Schedule 19 – Part 2 Equator Principles Contractor accepts to comply with the responsibility matrix below based on the extract of the Equator principles. With respect to items I, II, III, and from 1 to 3: Contractor should provide, when needed, all necessary and relevant technical information and data, which can be reasonably collected to support the Employer on this issue. Key R = Responsible: Those responsible for the performance of the task. There should be exactly one person with this assignment for each task. A = Assists: Those who assist completion of the task C = Consulted: Those whose opinions are sought and with whom there is two-way communication I = Informed: Those who are kept up-to-date on progress and with whom there is one-way communication WB/ IFC Guideline Description Employer Contracto r I Development of Environmental Management Plans for construction and operational phases R A II Environmental Permit R A III Grievance management and community relations during operational phase. Interface with community during construction phase. R A/C 1

Upload: rochdibahiri4184

Post on 24-Sep-2015

7 views

Category:

Documents


1 download

DESCRIPTION

m

TRANSCRIPT

Schedule 7

Schedule 19 Part 2Equator Principles

Contractor accepts to comply with the responsibility matrix below based on the extract of the Equator principles.

With respect to items I, II, III, and from 1 to 3: Contractor should provide, when needed, all necessary and relevant technical information and data, which can be reasonably collected to support the Employer on this issue.

Key

R = Responsible: Those responsible for the performance of the task. There should be exactly one person with this assignment for each task.A = Assists: Those who assist completion of the task

C = Consulted: Those whose opinions are sought and with whom there is two-way communication

I = Informed: Those who are kept up-to-date on progress and with whom there is one-way communication

WB/ IFC Guideline

DescriptionEmployerContractor

IDevelopment of Environmental Management Plans for construction and operational phases

RA

IIEnvironmental Permit

RA

IIIGrievance management and community relations during operational phase. Interface with community during construction phase.

RA/C

Contractor Scope

DescriptionEmployer Contractor

1Provide, only for the provisions of the TSA/SAA, engineering and technical support and information to Employer for carrying out the Environmental Impact Assessment (EIA) review

A/CR

2Implementation of Construction and Operational Environmental Management Plan in accordance with Contractors Works defined under the TSA/SAA. e.g. transportation, traffic, noise, dust prevention, labour management, health and safety etc AR

3Support the Employer in addressing grievances with 3rd parties during construction and operation phase to the extent that such grievances are in relation to the scope of work of the Contractor.

A/CR

1