available) and NMC (2 batches were necessary)
Kick-offDelivery of small cells
(0.5 Ah)
Nov2009
Dec2010
Dec2011
June2011
Oct2012
Cycling,calendar &safety tests
Mid-termreport
Delivery of 4*70 cells (40Ah)
Final assessments
on performance, recyclability, cost, safety &
ageingmechanisms
AMENDMENT
Oct2013
Safetyresults &
post-mortem interm.
intermediate report
meetingMMMM
MMMM MMMM MMMM MMMM MMMMMMMM
MMMM
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Overall progress
� M18 mid term report submitted on time (june 2011)
� 18 deliverables submitted, 4 are late (draft versi on), 5 are postponed (due to late delivery of cells)
� Delivery of 70 (40 Ah) cells per technology by SAFT
� Start of cycling and calendar tests (6-14 months alreadyperformed)
� Abuse tests of small & large cells achieved.
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Next steps, future activities
� End of cycling tests
� Economical assessment
� Recycling study (at cell, pack level)
� Interpretation of the ageing results (post-mortem analysis)
� Dissemination
� 2nd intermediate report : end october 2013
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Exploitation potential
� HELIOS results would influence the choice and the integration of the best technologies on reliable, safe, cost and recyclability points of view, in vehicles (VE, PHEV) or trucks (HEV-APU) that will contribute to reduce the CO2 emissions .
� Specification of Common European procedures (Cycling & safety) for High Energy Li-ion batteries ���� inputs in European standards.
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Cooperation within the cluster
Testing procedures, Cost assessment
EUROLIION
recycling
PROPRIETE RENAULTF DELCORSO – RENAULT SAS 3d European Green Cars Initiative ProjectsClustering Event – 12th July 2012
Thanks for your attention
� For additional information,http://www.helios-eu.org
+33 1 768 57 598