    Erection , Testing &Commissioning of

    Isolators

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    2/13

    ISOLATORS TESTING &

    COMMISSIONING

    Objectives

    To ensure the completeness of theequipment before energisation.

    To rectify the defects identified duringthe testing.

    To ensure reliable trouble free operation

    of the isolators in all respects.To facilitate the charging clearance from

    the statutory authority.

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    3/13

    ISOLATORS - TESTING

    The testing procedures for isolatorsare classified as given below.

    General checks

    Electrical Motor checks

    Operational checks

    IR Value test

    Contact Resistance measurement

    Checking of interlocks

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    4/13

    ISOLATORSGENERAL

    CHECKS

    Equipment is free from all visible defectson physical inspection

    Support structures, marshalling box has

    been provided with two earthing pads All nuts and bolts are tightened as per the

    specified torque

    Equipment erection is complete in allrespects as per the approved drawing

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    5/13

    ISOLATORSGENERAL

    CHECKS

    Leveling and alignment of structureand base frame

    Control box/marshalling box is freefrom any physical defects

    Tightness of nuts and bolts ofterminal connectors

    Auxiliary contacts and relays havebeen cleaned and free from dust

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    6/13

    ISOLATORSGENERAL

    CHECKS

    Corona rings are provided andproperly fixed

    Cable termination and tightness

    External cabling completed in allrespects

    All the cable identification tags

    provided and all cores are providedwith identification ferules at M.B

    All moving parts are lubricated

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    7/13

    ISOLATORSGENERAL

    CHECKS

    Freeness of manual operation

    Greasing has been made on the maincontacts according to manufacturers

    specificationFunctional checking of auxiliary

    contacts for indications and

    interlocksErection completion certificate along

    with list of outstanding activities

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    8/13

    ISOLATORSGENERAL

    CHECKS

    All spare wires are terminated at theterminal blocks

    Earth switch connected to earththrough braided wires.

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    9/13

    ISOLATORS CHECKS ON

    ELECTRICAL MOTOR

    IR value of the motor windingbetween phase to ground for all thethree phases.

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    10/13

    ISOLATOROPERATIONAL

    CHECKS

    Operate the isolator and record themotor current

    Operation of isolator fromlocal/remote

    Measurement of operating time.

    Auxiliary contacts checking bothunder close and open condition

    Checking of control circuit

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    11/13

    ISOLATORS INSULATION

    RESISTANCE TEST

    Isolator close condition

    Between male side to ground andfemale side to ground

    Isolator open condition

    Between male side to ground andfemale side to ground

    Between male side to female side

  • 8/10/2019 Erection , Testing & Commissioning of Isolators

    12/13

    ISOLATORS OTHER CHECKS

    Contact resistance measurement

    Checking of interlocks

    Final documentation and approval ofthe test results.