esc residential connections · esc service improvement commitment kpi performance presentation in...

16
ESC Residential Connections Service Improvement Commitment 1H 2019 Performance report 08.07.19

Upload: others

Post on 28-May-2020

14 views

Category:

Documents


0 download

TRANSCRIPT

ESC Residential ConnectionsService Improvement Commitment1H 2019 Performance report

08.07.19

Executive summary

08.07.19 ESC Service Improvement Commitment KPI performance presentation2

Over the course of the past 6 months we’ve committed significant resources (people, time and investment) to deliver on the ESC Service Improvement commitments.

Whilst our work is not completed we have been able to improve our systems, process and methods of engagement and communication which have benefitted our stakeholders and customers.

This report outlines summarises our performance against targets at 5 key stages of the development and connection process

1. Master plan review2. Design review3. Construction audit4. Practical completion5. Construction tie in

We’ve also included additional performance information relating to design and audit quality

Key performance metrics

08.07.19 ESC Service Improvement Commitment KPI performance presentation3

1H 2019

Powercor has committed to improving in 5 key stages of the connection process

ESC Service Improvement Commitment KPI performance presentation

1

2

3

4

5

Master plan review

Design review

Practical completion

Construction ‘tie-in’

Construction audit

Replace staged scopes with a revised and contestable Master Planning

process – this will remove network scoping from the critical path

Target completion of design plan audits and re-audits within 20 business

days

Complete construction audit (from request to final report) within 5 to 8

business days

Grant practical completion in less than 10 business days from request

Meet customer dates and implement new process to offer the option of

a 20-business day construction tie in

New process 16.0 days2

Old process 34.0 days

6.1 days

2.3 days

18.4 days

New process being implemented

90% customer target date met in June

Stage Target 1H19 Performance1

1. All performance measures are in business days

2. New process is in trial and we only have a small sample size. We expect to roll the new process out in 2H2019

4 08.07.19

Project time with Powercor represented ~17% of the total job time in 1H 2019

ESC Service Improvement Commitment KPI performance presentation

1. SOC = Statement of compliance

Application

response

Customer

acceptance

Scope

Development

Design plan

development

Design Plan

Audit

Construction Construction

Audit

Practical

Completion

Construction

Tie-in

Powercor Developer Powercor Developer Powercor Developer Powercor Powercor Powercor

10.3 22.1 34.0 137.8 18.4 190.5 6.1 2.3 42.8

Projects that were completed in 1H2019 took an average of ~421 business

days from Application to SOC1

Developer

application

Consent for

SOC

Powercor was responsible for an average ~71 business days (~17%) of project development time from application to SOC

Developers were responsible for the remaining ~350 days (~83%)Developer

application (Day 0)Consent for SOC

at ~421 days

1 2 3 4 5

10.3

22.1 34.0 137.8 18.4 190.5

6.1

2.3

42.8

0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 450.0 500.0

Ave time

5 08.07.19

10.3

22.1 34.0 137.8 18.4 190.5

6.1

2.3

42.8

0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 450.0 500.0

Ave time

Staged scopes are being replaced with a contestable Master Planning process

ESC Service Improvement Commitment KPI performance presentation

In the very early stages this change has resulted in a reduction in time frames from 34

to 16 days1. The change also removes network scoping from project critical path.

1Master Plan review

• We recognised that the staged

scope process was creating

unnecessary delays

• We are trialling the new Master

Plan review process on a small

number of projects with positive

results

• We are seeking to implement this

process by the end of 2019

• Our target will be to turn these

around in 10 business days

significantly reducing timeframes

Performance Target

16.0 10V

34

16

0

5

10

15

20

25

30

35

40

Old Staged Scope Process New Master Planning Process

Avera

ge D

ays

Master Planning Performance 1H2019

1. Small sample size due to early stages of roll out

New process roll out

will gain momentum in

2H2019

6 08.07.19

10.3

22.1 34.0 137.8 18.4 190.5

6.1

2.3

42.8

0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 450.0 500.0

Ave time

Our target is to complete Design review within 20 business days.

ESC Service Improvement Commitment KPI performance presentation7

2 Design review

We’ve consistently been under 20 business days in 1H2019 averaging 18.4 business days

• Establishing our Contestable

Works Team has been a key

reason we’ve been able to meet

this performance targets

• Quality of submitted designs can

improve with only ~47.1%

passing at the first check

Performance Target

18.4 20V

0.0

5.0

10.0

15.0

20.0

25.0

30.0

0

10

20

30

40

50

60

70

80

90

100

January February March April May June

Day

s

Nu

mb

er o

f ch

ecks

Month

Design Approval 1H19

Number Checked Turnaround time

Target = 20 business days

08.07.19

10.3

22.1 34.0 137.8 18.4 190.5

6.1

2.3

42.8

0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 450.0 500.0

Ave time

Our target is to complete construction audits within 5 to 8 business days

ESC Service Improvement Commitment KPI performance presentation8

3 Construction Audit

We achieved 6.1 business days in 1H2019. Resourcing and improved processes

have been the keys to meeting this performance target in periods of high demand

• ~85.6% of projects have not

required a reaudit– up from

~71.7% in 20181

• May and June were very busy

periods where we were able to

manage work volume and meet

target timeframes

• Stopped ‘walk away’ policy and

implemented a process where all

above ground items are audited

at first audit to improve efficiency

0

1

2

3

4

5

6

7

8

9

10

0

10

20

30

40

50

60

70

80

Jan Feb Mar Apr May Jun

Audit t

ime

Audit V

olu

me

Month

Audit volumes and time

Audit Volume Re-audit volume Audit time Re-audit time

Audit Target < 8 business days

Re-audit target < 10 business days

Performance Target

6.1 5 to 8V

08.07.19

1. Few projects pass with zero non-conformances, most projects receive an unapproved status and their approval is subject to providing evidence that identified non-

conformances have in been fixed. This sometimes happens in real time with the auditor on site or via the contractor providing photographic evidence of the fix at a later date

10.3

22.1 34.0 137.8 18.4 190.5

6.1

2.3

42.8

0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 450.0 500.0

Ave time

Our target is to provide practical completion in less than 10 business days

ESC Service Improvement Commitment KPI performance presentation9

4 Practical Completion

We achieved a result of 2.3 business days in 1H2019. Improved communication and

a clear view of upcoming work has driven this performance

• We’ve streamlined this process to

be able to consistently

outperform this target

• We will continue to focus on

stakeholder management and

communication to maintain this

performance

Performance Target

2.3 10V

0

2

4

6

8

10

12

0

10

20

30

40

50

60

70

80

January February March April May June

Days

Subm

issio

ns

Month

Practical Completion Volumes and Completion Time

Practical completion requests Completion time

Target = 10 business days

08.07.19

10.3

22.1 34.0 137.8 18.4 190.5

6.1

2.3

42.8

0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 450.0 500.0

Ave time

We are working to meet customer dates. We now provide a rapid service of 20 days1

ESC Service Improvement Commitment KPI performance presentation10

5 Construction ‘tie-in’

1. This offer is subject to negotiation and subject to the customer meeting agreed development milestones including passed construction audit audit and safety requirements

Our average performance YTD is 42.8 business days. We are offering the option of

20 business day tie-in and are currently trialing this with suitable projects

• We are trialling a 20 day tie in

time frame for suitable projects

• We directly negotiate a tie in date

with our customers – our focus is

to deliver to these dates

• We achieved 90% delivery to

customer dates in June

• Customers with industrial,

commercial and public lighting

projects have expressed interest

in faster turnaround times

Performance Target

42.8 Agreed dateV

0

10

20

30

40

50

60

70

80

0

10

20

30

40

50

60

70

80

January February March April May June

Com

ple

tion t

imes

Tie

in r

equests

Tie in volumes and timeframes

Tie in requests 1H19 Tie-in completion times

Future option = 20 days

Current target < 50 days

08.07.19

Additional performance information

ESC Service Improvement Commitment KPI performance presentation11

1H 2019

08.07.19

Design quality can improve with only ~47.1% of submitted designs pass at the first check

ESC Service Improvement Commitment KPI performance presentation12

47.10%

48.50%

3.40% 1.00%

Design Approval Performance

First Audit Second Audit Third Audit Fourth Audit

• Design quality has improved

marginally in the past 12 months

• This is an area of focus for us

with the design consultants

• Improvement here should further

reduce delays

• Improved quality will reduce

rework and in turn improve

design plan approval times0

50

100

150

200

250

300

350

1H2019

Desig

n

revie

ws

Design reviews

We continue to work with stakeholders to improve the quality of designs submitted.

Improving quality here will reduce timeframes and improve construction quality

08.07.19

In 1H 2019 ~85.6% of projects have not required a reaudit– up from ~71.7% in 20181

ESC Service Improvement Commitment KPI performance presentation13

71.74%

22.57%

4.40% 1.28%

2018 Audit Performance

Audit only Reudit Second reaudit Third reaudit

85.66%

12.59%1.40% 0.35%

1H2019 Audit Performance

Audit only Reudit Second reaudit Third reaudit

545

0

100

200

300

400

500

600

2018

2018 Total Audits

286

0

50

100

150

200

250

300

350

1H 2019

1H 2019 Total Audits

• A change in audit process is

mostly responsible for the

improvement

• We’ve ceased the failed audit

‘walk away’ policy and now

complete a more extensive first

audit

• We also allow for real time fixes

or photographic evidence of

fixed items rather than re-audit

in certain circumstances

1. Few projects pass with zero non-conformances, most projects receive an unapproved status and their approval is subject to providing evidence that identified non-

conformances have in been fixed. This sometimes happens in real time with the auditor on site or via the contractor providing photographic evidence of the fix at a later date

08.07.19

Trends in construction audit non-conformance trends (2017 to YTD 2019)

ESC Service Improvement Commitment KPI performance presentation

As-built detailing, service pit installation and misaligned (or non-installation of) marker tape are

recurring construction audit issues that make up the majority of our audit non-conformances

14 08.07.19

2019 YTD top 5 construction audit non-conformance categories

ESC Service Improvement Commitment KPI performance presentation15 08.07.19

Connections Volume and Performance 2019

ESC Service Improvement Commitment KPI performance presentation

VPN have completed 12,154 new ‘line of mains’ connections in the first half of 2019

CR’s Completed & Fulfilled 1st of January – 30th of June 2019

Measure CitiPower Powercor VPNNew Connections Volume

Submitted any time, fulfilled 20192,274 9,880 12,154

New Connection PerformanceDays to Complete. Excludes jobs with appointments or by agreed

date3.81 Days 6.32 Days 6.17 Days

BTS ConnectionsMeter Position = Temporary BTS

251 278 529

BTS Cycle TimeExcludes jobs with appointments or by agreed date

2.61 Days 6.11 Days 4.50 Days

BTS via Appointment or Agreed DateMeter Position = Temporary BTS

55 48 103 (19%)

BTS Cycle TimeAverage days to complete for requests with an appointment or

agreed date17.98 Days 11.77 Days 15.08 Days

Temp Supply In PermRequests to establish temporary supply in permanent meter

position*109 3,647 3,756

Temp Supply in Perm Cycle TimeAverage days to complete for requests to establish temporary

supply in a permanent meter position^4.99 Days 6.28 Days 6.24 Days

*Temp in perm based on service order sub type “Establish Temporary in Permanent” & “Establish Temporary Supply”

^No requests for temporary supply in a permanent meter position were fulfilled via an agreed date or an appointment

16 08.07.19