Prof Awad S. Hanna

ESTIMATING

EARTHWORK

Page 2: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Estimating Earthwork Earthwork includes:

1. Excavation

2. Grading: Moving earth to change

elevation

3. Temporary shoring

4. Back fill or fill: Adding earth to raise grade

5. Compaction: Increasing density

6. Disposal

Page 3: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Productivity Factors

A. Job conditions

Material type

Water level and moisture content

Job size

Length of haul

Haul road condition (accessibility and load

restrictions)

Page 4: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Productivity Factors (cont.)

B. Management conditions

Equipment conditions and maintenance

practices

Skills of work force and management

Planning, supervision and coordination of

work.

Page 5: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Job Efficiency Factors for

Earthmoving Operations

Job Condit ions** Excellent Good Fair Poor

Excellent 0.84 0.81 0.76 0.70

Good 0.78 0.75 0.71 0.65

Fair 0.72 0.69 0.65 0.60

Poor 0.63 0.61 0.57 0.52

Management Condit ions*

Page 6: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Units of Measure

Cubic Yard (bank, loose, or

compacted) Bank (BCY): Materials in it s natural

state before disturbance

(in-place, in-sit u)

Loose (LCY): Material t hat has been

compacted or disturbed

or loaded

Compacted (CCY): Material aft er compact ion

Page 7: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

1.0

1.25

0.90

1.0 CUBIC YARD IN NATURAL CONDITION (IN-PLACE YARD)

1.25 CUBIC YARD AFTER DIGGING (LOOSE YARDS)

0.90 CUBIC YARD AFTER COMPACTED (COMPACTED YARDS)

In place Compacted Loose

Page 8: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Volume Bank: VB

Bank cubic yards (BCY)

Density B Lb /BCY

Loose: Vl

Loose cubic yards (LCY)

Density L Lb/LCY

Compacted: Vc

Compacted cubic yards (CCY)

Density C LB/CCY

Page 9: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Swell:

A soil increase in volume when it is excavated.

Swell (%) = ( - 1) x 100

Load factor =

Bank Volume = Loose volume x Load

factor

Loose density

Bank density

Bank density

Loose density

Page 10: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Shrinkage:

A soil decreases in volume when it is

compacted

Shrinkage (%) = (1 - )

x 100

Shrinkage factor = 1 - Shrinkage

Compacted volume

= Bank volume x Shrinkage factor

Bank density

Compacted density

Page 11: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Approximate Material Characteristics

Material

Loose

(lb/cy)

Bank

(lb/cy)

Swell

(%)

Load

Factor

Clay, dry 2,100 2,650 26 0.79

Clay, wet 2,700 3,575 32 0.76

Clay and gravel, dry 2,400 2,800 17 0.85

Clay and gravel, wet 2,600 3,100 17 0.85

Earth, dry 2,215 2,850 29 0.78

Earth, moist 2,410 3,080 28 0.78

Earth, wet 2,750 3,380 23 0.81

Gravel, wet 2,780 3,140 13 0.88

Gravel, dry 3,090 3,620 17 0.85

Sand, dry 2,600 2,920 12 0.89

Sand, wet 3,100 3,520 13 0.88

Sand and gravel, dry 2,900 3,250 12 0.89

Sand and gravel, wet 3,400 3,750 10 0.91

Exact values will vary with grain size, moisture content,

compaction, etc. Test to determine exact values for specific

soils.

Page 12: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Typical Soil Volume Conversion

Factors Init ial

Soil Type Soil Condit ion Bank Loose Compacted

Clay Bank 1.00 1.27 0.90

Loose 0.79 1.00 0.71

Compacted 1.11 1.41 1.00

Common earth Bank 1.00 1.25 0.90

Loose 0.80 1.00 0.72

Compacted 1.11 1.39 1.00

Rock (blasted) Bank 1.00 1.50 1.30

Loose 0.67 1.00 0.87

Compacted 0.77 1.15 1.00

Sand Bank 1.00 1.12 0.95

Loose 0.89 1.00 0.85

Compacted 1.05 1.18 1.00

Convrted to:

Page 13: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Estimating Earth work for

Trenches and Foundation

Angle of Repose 2’-0” or more

Page 14: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Approximate Angle of Repose For Sloping Sides of Excavation

Original

Ground Line

So

lid R

ock, S

late

or

Cem

en

ted

Sa

nd

an

d G

rave

l

(90

Deg.)

Page 15: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Calculating Earthwork

Quantities

1. End Area Method

2. Contour Line/ Grid Method

Page 16: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

1. End Area Method

Used in sites where length is much

greater than width

Page 17: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

CALCULATING EARTHWORK QUANTITIES

1. End Area Method

a. Take cross-sections at regular intervals,

typically, 100’ intervals.

b. Calculate the cross-section end areas

c. The volume of earthwork between sections

is obtained by taking the average of the end

areas at each station in square feet

multiplied by the distance between sections

in feet and dividing by 27 to obtain the

volume in cubic yards.

Page 18: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Project Site Showing 100 Stations

80

82

84

86

88

A’ B’ C’ D’ E’ F’

A B C D E F

100' 100' 100' 100' 100'

500'

30

0'

Page 19: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

80

78

76

82

80

78

84

82

80

86

84

88

86

90

88

78.5

80.3

82.3

84.2

86.2

88.2

Sec. A’- A

Sec. B’- B

Sec. C’- C

Sec. D’- D

Sec. E’- E

Sec. F’- F

Proj

ect

Cro

ss S

ect

ions

Page 20: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Cross-Section @ A- A

80

79

78

77

76

79.5

78.5

76.7

Section A’- A

Area = = 173.7 193 x 1.8

2

Area = = 53.5 107 x 1.0

2

Page 21: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Cross-Section @ B- B

82

81

80

79

78

81.8

80.3

76.7

Section B’- B

Area = = 189.0 210 x 1.8

2

Area = = 67.5 90 x 1.5

2

Page 22: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Table 1. Cumulative Earthwork

Quantities

Sect ion Emb (CCY) Exc. (BCY) Exc. x B/C

(CCY)

Net Exc.

(CCY)

Cum Exc

(CCY)

A-B 672 224 254 - 418 - 418

B-C 567 441 499 - 68 - 486

C-D 215 791 896 681 195

D-E 0 1031 1167 1167 1362

E-F 0 1222 1384 1384 2746

Page 23: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

2. Contour Line/ Grid Method

Used for parking lots and site “leveling”

Grid size from 10’x10’ to 50’x50’

the greater the terrain variance the

smaller the grid

Page 24: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

2. CONTOUR LINE/GRID CELL METHOD(cont.)

Step l

Determine by visual study of the site drawing if the net total

will be an import (more fill required than cut) an export (less fill

required than cut) or a blend (cut and fill about equal)

Step 2

Determine the pattern of calculation points or grid size.

Step 3

Determine elevations at each calculation location, the corners

of each grid.

Step 4

Calculate the cubic yards of cut or fill required in each grid

cell.

Step 5

Add the individual Grid Cell quantities together to arrive at the

total cut, total fill volume and the import or volume export

yardage required for the job.

Page 25: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

A B C D E F 87.6 88.6 89.4 90.4 91.6 93.2

G H J K L M 87.4 88.2 89.5 90.6 91.6 92.7

N O P Q R S 87.2 87.7 89.0 90.4 91.3 92.0

87.6 88.5 89.3 90.3 91.5 95.0

94.3

93.5

93.1

A B C D E F G 300’

88’ 89’ 90’ 91’ 92’ 93’ 94’

No Scale Notes: 1. Bring the entire site to elevation 90. 2. All grids are 50’x 50’ = 2500 sq. ft. 3. Present contours

Page 26: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Purpose

Grade the entire site to grade 90’

Quick and Dirty

Assume one grid

Existing 90.50

Proposed 90.00

Cut 0.50

Total Cost = = 833CY 150 x 300 x 0.50

27

300'

150' Need

Fill

Need

Cut

90'

90' 91'

90.5'

Page 27: ESTIMATING EARTHWORK - Universiti Teknologi Malaysiacivil.utm.my/shaifulamri/files/2012/09/Basic-Eathwork... ·  · 2015-03-30Prof Awad S. Hanna Estimating Earthwork Earthwork includes:

Prof Awad S. Hanna

Average elevation

=

= 88.08

change = 90-88.08

= 1.92

cut =

= 177.77 CY

and so on.

If we choose the grid size to be 50’x50’

87.6+88.5+87.6+88.6

4

87.6

88.6

87.6 87.6