Estimating Estimating
PS&E – Plans, specifications and estimate
1
![Page 2: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/2.jpg)
Types of Estimates Types of Estimates
Ball-Park (Planning phase)
Preliminary (Design Report/EIS)
Detailed (PS&E---Detailed Design)
2
![Page 3: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/3.jpg)
Estimate QualityEstimate Quality
Good book-keepingAccurate backup of quantitiesFamiliarity w/ projectExperience
3
![Page 4: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/4.jpg)
4
![Page 5: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/5.jpg)
Estimating ProcedureEstimating Procedure
List all item numbers-plans and similar plans
Estimate quantities and prepare a backup for each item #
Assign prices to each item (WAIPR) Lump sum price analysis Summary of quantities Add contingency Summarize final costs
5
![Page 6: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/6.jpg)
Item NumbersItem NumbersReferenced to spec bookExamples:
◦201.07 Clearing and Grubbing◦203.xxxx Grade and Reshape
Ditches◦304.xx Subbase◦610.0203 Establish Turf◦634.01 Survey and Stakeout
*Special specifications—General or Special (must be approved)
6
![Page 7: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/7.jpg)
UnitsUnitsUnit abbreviations
Definition
LS Lump Sum
EA Each
CY Cubic Yard
SY Square Yard
LF Linear Feet
TN Ton
MO Month
7
![Page 8: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/8.jpg)
Units-MetricUnits-MetricUnit abbreviations
Definition
CM Cubic Meters
SQM Square meters
MT Metric Ton
KG Kilograms
M Meters
8
![Page 9: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/9.jpg)
SpecificationsSpecificationshttps://www.dot.ny.gov/main/
business-center/engineering/specifications
9
![Page 10: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/10.jpg)
Pay Item CatalogPay Item Catalog
https://www.dot.ny.gov/pic
10
![Page 11: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/11.jpg)
Weighted Average Item Price Weighted Average Item Price Report (WAIPR)Report (WAIPR)
https://www.dot.ny.gov/divisions/engineering/design/dqab/waipr
11
![Page 12: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/12.jpg)
Special Spec RepositorySpecial Spec Repository
https://www.dot.ny.gov/spec-repository-us/
12
![Page 13: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/13.jpg)
ContingencyContingencyAdded to estimate to account for
unknowns Usually a percentage of final cost
13
![Page 14: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/14.jpg)
Cost Estimate ExampleCost Estimate ExampleItem # Description Unit QTY Price Subtotal
201.0601 Clear & Grub LS 1.0 $12,500.00
$12,500.00
203.0100 Earth Cut & Emb
CY 14,545.0
$12.00 $174,540.00
10209.0100
Bale Dikes LF 42.0 $7.50 $315.00
403.1100 Asph Base Course
TN 6392.0 $38.00 $242,896.00
603.7303 24” RCP End Sec
EA 4.0 $700.00 $2,800.00
637.0701 Office MO 6 $1,000.00
$6,000.00
645.2140 Traffic Sign EA 8 $170.00 $1,360.00
14
![Page 15: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/15.jpg)
Backup for Estimate ExampleBackup for Estimate ExampleITEM 640.0102 (White Paint Reflective Paint ITEM 640.0102 (White Paint Reflective Paint Stripes)Stripes)2 Shoulder StripesSta 26+44 to Sta 30+922*448’ = 896’Say 900’
15
![Page 16: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/16.jpg)
Asphalt – English TonsAsphalt – English Tons.06865 Tons per Cubic Foot (Base).07525 Tons per Cubic Foot (Binder).07265 Tons per Cubic Foot (Top-
6F)
Old Marshall Design
New Superpave?????
16
![Page 17: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/17.jpg)
Lump Sum Price AnalysisLump Sum Price AnalysisEstimate for items paid as a “Lump
Sum”
Includes:◦ Labor◦ Materials◦ Equipment◦ Rental costs◦ Profit and Overhead
Typical lump sum items:◦ Clearing and Grubbing◦ Survey and Stakeout◦ Temporary Traffic Signals
17
![Page 18: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/18.jpg)
Lump Sum Analysis ExampleLump Sum Analysis ExampleItem 619.13 (Temporary Traffic Item 619.13 (Temporary Traffic Signal)Signal) Labor Costs
◦ Backhoe Operator-$30.05/hr
◦ Electrician-$32.99/hr
◦ Laborer-$22.95/hr
Prevailing Wages http://wpp.labor.state.ny.us/wpp/publicViewPWChanges.do?method=showIt
Installation and Removal of Temp. Poles◦ 1 Backhoe Operator $30.05/hr * 16 hours =
◦ 2 Laborers @ $22.95/hr * 16 hours =
Installation and Removal of Temp. Signal Heads◦ 1 Electrician @ $32.99/hr * 16 hours =
◦ 2 Laborer@ $22.95/hr * 16 hours =
Installation and Removal of Controller◦ 1 Electrician @ $32.99 * 16 hours =
◦ 1 Laborer @ $22.95 * 16 hours =
18
![Page 19: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/19.jpg)
Lump Sum Analysis Lump Sum Analysis Example-Cont.Example-Cont.Item 619.13 (Temporary Traffic Item 619.13 (Temporary Traffic Signal)Signal) Materials
◦ Temporary Poles 4 @ $1,300.00 each
◦ Temporary Signal Heads 4 @ $250.00 each
◦ Controller, Fixed Time 1@ $1,000.00
◦ Misc. Hardwire and Wire $1,000.00
Equipment (Installation and Removal)
◦ 1 Bucket Truck @ $18.00/hr * 24 hours
◦ 1 Backhoe @ $35.00/hr * 24 hours
Profit and Overhead (20%)
19
![Page 20: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/20.jpg)
Estimate SharesEstimate Shares
Highway BridgeUtilitiesDifferent Counties
20
![Page 21: Estimating PS&E – Plans, specifications and estimate 1](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ef45503460f94c06b27/html5/thumbnails/21.jpg)
Engineer’s EstimateEngineer’s Estimate
Quantities included in plans
Engineer’s estimate not given to contractor
Prices not available to contractor—each contractor provides their own bid
Lowest bidder gets the contract21