Guneet | Jasdeep | Manan | Shanu |Akash 1
Enrolment Number Name
2011PGP013 Guneet Singh
2011PGP017 Jasdeep Singh Bhatia
2011PGP024 Manan Jain
2011PGP39 Shanu Fatehpuria
2011PGP057 Akash Mohan
Guneet | Jasdeep | Manan | Shanu |Akash 2
Executive Summary 3
Introduction 4
Study rationale 4
Project scope and Basic assumptions 5
Technical know how resource requirement 7
Foreseable Difficulties and Constraints 8
Work breakdown structure 9
Activity Listhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip10
Responsibility matrix 11
Milestone Pert chart of the proposed Project 12
Project duration and financial Budget 1314
Risks to the proposed project 15
Expected Benefits 16
Risks Mitigation Plan 16
Critical Success Factors and proposed modalities of execution and monitoringhelliphelliphelliphelliphelliphelliphelliphelliphellip17
Limitations 18
Future Scope of Research 18
Lessons learned and difficulties 19
Project Auditing 20
Initiating and Staffing 21
Data Collection and Analysis 21
Reporting 21
Project Closure 22
References 23
Appendix 24
Apendix 1 Audit areas and project stages 24
Appendix 2 Questions 26
Appendix 3 Earned Value 27
Guneet | Jasdeep | Manan | Shanu |Akash 3
The project deals with establishing the first Starbucks Cafeacute in the Indian Subcontinent Establishing a new restau-
rant or a cafeacute in any market is a daunting task since it consists of not only leasing out a space but also meeting
the specifications and the hygiene factors of that country city There are many legal formalities that need to be
completed as well as placing orders for specialized equipment picking out the right deacutecor furnishing fixtures
hiring the appropriate personnel etc Opening a new Cafeacute though being a difficult task provides valuable in-
sights into a field such as project management in terms of the project duration resource requirement budgeting
etc
The objective of the project was to set up the Starbucks Cafeacute at an initial cost of INR 40 lakhs such that the cafeacute
meets the necessary specifications For completing the project resources were allocated critical path was found
out levelling was done to optimize the use of the resources etc The project is scheduled to be completed on time
and within budget ie 33 lakhs
The project proved to be an important learning tool in the application of the concepts learned in the project
management class as well as the use of the tool Microsoft Project which was also taught in class
Guneet | Jasdeep | Manan | Shanu |Akash 4
Introduction
Started in 1971 as a small coffee shop Starbucks today is the largest coffee retailer in the world with over
10000 shops in 30 countries The company wants to establish Starbucks as the most recognized and respected
brand in the world Starbucks relies on retail expansion product innovation and service expansion and has now
decided to target the Indian Market to improve its financial position and market share The new customer culture
emerging in India is reflective of a high probability of the success of Starbucks especially with the first two loca-
tions proposed for the site ie Delhi and Mumbai which are highly reflective of a fast westernized culture
Study rationale
The group decided to take up this project as an external consultant to Starbucks due to the following reasons
The entry of Starbucks in the Indian market is a complex non-routine effort which is limited by time and
money and is performance specific
The project deals with identification and scheduling of resources to complete the task in the given time and
resource frame
Determine the various types of risks and constraints that could be associated with managing a project as
well as how to mitigate and manage the same
Learn about the various compliances needed for opening a restaurant cafeacute in the Indian scenario
It is an opportunity to apply the principles of project management learnt in class as well as the tools for
the same
Guneet | Jasdeep | Manan | Shanu |Akash 5
4 Project Deliverables
The major Deliverables at the end of the project will be
A 1200 square foot finished retail outlet
A fully furnished store with a seating capacity of 20
Kitchen appliances to include an oven dishwasher refrigerator microwave coffee vending ma- chine
coffee grinding machine freezer automated order taking machines
3 Project Description
Starbucks the Seattle based coffee and food company has entered into a joint venture with the Tata Group to
enter the large untapped Indian market There are many factors that support the probability of success for the
firm foremost among them being the new consumer culture of the young India increased urbanization and the
growing pop culture Thus one needs to have a detailed plan for the establishment of the brand in the respec-
tive target markets
This Project Will help them to establish in India leading to creation of prospects for further growth
1 General Information Project Name Launch of Starbucks India
Project ID PR_001 Project Priority High
DepartmentDivision PROJECT MANAGEMENT
Prepared by Group Date (20121014)
2 Project Objectives Establishment of Starbucks Retail Outlet in India
Allocated budget for this project is INR 4000000 and should be completed within one year from the com-
mencement of the project The outlets will be nearly similar to the existing ones outside India Furniture and appli-
ances will be sourced from India No major imports will be involved
5 Milestones
Approval of Layout
Completion of installation of kitchen appliances and technical equipment
Obtaining all approvalsmdashwater waste electricity Income tax etc
Obtaining insurance papers for final evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 6
5 Technical Requirements
Registration under section 17[2] and rule 12[B] of the PFAndash Prevention of Food and Adultera- tion Act
1954 and Shops Establishment Act
Permit from PPL (Phonographic Performance Limited) to play recorded music
License from FSSAI
Eating House License from the police commissioner of the city
NOC from the fire department
Power Backup for 3 hours
6 Limits and Exclusion
Location of the store to be decided by the company
Permits and licenses are subjected to their approval
The stores will be built to the specifications and design approved by the customer initially
Decision of the further subcontractors will completely lie with the project management team
Site work limited to Monday through Friday 800AM to 600 PM
7 Customer Review
Tata Tea amp Starbucks
8 Basic Assumptions
The location of the store will be selected by the company including the locality within the city Thus the
task of the company is limited to setting up a fully functional and working store at the desired location
The project cost will thus vary depending on the rentals of the location
Permits and licenses are subject to approval from the corresponding government authorities Any delays in
getting the license will affect the project schedule However the same will be communicated to the client
accordingly The company will not be liable to any project delays due to delays in obtaining the license
Site work will be limited to weekdays from 8AM to 5PM Local and national holidays will be observed as
per the calendar of the company or the circular issued by the government
The company is free to outsource or subcontract part of its work to a third party without informing the cli-
ent
The store will be built as per the design specifications approved by the customer initially No further
changes in design will be incorporated after the design freeze
The company is just a party in facilitating the process of obtaining licenses and will be done on behalf of
the client
Guneet | Jasdeep | Manan | Shanu |Akash 7
The project would require the management to be adept at comprehending the requirements of the project in-
cluding the documentation and filling for approvals manpower and materials They must have the ability to del-
egate the work as per the skillsets of the individuals involved and form the teams accordingly Also they must be
aware of the Starbucks International standards so that the store to be established complies with the set stand-
ards The project would also require planning monitoring and evaluation skills and an understanding of costing
tax structures and the legalities involved
We would require following resources for successful completion of the project
Human resources
Management
Contractor and sub-contractor
Interior designer
Accountant
Lawyer
Labour
Materials
Furniture
Fixtures
Technical equipment such as computers printer card reader wires etc
Kitchen Appliances including oven dishwater refrigerator microwave coffee vending machine etc
Paint
Guneet | Jasdeep | Manan | Shanu |Akash 8
There could be difficulties in acquiring permits and licenses due to corruption and red tapism
Difficulties in obtaining the desired location on lease or rent
Delays in obtaining machinery and equipment imported from other countries
The construction plan has to adhere to the municipal guidelines and the construction blueprint will have to
be approved by the municipal body So the design will be constrained by the rules and regulations and
will be subject to approval from the municipal body
Delays in acquiring raw materials
There may be a social backlash against the opening of a coffee joint as it might be against the local cul-
ture and can potentially hurt the sentiments of the local community
Skilled workers might not be available to run the daily operations of the store
Delay in any activities like passing of construction blueprint can lead to escalation of costs which might
then needs to be approved from the client leading to more delays
The quality of the products will be constrained by the quality of the raw materials
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 2
Executive Summary 3
Introduction 4
Study rationale 4
Project scope and Basic assumptions 5
Technical know how resource requirement 7
Foreseable Difficulties and Constraints 8
Work breakdown structure 9
Activity Listhelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphelliphellip10
Responsibility matrix 11
Milestone Pert chart of the proposed Project 12
Project duration and financial Budget 1314
Risks to the proposed project 15
Expected Benefits 16
Risks Mitigation Plan 16
Critical Success Factors and proposed modalities of execution and monitoringhelliphelliphelliphelliphelliphelliphelliphelliphellip17
Limitations 18
Future Scope of Research 18
Lessons learned and difficulties 19
Project Auditing 20
Initiating and Staffing 21
Data Collection and Analysis 21
Reporting 21
Project Closure 22
References 23
Appendix 24
Apendix 1 Audit areas and project stages 24
Appendix 2 Questions 26
Appendix 3 Earned Value 27
Guneet | Jasdeep | Manan | Shanu |Akash 3
The project deals with establishing the first Starbucks Cafeacute in the Indian Subcontinent Establishing a new restau-
rant or a cafeacute in any market is a daunting task since it consists of not only leasing out a space but also meeting
the specifications and the hygiene factors of that country city There are many legal formalities that need to be
completed as well as placing orders for specialized equipment picking out the right deacutecor furnishing fixtures
hiring the appropriate personnel etc Opening a new Cafeacute though being a difficult task provides valuable in-
sights into a field such as project management in terms of the project duration resource requirement budgeting
etc
The objective of the project was to set up the Starbucks Cafeacute at an initial cost of INR 40 lakhs such that the cafeacute
meets the necessary specifications For completing the project resources were allocated critical path was found
out levelling was done to optimize the use of the resources etc The project is scheduled to be completed on time
and within budget ie 33 lakhs
The project proved to be an important learning tool in the application of the concepts learned in the project
management class as well as the use of the tool Microsoft Project which was also taught in class
Guneet | Jasdeep | Manan | Shanu |Akash 4
Introduction
Started in 1971 as a small coffee shop Starbucks today is the largest coffee retailer in the world with over
10000 shops in 30 countries The company wants to establish Starbucks as the most recognized and respected
brand in the world Starbucks relies on retail expansion product innovation and service expansion and has now
decided to target the Indian Market to improve its financial position and market share The new customer culture
emerging in India is reflective of a high probability of the success of Starbucks especially with the first two loca-
tions proposed for the site ie Delhi and Mumbai which are highly reflective of a fast westernized culture
Study rationale
The group decided to take up this project as an external consultant to Starbucks due to the following reasons
The entry of Starbucks in the Indian market is a complex non-routine effort which is limited by time and
money and is performance specific
The project deals with identification and scheduling of resources to complete the task in the given time and
resource frame
Determine the various types of risks and constraints that could be associated with managing a project as
well as how to mitigate and manage the same
Learn about the various compliances needed for opening a restaurant cafeacute in the Indian scenario
It is an opportunity to apply the principles of project management learnt in class as well as the tools for
the same
Guneet | Jasdeep | Manan | Shanu |Akash 5
4 Project Deliverables
The major Deliverables at the end of the project will be
A 1200 square foot finished retail outlet
A fully furnished store with a seating capacity of 20
Kitchen appliances to include an oven dishwasher refrigerator microwave coffee vending ma- chine
coffee grinding machine freezer automated order taking machines
3 Project Description
Starbucks the Seattle based coffee and food company has entered into a joint venture with the Tata Group to
enter the large untapped Indian market There are many factors that support the probability of success for the
firm foremost among them being the new consumer culture of the young India increased urbanization and the
growing pop culture Thus one needs to have a detailed plan for the establishment of the brand in the respec-
tive target markets
This Project Will help them to establish in India leading to creation of prospects for further growth
1 General Information Project Name Launch of Starbucks India
Project ID PR_001 Project Priority High
DepartmentDivision PROJECT MANAGEMENT
Prepared by Group Date (20121014)
2 Project Objectives Establishment of Starbucks Retail Outlet in India
Allocated budget for this project is INR 4000000 and should be completed within one year from the com-
mencement of the project The outlets will be nearly similar to the existing ones outside India Furniture and appli-
ances will be sourced from India No major imports will be involved
5 Milestones
Approval of Layout
Completion of installation of kitchen appliances and technical equipment
Obtaining all approvalsmdashwater waste electricity Income tax etc
Obtaining insurance papers for final evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 6
5 Technical Requirements
Registration under section 17[2] and rule 12[B] of the PFAndash Prevention of Food and Adultera- tion Act
1954 and Shops Establishment Act
Permit from PPL (Phonographic Performance Limited) to play recorded music
License from FSSAI
Eating House License from the police commissioner of the city
NOC from the fire department
Power Backup for 3 hours
6 Limits and Exclusion
Location of the store to be decided by the company
Permits and licenses are subjected to their approval
The stores will be built to the specifications and design approved by the customer initially
Decision of the further subcontractors will completely lie with the project management team
Site work limited to Monday through Friday 800AM to 600 PM
7 Customer Review
Tata Tea amp Starbucks
8 Basic Assumptions
The location of the store will be selected by the company including the locality within the city Thus the
task of the company is limited to setting up a fully functional and working store at the desired location
The project cost will thus vary depending on the rentals of the location
Permits and licenses are subject to approval from the corresponding government authorities Any delays in
getting the license will affect the project schedule However the same will be communicated to the client
accordingly The company will not be liable to any project delays due to delays in obtaining the license
Site work will be limited to weekdays from 8AM to 5PM Local and national holidays will be observed as
per the calendar of the company or the circular issued by the government
The company is free to outsource or subcontract part of its work to a third party without informing the cli-
ent
The store will be built as per the design specifications approved by the customer initially No further
changes in design will be incorporated after the design freeze
The company is just a party in facilitating the process of obtaining licenses and will be done on behalf of
the client
Guneet | Jasdeep | Manan | Shanu |Akash 7
The project would require the management to be adept at comprehending the requirements of the project in-
cluding the documentation and filling for approvals manpower and materials They must have the ability to del-
egate the work as per the skillsets of the individuals involved and form the teams accordingly Also they must be
aware of the Starbucks International standards so that the store to be established complies with the set stand-
ards The project would also require planning monitoring and evaluation skills and an understanding of costing
tax structures and the legalities involved
We would require following resources for successful completion of the project
Human resources
Management
Contractor and sub-contractor
Interior designer
Accountant
Lawyer
Labour
Materials
Furniture
Fixtures
Technical equipment such as computers printer card reader wires etc
Kitchen Appliances including oven dishwater refrigerator microwave coffee vending machine etc
Paint
Guneet | Jasdeep | Manan | Shanu |Akash 8
There could be difficulties in acquiring permits and licenses due to corruption and red tapism
Difficulties in obtaining the desired location on lease or rent
Delays in obtaining machinery and equipment imported from other countries
The construction plan has to adhere to the municipal guidelines and the construction blueprint will have to
be approved by the municipal body So the design will be constrained by the rules and regulations and
will be subject to approval from the municipal body
Delays in acquiring raw materials
There may be a social backlash against the opening of a coffee joint as it might be against the local cul-
ture and can potentially hurt the sentiments of the local community
Skilled workers might not be available to run the daily operations of the store
Delay in any activities like passing of construction blueprint can lead to escalation of costs which might
then needs to be approved from the client leading to more delays
The quality of the products will be constrained by the quality of the raw materials
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 3
The project deals with establishing the first Starbucks Cafeacute in the Indian Subcontinent Establishing a new restau-
rant or a cafeacute in any market is a daunting task since it consists of not only leasing out a space but also meeting
the specifications and the hygiene factors of that country city There are many legal formalities that need to be
completed as well as placing orders for specialized equipment picking out the right deacutecor furnishing fixtures
hiring the appropriate personnel etc Opening a new Cafeacute though being a difficult task provides valuable in-
sights into a field such as project management in terms of the project duration resource requirement budgeting
etc
The objective of the project was to set up the Starbucks Cafeacute at an initial cost of INR 40 lakhs such that the cafeacute
meets the necessary specifications For completing the project resources were allocated critical path was found
out levelling was done to optimize the use of the resources etc The project is scheduled to be completed on time
and within budget ie 33 lakhs
The project proved to be an important learning tool in the application of the concepts learned in the project
management class as well as the use of the tool Microsoft Project which was also taught in class
Guneet | Jasdeep | Manan | Shanu |Akash 4
Introduction
Started in 1971 as a small coffee shop Starbucks today is the largest coffee retailer in the world with over
10000 shops in 30 countries The company wants to establish Starbucks as the most recognized and respected
brand in the world Starbucks relies on retail expansion product innovation and service expansion and has now
decided to target the Indian Market to improve its financial position and market share The new customer culture
emerging in India is reflective of a high probability of the success of Starbucks especially with the first two loca-
tions proposed for the site ie Delhi and Mumbai which are highly reflective of a fast westernized culture
Study rationale
The group decided to take up this project as an external consultant to Starbucks due to the following reasons
The entry of Starbucks in the Indian market is a complex non-routine effort which is limited by time and
money and is performance specific
The project deals with identification and scheduling of resources to complete the task in the given time and
resource frame
Determine the various types of risks and constraints that could be associated with managing a project as
well as how to mitigate and manage the same
Learn about the various compliances needed for opening a restaurant cafeacute in the Indian scenario
It is an opportunity to apply the principles of project management learnt in class as well as the tools for
the same
Guneet | Jasdeep | Manan | Shanu |Akash 5
4 Project Deliverables
The major Deliverables at the end of the project will be
A 1200 square foot finished retail outlet
A fully furnished store with a seating capacity of 20
Kitchen appliances to include an oven dishwasher refrigerator microwave coffee vending ma- chine
coffee grinding machine freezer automated order taking machines
3 Project Description
Starbucks the Seattle based coffee and food company has entered into a joint venture with the Tata Group to
enter the large untapped Indian market There are many factors that support the probability of success for the
firm foremost among them being the new consumer culture of the young India increased urbanization and the
growing pop culture Thus one needs to have a detailed plan for the establishment of the brand in the respec-
tive target markets
This Project Will help them to establish in India leading to creation of prospects for further growth
1 General Information Project Name Launch of Starbucks India
Project ID PR_001 Project Priority High
DepartmentDivision PROJECT MANAGEMENT
Prepared by Group Date (20121014)
2 Project Objectives Establishment of Starbucks Retail Outlet in India
Allocated budget for this project is INR 4000000 and should be completed within one year from the com-
mencement of the project The outlets will be nearly similar to the existing ones outside India Furniture and appli-
ances will be sourced from India No major imports will be involved
5 Milestones
Approval of Layout
Completion of installation of kitchen appliances and technical equipment
Obtaining all approvalsmdashwater waste electricity Income tax etc
Obtaining insurance papers for final evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 6
5 Technical Requirements
Registration under section 17[2] and rule 12[B] of the PFAndash Prevention of Food and Adultera- tion Act
1954 and Shops Establishment Act
Permit from PPL (Phonographic Performance Limited) to play recorded music
License from FSSAI
Eating House License from the police commissioner of the city
NOC from the fire department
Power Backup for 3 hours
6 Limits and Exclusion
Location of the store to be decided by the company
Permits and licenses are subjected to their approval
The stores will be built to the specifications and design approved by the customer initially
Decision of the further subcontractors will completely lie with the project management team
Site work limited to Monday through Friday 800AM to 600 PM
7 Customer Review
Tata Tea amp Starbucks
8 Basic Assumptions
The location of the store will be selected by the company including the locality within the city Thus the
task of the company is limited to setting up a fully functional and working store at the desired location
The project cost will thus vary depending on the rentals of the location
Permits and licenses are subject to approval from the corresponding government authorities Any delays in
getting the license will affect the project schedule However the same will be communicated to the client
accordingly The company will not be liable to any project delays due to delays in obtaining the license
Site work will be limited to weekdays from 8AM to 5PM Local and national holidays will be observed as
per the calendar of the company or the circular issued by the government
The company is free to outsource or subcontract part of its work to a third party without informing the cli-
ent
The store will be built as per the design specifications approved by the customer initially No further
changes in design will be incorporated after the design freeze
The company is just a party in facilitating the process of obtaining licenses and will be done on behalf of
the client
Guneet | Jasdeep | Manan | Shanu |Akash 7
The project would require the management to be adept at comprehending the requirements of the project in-
cluding the documentation and filling for approvals manpower and materials They must have the ability to del-
egate the work as per the skillsets of the individuals involved and form the teams accordingly Also they must be
aware of the Starbucks International standards so that the store to be established complies with the set stand-
ards The project would also require planning monitoring and evaluation skills and an understanding of costing
tax structures and the legalities involved
We would require following resources for successful completion of the project
Human resources
Management
Contractor and sub-contractor
Interior designer
Accountant
Lawyer
Labour
Materials
Furniture
Fixtures
Technical equipment such as computers printer card reader wires etc
Kitchen Appliances including oven dishwater refrigerator microwave coffee vending machine etc
Paint
Guneet | Jasdeep | Manan | Shanu |Akash 8
There could be difficulties in acquiring permits and licenses due to corruption and red tapism
Difficulties in obtaining the desired location on lease or rent
Delays in obtaining machinery and equipment imported from other countries
The construction plan has to adhere to the municipal guidelines and the construction blueprint will have to
be approved by the municipal body So the design will be constrained by the rules and regulations and
will be subject to approval from the municipal body
Delays in acquiring raw materials
There may be a social backlash against the opening of a coffee joint as it might be against the local cul-
ture and can potentially hurt the sentiments of the local community
Skilled workers might not be available to run the daily operations of the store
Delay in any activities like passing of construction blueprint can lead to escalation of costs which might
then needs to be approved from the client leading to more delays
The quality of the products will be constrained by the quality of the raw materials
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 4
Introduction
Started in 1971 as a small coffee shop Starbucks today is the largest coffee retailer in the world with over
10000 shops in 30 countries The company wants to establish Starbucks as the most recognized and respected
brand in the world Starbucks relies on retail expansion product innovation and service expansion and has now
decided to target the Indian Market to improve its financial position and market share The new customer culture
emerging in India is reflective of a high probability of the success of Starbucks especially with the first two loca-
tions proposed for the site ie Delhi and Mumbai which are highly reflective of a fast westernized culture
Study rationale
The group decided to take up this project as an external consultant to Starbucks due to the following reasons
The entry of Starbucks in the Indian market is a complex non-routine effort which is limited by time and
money and is performance specific
The project deals with identification and scheduling of resources to complete the task in the given time and
resource frame
Determine the various types of risks and constraints that could be associated with managing a project as
well as how to mitigate and manage the same
Learn about the various compliances needed for opening a restaurant cafeacute in the Indian scenario
It is an opportunity to apply the principles of project management learnt in class as well as the tools for
the same
Guneet | Jasdeep | Manan | Shanu |Akash 5
4 Project Deliverables
The major Deliverables at the end of the project will be
A 1200 square foot finished retail outlet
A fully furnished store with a seating capacity of 20
Kitchen appliances to include an oven dishwasher refrigerator microwave coffee vending ma- chine
coffee grinding machine freezer automated order taking machines
3 Project Description
Starbucks the Seattle based coffee and food company has entered into a joint venture with the Tata Group to
enter the large untapped Indian market There are many factors that support the probability of success for the
firm foremost among them being the new consumer culture of the young India increased urbanization and the
growing pop culture Thus one needs to have a detailed plan for the establishment of the brand in the respec-
tive target markets
This Project Will help them to establish in India leading to creation of prospects for further growth
1 General Information Project Name Launch of Starbucks India
Project ID PR_001 Project Priority High
DepartmentDivision PROJECT MANAGEMENT
Prepared by Group Date (20121014)
2 Project Objectives Establishment of Starbucks Retail Outlet in India
Allocated budget for this project is INR 4000000 and should be completed within one year from the com-
mencement of the project The outlets will be nearly similar to the existing ones outside India Furniture and appli-
ances will be sourced from India No major imports will be involved
5 Milestones
Approval of Layout
Completion of installation of kitchen appliances and technical equipment
Obtaining all approvalsmdashwater waste electricity Income tax etc
Obtaining insurance papers for final evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 6
5 Technical Requirements
Registration under section 17[2] and rule 12[B] of the PFAndash Prevention of Food and Adultera- tion Act
1954 and Shops Establishment Act
Permit from PPL (Phonographic Performance Limited) to play recorded music
License from FSSAI
Eating House License from the police commissioner of the city
NOC from the fire department
Power Backup for 3 hours
6 Limits and Exclusion
Location of the store to be decided by the company
Permits and licenses are subjected to their approval
The stores will be built to the specifications and design approved by the customer initially
Decision of the further subcontractors will completely lie with the project management team
Site work limited to Monday through Friday 800AM to 600 PM
7 Customer Review
Tata Tea amp Starbucks
8 Basic Assumptions
The location of the store will be selected by the company including the locality within the city Thus the
task of the company is limited to setting up a fully functional and working store at the desired location
The project cost will thus vary depending on the rentals of the location
Permits and licenses are subject to approval from the corresponding government authorities Any delays in
getting the license will affect the project schedule However the same will be communicated to the client
accordingly The company will not be liable to any project delays due to delays in obtaining the license
Site work will be limited to weekdays from 8AM to 5PM Local and national holidays will be observed as
per the calendar of the company or the circular issued by the government
The company is free to outsource or subcontract part of its work to a third party without informing the cli-
ent
The store will be built as per the design specifications approved by the customer initially No further
changes in design will be incorporated after the design freeze
The company is just a party in facilitating the process of obtaining licenses and will be done on behalf of
the client
Guneet | Jasdeep | Manan | Shanu |Akash 7
The project would require the management to be adept at comprehending the requirements of the project in-
cluding the documentation and filling for approvals manpower and materials They must have the ability to del-
egate the work as per the skillsets of the individuals involved and form the teams accordingly Also they must be
aware of the Starbucks International standards so that the store to be established complies with the set stand-
ards The project would also require planning monitoring and evaluation skills and an understanding of costing
tax structures and the legalities involved
We would require following resources for successful completion of the project
Human resources
Management
Contractor and sub-contractor
Interior designer
Accountant
Lawyer
Labour
Materials
Furniture
Fixtures
Technical equipment such as computers printer card reader wires etc
Kitchen Appliances including oven dishwater refrigerator microwave coffee vending machine etc
Paint
Guneet | Jasdeep | Manan | Shanu |Akash 8
There could be difficulties in acquiring permits and licenses due to corruption and red tapism
Difficulties in obtaining the desired location on lease or rent
Delays in obtaining machinery and equipment imported from other countries
The construction plan has to adhere to the municipal guidelines and the construction blueprint will have to
be approved by the municipal body So the design will be constrained by the rules and regulations and
will be subject to approval from the municipal body
Delays in acquiring raw materials
There may be a social backlash against the opening of a coffee joint as it might be against the local cul-
ture and can potentially hurt the sentiments of the local community
Skilled workers might not be available to run the daily operations of the store
Delay in any activities like passing of construction blueprint can lead to escalation of costs which might
then needs to be approved from the client leading to more delays
The quality of the products will be constrained by the quality of the raw materials
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 5
4 Project Deliverables
The major Deliverables at the end of the project will be
A 1200 square foot finished retail outlet
A fully furnished store with a seating capacity of 20
Kitchen appliances to include an oven dishwasher refrigerator microwave coffee vending ma- chine
coffee grinding machine freezer automated order taking machines
3 Project Description
Starbucks the Seattle based coffee and food company has entered into a joint venture with the Tata Group to
enter the large untapped Indian market There are many factors that support the probability of success for the
firm foremost among them being the new consumer culture of the young India increased urbanization and the
growing pop culture Thus one needs to have a detailed plan for the establishment of the brand in the respec-
tive target markets
This Project Will help them to establish in India leading to creation of prospects for further growth
1 General Information Project Name Launch of Starbucks India
Project ID PR_001 Project Priority High
DepartmentDivision PROJECT MANAGEMENT
Prepared by Group Date (20121014)
2 Project Objectives Establishment of Starbucks Retail Outlet in India
Allocated budget for this project is INR 4000000 and should be completed within one year from the com-
mencement of the project The outlets will be nearly similar to the existing ones outside India Furniture and appli-
ances will be sourced from India No major imports will be involved
5 Milestones
Approval of Layout
Completion of installation of kitchen appliances and technical equipment
Obtaining all approvalsmdashwater waste electricity Income tax etc
Obtaining insurance papers for final evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 6
5 Technical Requirements
Registration under section 17[2] and rule 12[B] of the PFAndash Prevention of Food and Adultera- tion Act
1954 and Shops Establishment Act
Permit from PPL (Phonographic Performance Limited) to play recorded music
License from FSSAI
Eating House License from the police commissioner of the city
NOC from the fire department
Power Backup for 3 hours
6 Limits and Exclusion
Location of the store to be decided by the company
Permits and licenses are subjected to their approval
The stores will be built to the specifications and design approved by the customer initially
Decision of the further subcontractors will completely lie with the project management team
Site work limited to Monday through Friday 800AM to 600 PM
7 Customer Review
Tata Tea amp Starbucks
8 Basic Assumptions
The location of the store will be selected by the company including the locality within the city Thus the
task of the company is limited to setting up a fully functional and working store at the desired location
The project cost will thus vary depending on the rentals of the location
Permits and licenses are subject to approval from the corresponding government authorities Any delays in
getting the license will affect the project schedule However the same will be communicated to the client
accordingly The company will not be liable to any project delays due to delays in obtaining the license
Site work will be limited to weekdays from 8AM to 5PM Local and national holidays will be observed as
per the calendar of the company or the circular issued by the government
The company is free to outsource or subcontract part of its work to a third party without informing the cli-
ent
The store will be built as per the design specifications approved by the customer initially No further
changes in design will be incorporated after the design freeze
The company is just a party in facilitating the process of obtaining licenses and will be done on behalf of
the client
Guneet | Jasdeep | Manan | Shanu |Akash 7
The project would require the management to be adept at comprehending the requirements of the project in-
cluding the documentation and filling for approvals manpower and materials They must have the ability to del-
egate the work as per the skillsets of the individuals involved and form the teams accordingly Also they must be
aware of the Starbucks International standards so that the store to be established complies with the set stand-
ards The project would also require planning monitoring and evaluation skills and an understanding of costing
tax structures and the legalities involved
We would require following resources for successful completion of the project
Human resources
Management
Contractor and sub-contractor
Interior designer
Accountant
Lawyer
Labour
Materials
Furniture
Fixtures
Technical equipment such as computers printer card reader wires etc
Kitchen Appliances including oven dishwater refrigerator microwave coffee vending machine etc
Paint
Guneet | Jasdeep | Manan | Shanu |Akash 8
There could be difficulties in acquiring permits and licenses due to corruption and red tapism
Difficulties in obtaining the desired location on lease or rent
Delays in obtaining machinery and equipment imported from other countries
The construction plan has to adhere to the municipal guidelines and the construction blueprint will have to
be approved by the municipal body So the design will be constrained by the rules and regulations and
will be subject to approval from the municipal body
Delays in acquiring raw materials
There may be a social backlash against the opening of a coffee joint as it might be against the local cul-
ture and can potentially hurt the sentiments of the local community
Skilled workers might not be available to run the daily operations of the store
Delay in any activities like passing of construction blueprint can lead to escalation of costs which might
then needs to be approved from the client leading to more delays
The quality of the products will be constrained by the quality of the raw materials
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 6
5 Technical Requirements
Registration under section 17[2] and rule 12[B] of the PFAndash Prevention of Food and Adultera- tion Act
1954 and Shops Establishment Act
Permit from PPL (Phonographic Performance Limited) to play recorded music
License from FSSAI
Eating House License from the police commissioner of the city
NOC from the fire department
Power Backup for 3 hours
6 Limits and Exclusion
Location of the store to be decided by the company
Permits and licenses are subjected to their approval
The stores will be built to the specifications and design approved by the customer initially
Decision of the further subcontractors will completely lie with the project management team
Site work limited to Monday through Friday 800AM to 600 PM
7 Customer Review
Tata Tea amp Starbucks
8 Basic Assumptions
The location of the store will be selected by the company including the locality within the city Thus the
task of the company is limited to setting up a fully functional and working store at the desired location
The project cost will thus vary depending on the rentals of the location
Permits and licenses are subject to approval from the corresponding government authorities Any delays in
getting the license will affect the project schedule However the same will be communicated to the client
accordingly The company will not be liable to any project delays due to delays in obtaining the license
Site work will be limited to weekdays from 8AM to 5PM Local and national holidays will be observed as
per the calendar of the company or the circular issued by the government
The company is free to outsource or subcontract part of its work to a third party without informing the cli-
ent
The store will be built as per the design specifications approved by the customer initially No further
changes in design will be incorporated after the design freeze
The company is just a party in facilitating the process of obtaining licenses and will be done on behalf of
the client
Guneet | Jasdeep | Manan | Shanu |Akash 7
The project would require the management to be adept at comprehending the requirements of the project in-
cluding the documentation and filling for approvals manpower and materials They must have the ability to del-
egate the work as per the skillsets of the individuals involved and form the teams accordingly Also they must be
aware of the Starbucks International standards so that the store to be established complies with the set stand-
ards The project would also require planning monitoring and evaluation skills and an understanding of costing
tax structures and the legalities involved
We would require following resources for successful completion of the project
Human resources
Management
Contractor and sub-contractor
Interior designer
Accountant
Lawyer
Labour
Materials
Furniture
Fixtures
Technical equipment such as computers printer card reader wires etc
Kitchen Appliances including oven dishwater refrigerator microwave coffee vending machine etc
Paint
Guneet | Jasdeep | Manan | Shanu |Akash 8
There could be difficulties in acquiring permits and licenses due to corruption and red tapism
Difficulties in obtaining the desired location on lease or rent
Delays in obtaining machinery and equipment imported from other countries
The construction plan has to adhere to the municipal guidelines and the construction blueprint will have to
be approved by the municipal body So the design will be constrained by the rules and regulations and
will be subject to approval from the municipal body
Delays in acquiring raw materials
There may be a social backlash against the opening of a coffee joint as it might be against the local cul-
ture and can potentially hurt the sentiments of the local community
Skilled workers might not be available to run the daily operations of the store
Delay in any activities like passing of construction blueprint can lead to escalation of costs which might
then needs to be approved from the client leading to more delays
The quality of the products will be constrained by the quality of the raw materials
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 7
The project would require the management to be adept at comprehending the requirements of the project in-
cluding the documentation and filling for approvals manpower and materials They must have the ability to del-
egate the work as per the skillsets of the individuals involved and form the teams accordingly Also they must be
aware of the Starbucks International standards so that the store to be established complies with the set stand-
ards The project would also require planning monitoring and evaluation skills and an understanding of costing
tax structures and the legalities involved
We would require following resources for successful completion of the project
Human resources
Management
Contractor and sub-contractor
Interior designer
Accountant
Lawyer
Labour
Materials
Furniture
Fixtures
Technical equipment such as computers printer card reader wires etc
Kitchen Appliances including oven dishwater refrigerator microwave coffee vending machine etc
Paint
Guneet | Jasdeep | Manan | Shanu |Akash 8
There could be difficulties in acquiring permits and licenses due to corruption and red tapism
Difficulties in obtaining the desired location on lease or rent
Delays in obtaining machinery and equipment imported from other countries
The construction plan has to adhere to the municipal guidelines and the construction blueprint will have to
be approved by the municipal body So the design will be constrained by the rules and regulations and
will be subject to approval from the municipal body
Delays in acquiring raw materials
There may be a social backlash against the opening of a coffee joint as it might be against the local cul-
ture and can potentially hurt the sentiments of the local community
Skilled workers might not be available to run the daily operations of the store
Delay in any activities like passing of construction blueprint can lead to escalation of costs which might
then needs to be approved from the client leading to more delays
The quality of the products will be constrained by the quality of the raw materials
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 8
There could be difficulties in acquiring permits and licenses due to corruption and red tapism
Difficulties in obtaining the desired location on lease or rent
Delays in obtaining machinery and equipment imported from other countries
The construction plan has to adhere to the municipal guidelines and the construction blueprint will have to
be approved by the municipal body So the design will be constrained by the rules and regulations and
will be subject to approval from the municipal body
Delays in acquiring raw materials
There may be a social backlash against the opening of a coffee joint as it might be against the local cul-
ture and can potentially hurt the sentiments of the local community
Skilled workers might not be available to run the daily operations of the store
Delay in any activities like passing of construction blueprint can lead to escalation of costs which might
then needs to be approved from the client leading to more delays
The quality of the products will be constrained by the quality of the raw materials
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 9
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 10
Activity List
Setting up of teams for each activity
Permits floor plan sanitation plumbing Hire a construction engineer Preparation of construction blueprint Approval of the blueprint from management Requirements gathering for application filing Filing of application
Insurance (Fire theft Earthquake Public liability product liability) Proposals from different insurance agents Selection of insurance policy Processing of the insurance
Waste management compliance Study of the waste management rules and regulations Preparation of waste management plan Approval of the waste management plan from the concerned authority Preparation of documents and handbook for compliance with standards
Water board approval Preparation of documents for commercial water connection Filing with the water board
Electricity board approval Preparation of documents for commercial electricity connection Filing with the electricity board
Income tax registrations Hiring a team consisting of accountants and lawyers Detailed study of the existing tax structure Preparation of documents for sales tax and other tax registrations Filing of application for the tax registrations
Hiring and training of personnels
Interiors Hiring of an interior designer Study of layout of other Starbucks store Preparation of layout design for the store Approval of the store layout from the management Hiring of construction workers Formation of a purchase committee Purchase amp Setup of materialsequipments required Purchase of materials requirement Construction and interior designing work Inspection of the completed layout by the management
Installation of technical infrastructure Application filing for telephone and internet connection Setup of billing system including computer printer card readers automatic ordering sys-
tem etc Procurement of technical equipments
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 11
Task Akash Guneet Jasdeep Shanu Manan
1 Setting up of teams for each activity R R R R R
2 Permits floor plan sanitation plumbing R S S
3 Insurance (Fire theft Earthquake Public
liability product liability) S R S
4 Waste management compliance S R
5 Water board approval S R
6 Electricity board approval S R S
7 Income tax registrations S R S
8 Hiring and training of personnels R
9 Interiors R
10 Installation of technical infrastructure S R S
11 Site Review S R S
12 Monitoring Progress R S
13 Evaluation of Deliverables S R
R = Responsible S = Support Assistant
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 12
A project milestone is an event that receives special attention It signifies the end of a phase and could also indi-
cate a deliverable
The project consists of the following milestones
Approval of the layout of the building This milestone indicates the readiness of the team for going for the
next phase of the project which is to begin the interior designing and the construction phase This task is a
milestone since it signifies the end of the preparation phase for the project and starts with the implementa-
tion of the same
Completion of the installation of the kitchen appliances technical equipment This is a milestone since it
signifies the readiness of the Starbucks Cafeacute in terms of opening it for customers from a service point of
view
Obtaining all approvals- water waste electricity income tax etc Signifies the readiness of the complet-
ed Cafeacute in terms of meeting the technical specifications of the project which were stated in the project
charter or the scope
Obtaining the Insurance papers for the final evaluation This milestone signifies the readiness of the Cafeacute
to be shown to the top management and then to open the Cafeacute to the public since reaching this milestone
is an indication that the Cafeacute meets all the modalities and is also complying with the specifications of the
project charter or the project scope
All the 4 of the milestones along with the expected timeline is shown in the image below
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 13
The duration of a project and the budget are an important
part of any project Depending on the sensitivity and the na-
ture of the project each of the two factors plays and important
role and generally there is a payoff between them For exam-
ple projects belonging to the Government will have a fixed
cost but the schedule will vary while for the defence depart-
ment the cost is of no consequence because the duration is of
national importance
In the given project cost has been considered to be more im-
portant than the duration since it is a cafeacute opening and the
duration is not of a very large consequence
Calendar for the project
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 14
ID Task Name Fixed Cost Accrual Total Cost Baseline 30 Completion of setup-techapplian Prorated Rs 180900000 Rs 180900000
29 Completion of Interiors Prorated Rs 61700000 Rs 61700000
40 Kitchen appliances (oven dishwa Prorated Rs 28710000 Rs 28710000
38 Furniture and Fixtures Prorated Rs 7200000 Rs 7200000
17 Preperation of documents and ha Prorated Rs 6240001 Rs 6240001
52 RFQ- Request for Quotes Prorated Rs 5520000 Rs 5520000
39 Technical equipment(telephone Prorated Rs 4800000 Rs 4800000
14 Preparation of waste manageme Prorated Rs 3600000 Rs 3600000
46 Detailed study of existing tax stru Prorated Rs 2280000 Rs 2280000
54 Processing of insurance request Prorated Rs 1840000 Rs 1840000
35 Selection of subcontractors Prorated Rs 1800000 Rs 1800000
13 Study of the rules and regulations Prorated Rs 1680000 Rs 1680000
44 Approval from the board Prorated Rs 1680000 Rs 1680000
11 Approval Prorated Rs 1440000 Rs 1440000
43 Preparing a budget for the projec Prorated Rs 1428000 Rs 1428000
22 Preparation of floor plan Prorated Rs 1240000 Rs 1240000
16 Approval of the plan Prorated Rs 1200000 Rs 1200000
33 Hiring construction engineer Prorated Rs 1200000 Rs 1200000
34 Hiring an interior designer Prorated Rs 1200000 Rs 1200000
36 Team of accountants and lawyers Prorated Rs 1200000 Rs 1200000
47 Preperation of documents for sal Prorated Rs 1200000 Rs 1200000
53 Selection of the insurance policy Prorated Rs 920000 Rs 920000
7 Approval Prorated Rs 840000 Rs 840000
25 approval from municipality Prorated Rs 840000 Rs 840000
49 Approval Prorated Rs 840000 Rs 840000
2 Setting up teams for the activities Prorated Rs 720000 Rs 720000
5 Documentation for commercial e Prorated Rs 720000 Rs 720000
9 Documentation for commercial w Prorated Rs 720000 Rs 720000
23 approval from management Prorated Rs 600000 Rs 600000
28 Approval of the layout from the Prorated Rs 600000 Rs 600000
56 Final Evaluation Prorated Rs 600000 Rs 600000
6 Filing documents with the electri Prorated Rs 240000 Rs 240000
10 Filing documents with the water Prorated Rs 240000 Rs 240000
15 Filing of the plan Prorated Rs 240000 Rs 240000
19 File for connection Prorated Rs 240000 Rs 240000
48 Filing the application Prorated Rs 120000 Rs 120000
24 filing with municipality Prorated Rs 120000 Rs 120000
27 Preperation of layout design for t Prorated Rs 000 Rs 000
31 Completion of installation Prorated Rs 000 Rs 000
50 All approvals obtained Prorated Rs 000 Rs 000
55 Insurance papers Prorated Rs 000 Rs 000
Rs 326658001 Rs 326658001
Budget
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 15
Risk of the proposed project can be subdivided into three categories The image below shows the different cat-egories of risk and the table describe its further
Risk Description
Subcontractor ampSupplier On time quality control and check performance raw material cost transporta-tion labour cost
Market Saturated Market
Customer taste preference pricing promotion
Weather Suitable for construction
Regulatory Meeting the various compliance requirements as outlined in the scope
Estimating Error in estimation could throw off the entire budget work time and the sched-ule Could arise from inflation miscalculation etc
Planning Scheduling of resources critical path selection
Controlling Keeping a check on the project milestones deliverables to ensure the project is on time and within budget
Communication Among the team members and the team and the client
Project Dependencies Internal audit internal review internal approval to plans
Resources Competence of the team members chosen for the task
Funding Source Budget constraints spending accounting for over spending
Prioritization Deciding the hierarchy of tasks to be performed importance of each depend-ence among them
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 16
Expected Benefits
Entry into one of the largest and growing emerging markets of the world
Increased cash flows to strengthen the financial position
Increased market share to help maintain the number one position in the coffee retail segment
Can leverage on the relationship with TATA in terms of sourcing of beans and other raw materials and
also export to nearby countries if there is a cost benefit
The two strategically chosen locations could be a beginning to gaining a stronghold in the Indian market
Risks Mitigation Plan
A vendor pool will be formed wherein the potential vendors will be listed who can supply the raw materi-
als In case of quality issues from a particular vendor the issue will be brought in notice to the vendor In
case the issue still persists business will be conducted with another vendor to ensure the desired quality
In case of delays in the acquisition of raw materials a penalty will be imposed on the responsible party
as mentioned in the contract If the delay is greater than the buffer time then the raw materials will be
sourced from another vendor as given in the vendor pool list
Any increase in the labor cost or the raw material cost will be mitigated by signing a contract to deliver
the raw materials and labor at a pre decided price for the entire duration of the project
To mitigate the risk of effect of weather on the construction and design appropriate technologies will be
used For instance anti-seepage or anti-fungal treatment of walls will be done in case the painting of
walls is affected by rains
To mitigate the risk of delays in clearances and acquisition of permits and licenses the corresponding gov-
ernment department will be contacted to know the reasons for delays and to complete any formalities
Any miscalculations in the budget or errors in the budget will be brought to the notice of the senior man-
agement and approvals for new budget will be sought In case of non-approval of budgets the nature
and scope of the activity will be toned with approval from the management and the client
Non availability of resources for a particular task will be worked out by assigning more resources from
the bench
To mitigate the risk due to delays in the tasks performed status updates will be carried out each day and
the respective risk action plan will be executed in case the delay exceeds a particular threshold
Emails and phone calls will be used for the purpose of communication and to ensure no miscommunication
of ideas all tasks roles and responsibilities to be performed the minutes of the meeting will be document-
ed and the same will be communicated across to all the team members and concerned stakeholders
In case of team members not skilled enough for a corresponding task employees on bench will be taken
onboard to assist in the activities
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 17
It has to be made sure that team handling the project is clear about the objectives of Starbucks their
standards and compliance norms Expectations must be clearly communicated between all the entities in-
volved in the project including TATA Starbucks and the project management team
Completing the activities (especially compliance which includes getting all the approvals) on time is very
crucial for the project
Risks involved must be identified clearly at the onset of the project and a mitigation plan should be devel-
oped to control any detrimental effect on the schedule of the project
Starbucks management must be in regular contact and is expected to deliver an immense support to the
team to ensure that the project scope does not change and the construction goes as planned for a timely
launch of Starbucks in the country
To avoid cost over-runs the accountants and the management (handling the budgeting) must have a clear
target in mind and hence plan the expenditure accordingly
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 18
Limitations
The limitations of the project are
Changes in the requirements have not been considered
Site selection and its associated cost have not been considered
A very detailed risk planning mitigation and contingency plan could not be formulated
The possible problems after the setting up of the restaurant have not been considered since they were out
of scope of the project
Future Scope of Research
Market research could be included as part of the project for the selection of the location of the store
A more comprehensive breakdown of the work structure into work packets could be done
A detailed risk plan mitigation and contingency plan can be formulated
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 19
Lessons Learned
The project work facilitated an in-depth understanding of all the intricacies involved in the project life cy-
cle including defining planning executing and delivering
Resources can be put to an effective use only if planned properly
Both under or over utilization of resources is detrimental for the project and thus proper planning is re-
quired in this regard
Separate buffer time should be accounted for different activities to absorb small delays due to various
external or internal factors
A checklist is needed to measure whether the project going as per schedule or not Also it should be com-
plemented with a contingency plan which should illustrate the actions to be taken if the project is not track
It is important to identify the risks associated with the project and make a mitigation plan to reduce any
effect of these risks on the execution
Difficulties faced while preparing the project plan
The process of planning was very time consuming since it required an in-depth understanding of all the
processes that might be involved in setting up a cafe
The team lacked expertise for project costing thus it was a challenge to prepare the project plan within
the budget
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 20
The project auditing will involve auditing the project in terms of its project management its business case or its
business requirements inclusive of its business requirements
The project auditing will be done at the following stages
Project Initiation
Planning
Execution
Completion
Post Implementation
At each of the above stages independent and unbiased evaluation will be done on the following parameters
1 Project Organization
2 Integration Management
3 Content and Scope Management
4 Time Management
5 Cost Management
6 Quality and Test Management
7 Human Resource Management
8 Communication Management
9 Project Reporting
10 Risk Management
11 Procurement Management
12 Business Case
13 Business Requirements
The project audit matrix as attached in the appendix will be used for the purpose of evaluation
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 21
Initiating and Staffing
An internal team will be formed to carry on the auditing of the project The team will not be consisting of any
members working on the project to remove any biasness
Following will be the structure of the team
Senior Project Manager
Project Manager
Accountants
HR Manager
Data Collection and Analysis
The audit template as in appendix 2 will be used for the purpose of data collection and analysis
Reporting
The audit report will be presented to the project manager and the senior project manager It will be kept in the
archive for the purpose of future use and reference by the organization Following will be the outline used for
the report
ClassificationmdashThe classification of the report will be done as follows
Project type
Size (Monetary)
Number of staff
Technology level
Analysis
Recommendations
Lessons Learned
Appendix
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 22
The following activities will be performed for the project closure
Delivery acceptance from the customer
Shutting down resources and releasing to new uses
Reassigning project team members
Closing accounts and clearing off all the bills
Evaluation of the project team viz the project team members and the project manager
Documenting the process and procedures and the lessons learned
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 23
Project Management- The managerial process Fourth edition
Project management on new product development ndash Professor Virgil POPA PHD
Starbucks a Strategic Analysis- Brown University Economics Department 2008
MS Project online help
Standard for auditing projects German Institute for Internal Auditing
Project Auditing and Risk management Deloitte
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 24
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 25
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 26
Was the organizational culture supportive and correct for this type of project Why or why not
Was senior Managementrsquos support adequate
Did the project accomplish its intended purpose
Is there a clear link to organizational strategy and objectives
Does the priority system reflect importance to the future of the organization
Has the environment (internal or external) changed the need for projectrsquos completion
Were the risks for project appropriately identified and assessed
Were contingency plans used
Were the contingency plans realistic
Have risk events occurred that had impact greater than anticipated
Were the people with right talent and skill set assigned for the project
If the project is completed then has the staff been fairly assigned to the new projects
Were the project startup and handoff successful Were the customers satisfied
Were the project planning and control systems appropriate for this type of project
Did the project conform to plan Was the project over or under budget or schedule Why
Did the team have adequate access to organizational resources ndash people budget support groups equip-
ment
Were there any resource conflicts with other ongoing projects
Was the team managed well
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001
Guneet | Jasdeep | Manan | Shanu |Akash 27
ID Task Name Planned Value Earned Value AC (ACWP) EAC 2 Setting up teams for the activities Rs 720000 Rs 720000 Rs 720000 Rs 720000
5 Documentation for commercial e Rs 720000 Rs 720000 Rs 720000 Rs 720000
6 Filing documents with the electri Rs 240000 Rs 240000 Rs 240000 Rs 240000
7 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
9 Documentation for commercial w Rs 720000 Rs 720000 Rs 720000 Rs 720000
10 Filing documents with the water Rs 240000 Rs 240000 Rs 240000 Rs 240000
11 Approval Rs 1440000 Rs 1440000 Rs 1440000 Rs 1440000
13 Study of the rules and regulations Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
14 Preparation of waste manageme Rs 3600000 Rs 3600000 Rs 3600000 Rs 3600000
15 Filing of the plan Rs 240000 Rs 240000 Rs 240000 Rs 240000
16 Approval of the plan Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
17 Preperation of documents and ha Rs 6240001 Rs 6240001 Rs 6240001 Rs 6240001
19 File for connection Rs 240000 Rs 240000 Rs 240000 Rs 240000
22 Preparation of floor plan Rs 1240000 Rs 1240000 Rs 1240000 Rs 1240000
23 approval from management Rs 600000 Rs 600000 Rs 600000 Rs 600000
24 filing with municipality Rs 120000 Rs 120000 Rs 120000 Rs 120000
25 approval from municipality Rs 840000 Rs 840000 Rs 840000 Rs 840000
27 Preperation of layout design for t Rs 000 Rs 000 Rs 000 Rs 000
28 Approval of the layout from the Rs 600000 Rs 600000 Rs 600000 Rs 600000
29 Completion of Interiors Rs 61700000 Rs 61700000 Rs 61700000 Rs 61700000
30 Completion of setup-techapplian Rs 180900000 Rs 180900000 Rs 180900000 Rs 180900000
31 Completion of installation Rs 000 Rs 000 Rs 000 Rs 000
33 Hiring construction engineer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
34 Hiring an interior designer Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
35 Selection of subcontractors Rs 1800000 Rs 1800000 Rs 1800000 Rs 1800000
36 Team of accountants and lawyers Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
38 Furniture and Fixtures Rs 7200000 Rs 7200000 Rs 7200000 Rs 7200000
39 Technical equipment(telephone Rs 4800000 Rs 4800000 Rs 4800000 Rs 4800000
40 Kitchen appliances (oven dishwa Rs 28710000 Rs 28710000 Rs 28710000 Rs 28710000
43 Preparing a budget for the projec Rs 1428000 Rs 1428000 Rs 1428000 Rs 1428000
44 Approval from the board Rs 1680000 Rs 1680000 Rs 1680000 Rs 1680000
46 Detailed study of existing tax stru Rs 2280000 Rs 2280000 Rs 2280000 Rs 2280000
47 Preperation of documents for sal Rs 1200000 Rs 1200000 Rs 1200000 Rs 1200000
48 Filing the application Rs 120000 Rs 120000 Rs 120000 Rs 120000
49 Approval Rs 840000 Rs 840000 Rs 840000 Rs 840000
50 All approvals obtained Rs 000 Rs 000 Rs 000 Rs 000
52 RFQ- Request for Quotes Rs 5520000 Rs 5520000 Rs 5520000 Rs 5520000
53 Selection of the insurance policy Rs 920000 Rs 920000 Rs 920000 Rs 920000
54 Processing of insurance request Rs 1840000 Rs 1840000 Rs 1840000 Rs 1840000
55 Insurance papers Rs 000 Rs 000 Rs 000 Rs 000
56 Final Evaluation Rs 495000 Rs 495000 Rs 495000 Rs 600000
Rs 326553001 Rs 326553001 Rs 326553001 Rs 326658001