epri's integrated grid cost benefit analysis framework ... · epri’s integrated grid cost...

18
EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project Manager, EPRI NREL Workshop: Benchmarking Distribution Grid Integration Costs under High Distributed PV Penetrations September 19, 2017 © 2017 Electric Power Research Institute, Inc. All rights reserved.

Upload: hoangthien

Post on 06-Jun-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

EPRI’s Integrated Grid Cost Benefit Analysis

Framework Modeling Distribution

System Costs

Nadav Enbar Principal Project Manager, EPRI

NREL Workshop: Benchmarking Distribution Grid Integration Costs under

High Distributed PV Penetrations

September 19, 2017

© 2017 Electric Power Research Institute, Inc. All rights reserved.

Page 2: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

EPRI’s Integrated Grid Initiative: The Foundation for a CBA Framework

2 © 2017 Electric Power Research Institute, Inc. All rights reserved.

The dynamic power system of the future requires an

end-to-end integrated approach.

An Integrated

Grid

3002002733

3002004878

At EPRI.com, search for the complete number: 300200xxxx

Page 3: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

What do we mean by “Benefit-Cost Framework”?

Benefit-Cost Analysis Process

Phenomena

Net Costs & Benefits

Cost &Benefit

Components ∆ Fuel

∆ O&M

∆ Revenue Requirements

∆ CustomerCosts

∆ Interruption Cost

Costs, Investments

Impacts & Phenomena

∆ Loss kWh

∆ LoadkWh

∆ GenkWh

∆ AncillaryServices

∆ T&D Investment

Proposed Project

Base/ Comparison

Case

Costs, Investments

Phenomena

A BCA “Framework” canbe expressedinterms of impacts & phenomena to beincluded,or interms of cost andbenefit components.

A framework also specifies the perspective or point of view.

© 2017 Electric Power Research Institute, Inc. All rights reserved. 3

Page 4: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

mul

i rma

i ansi

Hosting Energy

Capacity Reliability

DER Adoption

Market Conditions

System Assumptions

Customer or Owner

Cost/Benefits

Societal Costs/BenefitsSystem

Cost Changes

isting stemdel(s)

ad recasts

riability ofiles

isting neration

isting twork del

st of se se

st of enario

4 © 2017 Electric Power Research Institute, Inc. All rights reserved.

Bulk SystemResource Adequacy

Flexibility

Operational Practices & Si ation

Transm ssion Perfo nce

Transm ssion Exp on

LOLE/ReserveMargin &CapacityCredit

Distribution System

Scenario Definition Benefit/Cost

B

Feeder Performance Characterization

Feeder HostingCapacity Analysis

Feeder ClusteringBased on Hosting

Feeder ClusteringBased on Energy

Impacts

Capacit Analysis

Energ Analysis onSelect Feeders

Losse s/ConsumptionResults Extrapolated

to System

Miti gationEvaluation

Benefit/Cost Analysis

Bul System Analysis

FeederMode ls

Load Data

Hosting Capacity Analysis

Energ Analysis

Capacity Analysis

Asset De ferral

DE PerformanceCharacterization

DER Data

B

C

D

Reliability Analysis

Reliability Analysis

E

Substation – LevelHosting Capacity for

DER

A

LO

Transmission System

Performance Studies

DERScenarios

Resource Adequacy

Ex Sy Mo

Lo Fo

Va Pr

Ex Ge

Ex Ne Mo

Resource Epxansion

New Resources/ Expansion Plan

Thermal /Voltage Impacts

Operational Simulations

Resource Dispatches

Transmission System Upgrades

Technology options

Transmission Expansion

Losses

Reliability ImpactsReserve &

Operational Changes

LE/ Reserve Margin &Capacity Credit

New Reserve & Operational

Modes

Integrated Grid Bulk System Analysis Framework

Costs of newresources

Production Costs &Marginal Costs

Costs of mitigation/ upgrades

Cost of Losses

Co Ba Ca

Co Sc

System Flexibility Assessment

Flexibility Metrics

Line Type Legend Data Input Final Result Feed-Forward Result Feed Back Result

Frequency Impacts

Hosting Capacity PV & Demand Profiles (See Fig. 5.3)

PQ &Protection Impacts

Integrated Grid Methodology

The Integrated Grid’s benefit-cost frameworkcontains both bulk system and distribution system elements.

Optimal HostingCapacity Location

Feeder-SpecificHosting Capacity for

DER

Page 5: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Categories of Costs and Benefits for Utilities, Customers and Society

Societal Perspective

Customer Perspective

è

Utility-Cost

Function

§Utility Operations (people and how they do their jobs: non-fuel O&M, non-production assets, safety)

§System Operations (the power system and its efficiency: losses,combustion, dispatch optimization, emissions)

§Utility Assets (production assets required: GT&D)

§Reliability & Power Quality (frequency and duration of customer interruptions, harmonics, sags/swells, voltage violations)

§Direct Customer Costs & Benefits (equipment & other direct customer costs)

§Environmental, Other Costs & Benefits (environmental & other costs & benefits otherwise externalized)

è

© 2017 Electric Power Research Institute, Inc. All rights reserved. 5

Page 6: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

A General Benefit-Cost Analysis Approach

§ BCA examines cost changes between at least two alternatives with different physical circumstances.

§ Comparing the alternative with the base case reveals physical changes, or impacts. Changes in utility assets and/or expenses may result. Some costs are avoided, while others incurred. Market interactions (price, power flows) may be affected.

§ In some cases customers are impacted directly, affecting quality of service. Customers may also affect the system with their DER.

§ An analysis can be customer-oriented in utility-planning fashion, or can adopt a societal perspective.

Utility/Market Impacts

Change in Asset Costs ($) [acceleration / deferral, ∆ expected life, etc.]

Change in O&M expenses ($) [∆ labor, ∆ duty cycles, etc.]

Change in Energy Costs (¢/kWh) [∆ fuel, ∆ variable O&M]

AND/OR: Change in Market Purchases [∆ Energy, ∆ Capacity, ∆ Ancillary Services]

Customer Impacts Change in Other Customer Costs

[Value of Reliability, Power Quality, etc.]

Societal Impacts Change in Societal Costs/Benefits [Emissions, Economic Impacts]

© 2017 Electric Power Research Institute, Inc. All rights reserved. 6

Page 7: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

An Integrated Approach for Distribution Analysis § Hosting Capacity Analysis – Voltage/Protection/Reliability components Voltage

– Mitigation required to prevent potential adverse issues

§ Thermal Capacity Analysis – Capacity component – Deferral of system upgrades

§ Energy Analysis – Energy component – Change in losses/consumption

§ Benefit-Cost Analysis – Benefit and/or cost implications of capacity and energy analyses at a given PV penetration level

Energy Reliability

Integrated Approach

Protection Thermal Capacity

Watts

Impedanceà

Load Only

Load and PV

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Month EnergyLosses

Energy

Timeà

unservedenergy

energyexceeding normal

Curren

t

Impedanceà

relaydesensitization

volta

ge

timeà

limit

unacceptable overvoltage

© 2017 Electric Power Research Institute, Inc. All rights reserved. 7

Page 8: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Analysis for Distribution Assessment Analysis Topic Area Description

Transformer Deferral Thermal Capacity Analysis of the potential for PV to defer substation

transformer upgrades by reducing net feeder demand

Analysis of the reduction in distribution line and

Energy Feeder Losses transformer losses due to generation sources being

located closer to the load

Energy Consumption

Effect of customer-based PV on delivery voltages

Feeder Voltage Analysis of overvoltage deviation issues due to PV along with mitigation options and associated costs

Analysis of thermal loading issues due to potential Hosting Capacity Thermal reverse power flow with mitigation options and associated and Mitigation costs

Analysis of protection coordination issues due to changes Feeder Protection in fault current along with mitigation options and

associated costs

© 2017 Electric Power Research Institute, Inc. All rights reserved. 8

Page 9: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Example: PV’s Impact on Distribution Plans

§Example is a 20-year rooftop PV scenario, high penetration, unguided location:

PV Energy as a % of Total Feeder Load

§Circuit analyzed with a detailed technical model; plans maintain voltage, protection, and thermal limitations

© 2017 Electric Power Research Institute, Inc. All rights reserved. 9

Page 10: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Change-case Capital

T I M E

Base-case Capital

Projects Required to Maintain Circuit Within Limits

1ø Reconductor 1.6 km

3ø Reconductor 5.2 km Directional Relaying at Sub

1ø Reconductor .4 km 2-year deferral Reconductor: 3ø 5.2 km, 1ø 1.6 km

3ø Reconductor 1.3 km

2-year deferral Reconductor: 3ø 1.3 km, 1ø 3.4 km

© 2017 Electric Power Research Institute, Inc. All rights reserved. 10

Page 11: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Example: Capital à Economic Present Worth Costs

Reconductor project appears in Year 9 in Base Case

Project deferred to Year 11 in Change Case

Difference between the plans is net deferral value.

© 2017 Electric Power Research Institute, Inc. All rights reserved. 11

Page 12: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Example: Capital à Economic Present Worth Costs

5.2 km 3ø recon

5.2 km 3ø recon 1.6 km 1ø

1.3 km 3ø recon

1.3 km 3ø recon 3.4 km 1ø

Since these are PW$, the difference in cost between the two scenarios

is their arithmetic sum.

Costs in the out years are from the two added 1ø reconductor projects in 10 & 13.

Present Worth Difference, Change minus Base Case

Over the 20 year period, Capital Costs Increase by $377k = 1.91 ¢/kWhgen

© 2017 Electric Power Research Institute, Inc. All rights reserved. 12

Page 13: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Deferral period2nd Deferral period

Changes in Load & Losses Between Base and Change Case

+ 3% increase in Consumption (compared with low voltages in base case)

17% decrease ∆ Losses ∆ Consumption

1% decrease

Year Consumption Savings of 0.08 ¢/kWhgen

Megawatt-hours

Distribution Loss Savings of 0.07 ¢/kWhgen

§ Circuit reacts to changing conditions and investments – PV reduces line losses, but changes in voltage and voltage control alter both loads and losses. – %-Consumption changes are small relative to total load, but are often larger than ∆MWh losses. – 3% increase in consumption in year 8 related to a decrease in consumption in the base casedue to low voltage. This was corrected when the reconductor project went in-service in year 9.

– Overall voltage is reduced in the change case because of lower tap settings and lower off-peak voltage. Some of the change in losses is associated with this reduction in voltage.

© 2017 Electric Power Research Institute, Inc. All rights reserved. 13

Page 14: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Example Total Net Distribution Value Feeder HM: Moderate PV, Unguided, Rooftop vs. Base Case (no PV)

Note: The full distribution cost would also include an assessment of the value of transformer deferral due to peak demand reduction.

© 2017 Electric Power Research Institute, Inc. All rights reserved. 14

Page 15: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Sample of EPRI CBA Research and Applications

Title Year

Published A Systematic Framework for Analyzing the Cost-Benefit of Using Energy Storage 2017to Mitigate Grid Issues

Microgrid Economics and a Cost-Benefit Framework 2017

Comparing the Cost-Benefit of Guided vs. Unguided PV Deployment on 2016Distribution

Time and Locational Value of DER: Methods and Applications 2016

A Framework for Determining the Technical and Economic Impacts of PV System 2015Wide

Guidebook for Cost/Benefit Analysis of Smart Grid Demo Projects 2015

The Economics of Solar PV Plant Variability on Distribution Equipment 2015

The Integrated Grid: A Benefit-Cost Framework 2015

The Integrated Grid: Realizing the Full Value of Central and Distributed Energy 2014Resources

Understanding the Costs and Benefits of Increasing Grid Penetrations of PV 2014

Methodological Approach for Estimating the Benefits and Costs of Smart Grid 2010Projects

© 2017 Electric Power Research Institute, Inc. All rights reserved. 15

Page 16: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Some Research Takeaways

Considerations for quantifying the time and locational value of distributed PV

§ Identify feeder-specific issues that can be solved with solar – Likely to be the most effective way to increase distributed PV’s net distribution system value

§ Determine feeder-specific PV hosting capacity

§ Areas with mid-day peak loads and limited remaining head room are more likely to benefit from distributed PV

§ Detailed energy analysis at the distribution system is not a high priority due to low cost of energy relative to high cost of capital upgrades

§ “Smart Inverter” functions show promise for low cost voltage management and grid support – Potential low cost solution; more research needed to determine the “best” functions to use; need updates to codes and standards (IEEE 1547)

© 2017 Electric Power Research Institute, Inc. All rights reserved. 16

Page 17: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Research Gaps & Next Steps

§Market Signals for DER – To achieve optimal economic outcomes, what are the market signals that balance the tradeoffs of increasing hosting capacity (delivery capacity) vs. increasing DER that has to be curtailed?

§Distribution challenges with locational marginal prices §Centralized control/optimization vs. Market-based DER dispatch

§What is a utility’s obligation to serve? – How will costs be allocated fairly over time? When first-comers use up the available hosting capacity, is it fair to impose a cost on late-comers?

§Requirements for DER to be used as a capacity resource

– What capacity contribution does PV provide to distribution?

§Probabilistic-based planning and DER forecasting

© 2017 Electric Power Research Institute, Inc. All rights reserved. 17

Page 18: EPRI's Integrated Grid Cost Benefit Analysis Framework ... · EPRI’s Integrated Grid Cost Benefit Analysis Framework Modeling Distribution System Costs Nadav Enbar Principal Project

Together…Shaping the Future of Electricity

Steven Coley Nadav Enbar Tanguy Hubert Sr. Project Engineer Principal Project Manager Sr. Project Engineer [email protected] [email protected] [email protected]

Jeff Roark Dean Weng Technical Executive Sr. Project Engineer [email protected] [email protected]

© 2017 Electric Power Research Institute, Inc. All rights reserved. 18