environmental impact assessment reporthppcb.nic.in/iocl_eia.pdf · eia report for lpg bottling...
TRANSCRIPT
EIA Report for LPG Bottling Plant Una, Himachal Pradesh i
ENVIRONMENTAL IMPACT ASSESSMENT REPORT
FOR
PROPOSED AUGMENTATION IN LPG BULK STORAGE CAPACITY AT LPG BOTTLING PLANT AT MEHATPUR, UNA, HIMACHAL PRADESH
SUBMITTED TO
M/s INDIAN OIL CORPORATION LIMITED
PREPARED BY
M/s. ULTRA-TECH ENVIRONMENTAL LABORATORY AND CONSULTANCY
(GazzetedByMoEF) Unit No. 206, 224, 225 Jai Commercial Complex, Eastern Express Highway,
Opp Cadbury Factory, Khopat, Thane (West) – 400 061 Tel: 022 2534 2776, Fax: 022 25429650, Email: [email protected]
Website: www.ultratech.in
EIA Report for LPG Bottling Plant Una, Himachal Pradesh ii
TABLE OF CONTENTS EXECUTIVE SUMMARY .......................................................................................................... 1 CHAPTER 1. INTRODUCTION ................................................................................................ 6
1.1 Introduction of Project and Project Proponent ................................................................. 6 1.2 Brief description of Nature, Size and Location of the project ......................................... 7 1.3 Scope of the Study............................................................................................................ 9 1.4 Applicable Environmental Regulations ........................................................................... 9 1.5 Objective and Scope of EIA Study ................................................................................ 10 1.6 Structure of EIA Report ................................................................................................. 10
CHAPTER 2. PROJECT DISCRIPTION ................................................................................ 12 2.1 Type of project ............................................................................................................... 12 2.2 Need and Justification of the Project .............................................................................. 12 2.3 Location & Layout ......................................................................................................... 12 2.4 Salient Features of the Project ........................................................................................ 18
2.4.1 Proposed Schedule and Approval for Implementation ........................................... 19 2.4.2 Land use .................................................................................................................. 19
2.5 Process Description ........................................................................................................ 19 2.5.1 LPG Receipt and Storage ........................................................................................ 19 2.5.2 Unloading ................................................................................................................ 19 2.5.3 LPG Pump House ................................................................................................... 19 2.5.4 Air Compressor and Air Drying Unit ..................................................................... 19 2.5.5 LPG Cylinder filling and associated facilities ........................................................ 20
2.6 Process Flow Chart......................................................................................................... 21 2.7 Infrastructure at the Facility ........................................................................................... 22
2.7.1 Description of Mounded Bullets ............................................................................. 22 2.7.2 Parking Lot.............................................................................................................. 23
2.8 Fire Prevention System .................................................................................................. 23 2.9 Plant and Equipment Details .......................................................................................... 25 2.10 Power Requirement ........................................................................................................ 27 2.11 Manpower Requirement ................................................................................................. 27 2.12 Water and Wastewater Management .............................................................................. 28 2.13 Solid and Hazardous Waste Disposal System ................................................................ 28
CHAPTER 3. DESCRIPTION OF THE ENVIRONMENT .................................................. 29 3.1 General ........................................................................................................................... 29 3.2 Methodology .................................................................................................................. 29 3.3 Study Area included in Environmental Setting .............................................................. 29
3.3.1 Land Use/Land Cover of the Study Area ................................................................ 29 3.3.2 Drainage Pattern ...................................................................................................... 32 3.3.3 Contour Pattern of the Study Area .......................................................................... 32
3.4 Meteorological Data ....................................................................................................... 34 3.5 Ambient Air Quality ....................................................................................................... 36
3.5.1 Methodology Adopted for the Study ...................................................................... 37 3.5.2 Sampling and Analytical Techniques ..................................................................... 38
3.6 Noise............................................................................................................................... 39 3.6.1 Objective ................................................................................................................. 39
EIA Report for LPG Bottling Plant Una, Himachal Pradesh iii
3.6.2 Methodology ........................................................................................................... 39 3.6.3 Method of Monitoring and Parameters Measured .................................................. 40 3.6.4 Noise Results .......................................................................................................... 41
3.7 Water Environment ........................................................................................................ 42 3.7.1 Ground Water Hydrology ....................................................................................... 42 3.7.2 Selection of Sampling Locations ............................................................................ 42 3.7.3 Methodology ........................................................................................................... 43 3.7.4 Ground and Surface Water Quality ......................................................................... 43
3.8 Soil ................................................................................................................................. 44 3.8.1 Selection of sampling Locations ............................................................................. 44 3.8.2 Methodology ........................................................................................................... 45 3.8.3 Soil Results ............................................................................................................. 45
3.9 Biological Environment ...................................................................................................... 47 3.9.1 Introduction ............................................................................................................. 47 3.9.2 Existing status of Flora in the Study Area: ............................................................. 48 3.9.3 Existing status of Fauna in the area: ....................................................................... 49
3.10 Socio-Economic Environment ....................................................................................... 50 CHAPTER 4. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ................................................................................................................................ 56
4.1 Introduction .................................................................................................................... 56 4.2 Impact Assessment ......................................................................................................... 56
4.2.1 During Construction Phase ..................................................................................... 56 4.2.2 During Operation Phase .......................................................................................... 57
4.3 Impact Mitigation Measures ........................................................................................... 58 4.3.1 During Construction Phase ..................................................................................... 58 4.3.2 During Operation Phase .......................................................................................... 60
4.4 Impact Matrix ................................................................................................................. 61 4.5 Summary of Environment Impacts and Mitigation Measures ....................................... 64 4.6 Conclusion ...................................................................................................................... 67
CHAPTER 5: PROJECT BENEFITS ...................................................................................... 68 5.1 Project Benefits .............................................................................................................. 68 5.2 Improvements in the Physical Infrastructure ................................................................. 68 5.3 Improvements in the Social Infrastructure ..................................................................... 68 5.4 Employment Potential .................................................................................................... 69 5.5 CSR and Socio-Economic Development ....................................................................... 69 5.6 Direct Revenue Earning to the National and State Exchequer ....................................... 70 5.7 Other Tangible Benefits ................................................................................................. 70
CHAPTER 6: ANALYSIS OF ALTERNATES ....................................................................... 71 6.1 Alternative Technology .................................................................................................. 71 6.2 Alternative Site ............................................................................................................... 71
CHAPTER 7. ADDITIONAL STUDIES .................................................................................. 72 7.1 Public Consultation ........................................................................................................ 72 7.2 Quantitative Risk Assessment ........................................................................................ 72
7.2.1 Methodology ........................................................................................................... 72 7.2.2 QRA Approach ....................................................................................................... 72 7.2.3 Hazard Identification .............................................................................................. 75
EIA Report for LPG Bottling Plant Una, Himachal Pradesh iv
7.2.4 Events and Ignition Probability .............................................................................. 78 7.2.5 Consequential Events .............................................................................................. 79 7.2.6 Consequence Analysis ............................................................................................ 81 7.2.7 Likelihood Estimation ............................................................................................. 98 7.2.8 Risk Analysis ........................................................................................................ 100 7.2.9 Risk Contours........................................................................................................ 100 7.2.10 Conclusion ............................................................................................................ 102 7.2.11 Recommendations ................................................................................................. 102
CHAPTER 8. ENVIRONMENT MANAGEMENT AND MONITORING PLAN ............ 105 8.1 Introduction .................................................................................................................. 105 8.2 EMP during Construction Phase .................................................................................. 105
8.2.1 Air Environment ................................................................................................... 105 8.2.2 Noise Environment ............................................................................................... 106 8.2.3 Water Environment ............................................................................................... 106 8.2.4 Land Environment ................................................................................................ 107 8.2.5 Biological Environment ........................................................................................ 107 8.2.6 Socio-economic Environment ............................................................................... 107 8.2.7 Health and Safety .................................................................................................. 107
8.3 EMP during Operation Phase ....................................................................................... 108 8.3.1 Air Environment ................................................................................................... 108 8.3.2 Noise Environment ............................................................................................... 108 8.3.3 Water Environment ............................................................................................... 109 8.3.4 Land Environment ................................................................................................ 109 8.3.5 Biological Environment ........................................................................................ 109 8.3.6 Socio-economic Environment ............................................................................... 110
8.4 Environmental Monitoring Programme ...................................................................... 110 8.4.1 Ambient Air Quality ............................................................................................. 111 8.4.2 Surface Water Quality ........................................................................................... 112 8.4.3 Noise Level ............................................................................................................... 112
8.5 Environmental Management Cell ................................................................................. 112 8.6 Budgetary Allocation for Environmental Protection Measures ................................... 112
CHAPTER 9. DISCLOSURE OF CONSULTANTS ENGAGED ....................................... 114 9.1 Consultants Engaged .................................................................................................... 114 9.2 Laboratory for Analysis ............................................................................................... 115
LIST OF TABLES
Table 1.1: Project and Project Proponent Description .................................................................... 6 Table 2.1: Environmental Setting around Project Site .................................................................. 13 Table 2.2: Salient Features of Existing /Proposed facility ............................................................ 18 Table 2.3: Non-Plant Shed/Building ............................................................................................. 25 Table 2.4: Plant Shed/Building ..................................................................................................... 26 Table 2.5: Brief Description of Facilities ..................................................................................... 26 Table 2.6: Electrical Systems ........................................................................................................ 27
EIA Report for LPG Bottling Plant Una, Himachal Pradesh v
Table 2.7: Safety data ................................................................................................................... 27 Table 2.9: Non-Hazardous Waste ................................................................................................. 28 Table 2.10: Hazardous waste ........................................................................................................ 28 Table 3.1: Landuse / Landcover Statistics of Area within 10 km Radius ..................................... 31 Table 3.3: Meteorological Monitoring At study area ................................................................... 34 Table 3.4: Meteorological Data Recorded at study area ............................................................... 35 Table 3.4: Ambient Air Monitoring Locations ............................................................................. 37 Table 3.5: Ambient Air Quality Monitoring Results .................................................................... 37 Table 3.6: Techniques Used For Ambient Air Quality Monitoring .............................................. 38 Table 3.7: Noise Level Monitoring Stations in the Study Area .................................................... 40 Table 3.8: Ambient Noise Monitoring Results ............................................................................. 41 Table 3.9: Ambient Noise Standards ............................................................................................ 42 Table 3.10: Water Quality Sampling Locations .......................................................................... 43 Table 3.11: Ground Water Characteristics .................................................................................... 43 Table 3.12: Surface Water Characteristics .................................................................................... 44 Table 3.13: Soil Sampling Stations in the Study Area.................................................................. 44 Table 3.14: Chemical Characteristics of Soil in the Study Area .................................................. 46 Table 3.15: List of naturally occurring trees within Study Area .................................................. 48 Table 3.16: List of under growth plants ........................................................................................ 48 Table 3.17: List of fruit trees ........................................................................................................ 49 Table 3.18: List of Faunal members of the project area ............................................................... 49 Table 3.19: Demography of Una & Rupnagar Districts ............................................................... 50 Table 3.20: Village & Town Breakup in the Study Area ............................................................. 51 Table 3.21: Population & Sex Ratio Breakup in the Study Area.................................................. 51 Table 3.22: Population & Sex Ratio Breakup in the Study Area.................................................. 52 Table 3.23: SC & ST Population break-up in the Study Area ...................................................... 52 Table 3.24: Literacy break-up in the Study Area .......................................................................... 52 Table 3.25: Urban/Rural Population break up in the Study Area ................................................. 53 Table 3.26: Status of working population in the study area ......................................................... 53 Table 4.1: Impact Matrix .............................................................................................................. 62 Table 4.2: Summary of Impacts and Mitigation Measures ........................................................... 64 Table 4.3: Overall Matrix ............................................................................................................. 67 Table 7.1: List of identified Scenarios .......................................................................................... 76 Table 7.2: Typical Pasquill Stability classes ................................................................................. 78 Table 7.3: Ignition Probabilities as used in PHAST. .................................................................... 80 Table 7.4: Leak sizes considered .................................................................................................. 81 Table 7.5: Thermal Radiation Impact Criteria for Personnel ....................................................... 82 Table 7.6: Thermal Radiation Impact Criteria for Equipment ...................................................... 82 Table 7.7: Flammable (LFL) dispersion distances ....................................................................... 83 Table 7.8: Jet fire radiation distances ........................................................................................... 89
EIA Report for LPG Bottling Plant Una, Himachal Pradesh vi
Table 7.9: Pool fire radiation distances ......................................................................................... 95 Table 7.10: Fireball Radiation Distances ...................................................................................... 95 Table 7.11: Estimated failure frequency ....................................................................................... 99 Table 8.1: Post Study Environmental Monitoring Program ....................................................... 111 Table 8.3: Cost of Environmental Protection Measures ......................................................... 113 Table 9.1: EIA Team ................................................................................................................... 114 Table 9.2: Functional Area Experts Involved in the EIA ........................................................... 115
LIST OF FIGURES Figure 1.1: Connectivity Map ......................................................................................................... 8 Figure 2.1: Project Location ......................................................................................................... 15 Figure 2.2: Google Image of the Project Site ............................................................................... 16 Figure 2.3: Google Image of the Project Site ............................................................................... 17 Figure 2.4: Process Flow Chart ..................................................................................................... 22 Figure 2.5: Typical Mounded Bullet System ................................................................................ 23 Figure 3.1A: Satellite Map of the study area ................................................................................ 30 Figure 3.1B: Landuse/Landcover of 10 Km Study Area .............................................................. 31 Figure 3.2A: Drainage Map of the study area ............................................................................... 32 Figure 3.2B: Drainage Map of the study area ............................................................................... 33 Figure 3.3: Baseline Sampling Monitoring Locations .................................................................. 34 Figure 3.4: Windrose for period of January 2017 to April 2017. ................................................. 36 Figure 3.5: Percentage Distribution of Main Workers in the Study Area .................................... 55 Figure 7.1: Risk Acceptance Criteria ............................................................................................ 73 Figure 7.2: Event tree for Continuous release with rainout (from PHAST software) .................. 79
LIST OF ANNEXURE
ANNEXURE I: Project Site Layout Plan ANNEXURE II: Ambient Air Quality Monitoring Results
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 1
EXECUTIVE SUMMARY
Introduction M/s. Indian Oil Corporation Limited (IOCL) is a government of India enterprise with a Maharatna status and a Fortune 500 and Forbes 2000 company. Incorporated as Indian Oil Corporation Ltd. on 1st September, 1964 Indian Oil and its subsidiaries account for approximately 48% of petroleum products market share, 34% national refining capacity and 71% downstream sector pipelines capacity in India. It is India’s flagship national oil company and downstream petroleum major thus being India’s largest commercial enterprise. As the flagship national oil company in the downstream sector, Indian Oil reaches precious petroleum products to millions of people every day through a countrywide network of about 35,000 sales points. They are backed for supplies by 167 bulk storage terminals and depots, 101 aviation fuel stations and 91Indane (LPG) bottling plants. IOCL is a premier public sector company in the Oil & Gas Sector and is engaged in the business of refining and retailing of petroleum products including LPG in the country. IOCL is having about 91 LPG bottling plants, which serve every corner of the country. Indane (the trade name of LPG of IOCL) is supplied to the consumers through a network of about 5,456 distributors (51.8% of the industry).The growth in demand of LPG for domestic purpose is increasing at a rapid pace. In order to meet the local need in the State of Himachal Pradesh,IOCL is proposing to augment the storage capacity at Una LPG Bottling Plant withinIOCLpremises of32.56 Acres. Project Description There will be no chemical process involved and the operation carried out will be receipt of LPG in Bulk form in tank trucks from the sources namely IOCL Jalandhar, Lonietc. The storageshall be in mounded bullets (existing and proposed) and filling of LPG into cylinders using carousel and associated systems. The cylinders filled will be checked for quality and then dispatched. In the proposed augmentation of storage capacity at LPG bottling plant the storage will be pressurized form in mounded storage. The LPG storage will be in existing 3 bullets of 300 MT (i.e. 900 MT existing) each and proposed 2 bullets of 600 MT each (i.e. 1200 MT proposed)with a total capacity of 2100 MT. TheMounded Bullet System will store the LPGin liquid form. The system of mounded storage has been recognized as one of the safest form of storage for LPG.Mounded Bullets will be submerged in ground and encased in four sided retaining wall having a designed layer of earth over the bullets Technology and Activity (Process) Description There is no manufacturing process involved in the LPG Bottling Plant. The operations can be divided into:
Receipt of LPG is by bulk truck from Jalandhar,Loni,etc Storage of LPG in mounded bullets fabricated as per PESO standards
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 2
Filling of LPG in cylinder by carousel in domestic/ commercial/ industrial cylinders
Dispatch of packed LPG cylinder by packed trucks
The entire operation of RECEIPT, STORAGE, FILLING AND DISPATCH of LPG is carried out in a closed system thereby eliminating risk of leakage of products and to achieve enhanced safety. There is no chance of mixing LPG with atmosphere outside during normal operations.
Table1: Project Capacity SN Product Existing (MT) Proposed (MT) Total (MT) 1 Storage of LPG
(Mounded Bullets) 3x300 -- 900
2 - 2x600 1200 Total 2100
Power Requirement
Power required for the existing operations is 450 KW contracted demand from Himachal Pradesh State Electricity Board. D.G Sets are used of 1x250 kVA, 1x400 kVA and 1x500 kVA. No additional power or DG Sets are required for proposed augmentation. Water Supply Total water requirement approx. 15 m3/day including domestic and fire water is being sourced from existing tube wells from site and no additional requirement is envisaged with proposed augmentation. The existing premises of LPG BP include STP of 5 m3/day capacity.
Table 2: Water Consumption SN Description Water Consumption in
m3/day Source
1 Domestic 4 Fresh Water 2 Cylinder washing 5 Approx 4 m3/day shall be
recycled and reused. Remaining 1 m3/day shall be
sourced as Fresh Water
3 Gardening 3 Treated water from STP 4 Fire Water Makeup 3 Fresh Water
Needed once a month during fire-mock drills
Total 15 The existing premises of LPG BP also include ETP (effluent treatment plant) of 3 KLPD capacity for treatment of waste process water.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 3
Fire Fighting Facilities Medium velocity Water Sprinkler systemis availablein product pump house,TLD
decantation Shed, Mounded Bullets, CR shed, Empty shed, Filling Shed and Filled Shed as per prevailing safety guidelines issued by OISD-144.
Fire fighting system comprising of MVWS System & Fire hydrant ring on proposed LPG Mounded Bulletsshall be provided as per prevailing safety guidelines issued by OISD-150.
Provision of Fire hydrant piping network with intermittent deluge valves covering full licensed area is available in line with OISD144 and shall be provided for proposed augmentation as per OISD 150.
The Fire Water tanks have been provided as shown in Table 2 and Schedule of Fire Pumps have been provided in Table 3.
Table 2: Details of Fire Tanks
SN Product Type of Tank Capacity
1 Existing Fire Water Tank
Vertical Above ground cone roof 2 X 3700 m3
Table 3: Schedule of Fire Pumps
SN Description Capacity Head mWC
Nos of Pumps
Operating Standby
1 Main Pumps Diesel Engine Driven
5x410 m3/hr 85m 3 2
2 Jockey Pumps Electrical Driven
2x10 m3/hr 85m 1 1
Instrumentation and Automation Instrumentation and Automation will be provided for the proposed Mounded Storage Vessels:
Tank Farm Management System: These shall comprise of automation of receipt of products.
Valve Automation system: The tank body Valves have been fitted with Electro-pneumaticRemote Operated Valves (ROV) to be closed by bleeding air manually or by a safety PLC in case of emergency.
Servo gauges: The gauges functions in remote for the tank inventory and tank shut down procedures
Interlock Shutdown System has been provided per the provision of OISD 144.
Earthing system at grid.
Gas Monitoring system having sensors all over the license area to pre-warn slightest of Leakage and MIMIC panel to communicate real time status
Access Control System: The system permits only authorized personnel to enter Plant.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 4
Control Room with equipment: The control room monitors and logs all events pertaining to the operation of the LPG BottlingPlant on real time basis.
Manpower The total IOCL manpower requirement at the LPG BP is 23. No additional requirement is envisaged with proposed augmentation. Description of Environment The area around the LPG Bottling Planthas been surveyed for physical features and existing environmental scenario. The field survey and baseline monitoring has been done from the period ofmid-January 2017 to mid-April 2017 Anticipated Environment Impacts and Environment Management Plan Land/Soil Environment Impact Mitigation During construction phase the top soil will be stored carefully and will be used again after construction/installation phase is over so as to restore the fertility of project site. During operation phase, as the complete system is closed loop, no leakage is envisaged and hence negligible impact on the topography during operation phase. Air Impact Mitigation The emission anticipated during construction period will include fugitive dust due to excavation of soil, levelling of soil, use of DG sets, movement of heavy construction equipment/vehicles, site clearing and other activities. Also water sprinkling shall be carried out to suppress fugitive dust during earthworks and along unpaved sections of access roads.During operational phase the facilityhas already been equipped with leak detection systems and shall be extended further to the augmented mounded bullets system. The air environment has minimal impact due to truck movement for receipt and dispatch. Noise Impact Mitigation Noise is generated from operation of pumps, blowers and DG sets and during vehicular movement. The mitigation measures have been implemented like acoustic enclosures for DG Sets as per CPCB guidelines,provision of ear plugs for labour in high noise area, green belts and landscaping have been developed which act as noise buffer. Water Impact Mitigation Avoid unwanted wastage of water and use of tanker water for construction activity. Wastewater generated will be continued to be recycled/ reused during operation of the LPG Plant and rain water harvesting shall be further promoted. Additionally, the rainwater from the landscape area will be continuedto recharge the ground water sources through recharge pit.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 5
Ecology and Biodiversity Impact Mitigation The proponent plans to strengthen and maintain the extensive green belt encompassing minimum 33% of plot area. The probability and consequences of significant ecological impacts occurring as a result of the operation of the facility are considered to be almost negligible.Municipal solid waste will be continued to be disposed through local bodies andspent lube oil from D.G. set will be sold to HPPCB Authorized recyclers. Hence no impact on flora and fauna is envisaged. Moreover there are no reserve forest and protected areas within 10 km radius. There will be no effluent discharge in the water body. Thus there is no impact on the aquatic biota present in vicinity of proposed project. Socio-Economic Environment Impact Mitigation The construction of the proposed augmentationis expected to provide temporary indirect employment to a good number of skilled and unskilled workers. The project will contribute to the socio-economic development of the area at the local level in turn reducing migration for employment. Hence the proposed project will have positive impact on the socio-economic environment. Environmental Monitoring Programme It is imperative that the IOCL shall continueto monitor environmental health, post clearance.
It helps to verify the predictions on environmental impacts presented in this study.
It helps to indicate warnings of the development of any alarming environmental situations, and thus, provides opportunities for adopting appropriate control measures in advance.
Project Benefits To cater the domestic as well as non-domestic LPG demand, Bulk LPG and Auto LPG demand of Unaand surrounding districts.
Proposed Schedule and Approval for Implementation The plant activities will be completed in a period of 12-15 months from the date of receipt of all the approvals from statutory authorities.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 6
CHAPTER 1. INTRODUCTION
1.1 Introduction of Project and Project Proponent M/s. Indian Oil Corporation Limited (IOCL) is a government of India enterprise with a Navratna status, and a Fortune 500 and Forbes 2000 company. Incorporated as IOCL on 1st September, 1964 Indian Oil and its subsidiaries account for approximately 48% petroleum products market share, 34% national refining capacity and 71% downstream sector pipelines capacity in India. It is India’s flagship national oil company and downstream petroleum major thus being India’s largest commercial enterprise. As the flagship national oil company in the downstream sector, Indian Oil reaches precious petroleum products to millions of people every day through a countrywide network of about 35,000 sales points. They are backed for supplies by 167 bulk storage terminals and depots, 101 aviation fuel stations and 91Indane (LPG) bottling plants. Indian Oil's vast marketing infrastructure of petrol/diesel stations, Indane (LPG) distributorships, SERVO lubricants and greases outlets and large volume consumer pumps are backed by bulk storage terminals and installations, inland depots, aviation fuel stations, LPG bottling plants and lube blending plants amongst others. The countrywide marketing operations are coordinated by 16 State Offices and over 100 decentralized administrative offices IOCL is a premier public sector company in the Oil & Gas Sector and is engaged in the business of refining and retailing of petroleum products including LPG in the country. It is the leading Indian corporate in the Fortune 'Global 500' listing, ranked at the 168th position in the year 2017. IOCL is having about 91 LPG bottling plants, which serve every corner of the country. Indane (the trade name of LPG of IOCL) is supplied to the consumers through a network of about 5,456 distributors (51.8% of the industry).The growth in demand of LPG for domestic purpose is increasing at a rapid pace. Bulk Liquefied Petroleum Gas (LPG) is received in a bullet tanker – truck from IOCL Jalandhar and Loniunloaded by using vapor compressors and stored in Mounded Bullets. The empty cylinders are unloaded in the unloading shed and sent bymeans of conveyors to the carousel for filling them with LPG. LPG is filled in cylinders of capacity 5 kg,14.2 kg, 19.0 kg and 47.5 kg. LPG from the storage area is pumped to the filling machine by means of LPGpumps for filling the cylinders. After filling cylinders and subsequent checks, the filled cylinders are sent tothe filled cylinder shed and loaded on to the trucks for dispatch to the LPG distributors to use for house holdand industrial purposes.The details of the Project and Proponents are as mentioned in Table 1.1.
Table 1.1: Project and Project Proponent Description Name of Project Proposed augmentation in LPG Bulk Storage capacity at
LPG Bottling Plant atMehatpur, Una, Himachal Pradesh by M/s Indian Oil Corporation Ltd.
Project Proponent M/s Indian Oil Corporation Limited
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 7
Name, contact number and address of Project Proponent
M/s Indian Oil Corporation Limited ShriJyotiprakashChakraborty Sr. Mgr(LPG-E), PSO Indian Oil Corporation Limited, Punjab State Office, Indian Oil Bhavan, Plot No. 3A, Sector-19A, Madhya Marg, Chandigarh - 160 019
Location of the Project
Village : Raipur Sahoran District : Una Taluka : Una State : Himachal Pradesh Latitude : 31°23'43.72"N Longitude : 76°19'40.43"E
Name, contact number and address of Consultant
Environmental Consultants : M/s. Ultra-Tech Environmental Consultancy & Laboratory (An ISO 9001-2008 Company, Accredited by NABET, Lab: recognised by MOEF&CC, GoI) Unit No. 206, 224, 225, Jai Commercial Complex, Eastern Express Highway, Opp. Cadbury Factory, Khopat, Thane (W) – 400601 Tel.: 91-22-25342776, 25380198, 25331438 Fax : 91-22-25429650 Email: [email protected] Website : www.ultratech.in
Size of proposed project activity 13.17 ha (32.56 acres) Plant Overview 1. LPG bottling plant
2. Distribute bulk products by road (by tank lorries ) Category of Project i.e. ‘A’ or ‘B’
Category ‘A’
Proposed capacity/area/length/tonnage to be handled/command area/lease area/number of wells to be drilled
Proposed expansion from 900 MT storage capacity of LPG to 2100 MT by installing 2x600 = 1200 MT of additional Mounded LPG Bullets
1.2 Brief description of Nature, Size and Location of the project The project activity isaugmentation in LPG Bulk Storage capacity at LPG Bottling Plant at Mehatpur, Una. As per the Environment Impact Assessment (EIA) Notification dated 14th September, 2006 as amended, the proposed project falls under 'Type 6b - Isolated Storage and
EI
Handlingschedule Environm This EIAmitigatioReferencIsolated Forests &TheBottlPlantfacicarried onearest rairport is
IA Report fo
g of Hazardo2 and 3 of
mental Impac
A Report addon measuresce (ToR) forStorage & H
& Climate Chling plant is ility is approout within thrailway statis Chandigarh
or LPG Bottl
ous Chemicaof MSIHC Rct Assessme
dresses the e for the sam
r EIA/EMP RHandling ofhange (MoElocated at U
oximately 13e premises oion is RaiM
h Airport at a
ling Plant U
als’ (As per Rules 1989 ent (EIA) Re
environmentme. The repReport for Pf HazardousEF&CC). Unadistrict i3.17hectare of the Bottlin
MehatpurRailwabout 118Km
Figure 1.1:
Una, Himacha
threshold plamended 20
eport.
tal impacts oport is prep
Projects requs Chemicals
n Himachal (32.56 acresng Plant. Thway Station m.
Connectivi
al Pradesh
lanning quan000), which
of the propopared, baseduiring Enviro
project by
Pradesh.Ths). The prophe site is easat approxim
ity Map
ntity indicateh requires p
sed project d on the Staonmental ClMinistry of
he total plotaposed augmesily accessibmately 0.4k
8
ed in columnpreparation o
and proposeandard Termlearance (ECf Environme
area of the Lentation shalble by road. km. The nea
n 3 of of an
es the ms of C) for ent &
LPG ll be The
arest
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 9
1.3 Scope of the Study EIA integrates the environmental concerns in the developmental activities so that it can enable the integration of environmental concerns and mitigation measures in project development. The study includes detailed characterization of existing status of environment in an area of 10 km radius around project site. In order to get an idea about the existing state of the environment, various environmental attributes such as meteorology, air quality, water quality, soil quality, noise level, ecology and socio-economic environment are studied /monitored. Environmental baseline monitoring has been carried out during mid-January 2017 to mid-April 2017 used to identify potential significant impacts. The report is prepared as per the Standard ToR and additional ToR granted at the21stEAC meeting held on 28th March, 2017 at Delhi The scope of the study broadly includes:
To describe the project and associated works together with the requirements for carrying out the proposed development
To establish the baseline environmental and social scenario of the project site and its surroundings
To identify and describe the elements of the community and environment likely to be affected by the project
To identify, predict and evaluate environmental and social impacts during the construction and operation phase of the project
To study the existing traffic load, predict the increment in traffic due the project and to suggest the management plan for the same
Details about conservation of resources
To design and specify the monitoring and audit requirements necessary to ensure the implementation and the effectiveness of the mitigation measures adopted
To access risk during construction and operation phase and formulate the disaster management plan onsite and offsite
To evaluate proposed pollution control measures and delineate Environmental Management Plan (EMP)
To delineate post-project environmental quality monitoring program 1.4 Applicable Environmental Regulations With respect to prevention and control of environmental pollution, the following Acts and Rules of Ministry of Environment and Forest, Government of India govern the proposed project:
Water (Prevention and Control of Pollution) Act, 1974 as amended in 1988
Air (Prevention and Control of Pollution) Act, 1981 as amended in 1987
Environment (Protection) Act, 1986 amended in 1991 and Environment (Protection) rules, 1986 and amendments thereafter
The Municipal Solid Wastes (Management and Handling) Rules, 2000
The Hazardous Wastes (Management, Handling and Trans boundary Movement) Rules,2009 as amended
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 10
The Manufacture, Storage and Import of Hazardous Chemical Rules, 1989
E-waste Management (Management and Handling) Rules, 2011
The Noise Pollution (Regulation and Control) Rules, 2000 and as amended
EIA Notification dated 14.09.2006 as amended 1.5 Objective and Scope of EIA Study EIA integrates the environmental concerns in the developmental activities so that it can enable the integration of environmental concerns and mitigation measures in project development. EIA can often prevent future liabilities or expensive alterations in project design. The study included detailed characterization of existing status of environment in an area of 10 km radius around project site. In order to get an idea about the existing state of the environment, various environmental attributes such as meteorology, air quality, water quality, soil quality, noise level, ecology and socio-economic environment are studied /monitored by an accredited Functional Area Expert. Environmental baseline monitoring has been carried out during January 2017 to April 2017and used to identify potential significant impacts. The scope of the study broadly includes:-
To describe the project and associated works together with the requirements for carrying out the proposed development
To establish the baseline environmental and social scenario of the project site and its surroundings
To identify and describe the elements of the community and environment likely to be affected by the project
To identify, predict and evaluate environmental and social impacts during the construction and operation phase of the project
To study the existing traffic load, predict the increment in traffic due the project and to suggest the management plan for the same
Conservation of resources
To design and specify the monitoring and audit requirements necessary to ensure the implementation and the effectiveness of the mitigation measures adopted.
To evaluate proposed pollution control measures and delineate environmental management plan (EMP) outlining additional control measures to be adopted for mitigation of adverse impacts.
To delineate post-project environmental quality monitoring program 1.6 Structure of EIA Report EIA report contains baseline data, project description and assessment of impacts and preparation of Environmental Management Plan and Disaster Management Plan. The report is organized in following ten chapters:
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 11
Executive Summary This chapter gives the Executive Summary of the EIA report. Chapter 1: Introduction This chapter describes objectives and methodology for EIA. Chapter 2: Project Description This chapter gives a brief description of the location, approachability, amenities, layout and utilities of the proposed project. This chapter also gives outline of status of completion of construction activities as this is an expansion project Chapter 3: Description of the Environment This chapter presents details of the baseline environmental status for microclimate, air quality, noise, traffic, water quality, soil quality, flora, fauna and socio-economic status etc. Chapter 4: Anticipated Environmental Impact and Mitigation Measures This chapter discusses the possible sources of pollution and environmental impacts due to the project during construction and operation phases and suggests the mitigation measures. Chapter 5: Project Benefits This chapter presents the benefits from this project. Chapter 6: Analysis of Alternatives This chapter covers Analysis of Site and Technology that were analyzed while preparing this report. Chapter 7: Additional Studies This chapter covers information about Public Consultation and Risk Assessment Studies for the construction and operation phase, the safety precautions that are taken during construction phase. Chapter 8: Environmental Management and Monitoring Plan This chapter deals with the Environmental Management Plan (EMP) for the proposed Project and indicates measures proposed to minimize the likely impacts on the environment during construction and operation phases and budgetary allocation for the same. This chapter also discusses the details about the environmental monitoring program during construction and operation phases. Chapter 9: Disclosure of Consultants This chapter deals with the details of consultants engaged and the NABET accreditation details of environmental consultants.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 12
CHAPTER 2.PROJECT DISCRIPTION
2.1 Type of project
Una LPG Bottling Plant (BP) operates strictly as a storage & packing facility for LPG. No by-products / additional products are generated / manufactured during the operations. The proposed augmentation enhances the storage capacity of LPG from 900 MT to 2100 MT. Hence, the present proposal is classified under Schedule 6(b) & Category ‘B’ according to EIA Notification 2006 & subsequent amendments.
2.2 Need and Justification of the Project
Liquid LPG is a clean fuel and is extensively used as cooking fuel in India. Due to increase in urbanization and improved quality of life the demand for its consumption is increasing. In order to increase its new customer base and to serve the existing customers in a better way M/s Indian Oil Corporation Ltd. are augmenting their existing bottling plants and setting up new plants. With the present LPG Bottling facilities in Himachal Pradesh, IOCL is unable to meet the growing demand of LPG in the State. As per the installed capacity, plant can bottle around 250 MT per day. Therefore, the existing tankage of 900 MT provides a cover equivalent to bottling of around 4 days. Moreover, with increase in demand in Himachal Pradesh and Punjab, there will be a need to operate the plant in two shifts, which will further reduce the cover to 2-3 days. Bulk LPG to the BP is positioned by road tankers which are loaded primarily from Loni BP near Delhi which is at a distance of about 350 kms from Una. In the event of non-availability of product at Loni, either due to high demand at other plants/markets or any technical constraint in JLPL, bulk LPG supplies to Una BP is executed from alternate sources e.g. Jaipur, Dumad, Kandla or Jamngar, which are at a distance higher than Loni. This may result in non-availability of product at Una if sufficient stock at plant is not maintained. The existing tankage at Una BP is sufficient for bottling of around 4 days. Any disruption in supplies either due to non-availability of product may result in dry out. In view of the foregoing, IOCL has proposed for provision of augmentation with 2nos of mounded bullets with 600 MT capacities at Una LPG BP. The augmentation of the storage capacity of Bottling Plant is estimated to cost 21.70crores.
2.3 Location & Layout
LPG bottling plant is located atapproximately 2.2 km from NH-503 and abutting SH-PWD Pump House Road. The nearest railway station is RaiMehatpur Railway station at approximately 0.4 km. The nearest airport is Chandigarh Airport ataround118 km. The Environmental Settingaround the project site is given in the Table 2.1:
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 13
Table 2.1: Environmental Setting around Project Site
SN Particulars Details 1. Name of Project Proposed augmentation in LPG Bulk
Storage capacity at LPG Bottling Plant atMehatpur, Una, Himachal Pradesh by M/s Indian Oil Corporation Ltd.
2. Project Proponent M/s Indian Oil Corporation Limited
3. Plant location Mehatpur, Una, Himachal Pradesh by M/s Indian Oil Corporation Ltd.
4. Site Coordinates Latitude : 31°23'43.72"N Longitude : 76°19'40.43"E
5. Present land use at the site Land use pattern is notified for industrial use
6. Nearest railway station Railway:RaiMehatpur Railway Station: 0.4 km
7. Nearest Airport Airport: Chandigarh Airport : 118 km
8. Nearest major water bodies Satluj Lake: 3.5 Km, E Nangal Dam: 10.0 Km, E
9. Nearest town/City Nearest City Nangal:8 km District HQ Una: 12 km
10. Archaeologically important places None within 10 km
11. Protected areas as per Wildlife Protection Act, 1972 (Tiger reserve, Elephant reserve, Biospheres, National parks, Wildlife sanctuaries, community reserves and conservation reserves)
None within 10 km
12. Reserved / Protected Forests None within 10 km
13. Defence Installations None within 10 km
14. Seismicity The proposed project is located in Seismic Zone IV as per IS: 1893 and all designs will be as per IS Codes
North Side : Railway Route East Side : State Highway(PWD Pump House Road) South Side : Vacant space West Side : Small Scale Habitation The project location and google image are provided as Figure 2.1 and Figure 2.2 respectively. The layout of the bottling plant has been prepared as per prescribed OISD-144 & 150. The road network is designed to ensure smooth movement of bulk/filled cylinder trucks. Layout plan of
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 14
the bottling plant including existing and proposed facilities have been given in Figure 2.3 and also as Annexure II. The design considerations for the site layout of the proposed project are provided as below: Design Parameters: Temperature, Pressure, Internal Corrosion, Hydro Test Pressure Design Procedure: As per the Design Code: ASME SEC. VIII or equivalent duly approved
by PESO. Piping layout is as per OISD-150. One liquid line, one vapour line, 2no’s SRVs, ROVs on
liquid and vapour lines
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 15
Figure 2.1: Project Location
EIA RReport for LPG B
Fig
Bottling Plant U
gure 2.2: Goog
Una, Himachal P
le Image of the
Pradesh
e Project Site
16
EIA RReport for LPG B
Fig
Bottling Plant U
gure 2.3: Goog
Una, Himachal P
le Image of the
Pradesh
e Project Site
17
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 18
2.4 Salient Features of the Project The salient features of the Una LPG BP are presented in Table 2.2.
Table 2.2: Salient Features of Existing /Proposed facility Sr. No.
Description Details
1 Total Land 32.56 acres
2 Capacity of Storage Tanks
Type of Vessel/Status
Nos Capacity Total Capacity
Existing Mounded Bullets
3 300 MT 900 MT
Proposed Mounded Bullets
2 600 MT 1200 MT
3 Power requirement 450 KW 4 Water requirement No additional requirement is envisaged with
proposed augmentation of storage capacity. 5 Man power No additional Manpower is envisaged with
proposed augmentation of storage capacity 6 Project Expansion
Cost INR 21.70 Crores.
7 Cost towards environment protection
INR42 lakhs
8 Fire Fighting Facilities A Fire water storage 2 X 3700 m3 B Fire water pumps Diesel Driven Pumps of 5*410 kL/hr capacity
C Jockey pumps Electric motor driven 2*10 m3/hr capacity C Water sprinkler /
Deluge system At all relevant places (will be converted to auto sprinkler system supported by PLC based ILSD)
D Fire Hydrant/monitor piping network
As per prescribed OISD
E DCP & CO2 extinguishers
As per prescribed OISD
F Gas Monitoring System
As per prescribed OISD
G ILSD As per OISD-144 Source: IOCLUna BP
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 19
2.4.1 Proposed Schedule and Approval for Implementation The construction of LPG storage and related activities will commence on receipt of Environmental Clearance (EC) from EAC, and Consent to Establish (CTE) from HPPCB and other statutory approvals/NOCs as required. It is envisaged that construction activities will take 12-15 months post the necessary approvals. 2.4.2 Land use The proposed expansion will be carried out within the existing facilities of LPG BP at Una. The site earmarked for proposed expansionis currently vacant. There is no change in land use. 2.5 Process Description 2.5.1 LPG Receipt and Storage Bulk LPG is being received through road tankers of approx18 MT capacities from IOCLJalandhar, Loni etc. 2.5.2 Unloading LPG in road tankers will be unloaded in TLD shed comprising 8 nos. of unloading bays. LPG will be unloaded from the road tanker by differential pressure method. During LPG unloading, vapour from one storage bullet will be sucked and will be compressed in LPG compressor. The compressed LPG vapour will be fed to bulk tanker to pressurize it and LPG (Liquid) will be transferred from the road tanker to the Bullet. After LPG unloading, the compressor suction will be reversed by changing the valve position and LPG vapour will be recovered from road tanker through the same compressor and discharged till the suction pressure of tanker is approximately1.5 Kg/cm2. 2.5.3 LPG Pump House
LPG Pumps Vertical Cam Type LPG pumps will take suction from bottom of Mounded Bullets and deliver liquid to carousal for filling in empty cylinders.
LPG Vapour Compressors Total three compressors of Capacity- 2*150cfm each and 1*65cfmhave been provided. The compressor is used for unloading of LPG from road tankers by pressurization and thereafter for recovery of LPG vapour from the road tankers when unloading will be complete. The compressor will be equipped with a suction receiver (knock out drum) to trap any condensed liquid. 2.5.4 Air Compressor and Air Drying Unit 2 nos. of reciprocating type compressor and one lubricated type screw type Air compressor provided for supply of compressed air for plant requirement as well as for preparation of
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 20
instrument air at a press of 5-6.5 Kg/cm2a. Compressed air shall be generally required as plant air/service air and a part of the compressed air passes through air drying unit for generation of instrument air at 5.6.5 Kg/cm2a and relative humidity at -15ºC. Instrument air will be required for LPG handling and filling system, operation of instruments including ROVs and thermal fuse bulbs etc. The air compressor and air drying unit are located at a sufficient distance from LPG handling facilities. 2.5.5 LPG Cylinder filling and associated facilities Empty cylinders from empty cylinder storage shed are drawn in the filling shed by chain conveyer. LPG will be filled by means of rotary machines called "Carousel". The carousel consists of a rotating frame with running wheels on rail (and corresponding rail), a central column for gas and air and which rotates with the carousel frame a hydraulic driving unit. The speed of the driving unit will be variable so that the rotation of the carousel can be adapted to various filling capacities. The carousel will be equipped with 24 filling guns.LPG filling machine mounted on the carousel works on gross weighing principle. The machine will be preset for the net filling required in the cylinders. The cylinders are placed on the machine and the filling head will be connected to the cylinder valve and LPG supply valve opens. The operator punches rate of each incoming LPG cylinders and filling machine of the corresponding cylinder will be adjusted for the respective tare weight of the cylinders. Remaining the filled LPG weight constant the lling gets automatically cut off when the total gross weight (Adjusted Tare weight + contant LPG weight) reaches.
Checking of weight and Leak testing After filling, every cylinder will be checked for its weight on a check weighing scale and the cylinders having less or more weight are segregated and are sent through a integrated weight correction unit. The cylinders are checked for valve leakage by Gas Detector and ”O”-Ring leak by Pressure Tester, then checking for body and bung leaks by totally submerging cylinders under water as per prevailing practice. After leak testing, sample of cylinders are segregated for Statistical Quality Checking (SQC), then cylinders are sent to filled cylinder storage shed by means of chain conveyers for loading in the packed trucks.
Air removal from cylinders and LPG vapour filling - Purging Unit This unit will be required to fill LPG vapour in cylinders (new and repaired) after sucking the air from cylinders by vacuum pumps. This operation is required to eliminate the possibility of forming explosive mixture with air. Vacuum will be created upto 300 mm of Hg inside the cylinder and then LPG vapour will be injected into the cylinder up to a pressure of 1.5 to 2 kg/cm2g before using them for filling of LPG.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 21
Evacuation of leaky cylinders Defective valves of LPG Cylinders shall be replaced by using Valve Change without Evacuation Unit. In this unit the defective valves are replaced without evacuating the LPG from the defective cylinders.
Storage of filled cylinders and transportation Filled cylinders after leak testing, weight testing and fixing safety caps will be stacked in the filled cylinder shed near the delivery end as per rules laid down by OISD-144/Gas Cylinder Rules, 1981. Filled cylinders will be delivered only to the PESO approved godown of authorized LPG distributors. Drivers of the trucks carrying LPG shall have valid license and training in safety and fire fighting procedures. Note: Whole filling shed are comes under the network of medium velocity sprinkler system 2.6 Process Flow Chart There is no manufacturing process involved in the LPG bottling plant. The process involved can be divided into 4 Stages as below and as shown in Figure 2.4: Receiptof Bulk LPG through LPG bulk trucks. Storage of LPG in mounded storage vessel tanks as per OISD-150. Filling of the LPG into cylinders (domestic/ commercial/ industrial). Dispatch of LPG cylinders through Vehicles (Packed cylinder Truck
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 22
Receipt of LPG by Bulk Truck
Transfer of LPG in existing 3X300 MT and proposed 2 x 600 MT Mounded Storage Vessel
Cylinders are filled up by Operating LPG Pumps
14.2 kg & 19 Kg Cylinder are filled by weight through Carousals, 47.5 Kg cylinders filled through unit filling machine tested for weight and leakages
and sealed before dispatch.
Bottling of LPG Cylinder at filling shed
Dispatch of filled LPG cylinder in Packed Truck
Figure 2.4: Process Flow Chart
2.7 Infrastructure at the Facility 2.7.1 Description of Mounded Bullets The mounded storage of LPG has proved to be safer compared to above ground storage vessels since it provides intrinsically passive and safe environment and eliminates the possibility of Boiling Liquid Expanding Vapour Explosion (BLEVE). The cover of the mound protects the vessel from fire engulfment, radiation from a fire in close proximity and acts of sabotage or vandalism. The area of land required to locate a mounded system is minimal compared to conventional storage. Excavation up to a depth of 0.75 m is done for construction of mounded bullet foundation (below FGL). Cathodic protection through sacrificial anode method has been provided for all the three bullets to prevent them from corrosion. A typical drawing of the mounded bullets system is as shown in Figure 2.5.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 23
Figure 2.5: Typical Mounded Bullet System
2.7.2 Parking Lot The proposed Bottling Plant has provided facility for approximately 20 Bulk Tank Trucks (TT) and 65Packed Truck Parking Area. 2.8 Fire Prevention System The gas leak detection, fire prevention and control system implemented at Una LPG Bottling Plant complies with the norms prescribed under OISD 144 and OISD 150. The following are the systems which are provided at Una LPG Bottling Plant:- Gas Monitoring System: The system consists of gas detecting sensors linked to a computerized processing unit and with alarm panels at control room, filing shed, plant manager’s cabin as well as security gate having audio / visual alarms and MIMIC Panel to alert the plant personnel. The sensors are located at all sensitive or potential hazard areas in the plant as indicated in OISD 144. Air/Vapor Extraction System: It is a blower with ducts extended to different operating points in filling shed. The blower extracts any leaking LPG vapor from the floor level and cold flares the same to the free atmosphere at the height of 1.5 meter from the highest points of eves of the shed. This system is interlocked with filling system, such that the blower has to be started before the carousel is started for filling operation. Blower runs during filling operation continuously. A standby blower is also given to meet situations where one of the blowers is out of order. In this
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 24
way there is no accumulation of LPG at plant floor level and any minor leaks due to operation is immediately evacuated and not allowed to reach the lower explosive limit. Remote (Control) Operated Valves: These are pneumatically operated quick shut off valves provided on LPG pipelines (in liquid line) connected to LPG equipment (like storage vessels, carousel, TLD lines) with actuating points located both remotely and nearer to operating facilities in plant. When actuated, the valves will close within 30 seconds, stopping the flow of LPG in pipelines. Besides, in case of leakage of LPG through flange joint or rupture of pipeline, the Excess Flow Check Valve are operated restricting the leakage of LPG to the sections between two Gate Valves in LPG pipe line and the LPG in upstream area and the storage bullet area is cut off from the leaking point, thereby preventing major leakage or fire. High Level Alarm: This kind of alarm is installed in bullets. In case of filling of more than 85 % the alarm will be actuated at Pump House and remote operated valves installed in storage vessel will close the flow of LPG to vessel. The actuation of remote operated valve and alarm is interlocked with the level of LPG liquid in vessel. Fire Hydrant Network: All round the plant in licensed and non licensed area there are fire water line ring network. In both licensed & non licensed area there are intermittent fire hydrants and water motitors in a specific distance. Further in licensed area there are deluge valve in all critical areas (called as fire zones), as per OISD 144. MV sprinkler system can be operated from deluge valves. Emergency Trip Buttons and Manual call Points: These emergency push buttons are provided at strategic places in the plant. In case of emergency, when the emergency trip button is actuated action takes place as specified in the clause 11.11 of OISD 144 which involves tripping of electricity to all the operating equipment in the hazardous area of the plant, closure of all remote operated valves on the LPG pipelines and sounding of siren. Operation of manual call point will denote an abnormal situation alerting the plant personnel and will involve the sounding of siren only. An annunciator panel installed at manned control room will indicate the location from where Manual Call Point is actuated. These points are provided at strategic locations in the plant. Medium Velocity Spray System : This sprinkle system is provided in the operating areas of hazardous areas of plant like sheds involving filling, storage and operation on cylinders, tank lorry decantation shed, expose flanges of mounded storage, LPG pump house, etc., as per the specifications given in OISD 144 / 150. Adequate storage of fire water in exclusive above ground tanks is maintained as per the fire water calculation. There is a fire water pipeline system which is constantly kept pressurized with a minimum of 7 kg per cmsquare at farthest point using jockey pumps which start and stop automatically at preset pressures. The fire water pipeline is connected to the MV spray system
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 25
through deluge valves where an air water balance is maintained. The MV Spray system is equipped with a quartzite bulb fire detection system. When the temperature reaches 79º C the bulb will be burst releasing the air water balance at the deluge valve and thereby starting the sprinkling of water. This will reduce the pressure in the pipeline which will actuate the fire water pumps by a preset mechanical pressure switch. This process will repeat until other fire pump start and same will stabilize when quantum of fire water as per designed scenario of fire fighting is achieved.Thus the entire system of fire protection is automatic. Interlock Shut Down System: As per OISD 144 all the plant has Inter Locked Shut Down System (ILSD) in place. It is a combination of syncrhonised activity to control a emergency situation in a far better way. In the plant with ILSD if fire water started at any point by any of the 4icases of actuation of sprinkler either by bursting of quartzite bulb, or operating sprinkler manually, all plant machineries will trip electrically, electric siren will be sounded, fire engine will be started, all remote operated valve in liquid LPG line will be closed and emergency light will be activated (at night). This system is called Interlocked Shut down System. Apart from that zone of emergency will be indicated in annuciator panel at control room. Mutual Aid – 2.9 Plant and Equipment Details The existing as well as proposed plant and equipment details along with sizing are detailed in brief in Table 2.3. Table 2.4, Table 2.5, Table 2.6 and Table 2.7. Further Site Plan Layout is referenced as Annexure II.
Table 2.3: Non-Plant Shed/Building Security (Main Gate) 03 M X 03 M CR/S & D 8 M X 10 M Administrative Bldg, conf room (2 Story) 10 M X 14M 10 M X 10M HSD storage 18 N X 15 M Truck Crew Rest Room 8.5 M X 10 M Stores Building 27 M X 10.56 M Car/Scooter parking 5 M X 20 M Fire Pump House and Air Compressor House 10 M X 15 M Fire Water Tank 10 X 30M Weigh Bridge 15 M X 3 M TLD (8bays) 15 M X 5.5 M X 8 M Filled Cylinder Shed 36.4 M X 44.8M +16.8 M X 42.3 M Empty cum filling shed 53.36 M X 58.03 M Mounded Storage Vessels (Proposed) 5.2M X 32.40 M
(2 X 600 MT) LPG Pump House 8 M X 28 M
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 26
Cooling water tank 1Nos 1 X 10 KL Emergency Exit 2 GATES Electric Substation 8 M X 44 M Value Change Shed 16.8 M X 16.8 M
Table 2.4: Plant Shed/Building
No. Description Size
1 Empty cum Filling Shed 53.36 M X 58.03 M 2 Filled Cylinder Shed 36.4 M X 44.8M +16.8 M X
42.3 M 3 TLD 15 M X 5.5 M X 8 M
Table 2.5: Brief Description of Facilities
No. of TLD bays 8 No. of Water Storage Tanks 2 No. No. of Water cooling pumps 1 No. of Bore Wells 2 No. of DG sets 3 (1x250 kVA, 1x400 kVA and 1x500 kVA.) No. of LPG pumps 2*48 M3/Hr and 1*85 M3/Hr No. of LPG compressors 2*150 CFM and 1*65 CFM No. of Air Compressors 2*150 CFM and 1*300 CFM No. of Security Air Compressors 2 No. of Fire Pumps 5 * 410 M3/hr No. of Jockey Pumps 2 * 10 M3/Hr No. of DVs 14 No. of Telescopic Conveyors 8 Gas Monitoring System: Make and No. of sensors
1
Carousal : Make, No. of Filling Points 2 x 24 Machines electronic carousal Leak Detector(GD) : 1800 cyls/ hr one each carousal Pressure Tester (PT) 1800 cyls/ hr one each carousal IWCU (Integrated Weight Correction Unit) 1 unit one each carousal Dynamic Check Scale 1 unit each carousal Evacuation Unit : Make and No of guns Stand with 2 guns. Valve Change unit Without Evacuation 1 unit one each carousal Purging Unit: Make and Capacity 1 unit Valve Changing Machine 1 unit Hot Air Sealing System (HASS) 1800 cyls/ hr one each carousal Weigh Bridge 50 MT
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 27
Vapour Extraction system 1 system Test Bath 15 cyls holding capacity one each carousal Conveyor system 1 system for each carousal
Table 2.6: Electrical Systems
No. Description Size 1 Transformers To suit requirement – tentatively - 2 (1 x 750 kVA
power and 1 x 250 kVA lighting) 2 Energy Saver To suit requirement – tentatively - 160 kVA 3 Capacitor Bank To suit requirement – tentatively - 125 kVA 4 Battery Charger/Bank To suit requirement – tentatively - 110 kVA 5 Earth Pits To suit requirement – tentatively - 71 nos 6 Automatic Transfer Switch (ATS) 2 nos 7 Contract Demand To suit requirement – tentatively - 300 kVA 8 Connected Load (Power) To suit requirement – tentatively - 410 kW 9 HT VCB 11 kV, 400 A 10 PMCC and MLDB 1 system 11 High mast 5 nos.
Table 2.7: Safety data
No of monitors Monitors and Hydrant points (alternate) in hydrant ring @ 30 m. Numbers as per requirement
Hydrant points Monitors and Hydrant points (alternate)in hydrant ring @ 30 m. Numbers as per requirement
Fire extinguishers 10 kg DCP, 75 kg DCP, and CO2 fire extinguishers as per requirement given in OISD – 144
Hand Siren As per requirement mentioned in OISD -144 ETB As per requirement mentioned in OISD -144 MCP As per requirement mentioned in OISD -144 2.10 Power Requirement Power required for the existing operations is 450 KW sourced fromHimachal Pradesh State Electricity Board. D.G sets are used of 1x250 kVA, 1x400 kVA and 1x500 kVA. 2.11 Manpower Requirement The total manpower requirement will be same as existing for the operation phase.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 28
2.12 Water and Wastewater Management Total water requirement including domestic and fire water is being sourced from existing tube wells from site and no additional requirement is envisaged with proposed augmentation of storage capacity. The existing premises of LPG BP includes and STP of 5 m3/day capacity.
Table 2.8: Water Consumption SN Description Water Consumption in
m3/day Source
1 Domestic 4 Fresh Water 2 Cylinder washing 5 Approx 4 m3/day shall be
recycled and reused. Remaining 1 m3/day shall be
sourced as Fresh Water
3 Gardening 3 Treated water from STP 4 Fire Water Makeup 3 Fresh Water
Needed once a month during fire-mock drills
Total 15 2.13 Solid and Hazardous Waste Disposal System Details of the solid and hazardous generation with their category and its quantity, disposal system are mentioned in Table 2.9 and Table 2.10.
Table 2.9: Non-Hazardous Waste
Sr. No.
Solid Waste Generation
Type of waste
Total (approx)
Management
1
From Domestic Activities
Dry garbage 4.5 Kg/day Handed over to the authorised recyclers
Wet garbage 2.5 Kg/day Vermi composting and manure usage for gardening
Table 2.10: Hazardous waste
Sr. No.
Schedule I Category No. Type
Qty Method of Disposal
1 Sch. 5.1 – Used Oil 5 LPM To be disposed off as per HPPCB norms
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 29
CHAPTER 3. DESCRIPTION OF THE ENVIRONMENT 3.1 General This chapter provides the description of the existing environmental status of the study area with reference to the environmental attributes like air, water, noise, soil, land use, ecology, socio economics, etc. The study area covers 10 km radius around the project site. The existing environmental setting is considered to adjudge the baseline conditions which are described with respect to climate, atmospheric conditions, water quality, soil quality, ecology, socioeconomic profile, land use and places of archaeological importance. 3.2 Methodology The methodology for conducting the baseline environmental survey obtained from the guidelines given in the EIA Manual of the MoEF&CC. Baseline information with respect to air, noise, water and land quality in the study has been collected by primary sampling/field studies during the period of mid-January 2017 to mid-April 2017. The meteorological parameters play a vital role in transport and dispersion of pollutants in the atmosphere. The collection and analyses of meteorological data, therefore, is an essential component of environmental impact assessment studies. The long term and short term impact assessment could be made through utilization and interpretation of meteorological data collected over long and short periods. Since the meteorological parameters exhibit significant variation in time and space, meaningful interpretation can only be done through a careful analysis of reliable data collected very close to the site. 3.3 Study Area included in Environmental Setting The study area is considered to be area within a radius of 10 km of the IOC plant boundary at Una. The EIA guidelines of the MoEF mandate the study area in this manner for EIA’s. 3.3.1 Land Use/Land Cover of the Study Area Land Use Land Cover studies are conducted using satellite imagery. The details of satellite image are as follows: Satellite Data: Landsat 8 cloud free data has been used for Landuse / landcover analysis. Satellite Sensor – OLI_TIRS Path and Row – Path 148, Row 38 Spatial Resolution– 30 m Date of Pass: 19th March 2017 Ancillary Data: GIS and image-processing software are used to classify the image and for delineating drainage and other features in the study area.
EI
Error! Rradius arcreate theSatellite algorithmten sq. km The studclasses. Aand open3.1 and F
IA Report for
Reference soea from the e Falsecolor data was c
m classifier wm area aroun
dy area of 1Agriculture ln land togethFigure 3.1B
r LPG Bottli
Figure ource not foproposed prComposite
classified uswas used fornd the Projec
10 km radiuland dominaher of the lan
B
ing Plant Un
3.1A: Satelound.A showroject site. Bmap of the s
sing supervir the analysict Site
us from the ates the landnd use. The
na, Himacha
llite Map of ws the false Band combinstudy area. ised classifis. Six land u
centre of pd use pattern
LULC class
al Pradesh
f the study acolour comp
nation was d
ication technuse/ land cov
roject site sn of the area.ses are ident
area posite satelli
done from th
nique. Maxver classes w
shows six d. It is followtified and pr
30
ite map of 1he satellite da
imum likeliwere identifi
different landwed by scrubresented in T
0 km ata to
ihood ied in
d use b land Table
EI
Vegetatiodominate(10.65%)area.
IA Report for
F
Table 3.1
on (21.67%)es the land ), Open Scr
R
r LPG Bottli
Figure 3.1B:
: Landuse /
), Crop Lanuse pattern
rubs (10.03%
LULC Clas
Vegetation
Open Scrub
Crop Land
Builtup Lan
Barren Land
Rocky Regio
Waterbody
Total
ing Plant Un
Landuse/L
/ Landcover
nd (19.86), Bn covering 1%) and Wat
ss
n
b
d
nd
d
on
y
na, Himacha
Landcover o
r Statistics o
Barren Land10km surrouterbodies (1.
Area(Ha)
6805.22
3148.86
6236.78
5451.80
5821.13
3342.40
589.06
31395.24
al Pradesh
of 10 Km Stu
of Area with
d (18.54%) aunding the p.88%) also
A
2
1
1
1
1
1
udy Area
hin 10 km R
and Built-upproject site.spread throu
Area (%)
21.67 %
10.03 %
19.86 %
17.37 %
18.54 %
10.65 %
1.88%
100.00
31
Radius
p Land (17.3 Rocky Regughout the
37%) gions study
EI
3.3.2 DA drainabasin. Drno tributstreams jthird ordwith a lowfor givinorder i.edendritic
3.3.3 CContourilines joindistance 10 km r
IA Report for
Drainage Patge system israinage basintaries (or strjoin togetherer stream anwer order wg order to dr. Sutlej Riv
c and parallel
Contour Patting is the staning points obetween adjadius aroun
r LPG Bottli
ttern s the pattern ns can be dereams flowinr, they becom
nd so on for fwithout becom
rainage. Draver. Drainagl type of dra
Figu
tern of the Sandard methoof equal elevjacent conto
nd project si
ing Plant Un
formed by tescribed by ng into it) ame second oforth and furming a higheainage mapoe pattern w
ainage pattern
ure 3.2A: Dr
Study Area od of represvation on theour lines or tite predomin
na, Himacha
the streams, the order of
are termed forder steam.rther orders.er order streaof a study are
within 10 kmn.
rainage Ma
enting reliefe surface of the contour inantly show
al Pradesh
rivers, and f streams witfirst order st. Two secon However, aam.Strahler ea shows hig
m radius aro
ap of the stu
f on topograthe ground. interval is fi
ws an undul
lakes in a pathin them. Streams. Whe
nd order strea stream maymethod of oghest order ound project
udy area
aphic maps. CFor a given
ixed i.e.25mating terrain
32
articular draiStreams that en the first ams join to y have a tribordering wasof drainage site shows
Contour linen map the vem.Contour mn. The Nort
inage have order form
butary used as 6th both
es are ertical
map of theast
EI
directionsurface.
The 10 k
IA Report for
n shows a ch
km study area
r LPG Bottli
hain of high
Figure 3a inclusive o
ing Plant Un
h peaks and
3.2B: Drainof all the mo
na, Himacha
the adjacen
nage Map ofnitoring loca
al Pradesh
nt areas to p
f the study aations has be
project locat
area een as shown
33
tion shows a
n in Figure
a flat
3.3.
EI
3.4 MThe meteatmosphecomponeassessmeover long Since, thinterpretathe site.
S.N.
1 W
2 W
3 A
4 M
5 R
IA Report for
Meteorologiceorological pere. The coent of enviroent could be g and short p
he meteoroloation can on
Param
Wind Speed
Wind Directio
Ambient Tem
Max. & Min
Relative Hum
r LPG Bottli
Figure 3.3: cal Data parameters pollection anonmental immade throug
periods.
ogical paramnly be done t
Table 3.3: Mmeter
on
mperature
Temperature
midity
ing Plant Un
Baseline Sa
play a vital d analysis
mpact assessmgh utilizatio
meters exhibithrough a ca
Meteorolog
Automatistation (E
e Wet & Dr
Hygrome
na, Himacha
ampling Mo
role in tranof meteoroment studies
on and interp
it significantareful analys
gical MonitoInstrument
c Weather Envirotech W
ry Bulb Ther
eter
al Pradesh
onitoring Lo
sport and dilogical datas. The long
pretation of m
t variation inis of reliable
oring At stu
WM 251) C1
rmometer D
D
ocations
ispersion of a, therefore,
term and shmeteorologic
n time and spe data collec
dy area Freq
Continuous A1 hourly Ave
Daily at 08:3
Daily at 08:3
34
pollutants i, is an essehort term imcal data coll
pace, meanicted very clo
quency
Automatic erage
0 and 17:30
0 and 17:30
in the ential mpact ected
ngful ose to
IST
IST
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 35
S.N. Parameter Instrument Frequency 6 Rainfall Rain Gauge Daily
The aforesaid meteorological parameters were being observed in the field during monitoring period. The analysis of the field observations is given in Table 3.4. The wind rose during the study period is presented in Figure 3.4.
Table 3.4: Meteorological Data Recorded at study area
Month Temperature, °C
Relative Humidity, %
Wind Speed, m/s
Predominant wind direction
Min Max Min Max Mean January 2017 12 23.82 32 95 13.2 SE February 2017 11 31.5 37 95 11.1 SE March 2017 10.2 34 33 96 13.2 ESE April 2017 13 35 32 94 13.7 SE
EI
3.5 AThe ambaround ththe estimthe ambichosen fNitrogen
IA Report for
Figur
Ambient Airbient air quahe site of pr
mation of bacient air qualfor assessmen (NOx), Hyd
r LPG Bottli
re 3.4: Wind
r Quality ality monitoroject to knockground poity within thent of air qdrocarbon (M
ing Plant Un
drose for pe
oring was caow the existollutant conche region baquality wereMethane and
na, Himacha
eriod of Jan
arried out ating backgrocentration wased on the e PM10, PMd Non-metha
al Pradesh
uary 2017 t
t ten locatioound ambienas to assess activities of
M2.5, Sulphurane HC) and
to April 201
ons within thnt air quality
the impact f the projectr Dioxide (VOCs.
36
7.
he 10 km ry. The purpo
of the proje. The paramSO2), Oxide
radius ose of ect on meters es of
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 37
3.5.1 Methodology Adopted for the Study PM10, PM2.5, Sulphur dioxide (SO2), Oxides of Nitrogen (NOx), Hydrocarbon (Methane and Non-methane HC) and VOCs were the major pollutants associated with project. The baseline status of the ambient air quality has been established through field monitoring data on PM10, PM2.5, Sulphur dioxide (SO2), oxides of nitrogen (NOx), Hydrocarbon (HC) Methane and Non-methane HC) and VOCs at 10 locations within the study area. The locations for air quality monitoring were scientifically selected based on the following considerations using climatological data. Meteorological conditions on synoptic scale; Topography of the study area; Representative ness of the region for establishing baseline status; and Representative ness with respect to likely impact areas. Ambient air quality monitoring was carried out on 24 hour basis with a frequency of twice a week at a station during the study period for 8 locations. The location of the monitoring stations with reference to the project site is given in Table 3.4&Figure 3.3.
Table 3.4: Ambient Air Monitoring Locations Sl. No Location Location Code
1 Project Site A1
2 NayaNangal A2
3 Nangal A3 4 Kherabagh A4 5 Barsara A5 6 Palakwah A6 7 Una A7 8 Saontokgarh A8 9 Sukhsal A9 10 Brahmpur A10
The ambient air quality results are as summarized in Table 3.5. The detailed Ambient Air Quality results are as referenced in Annexure III
Table 3.5: Ambient Air Quality Monitoring Results
PM10 (µg/m3)
A1 A2 A3 A4 A5 A6 A7 A8 A9 A10
Min 75.0 79.0 72.0 72.0 80.0 80.0 72.0 80.0 80.0 80.0
Max 92.0 92.0 91.0 96.0 89.0 89.0 92.0 92.0 92.0 90.0
98 Percentile 92.0 92.0 90.5 95.5 88.1 88.1 90.2 91.5 91.1 90.0
Standard 100 100 100 100 100 100 100 100 100 100
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 38
PM2.5 (µg/m3)
A1 A2 A3 A4 A5 A6 A7 A8 A9 A10
Min 30.0 30.0 29.0 30.0 18.0 30.0 32.0 30.0 30.0 32.0
Max 48.0 42.0 40.0 44.0 38.0 43.0 42.0 39.0 43.0 71.0
98 Percentile 46.6 41.1 40.0 43.1 38.0 42.5 41.1 39.0 42.5 58.1
Standard 60 60 60 60 60 60 60 60 60 60
SO2 (µg/m3)
A1 A2 A3 A4 A5 A6 A7 A8 A9 A10
Min 3.0 2.0 2.0 3.0 2.0 3.0 2.0 3.0 3.0 3.0
Max 7.0 6.0 7.0 8.0 8.0 6.0 7.0 5.0 6.0 7.0
98 Percentile 7.0 6.0 6.5 7.5 8.0 6.0 6.5 5.0 6.0 6.5
Standard 80 80 80 80 80 80 80 80 80 80
NOx (µg/m3)
A1 A2 A3 A4 A5 A6 A7 A8 A9 A10
Min 3.0 5.0 4.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Max 10.0 9.0 9.0 10.0 10.0 8.0 8.0 78.0 10.0 9.0
98 Percentile 9.5 8.5 8.5 9.5 9.5 8.0 8.0 45.8 9.5 8.5
Standard 80 80 80 80 80 80 80 80 80 80
The other parameters such as CO, Benzene, Benzo (a) Pyrene, Ammonia, Hydro Carbons, VOCs, etc. are all below detection limits.
3.5.2 Sampling and Analytical Techniques Respirable Dust Samplers APM-451 of Envirotech instruments were used for monitoring Respirable fraction (<10 microns) and gaseous pollutants like SO2, NOx, Methane and Non-methane (HC) and VOCs. Table 3.5 shows the techniques for sampling and analysis for these parameters.
Table 3.6: Techniques Used For Ambient Air Quality Monitoring
Parameters Technique Technical Protocol
DetectableLimit, ug/m3
PM10 Respirable Dust Sampler (Gravimetric method)
HPPCB Guidelines
10.0
Sulphur Dioxide West and Gaeke IS-5182 (Part-II) 5.0 Nitrogen Oxide Jacob &Hochheiser IS-5182 (Part-VI) 5.0 Hydrocarbon (Methane and Non-Methane)
Gas Chromatograph (FID Detector)
Is-5182 (Part-XXI) 0.1 ppb
VOCs Activated Charcoal method (GC FID Detector)
EPA TO-17 1 mg/m3
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 39
Ambient air at the monitoring location is sucked through a cyclone. Coarse and non-respirable dust is separated from the air stream by centrifugal forces acting on the solid particles and these particles fall through the cyclone's conical hopper and get collected in the sampling cap placed at the bottom. The fine dust (<10 microns) forming the PM10 passes the cyclone and is retained on the filter paper. A tapping is provided on the suction side of the blower to provide suction for sampling air through a set of impingers for containing absorbing solutions for SO2 and NOx. Samples of gases are drawn at a flow rate of 0.2 liters per minute. PM10 has been estimated by gravimetric method. Modified West and Gaeke method (IS-5182 part-II, 1969) has been adopted for estimation of SO2 and Jacobs-Hochheiser method (IS-5182 part-VI, 1975) has been adopted for the estimation of NOx. Calibration charts have been prepared for all gaseous pollutants. 3.6 Noise Noise in general is sound, which is composed of many frequency components of various loudness distributed over the audible frequency range. The most common and universally accepted scale is the A weighted scale which is measured as dB (A). This is more suitable for audible range of 20 to 20,000 Hz and has been designed to weigh various components of noise according to the response of a human ear.The environmental assessment of noise from the industrial activity, construction activity and vehicular traffic can be undertaken by taking into consideration various factors like potential damage to hearing, physiological responses, and annoyance and general community responses. 3.6.1 Objective The main objective of monitoring of ambient noise levels was to establish the baseline noise levels in different zones. i. e. Residential, Industrial, Commercial and Silence zones, in the surrounding areas and to assess the total noise level in the environment of the study area. 3.6.2 Methodology
Identification of Sampling Locations A preliminary reconnaissance survey was undertaken to identify the major noise sources in the area. The sampling location in the area was identified considering location of industry, commercial shopping complex activities, residential areas with various traffic activity and sensitive areas like hospital, court, temple and schools also near the railway track for railway noise. The noise monitoring was conducted at eight locations in the study area during monitoring period. 10 sampling locations were selected for the sampling of noise.
Equivalent sound pressure level (Leq) The sound from noise source often fluctuates widely during a given period of time. Leq is the
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 40
equivalent continuous sound level, which is equivalent to the same sound energy as the actual fluctuating sound measured in the same time period.
Instrument used for Monitoring Noise levels were measured using an Integrating sound level meter manufactured by Cygnet (Model No. 2031). It had an indicating mode of Lp and Leq. Keeping the mode in Lp for few minutes and setting the corresponding range and the weighting network in “A” weighing set the sound level meter was run for one hour time and Leq was measured at all locations. There are different types of fields for measuring the ambient noise level, e categorized as free field, near field and far field.
Free Field The free field is defined as a region where sound wave propagates without obstruction from source to the receiver. In such case, the inverse square law can be applied so that the sound pressure level decreases by 6dB (A) as the distance is doubled.
Near Field The near field is defined as that region close to the source where the inverse square law does not apply. Usually this region is located within a few wavelengths from the source.
Far Field The far field is defined as that region which is at a distance of more than 1-meter from the source.
Table 3.7: Noise Level Monitoring Stations in the Study Area Sl. No Location Location Code
1 Project Site N1
2 NayaNangal N2
3 Nangal N3 4 Kherabagh N4 5 Barsara N5 6 Palakwah N6 7 Una N7 8 Saontokgarh N8 9 Sukhsal N9 10 Brahmpur N10
3.6.3 Method of Monitoring and Parameters Measured Noise monitoring was carried out continuously for 24-hours with one hour interval. During each hour parameters like L10, L50, L90 and Leq were directly computed by the instrument based on the sound pressure levels. Monitoring was carried out at ‘A’ weighting and in fast response mode.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 41
The important parameters to be measured are Leq, Lday, and Lnight. Leq: Latest noise monitoring equipments have the facility for measurement of Leq directly. However, Leq can also be calculated using the following equation: Leq (hrly) = L50 + (L10 - L90)
2 / 60 Where, L10 (Ten Percentile Exceeding Level) is the level of sound exceeding 10% of the total time of measurement. L50 (Fifty Percentile Exceeding Level) is the level of sound exceeding 50% of the total time of measurement. L90 (Ninety Percentile Exceeding Level) is the level of sound exceeding 90% of the total time of measurement. Lday: This represents Leq of daytime. Lday is calculated as Logarithmic average using the hourly Leq’s for day time hours from 6.00a.m to 10.00p.m Lnight: This represents Leq of night time. Lnight is calculated as Logarithmic average using the hourly Leq’s for nighttime hours from 10.00p.m to 6.00a.m. 3.6.4 Noise Results The values of noise level parameters like Leq (day), and Leq (night), were monitored during study period and are presented in Table 3.8.
Table 3.8: Ambient Noise Monitoring Results SN. Location No. Results
Day Night1 Project Site 59 46 2 NayaNangal 61 49 3 Nangal 54 45 4 Kherabagh 60 50 5 Barsara 64 52 6 Palakwah 58 48 7 Una 57 45 8 Saontokgarh 59 50
9 Sukhsal 53 44
10 Brahmpur 58 48
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 42
Noise Standards Ambient air quality standard in respect of noise have been stipulated by Govt. of India vide Gazette notification dated. 14.2.2000. Table 3.9 describes ambient noise standards. In Respect of Noise*
Table 3.9: Ambient Noise Standards
Area Code Category of AreaLimits in dB(A), Leq
** Day time #Night time A Industrial Area 75 70 B Commercial Area 65 55 C Residential Area 55 45 D Silence Zone @ 50 40
* As per Environment protection act. ** Day Time: 6.00a.m to 10.00p.m. # Night Time: 10.00p.m to 6.00a.m. @ Silence zone is defined as an area upto 100 meters around such premises ashospitals, educational institutions and courts. The silence zones are to be declared by the competent authority; Use of horns, loudspeakers and bursting of crackers shall be banned in these zones. The noise data compiled on noise levels is given in Table 3.8. Noise level of the study area varied from 55 to 64 dB (A) in day time and from 44 to 52 dB (A) in the night time. 3.7 Water Environment 3.7.1 Ground Water Hydrology Hydro-geologically the weathered and fractured zones of crystalline constitute the predominant hydro-geological units. Groundwater occurs under phreetic condition in the weathered horizons. Highly weathered and jointed granitic gneisses occuring the undulating plains form the potential aquifers in the hard rock terrain. Micaschists and shales having very thick weathered residuum also sometimes form good shallow aquifers to be tapped through dug wells. In the study area, ground water occurs under semi-confined and confined aquifer conditions. The quality of ground water at project site is saline. The depth of water table in the study area range varies from 4-5 m below ground level during pre-monsoon period and less than 2-4 m during post-monsoon period. (Source: CGWB). 3.7.2 Selection of Sampling Locations The assessment of present status of water quality within the study area was conducted by collecting water from ground water sources and surface water sources during Monitoring Period.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 43
The sampling locations were identified on the basis of their importance. Two surface water samples and Four ground water samples were collected during monitoring period.
Table 3.10: Water Quality Sampling Locations Station Code Location
GW1 Fatehpur
GW2 Santokgarh
GW3 Brahmpur
GW4 Una
SW1 Nangal Dam SW2 Soan River
3.7.3 Methodology Water samples were collected from all the sampling locations and analyzed for relevant physical, chemical and bacteriological parameters. Collection and analysis of the samples was carried out as per established standard methods and procedures, prescribed by HPPCB, relevant IS Codes and Standard Methods of Examination of Water. This report presents data for the Monitoring Period. Analyses of the parameters like temperature; pH, dissolved oxygen and alkalinity were carried out at the sampling stations immediately after collection of samples with the help of Field Analysis Kits. For analysis of other parameters, the samples were preserved and brought to laboratory. The metallic constituents like arsenic, mercury, lead, cadmium, chromium, copper, zinc, selenium, iron and manganese were analyzed with Atomic Absorption Spectroscope. 3.7.4 Ground and Surface Water Quality The analysis data for the monitoring period is presented in Table 3.11 and Table 3.12 The physico-chemical characteristics of Ground water are confirming to permissible limits of drinking water standards, prescribed in IS: 10500 (Test Characteristics for Drinking Water) and suitable for consumption.
Table 3.11: Ground Water Characteristics
Site Fatehpur Santokgarh Brahmpur Una
pH 7.25 7.40 7.25 7.45
TDS 320 135 265 298
Alkalinity 250 70 189 215 Chloride 28 08 15 10 Ca 28 24 12 20 Mg 48 6.8 40 30
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 44
Site Fatehpur Santokgarh Brahmpur Una
Total Hardness 260 90 185 195 Iron 0.13 0.02 0.03 0.10 E.coli Absent Absent Absent Absent Coliform Absent Absent Absent Absent
Table 3.12: Surface Water Characteristics
Site Nangal Dam Soan River
pH 7.24 7.14
TDS 125 120
Alkalinity 25 22 Chloride 5 3 Ca 14 12 Mg 3.5 3.2 Total Hardness 58 40 Iron 0.004 0.01 E.coli Absent Absent Coliform Absent Absent
3.8 Soil Soil is generally differentiated into two horizons of minerals and organic constituents of variable depth, which differ from the parent material below in morphology, physical properties, constituents, chemical properties, and composition and biological characteristics. The physico- chemical characteristics of soil have been determined at 4 locations during the monitoring period with respect to colour, texture, cation exchange capacity, pH, N, P, and K etc. The sampling locations have been selected to represent the study area. 3.8.1 Selection of sampling Locations The soil sampling locations were identified primarily based on the local distribution of vegetation and the agricultural practices. The sampling locations were mainly selected from agricultural field and project site. The sampling locations are given in Table 3.13 and presented in Figure 3.3.
Table 3.13: Soil Sampling Stations in the Study Area Code Locations
S1 Project Site S2 NayaNangal S3 Santokgarh S4 Brahmpur S5 Una S6 Barsara
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 45
3.8.2 Methodology The soil samples were collected during monitoring period. The samples collected from the all locations are homogeneous representative of each location. At random 6 sub locations were identified at each location and soil was dug from 30 cm below the surface. It was uniformly mixed before homogenizing the soil samples. The samples were filled in polythene bags, labeled in the field with number and site name and sent to laboratory for analysis. 3.8.3 Soil Results The detailed soil results of all the monitoring locations are as shown in Table 3.14.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 46
Table 3.14: Chemical Characteristics of Soil in the Study Area
SN PARAMETERS UNITS OF MEASUREMENT
Project Site
NayaNangal Santokgarh Brahmpur Una Brahmpur
1. Colour ----- Grayish Brownish Brownish Grayish Grayish Brownish 2. pH ----- 8.20 7.1 7.21 6.85 6.70 7.20 3. Conductivity (EC) micro mhos/cm at
25oC (Soil Water Ratio-
1:2)
380 420 385 415 410 370
4. Moisture Content % 8.25 1.58 2.32 3.14 3.21 2.30 5. Water Holding
Capacity(WHC) % 30 55 50 45 43 48
6. Texture ----- Sandy soil Sandy clay Sandy clay Sandy Soil Sandy Soil
Sandy clay
7. Sand % 37.8 28 32 38 36 32
8. Silt % 22.4 35 38 35 37 38 9. Clay % 39.8 37 30 27 27 30 10. Organic Carbon % 0.854 0.615 0.645 0.425 0.421 0.630 11. Ca % 0.021 0.025 0.013 0.014 0.011 0.012 12. Mg % 0.001 0.002 0.004 0.002 0.004 0.005 13. Chloride Mg/l 25 18 18 24 22 16 14. Total Kjeldahl
Nitrogen Kh/ha 108 95 85 118 117 90
15. Nickel Mg/kg 0.04 ND ND ND ND ND
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 47
3.9 Biological Environment
3.9.1 Introduction
Ecology is the study of surrounding environment wherein various living or biotic groups live together and form a system of existence where every component, whether small or big is interdependent and hence is an indispensable part of an Ecosystem. In an ecosystem, plants are important as primary producers of a food chain followed by small organisms that are food of the other organisms. An ecosystem gets disturbed even if a single member of it gets extinct. The various ecosystems constitute of the man and animals, plants, microorganisms, aquatic and desert animals and so on. Humans are dependent on their environment, as are all other organisms. Any change in the environment affects the living things and their behaviour. All organisms are dependent on each other in many ways. Destruction of one organism in the environment can lead to the destruction of other organisms. Technological advances have given humans the ability to exert great influence over the environment of all living things. However, the ability of ecosystems to sustain humans is becoming increasingly stunted. For this reason, it is necessary to have an understanding of ecology in order to survive. The EIA studies would be very much incomplete if proper attention is not provided towards project’s impact foreseeable on flora and fauna of the study area. Accordingly, conducted the necessary survey of terrestrial flora, fauna and literature review of aquatic A detailed flora fauna study was carried out in 10 km radius area of the site. The structure and type of vegetation depends on climatic conditions and physiography of an area. Climate of the study area is suited for the variety of vegetation. The contents of this subsection are based primarily on reconnaissance surve. & through secondary sources. The baseline study, for the assessment of the floral and faunal biodiversity of the study area, within 10 km radius of the site was conducted during Mid January 2017 to Mid April 2017. Methodology: The study region was earmarked for 10 km radius area and its relevant baseline data was collected from the Census data book. The survey methodology was based on the flora and fauna species identification in personal and recently recorded and found in the region by the localities. Sampling of grass species was carried out by quadrat sampling method to examine the species distribution and its frequency in the region. Quadrat Sampling Method: A quadrat (or plot-based) survey is a quantitative examination of species distribution and abundance. Quadrats are more likely to detect inconspicuous or threatened species because a
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 48
smaller area is sampled in a concentrated search. This survey technique also provides a basis for subsequent monitoring. The survey was carried out for the vegetation ground cover found in the road edges by 1 m2 quadrat and study on the edge effect due to rapid industrialization and urbanization. The vegetation of this area was represented by tall trees, middle layer trees and shrubs, ground layer of herbaceous and twiners and climbers. This biodiversity is the natural biological capital of the earth and presents important opportunities for all nations. It provides goods and services essential to support human livelihoods and aspirations and enables societies to adapt to changing needs and circumstances. In addition, biodiversity maintains the ecological balance necessary for planetary and human survival.
3.9.2 Existing status of Flora in the Study Area:
Overall 29 plant species have been recorded. Fabaceae was the most dominant family followed by Myrtaceae and Moraceae. The list of naturally occurring trees, under growth plants, fruit trees within the Study area are as shown in Table 3.15, Table 3.16 and Table 3.17 respectively.
Table 3.15: List of naturally occurring trees within Study Area
S. No. Plant species Common name Family 1 Acacia auriculiformis kikar Fabaceae 2 Acacia catechu Khair Fabaceae 3 Acacia nilotica Kikar Fabaceae 4 Albizziaprocera White siris Mimosaceae 5 Alstonia scholaris Blackboard tree Apocynaceae 6 Bauhinia variegate Kachnar Fabaceae 7 Bombaxmalabaricum Semal Bombacaceae 8 Dalberjiasissoo Shisham Fabaceae 9 Dendrocalamusstrictus Bans Poaceae 10 Eucalyptus citriodora Safeda Myrtaceae 11 Ficusreligiosa Peepal Moraceae 12 Ficus bengalensis Banyan tree Moraceae 13 Ficus retusa Fig Moraceae 14 Gravillearobusta Silver oak Proteaceae 15 Morusmacroura Shahtoot Moraceae 16 Populus alba Poplar Salicaceae 17 Terminaliaarjuna Arjun Combretaceae
Table 3.16: List of under growth plants
S. No. Plant species Common name Family 1 Bougainvillea glabra Paper Flower Nyctaginaceae
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 49
2 Cannabis sativa Bhang grass Cannabaceae 3 Durantaerecta Pigeon Berry/Skyflower Verbenaceae 4 Lantana indica Kuri Verbenaceae 5 Partheniumhysterophorus Gajarghass Compositae 6 Ricinuscommunis Arand/Arandi Euphorbiaceae7 Saccharumbengalense Sarkanda/MunjSweetcane Poaceae 8 Tylophoraasthmatica Khad/Khas grass Poaceae
Table 3.17: List of fruit trees
S. No. Plant species Vernacular/Common name Family 1 Embelicaofficinalis Amla Phyllanthaceae 2 Mangiferaindica Mango Anacardiaceae 3 Psidiumguajava Guava/Amrood Myrtaceae 4 Syzgiumnervosum Wild Jamun Myrtaceae
3.9.3 Existing status of Fauna in the area:
The faunal survey was also carried out in the project area. Overall, 12 naturally occurring and introduced animal and avian species belonging to 9 families have been recorded. The fauna was dominated by seasonal butterflies and variety of honey bees. Phasianidae and Columbidae were the most dominant families. The list of Faunal members in the Study Area are as provided in Table 3.18
Table 3.18: List of Faunal members of the project area
S. No. Plant species Common name Family 1 Melanerpesformicivorus Acorn woodpecker Picidae 2 Ectopistesmigratorius Pigeon Columbidae 3 ZenaidaZenaida Dove Columbidae 4 Meleagrisgallopavo Wild turkey Phasianidae 5 Rattusnorvegicus Brown rat Muridae 6 Hystrixindicus Indian Porcupine/Sehi Hystricidae 7 Helogaleparvula Mongoose Herpestidae 8 Sus scrofa Wild boar Suidae 9 Seasonal butterflies 10 Variety of honey bees
There are no ecologically sensitive areas like National Parks or Wildlife Sanctuaries, Tiger Reserves, Elephant Reserves, Turtle Nesting Ground and Core Zone Biosphere Reserve within the 10 km radius of the proposed project site. Though the area executes good floral diversity, there were no reports of any species falling in endangered category.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 50
3.10 Socio-Economic Environment Introduction Socio-economic assessment is an important part of the Environment Impact Assessment of any industrial project. It is conducted to develop the sustainability strategy for the area, where the industrial project would be executed. This section studies the socio-economic profile of the 10 km radius area for the IOCL Bottling plant project and analyses the baseline status as well as assess the social impacts of the projects in the study area and suggest mitigation measures to the anticipated adverse impacts of the project. The socio-economic aspects in general, divided into economy, demography, education, health, employment & infrastructure in the study area. Project Location The proposed expansion project i.e. M/s Indane Bottling Plant of IOCL is located near the Village: BadeharNichla Tehsil: Una, District: Una in Himachal Pradesh. Socio-Economic Details Of Study Area The data is collected and analysed using secondary sources viz. Census records, District Statistical Abstract, Official Document etc. The study area i.e. the 10 km radius area from the project site is spread over the tehsils of Una and Haroli in Una district of Himachal Pradesh and Nangal tehsil of Rupnagar district of Punjab. The demographic profile, infrastructure facilities and socio-economic condition is being described under different classifications in the following section. Methodology The data is collected and analysed using secondary sources. The secondary data was collected and collated from sources such as viz. District Census Handbook 2011, Census of India website, District Statistical Abstract etc.
Table 3.19: Demography of Una &Rupnagar Districts Demographic Attributes Una District RupnagarDistrct 1. Area 1,549 sq. km. 1,356 sq. km. 2. Population 521,173 684,627 3. Decadal Growth rate 16.24 % 8.9% 4. Male population 263,692 3,57,485 5. Female population 257,481 3,27,142 6. Density of population (persons per km2.) 338 505 7. Sex Ratio (females per 1000 males) 977 915 8. Literacy 87.23 % 82.19% 9. Male literacy 92.75 % 87.50% 10. Female literacy 81.67 % 76.42% 11. Urban Population 8.62 % 25.97%
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 51
Source: Primary Census Abstract, Census of India 2011 Demographic Profile of the Study Area The study area (10 KM radius of the project site) falls in 2 Districts comprising of 3 tehsils in the state of Himachal Pradesh & Punjab. There are totally 258 villages falling under these three tehsils. In addition, there are 4 towns that fall under the study area. District, Tehsil viz village & town breakup is shown in the Table 3.20
Table 3.20: Village & Town Breakup in the Study Area State District Taluk Total Villages Total Towns Himachal Pradesh
Una Una 140 3 Haroli 59 0
Punjab Rupnagar Nangal 59 1 Total 258 4
Source: Primary Census Abstract, Census of India 2011 Total Population The total population of these the study area per Census of 2011 is 395,083. The percentages of male, female population and sex ratio are 51%, 49% and 1000 (Males): 957 (females) respectively. There are about 54,008households in the study area. The average family size is about 5 persons per house. The sex ratio for the study area is very low as compared to the sex ratio of the Una district (977) and the state (972). Tehsil viz Population and Sex Ratio is shown in the Table 3.21
Table 3.21: Population & Sex Ratio Breakup in the Study Area S.No.
Study Area Total Population
Total Families Total
Males Total Females
Sex Ratio
Children (Age 0-6)
1. Una 190,082 39,901 97,066 93,016 958 21,277 2. Haroli 71,416 14,107 36,308 35,108 967 3. Nangal 133,585 27,754 68,598 64,987 947 13,950
Grand Total 395,083 54,008 201,972 193,111 957
Source: Primary Census Abstract, Census of India 2011 Population (Towns) There are 4 towns that falls under the study area. These are Una Municipal Council, Santokhgarh Nagar Panchayat&MehatpurBasdehra Nagar Panchayat in Una District and Nangal Municipal Council in Rupnagar District. The total population of these towns is 85,800. The percentages of male, female population and sex ratio are 52%, 48% and 1000 (Males): 897 (females) respectively. There are about 18,877households in the study area. The average family size is about 5 persons per house. The low sex ratio in the urban towns of the study can be linked to the presence of male migrant labourers from other parts of state.Townviz Population and Sex Ratio is shown in the Table 3.22
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 52
Table 3.22: Population & Sex Ratio Breakup in the Study Area S.No.
Towns Total Population
Total Families
Total Males
Total Females
Sex Ratio
1. Una 18,722 4,226 9,851 8,871 901 2. Santokhgarh 9,363 1,901 4,789 4,574 955 3. MehatpurBasdehra 9,218 2,012 4,942 4,276 865 4. Nangal 48,497 10,738 25,317 23,180 865 Grand Total 85,800 18,877 44,899 40,901 897
Source: Primary Census Abstract, Census of India 2011 Vulnerable Population The Schedule Caste (SC) population within the study area is 19.39% and the Schedule Tribe (ST) population is 0.86% of the total population of study area. Out of the tehsils, Nangal surprisingly does not have any ST population; however in other tehsils also ST population is negligible. SC and ST population break-up Tehsil viz is shown in the Table 3.23
Table 3.23: SC & ST Population break-up in the Study Area
Total Population
Total SC Population
% SC Population
Total ST Population
% ST Population
Una 190,082 35,250 18.54 594 0.31 Haroli 71,416 13,335 18.67 2,804 3.93 Nangal 133,585 28,020 20.98 0 0.00
Grand Total 395,083 76,605 19.39 3,398 0.86
Source: Primary Census Abstract, Census of India 2011 Literacy The total number of literates within the study area is 299,532 (84.87%). The percentage of male and female literacy to the total literate population is 90.40% and 79.24%, respectively. . The literacy rate is considerably higher in male population as compared to female population. Tehsil viz literacy break-up is shown in the Table 3.24
Table 3.24: Literacy break-up in the Study Area
Total Literates
% Literates
Total Male Literates
% Male Literates
Total Female Literates
% Female Literates
Una 145,027 85.91 78,114 91.09 66,913 80.57 Haroli 52,644 83.55 28,908 89.62 23,736 77.61 Nangal 101,861 85.14 55,355 90.49 46,506 79.55
Grand Total 299,532 84.87 162,377 90.40 137,155 79.24
Source: Primary Census Abstract, Census of India 2011
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 53
Urban/Rural Population As per Census 2011, there are total 10,738 families under Nangal Tehsil living in urban areas while 10,738 families are living within Rural areas. Thus around 36.3% of total population of Nangal Tehsil lives in Urban areas while 63.7% lives under Rural areas.
Table 3.25: Urban/Rural Population break up in the Study Area
Total Population
Rural population
% Rural Population
Urban Population
% Urban Population
Una 190,082 152,779 80.4 37,303 19.6 Haroli 71,416 71,416 100 0 0.00 Nangal 133,585 85,088 63.7 48,497 36.3
Grand Total 395,083 309,283 81.36 85,800 18.64
Source: Primary Census Abstract, Census of India 2011 Economic Activity As per the Census 2011, the workforce in the study area is more than one lakh and 40 thousand which constitutes 38.06% of the total population of the study area. The workers comprise more than one lakh main workers and thirty seven thousand marginal workers. Main workers1 constitute 74.36% percent of the total workers. The remaining 25.64% are marginal workers2. Among the main workers, male workers are more as compared to the female workers. Majority of female workers working are also from rural areas, as they are employed in farm sector. This is also more than that of male workers, which may be due to their being employed predominantly in activities like cultivation and agricultural labour. In the urban areas, majority of female workers are engaged in Households industry and other work.
Table 3.26: Status of working population in the study area
Total workers
Main workers
Marginal workers
Non workers
Work participation rate
Una 72,351 52,766 19,585 117,731 38.06 Haroli 27,160 17,339 9,821 44,256 38.03 Nangal 44,860 37,250 7,610 88,725 33.58 Grand Total 144,371 107,355 37,016 250,712 36.54
Source: Primary Census Abstract, Census of India 2011
1Main workers were those who had worked for the major part of the year preceding the date of enumeration i.e., those who were engaged in any economically productive activity for 183 days (or six months) or more during the year.
2Marginal workers were those who worked any time at all in the year preceding the enumeration but did not work for a major part of the year, i.e., those who worked for less than 183 days (or six months).
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 54
Occupational structure The occupational structure of the population in the study area has been studied. The Main workers are classified on the basis of Industrial category of workers into the following four categories: 1. Cultivators 2. Agricultural Labourers 3. Household Industry Workers 4. Other Workers Of the total main workers in the study area, about 70% is engaged in the other workers category. The type of workers that come under this category of 'Other Worker' include all government servants, municipal employees, teachers, factory workers, plantation workers, those engaged in trade, commerce, business, transport banking, mining, construction, political or social work, priests, entertainment artists, etc. In effect, all those workers other than cultivators or agricultural labourers or household industry workers are 'Other Workers'.
Table 3.28: Distribution of Main workers by category
Main Workers
Main Workers Cultivators Agricultural
Labourers Household Industry
Others
Una 52,766 11,204 2,868 910 37,784 Haroli 17,339 6,074 1,184 218 9,863 Nangal 37,250 5,818 2,388 1,053 27,991 Grand Total 107,355 23,096 6,440 2,181 75,638
Source: Primary Census Abstract, Census of India 2011 After other workers category, cultivators (22%) and agricultural labour (6%) together constitute 28% of the total main workers. It reflects that agricultural sector has only absorbed 28% of the main workers. Only 2% of workers in the study area are engaged in the household industry. Surprisingly, in the other workers category, more than 60% percent of the total main workers in other category are rural in nature whereas only 40% are urban in nature. Thus it reflects that the opportunities for other category workers are also available in rural areas of study area as compared to the urban areas.
EI
InfrastruThe studynature winfrastrucin the stuwith exceEducatioand, townsome largThere areMedical Una townPost andphone cocommuniDrinkingand wellRoad anroads anproportioenjoying
IA Report for
Figure 3.5
ucture y area consi
with 81% ascturefacilitieudy area. Unellent physiconal facilityns of the stuge villages he some 16-20facilities of
n and Nangad Telegraphonnections arication. g water is nl water. Somnd Rail connd connected
on of electripower supp
r LPG Bottli
5: Percentag
ists of 258 vs rural popueslikewatersuna town, the cal and sociay at the miniudy area. Thhave three pr0 adult literaf one or the al also have ah facility is re available
not a problemme villages nectivity is bd by bus serified village
ply facility fo
70%
ing Plant Un
ge Distribut
illages, 4 towulation and upply,roads,district head
al infrastructimum level
here are manrimary schooacy centres iother type aa big generaavailable inin most of t
m here as allalso have hbetter in thervices. Somees for the stor all the pur
22
na, Himacha
tion of Main
wns within t19% urban
, markets,badquarter is thture and basiof primary
ny villages hols. For collin the rural aare availableal hospital. n all the villathe villages b
the villageshand pump ae study area e villages artudy area isrposes.
2%
6%
al Pradesh
n Workers i
the radius arn populationanks,postoffihe biggest uric amenities.education isaving more ege educatio
area of the stu in all the vi
ages and towbut people te
s and towns and tube weas all the vire connecteds impressive
2%
Cult
Agr
Hou
Oth
in the Study
rea. The arean. This sectiices,schoolsarban pocket . s available ithan one pri
on the studenudy area. illages in the
wns of studyend to use m
have the facell as drinkinllages and tod to Railwaye. All villag
tivators
icultural Labou
usehold Indust
hers
55
y Area
a is more rurion analyseandelectrificin the study
n all the vilimary schoonts go to the
e study area
y area. Althmobile phone
cility of tap wng water soowns have py Line also.
ges and town
urers
ry
ral in s the
cation y area
llages ol and e city.
a. The
hough es for
water ource. paved . The n are
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 56
CHAPTER 4.ANTICIPATED ENVIRONMENTAL IMPACTS AND
MITIGATION MEASURES
4.1 Introduction Identification of impacts and mitigation measures of the same in Environmental Impact Assessment study helps in quantification and evaluation of impacts. During baseline study several impacts can be identified but it is necessary to identify the critical impacts both positive and negative on various components of the environment that are likely due to installation of LPG mounded bullets within the existing LPG BP Una. The environmental impacts can be categorized as either primary or secondary. Primary impacts are the ones that are caused directly due to the project activity on environmental attributes, whereas secondary impacts are indirectly induced. The construction and operational phase of the project activity comprises various activities, each of which may have either positive or negative impact on some or other environmental attributes. The proposed project activities would impart impact on the environment in two distinct phases:
During construction phase - Temporary or short term impact During operation phase - May have long term impact
4.2 Impact Assessment
4.2.1 During Construction Phase Land/Soil Environment During site preparation, excavation will be done at places in the project site where sheds, Mounded Storage bullets and the approach road will be constructed. This is required to provide solid base/foundations for structures & roads.
Improper disposal of the excavated earth during installation of storage tanks/structures may result into temporary loss of topsoil productivity of that particular area.
Storage of construction material/chemicals (if any) if not done at designated place can cause nuisance and hazards
Accidental spillage of Hazardous chemicals/oil during handling may lead to soil contamination
Improper segregation and disposal of solid waste generated during construction phase by workers working at site
Filth generation if dry waste/garbage generated during construction period is not handling efficiently
Air Environment The emission anticipated during construction period will include fugitive dust due to
excavation of soil, leveling of soil, use of DG sets, movement of heavy construction equipments/vehicles, site clearing and other activities
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 57
This type of fugitive dust is expected to result in change in the baseline air quality specifically during the construction phase
If burning of solid wastes is required it may cause air pollution
Noise Environment The proposed project will lead to emission of noise that may have significant impact on the surrounding communities in terms of increase in noise levels and associated disturbances. Following activities would result in increase in noise level;
Noise generated from operation of pumps and blower Noise generated from vehicular movement Noise generated from DG Set Nuisance to nearby areas due to noise polluting work at night
Water Environment
Increased water demand during construction phase for site preparation, dust spraying, construction activities, curing, domestic and other water requirements for labour and staff onsite
Increase in site runoff and sedimentation Stagnant water and unsanitary conditions may cause mosquito breeding at site
Socio-Economic Environment
The proposed project does not involve any displacement of inhabitants for the construction of LPG Bottling Plant.
Construction phase could lead to creation of employment and procurement opportunities. A multiplier effect will be felt on the creation of indirect employment through the local
community establishing small shops like tea stalls, supply of intermediate raw materials, repair outlets, hardware stores garrages etc.
Self- employment options for individuals possessing vocational or technical training skills like electricians, welders, fitters etc, which are likely to be sourced locally;
There would be influx of workers during construction phase which could lead to pressure on key local infrastructure such as water, healthcare, electricity.
The construction activity could lead to increased nuisance level from air emissions and noise due to transportation of material and equipment as well as labourers.
The construction activity could also lead to water stagnation at pockets which may lead to breeding of mosquito and related health impacts.
4.2.2 During Operation Phase Land/Soil Environment Soil quality may be affected by accidental leakage and spillage of hazardous chemicals/oils
during handling
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 58
Improper segregation and disposal of solid waste generated during operation of the proposed project
Air Environment No emission is envisaged during the storage and handling of LPG in mounded bullets No fugitive emission during loading and unloading of LPG in and from mounded bullets is
envisaged Impacts on ambient air during operation phase would be due to emissions from operation of
DG sets only during power outages.
Noise Environment Impact of noise due to vehicular traffic Noise generated due to DG set
Water Environment
Stress on existing water supply Generation of waste water & domestic effluent Increased run off from site
Socio-Economic Environment
Project and associated construction of LPG Bottling Plant will eventually lead to permanent job opportunities in the organized and unorganized sector. There is likely to be increased demand for security, kitchen help, need for drivers etc.
Development of physical infrastructure due to construction of the plant which could benefit the local population
4.3 Impact Mitigation Measures 4.3.1 During Construction Phase Land/Soil Environment
Top soil will be stored carefully and will be used again after construction/installation phase is over so as to restore the fertility of project site
Bituminous materials / other chemicals, if any, shall not be allowed to leach into the soil Methods to reuse earth material generated during excavation will be followed Waste oil generated from D. G. sets will be handed over to authorized recyclers approved by
HPPCB Usage of appropriate monitoring and control facilities for construction equipments deployed All hazardous wastes shall be securely stored, under a shed for eventual transportation and
disposal to the authorized dealers The solid waste generation due to workers working at site will be segregated and will be
transported and disposed of to waste disposal facility
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 59
Chemicals/Paints etc. used during construction phase will be stored safely Air
Checking of vehicles and construction machinery to ensure compliance to Indian Emission Standards3
Transportation vehicles, DG sets and machineries to be properly and timely maintained and serviced regularly to control the emission of air pollutants in order to maintain the emissions of NOX and SOX within the limits established by HPPCB
Minimize idling time for vehicles and adequate parking provision and proper traffic arrangement for smooth traffic flow
Use of good quality fuel and lubricants will be promoted. Moreover, low sulphur content diesel shall be used as fuel for DG sets to control emission of SO2
Water sprinkling shall be carried out to suppress fugitive dust during earthworks and along unpaved sections of access roads
Attenuation of pollution/ protection of receptor through strengthening of existing greenbelt/ green cover
However, the construction activities will be for temporary period and hence, its impact on the existing ambient air quality as well as vegetation will be reversible. Dust emissions are likely to be confined within the limited area. Noise
No noise polluting work in night shifts Acoustic enclosures for DG Sets will be provided as per CPCB guidelines Pumps – Enclosure in acoustic screen, allowing for engine cooling and exhaust, use of anti-
vibration mounting, flexible couplings of hoses, maintaining adequate inlet pressure Provision of Intake mufflers, unidirectional fan for Cooling and enclosures for electrical
motors Provision of ear plugs for labour in high noise area Provision of barricades along the periphery of the site All contractors and subcontractors involved in the construction phase shall comply with the
CPCB noise standards4 Activities that take place near sensitive receptors to be carefully planned (restricted to
daytime, taking into account weather conditions etc.) Vehicles and generator sets to be serviced regularly and maintained properly to avoid any
unwanted generation of noise or vibration from them
4http://CPCB.nic.in/divisionsofheadoffice/pci2/Noise-vehicle.pdf
http://cpcb.nic.in/divisionsofheadoffice/pci2/noise_rules_2000.pdf
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 60
Use of suitable muffler systems/ enclosures/ sound proof glass paneling on heavy equipment/ pumps/ blowers
Pumps and blowers may be mounted on rubber pads or any other noise absorbing materials In case of steady noise levels above 85 dB (A), initiation of hearing conservation measures Strengthening of greenbelt for noise attenuation may be taken up, etc.
Water
Water Avoidance of wastage of curing water Use of tanker water for construction activity. Provision of temporary toilets for labour Wastewater generated will be recycled/reused duringoperation of the LPG Plant
Socio-Economic Environment
Employing local people for construction work to the maximum extent possible. Providing proper facilities for domestic supply, sanitation, domestic fuel, education,
transportation etc. for the construction workers. Barricades, fences and necessary personnel protective equipment such as safety helmet,
shoes, goggles, gloves, harness etc. will be provided to the workers and employees. Constructional and occupational safety measures to be adopted during construction phase of
the industry. The health of workers will be checked for general illness; first time upon employment and
thereafter at periodic intervals, as per the local laws and regulations. The workers will be diagnosed for respiratory functions at periodic intervals and during
specific complaints etc. Medical Aid as per Factory Act and Panel doctor facility will be provided to the workers.
Job rotation schemes will be practiced for over-exposed persons. Insignificant impact is expected on the workers health and safety during the operation phase stage.
4.3.2 During Operation Phase Land/Soil Environment
Installation of drainage ditches at project site to prevent erosion All hazardous wastes shall be securely stored, under a shed for eventual transportation and
disposal to the authorized dealer by HPPCB The solid domestic waste shall be segregated and stored within the premises temporarily and
then sent to waste management facility Air
Checking of vehicles and construction machinery to ensure compliance to Indian Emission Standards5
5http://cpcb.nic.in/divisionsofheadoffice/pci2/Noise-vehicle.pdf
http://cpcb.nic.in/divisionsofheadoffice/pci2/noise_rules_2000.pdf
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 61
Transportation vehicles, generators and machineries to be properly and timely maintained and serviced regularly to control the emission of air pollutants in order to maintain the emissions of NOX and SOX within the limits established by CPCB
Stack height of DG sets shall be as per norms of CPCB to allow effective dispersion of pollutants
Storage facilities shall be equipped with leak detection systems Minimize idling time for vehicles and adequate parking provision and proper traffic
arrangement for smooth traffic flow Attenuation of pollution/ protection of receptor through strengthening of existing greenbelt/
green cover Noise
Provision of proper parking arrangement, traffic management plan for smooth flow of vehicles help to abate noise pollution due to vehicular traffic.
Green belts and landscaping shall act as noise buffer. Water
Waste water generated from cylinder washing shall be recycled /resuedafter sedimentation.
Rain water harvesting shall be promoted. Rainwater from the landscape area and hardscape area will be used to recharge the ground water sources through recharge pit
Provision of Storm water drainage system with adequate capacity, Proper maintenance of storm water drainage.
Socio-Economic Environment
Both skilled and unskilled local person shall be given preference for the jobs in the operation and maintenance of the plant.
4.4 Impact Matrix The matrix was designed for the assessment of impacts associated with almost any type of project. Its method of a checklist that incorporates qualitative information on cause-and-effect relationships but it is also useful for communicating results. Matrix method incorporates a list of impacting activities and their likely environmental impacts, presented in a matrix format. Combining these lists as horizontal and vertical axes in the matrix allows the identification of cause effect relationships, if any, between specific activities and impacts. The impact matrix for the actions identified in Table 4.1 along with various environmental parameters. A rating scale has been devised to give severity of impacts in the following manner. A. Beneficial (positive) impact – Long term
5http://cpcb.nic.in/Vehicular_Exhaust.php
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 62
B. Low beneficial impact – Short term C. Strong adverse (negative) impact – Long term D. Low adverse impact (localized in nature) – Short term E. No impacts on environment
Table 4.1: Impact Matrix
S.N. Activity Positive Impact Negative Impact
No Impact
Short Term
Long Term
Short Term
Long Term
Pre-Project Activity 1 Displacement and resettlement of
local people √
2 Change in land use √ 3 Loss of trees/vegetation √ 4 Shifting of equipment, machinery
and material √
5 Employment for local people √ Construction Phase
1 Pressure on infrastructure and transportation system
√
2 Impact on air quality including dust generation
√
3 Noise Pollution √ 4 Traffic √ 5 Impact on the land/soil
environment √
6 Impact on groundwater √ 7 Stacking and disposal of
construction material √
8 Impact on water quality √ 9 Health and safety conditions of
people √
10 Social impact √ 11 Economic impact √
Operation Phase 1 Increase in air pollution and noise
levels √
2 Water harvesting and recharge √ 3 Disposal of solid waste √ 4 Infrastructure development √
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 63
5 Quality of life √ 6 Handling operations for transfer,
charging of raw materials, final product
√
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 64
4.5 Summary of Environment Impacts and Mitigation Measures The summary of the Impacts and Mitigation measures for the above mentioned environmental attributes is as summarized in Table 4.2.
Table 4.2: Summary of Impacts and Mitigation Measures Impacting Activity Potential Impact
Mitigation Measures Environment/ Social Attribute
Compliance/ Standards/ Best
Practice Guidelines Environment/
Social Attribute Source
Contaminants Environment Health and Safety
Construction Phase
Construction Workers
Generation of sewage, organic wastes, construction debris etc.
Possible contamination of project site and nearby water bodies
Potential risk of respiratory irritation, discomfort, or illness to workers
Local workers will be employed, as far as possible.
Proper sanitation facilities will be provided for the workers
There are no temporary shelters provided because local workers will be engaged
--
Air Emissions Dust and air emission particularly due to the excavation, construction and movement of vehicles resulting in air pollution
Rise in RSPM level at project site
Potential risk of respiratory irritation, discomfort, or illness to workers
Barricading sheets shall be provided
Provision of spraying water to reduce dust emission
Excavated topsoil to be preserved and reused for landscaping
Ensuring all vehicles, generators and compressors are shall be maintained and regularly serviced
CPCB - National Ambient Air Quality Standards
Noise Generation Construction noise mainly due to excavation, Moving of vehicles, operations of cranes etc.
Rise in decibel level of ambient noise
Unwanted sound can cause problems within the body. Excessive noise pollution in working areas at construction sites can influence psychological health viz. occurrence of aggressive behaviour,
The vehicles used will be with the proper acoustic measures
Wherever this cannot be achieved the area will be earmarked as high noise level area requiring use of ear protection gadgets
Avoid night time work
CPCB - Noise Pollution (Regulation and Control) Rules
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 65
Impacting Activity Potential Impact Mitigation Measures
Environment/ Social Attribute
Compliance/ Standards/ Best
Practice Guidelines Environment/
Social Attribute Source
Contaminants Environment Health and Safety
disturbance of sleep, constant stress, fatigue and hypertension. Hampered sleeping pattern and may lead to irritation and uncomfortable situations.
Soil and Groundwater Contamination
Spillage of concrete mixture containing additives and plasticizers.
Spillage of construction material containing heavy metals, paints, coatings, liners, etc.
Leaking or empty drums will be handled as per environment management plan
Special care will be taken during deliveries of construction materials, especially when fuels and hazardous materials are being handled
Ensure that workers know what to do in the event of a spillage
Operation Phase
Air Emissions Release of emission from the DG Sets in case of power failure and operation of fire Engine in case of fire drill or emergency
Negligible Impact
Negligible Impact
The DG sets are provided with Stack Height per CPCB guidelines above roof level.
Wastewater Domestic waste water arising from Restroom and
Negligible Impact
Negligible Impact STP has been provided for domestic sewage.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 66
Impacting Activity Potential Impact Mitigation Measures
Environment/ Social Attribute
Compliance/ Standards/ Best
Practice Guidelines Environment/
Social Attribute Source
Contaminants Environment Health and Safety
Canteen Hazardous Materials, Fire and Explosion
Risk of fire and explosions due to the flammable and combustible nature of petroleum products.
Risk of leaks and accidental releases from equipment, tanks, pipes etc during loading and unloading (handling)
Potential risk of loss of life or injury due to fire
Storage equipment should meet standards for structural design and integrity. .
OISD-STD 144 - Fire Protection
Facilities for LPG Bottling Plant.
Hazardous Waste No Hazardous Waste except used lubricating Oil
Same to be Stored in barrels
Being stored in designated place on Concrete platform
To be disposed to HPPCB accredited vendors
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 67
The above table can be summarized as shown in below matrix as Table 4.3. Table 4.3: Overall Matrix
4.6 Conclusion From the above discussion it can be concluded that proposed project activity at Una, Himachal Pradesh shall not create any significant negative impact on physical features, water, noise and air environment. The proposed project shall generate additional indirect employment and indirect service sector enhancement in the region and would help in the socio-economic up-liftmen of the local area as well as the state.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 68
CHAPTER 5: PROJECT BENEFITS
5.1 Project Benefits
The Proposed project will have indirect positive impact on surrounding area which is as mentioned below:
Expansion will be carried out within existing premises; hence no displacement of people is required
Substantial Socio-economic benefits
Good Techno-commercial viability
Around the project site semi-skilled and unskilled workmen are expected to be available from local population in these areas to meet the manpower requirement during construction phase.
Infrastructural facilities will be improved due to the project
Secondary employment will be generated thereby benefiting locals
Thus a significant benefit to the socio-economic environment is likely to be created due to the project.
5.2 Improvements in the Physical Infrastructure
The project will improve supply position of LPG in Himachal Pradesh State.
Maintain continuity of LPG gas cylinder supply to the consumers through distributors.
Increase the days cover for LPG storage.
Safety measures for hazard detection and prevention system will be upgraded as per OISD-144/OISD-150.
By adding 2x600 MT Mounded Bullets, risk profile of the existing plant will not be enhanced.
Discourage deforestation and reduce the use of fire wood and fossil fuels.
Establishment of large developmental projects improve the availability of the physical infrastructures like approach roads, drainage, communication and transportation facilities etc.
5.3 Improvements in the Social Infrastructure
IOCL Una LPG Plant shall take up some community welfare activities under Corporate Social Responsibility and also improve the social infrastructures like education and health care system etc.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 69
5.4 Employment Potential
The project shall provide employment potential under unskilled, semi-skilled and skilled categories. The employment potential shall increase with the start of construction activities, reach a peak during construction phase and then reduce with completion of construction activities.
The direct employment opportunities with IOCL are extremely limited and the opportunities exist mainly with the contractors and sub-contractors. These agencies will be persuaded to provide the jobs to local persons on a preferential basis wherever feasible.
5.5 CSR and Socio-Economic Development
IOCLnot only carries out business but also understands the obligations towards the society. The unit is aware of the obligations towards the society and to fulfill the social obligations unit will employ semi-skilled and unskilled labor from the nearby villages for the proposed project as far as possible. Unit will also try to generate maximum indirect employment in the nearby villages by appointing local contractors during construction phase as well as during operation phase. The Project Proponents will contribute reasonably as part of their Corporate Social Responsibility (CSR) in and will carry out various activities in nearby villages.
Moreover, unit has planned to carry out various activities for the up-liftment of poor people, welfare of women and labors, education of poor students as part of CSR in the nearby villages and therefore , during and after proposed project, unit will spent more than that required by statutory norms every year towards CSR activities. The various CSR activates planned at present by the unit is described below;
Plantation along the road side and development of garden/greenbelt on government barren land/common plots
Education aids and scholarship to poor students
Organize medical camp and providing support for the development and maintenance of the health facilities
Financial support and assistance for the development and maintenance of the infrastructure facilities
Participate and contribute in local social programs
Organize various types of training program for the community like training on scientific agricultural practices, educational training, (training for tailoring, embroidery), etc. which ultimately helpful for income generation
Organize various types of awareness program for the community like awareness on the child labor, educational promotion etc.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 70
The activities listed above are not limited to and IOCL will plan and perform other activities according to the need of local community in future. The utilization of this fund in various areas with time bound action plan will be decided based on the requirement of the local community.
5.6 Direct Revenue Earning to the National and State Exchequer
This project will contribute additional revenue to the Central and State exchequer in the form of excise duty, income tax, state sales tax or VAT, tax for interstate movement, corporate taxes etc. Indirect contribution to the Central and State exchequer will be there due to Income by way of registration of trucks, payment of road tax, income tax from individual as well as taxes from associated units. Thus, the proposed project will help the Government by paying different taxes from time to time, which is a part of revenue and thus, will help in developing the area.
5.7 Other Tangible Benefits
Both tangible and non-tangible benefits will result from this activity and many of those are described above. Apart from direct employment, many other benefits will accrue like
Erosion control by nalla training, terracing and bunding
Flood control by rain-water arresting, and harvesting
Aesthetics improvement by general greening with emphasis on biodiversity
Developed economy strengthens democratic set-up.
Developed economy brings with it literacy and healthful living
Improved safety-security in surrounding with better Law and Order
Symbiosis and sustainable development will be the ultimate objective
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 71
CHAPTER 6: ANALYSIS OF ALTERNATES
6.1 Alternative Technology
The project proposal relates to installation of 02 nos. of Mounded Bullets of 600 MT capacity each for storage of LPG.
IOCL has mastered the art and technology of installation of Mounded Bullets.
The LPG department of Marketing Division of IOCL has earned a good credential for installation of Mounded Bullets.
The above expertise of IOCL is well proven and working efficiently at different locations of the country including North-Eastern states without fail.
IOCL is having excellent track record and progressive outlook in regularly updating its technology. The technology adopted by IOCL for installation of Mounded Bullets for storage of LPG is a fail-safe.
6.2 Alternative Site
The proposed Augmentation is within the existing premises at atMehatpur, Una, Himachal Pradeshwhich was commissioned on 27th Dec 2003. Theplant is spread over 32.56 acre of land and hence no alternative site has been analyzed.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 72
CHAPTER 7.ADDITIONAL STUDIES
7.1 Public Consultation This section shall be updated upon completion of Public Consultation. 7.2 Quantitative Risk Assessment 7.2.1 Methodology Methodology adopted for risk assessment of LPG Bottling Plant, Una is as per following principle steps;
1. Hazard Identification – Identify types of hazards which have the potential to cause harm to the fatalities such as hydrocarbon releases.
2. Development of accident events – For the purposes of modeling, each hazard identified is further divided into scenarios or events e.g. Leaks, ruptures etc.;
3. Frequency Analysis – The frequency of occurrence (i.e. likelihood of occurrence within a given period) of each accidental event occurring is estimated from historical data such as OGP Risk Assessment Data Directory, Process Release Frequencies, Report no. 434-1 and 434-3, March 2010.
4. Consequence Modeling – The consequences (i.e. extent) arising from realization of these accidental events such as Jet Fires, Explosions are calculated based on various models;
5. Risk Analysis – Based on the fatalities arising from the consequences and the frequency determined for an accidental event, the risk from the hazard is determined in terms of individual risk;
6. Risk Summation – Risks associated with these accidental events are integrated to quantify the risk levels at the facility;
7. Benchmarking – The risks are benchmarked against Risk Acceptance Criteria to arrive at the list of events associated with “unacceptable” and “acceptable” risks;
8. Risk Ranking – The dominant risk contributors in terms of their risk level from various accidental events are summarized.
7.2.2 QRA Approach Result Interpretation
The techniques used for risk prediction within the QRA have inherent uncertainties associated with them due to the necessary simplifications required. In addition, QRA incorporates a certain amount of subjective engineering judgment and the results are subjected to levels of uncertainty. For this reason, the results should not be used as the sole basis for decision making and should not drive deviations from sound engineering practice. The results should be used as a tool to aid engineering judgment and, if used in this way, can provide valuable information during the decision making process.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 73
The QRA results are dependent on the assumptions made in the calculations, which are clearly documented throughout the following sections of this report. Conservative assumptions have been used, which helps to remove the requirement for detailed analysis of the uncertainty. The results show the significant contributions to the overall risk and indicate where worthwhile gains may be achieved if further enhancement of safety is deemed necessary. Risk Criteria PNGRB risk tolerability criterion in terms of Individual Risk (IR) is defined in the Section 61 of the Petroleum and Natural Gas Regulatory Board Act, 2006 (19 of 2006),Guidelines for preparation of ERDMP, which is also applicable to IOCL facilities. The maximum tolerable IR is 1.0 x 10-3 per year, whilst an IR of 1.0 x 10-6 per year is regarded as broadly acceptable. An IR falling between these values is within the ALARP region of risk acceptability and must be demonstrated to be as low as reasonably practicable. These criteria are given here below –
Figure 7.1: Risk Acceptance Criteria
The assessment and control of risk are essential requirements for a proactive HSE management system. In order to make a valued judgment and to decide on what risks are acceptable, an easily understood set of criteria should be set and followed rigorously. Risk criteria are required to promote consistency in evaluating the results of relevant studies and to formulate a proactive approach to incident prevention. The following sections sets out the basis for selecting the risk acceptance criteria and explains some of the techniques used to arrive at the quantitative assessments made to understand the risk levels.
IRPA
10-3/yr
10-4/yr
10-5/yr
10-6/yr
Intolerable
The ALARP or Tolerableregion (Risk is tolerated only)
Broadly Acceptable region(no need for detailed working todemonstrate ALARP)
Fundamental improvements needed.Only to be considered if there are no
alternatives and people are well informed
Too high, significant effort required toimprove
High, investigate alternatives
Low, consider cost-effective alternatives
Negligible, maintain normal precautions
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 74
Risk Risk is defined as the probability that within a fixed time period, usually one year, an unwanted effect occurs. Consequently, risk is a dimensionless number. However, risk is often expressed in units of frequency, ‘per year’. Since failure frequencies are low, the probability that an unwanted effect will occur within a fixed time period of one year is, practically speaking, equal to the frequency of occurrence per year. Risk is the unwanted consequences of an activity connected with the probability of occurrence. Individual Risk Criteria (IR) The tolerable risk level lies between the acceptable and unacceptable levels in which ALARP must be demonstrated. Once a specific hazard is demonstrated by analysis to result in acceptable risk there is no requirement, other than following normal precautions and SOPs defined by company and statutes. Workers would include IOCL employees and contractors. The public includes the general public, visitors and any third party who is not directly involved in the IOCL work activities. The tolerability criteria above should not be misinterpreted as the number of fatalities that IOCL is prepared to accept in conducting operations. They must be used only in QRA context as a statistical probability that equipment, systems and procedures fail and result in fatalities. Presentation of Risk Results Location Specific Individual Risk (LSIR) LSIR measures and expresses the risk exposure of personnel who are continuously present in a particular area for the entire year (24x7x365). The risk exposure is calculated for all relevant hazards and summed to give the overall risk of LPG Bottling Plant, Una. In the fatality estimation, the consequences of each outcome due to a loss of containment are represented by the probability of death for personnel continuously present in a particular area of the plant when the event occurs. The LSIR can therefore be represented as: LSIR = Σ (End event outcome frequency x Probability of fatality in area) Individual Risk per Annum (IRPA) IRPA takes into account the amount of time personnel spend at the plant and is defined as the probability of an individual being killed by the accident scenario per unit time. IRPA from process events is determined as follows: IRPA = Σ (LSIR x Probability of personnel in area) x Presence factor The presence factor is the actual time spent at the plant in a year. Potential Loss of Life (PLL) The PLL is a measure of risk to a group of personnel as a whole and is an average rate of fatalities at the plant. The PLL can be established using the following equation – PLL = Σ (IRPA) x Number of personnel in worker group
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 75
7.2.3 Hazard Identification A substance or circumstance which may cause injury or damage due to being explosive, flammable, poisonous, corrosive, oxidizing, or otherwise harmful is defined as hazard. Hazards associated with storage tanks As per UK HSE’s guideline HSG176, the main hazards associated with the storage and handling of flammable liquids are fire and explosion, involving either the liquid or the vapour given off from it. Fires and explosions are likely to occur when vapour or liquid is released accidentally or deliberately into areas where there may be an ignition source, or when an ignition source is introduced into an area where there may be flammable atmospheres. Common causes of such incidents include,
1. Inadequate design and installation of equipment; 2. Inadequate inspection and maintenance; 3. Failure or malfunction of equipment; 4. Lack of awareness of the properties of flammable liquids; 5. Operator error, due to lack of training; 6. Exposure to heat from a nearby fire; 7. Inadequate control of ignition sources; 8. Electrostatic discharges; 9. Heating materials above their auto-ignition temperature; 10. Dismantling or disposing of equipment containing flammable liquids;
Hot work on or close to flammable liquid vessels Hazard Categories In order to identify hazards posed by the facility, it is very important to identify the type of hazards posed by the materials being handled. IOCL handles and stores LPG. All these are flammable and pose fire and burn risk. As there is no toxic material being handled at MOT, there is no toxic risk envisaged Hazardous Properties Combustion of liquids occurs when flammable vapours released from the surface of the liquid ignite. The amount of flammable vapour given off from a liquid, and therefore the extent of the fire or explosion hazard, depends largely on the temperature of the liquid, how much of the surface area is exposed, how long it is exposed for, and the air movement over the surface. The hazard also depends on the physical properties of the liquid such as flashpoint, auto-ignition temperature, viscosity, and the upper and lower explosion limits. These are the various materials are stored in tanks & have been taken into Quantitative Risk Assessment.
Properties LPG HSD Flash Point(°C) < -60 > 35°C
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 76
LFL 1.8 % (V) 0.4 % UFL 8.5 % (V) 5 %
Volatility
Vapour Pressure 2.007 at 21.1 °C (70.0 °F)
0.5 mm of Hg
Boiling point (°C) -0.5 (31.1 °F) at 1,013.25
hPa 110 °C to375°C
Relative density of gas or vapourto air
2 to 3 3 to 5
Physical State Gas Liquid Auto Ignition temp(°C) 287°C 230°Cto250°C
Scenarios Considering hazardous properties and facility, following scenarios have been considered for consequence and risk assessment – As per OGP – Risk Assessment Directory, for each of scenario four leak sizes are considered for release from Piping,
1. Small leak – Leak size 5 mm (representative size of 1 to 10mm) 2. Medium Leak – Leak size 25 mm (representative size of 10mm to 50mm) 3. Large Leak – Leak size 100 mm (representative size of 50 to 150mm) 4. Full Bore Rupture (FBR)
In case of release from storage, following leak sizes are considered: 1. Small leak – Leak size 5 mm (representative size of 1 to 10mm) 2. Medium Leak – Leak size 25 mm (representative size of 10mm to 50mm) 3. Large Leak – Leak size 100 mm (representative size of 50 to 150mm) 4. Catastrophic Rupture
Table 7.1: List of identified Scenarios
SN Section Number Section Description
1 IS-01 Piping from LPG Bullets to suction of compressors
2 IS-02 Piping from discharge of compressors to vapour arm
3 IS-03 Piping from liquid Loading & unloading arm to inlet
of LPG Bullets
4 IS-04 Piping from outlet of LPG Bullets to suction of LPG
filling pumps
5 IS-05 Piping from discharge of LPG filling pumps to filling
hall (LPG Cylinder filling operation)
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 77
SN Section Number Section Description
6 IS-06 Piping from LPG Bullets to suction of LPG tanker
loading pump
7 IS-07 Piping from discharge of LPG tanker loading pump
to LPG tanker loading arm
8 IS-08 600 MT Mounded Bullet - 1
9 IS-09 600 MT Mounded Bullet - 2
10 IS-10 300 MT Mounded Bullet - 1
11 IS-11 300 MT Mounded Bullet - 2
12 IS-12 300 MT Mounded Bullet - 3
13 IS-13 Diesel Tank 20KL
14 IS-14 Diesel Tank Transfer pump
Climatic Conditions Meteorological Data The consequences of released flammable material are largely dependent on the prevailing weather conditions. For the assessment of major scenarios involving release of flammable material, the most important meteorological parameters are those that affect the atmospheric dispersion of the escaping material. The crucial variables are wind direction, wind speed, atmospheric stability and temperature. Rainfall does not have any direct bearing on the results of the risk analysis; however, it can have beneficial effects by absorption / washout of released materials. Actual behavior of any release would largely depend on prevailing weather condition at the time of release. Atmospheric Stability Classes The tendency of the atmosphere to resist or enhance vertical motion and thus turbulence is termed as stability. Stability is related to both the change of temperature with height (the lapse rate) driven by the boundary layer energy budget, and wind speed together with surface characteristics (roughness) A neutral atmosphere neither enhances nor inhibits mechanical turbulence. An unstable atmosphere enhances turbulence, whereas a stable atmosphere inhibits mechanical turbulence. Stability classes are defined for different meteorological situations, characterised by wind speed and solar radiation (during the day) and cloud cover during the night. The so called Pasquill-Turner stability classes dispersion estimates include six (6) stability classes as below: A – Very Unstable B – Unstable C – Slightly Unstable D – Neutral E – Stable F – Very Stable
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 78
The typical stability classes for various wind speed and radiation levels during entire day are presented in table below:
Table 7.2: Typical Pasquill Stability classes
Wind Speed (m/s)
Day : Solar Radiation Night : cloud Cover
Strong Moderate Slight Think <
40% Moderate
Overcast > 80%
<2 A A-B B - - D
2-3 A-B B C E F D
3-5 B B-C C D E D
5-6 C C-D D D D D
>6 C D D D D D
The wind speed and Pasquill Stability class data used for the study is summarized below: Wind Speed Stability class
2m/s F 5 m/s D
7.2.4 Events and Ignition Probability Event Tree PHAST has an in-built event tree for determining the outcomes which are based on two types of releases namely continuous and instantaneous. Leaks are considered to be continuous releases whereas, ruptures are considered to be instantaneous releases. The event tree takes in to account factors affecting consequence of a release such as;
1. Material properties such as a. Flammability / toxicity b. Flash point c. Phase of material d. Density of material
2. Ambient conditions 3. Availability of Immediate / Delayed ignition
Based on these the event trees used in PHAST Risk are given here below –
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 79
Figure7.2: Event tree for Continuous release with rainout (from PHAST software)
7.2.5 Consequential Events Jet Fire A jet fire occurs following the ignition and combustion of pressurized flammable fluid continuously released from a pipe or orifice, which burns close to its release plane. The high heat intensity poses a hazard to personnel and causes damage to unprotected equipment due to direct flame impingement, causing it to fail within several minutes. Jet flames dissipate thermal radiation, away from the flame’s visible boundaries and transmit heat energy that could be hazardous to life and property. Pool Fire The released flammable material which is a liquid stored below its normal boiling point, will collect in a pool. The geometry of the pool will be dictated by the surroundings. If the liquid is stored under pressure above its normal boiling point, then a fraction of the liquid will flash into vapour and the remaining portion will form a pool in the vicinity of the release point. Once
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 80
sustained combustion is achieved, liquid fires quickly reach steady state burning. The heat release rate is a function of the liquid surface area exposed to air. An unconfined spill will tend to have thin fuel depth (typically less than 5 mm) which will result in slower burning rates. A confined spill is limited by the boundaries (e.g. a dyke area) and the depth of the resulting pool is greater than that for an unconfined spill. Pool fires are less directional and so may affect a larger area although it is mostly influenced by wind conditions. They will also cause structural failure of equipment although the time taken is longer than jet fires. Flammable Gas Dispersion / Flash Fire Flash Fire occurs when a vapour cloud of flammable material burns. The cloud is typically ignited on the edge and burns towards the release point. The duration of flash fire is very short (seconds), but it may continue as Jet fire if the release continues. The overpressures generated by the combustion are not considered significant in terms of damage potential to persons, equipment or structures. The major hazard from flash fire is direct flame impingement. Typically, the burn zone is defined as the area the vapour cloud covers out to the LFL. Even where the concentration may be above the UFL, turbulent induced combustion mixes the material with air and results in flash fire. Ignition Probability There are 2 main types of ignitions, namely:
1. Immediate ignition — Ignition following rapidly after the release is initiated, prior to personnel being able to escape from the area; and
2. Delayed ignition — Gas cloud drifting over an ignition source and depending on the ignition delay, personnel may be able to escape before fire or explosion occurs.
PHAST has systematic approach for deciding ignition probabilities depending upon type of release, phase of material released, reactivity and release rate. These have been used for the purpose of the study.
Table 7.3: Ignition Probabilities as used in PHAST. Type and Size of Release Type of Material Released
Continuous Instantaneous
K0 K1 K2 K3 K4Gas; liquid: Tfl< 0oC liquid: liquid: liquid: liquid
Reactivity: Reactivity:Tfl< 21oC
Tfl< 55oC
Tfl< 100oC
Tfl> 100oC
High, Average, Unknown
Low
< 10 kg/s < 1000 kg 0.2 0.02 0.065 0.01 0 0
10 - 100 kg/s 1000 - 10,000
kg 0.5 0.04 0.065 0.01 0 0
> 100 kg/s > 10,000 kg 0.7 0.09 0.065 0.01 0 0
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 81
7.2.6 Consequence Analysis Consequence analysis is carried out to determine the extent of spread (dispersion) by accidental release which may lead to jet fire or explosion resulting into generating heat radiation, overpressures, explosion impact etc. Modes of failure Leak and tank on fire are two types of scenarios considered in the study. Tank on fire is applicable only to floating roof tank. For leak scenario, the leak sizes considered are as under,
Table 7.4: Leak sizes considered Leak Sizes
Leak Description
Representative Hole Diameter
Remarks
Small (0 – 10 mm)
5 mm Represents leaks from flange joints and pump seals.
Medium (10 – 50 mm)
25 mm Represents release due to failure of small bore piping (instrument tapping, drain connection etc.).
Large (50 – 150 mm)
100 mm Represents release due to failure of large section of equipment or piping (e.g. damage due to external impact, failure of flexible pipe/ hose).
Rupture >150mm Represents release due to failure of large section of equipment or piping equivalent to its rupture / full bore release.
Above leak sizes are taken from Centre of Chemical Process Safety(CCPS) AIChE CCPS QRA guidelines, chapter 2 – Consequence analysis, also mentions about leak duration. It says that the Department of Transportation (1980) LNG Federal Safety Standards specified 10-min leak duration; other studies (Rijnmond Public Authority, 1982) have used 3 min if there is a leak detection system combined with remotely actuated isolation valves. Other analysts use a shorter duration. Actual release duration may depend on the detection and reaction time for automatic isolation devices and response time of the operators for manual isolation. The rate of valve closure in longer pipes can influence the response time. Due to the water hammer effect, designers may limit the rate of closure in liquid pipelines. Considering this and isolated facility of IOCL, we have considered 10min discharge duration as a conservative approach.Impact CriteriaAn impact criterion relates the modeling of the hazard effects to the resultant consequences to personnel and asset, and determines the nature and detail of results required from the simulation. The impact criteria for personnel and equipment on IOCL are summarised in the following sub-sections. Personnel Following table defines the impact of thermal radiation on personnel. The thermal radiation levels listed includes solar radiation of 1 kW/m2.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 82
Table 7.5: Thermal Radiation Impact Criteria for Personnel
Thermal Radiation Effect Description
1.6 kW/m2 Maximum radiant heat intensity at any location where personnel with appropriate clothing can be continuously exposed.
4 kW/m2 Maximum radiant heat intensity in areas where emergency actions lasting 2 to 3 minutes can be required by personnel without shielding but with appropriate clothing.
12.5 kW/m2 Maximum radiant heat intensity in areas where emergency actions lasting up to 30 seconds can be required by personnel without shielding but with appropriate clothing.
37.5 kW/m2 Limiting thermal radiation intensity for escape actions lasting a few seconds. Significant chance of fatality for extended exposure.
Table 7.6: Thermal Radiation Impact Criteria for Equipment
Thermal Radiation Effect Description 4 kW/m2 Glass breakage (30 minute exposure)
12.5 to 15 kW/m2 Piloted ignition of wood, melting of plastic (>30 minute exposure)
18 to 20 kW/m2 Cable insulation degrades (>30 minute exposure) 10 or 20 kW/m2 Ignition of fuel oil (120 or 40 seconds, respectively)
25 to 32 kW/m2 Unpiloted ignition of wood, steel deformation (>30 minute exposure)
35 to 37.5 kW/m2 Process equipment and structural damage (including storage tanks) (>30 minute exposure)
100 kW/m2 Steel structure collapse (>30 minute exposure)
The damage effects are different for different scenarios considered. In order to appreciate the damage effects produced by various scenarios, it will be appropriate to discuss the physiological/ physical effects of the accidental loss of containment event. Initial Release Rates A release at the tank farm may be modeled using a representative hole size or by fixing the release rate for a given scenario. In this assessment, the former method was used as the hole size is a major factor in influencing the characteristics of a release and determines the initial hydrocarbon mass release rate as well as release duration. Based on the hole sizes, material properties and operating / storage conditions, the corresponding initial release rates for fire modeling are obtained from PHAST.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 83
Liquid flash rates were used for dispersion in case of releases as there is no gaseous material being handled. The release rate decreases with time as the equipment depressurizes. This reduction depends mainly on the inventory and the action taken to isolate the leak and blow-down the equipment. Flammable Gas Dispersion The significance of these distances is that the cloud will ignite if it were to get source of ignition within UFL and LFL zone. Following table gives the LFL and UFL dispersion distances for various leak sizes under different weather conditions. The resultant flammable dispersion distances are given in the table below,
Table 7.7: Flammable (LFL) dispersion distances
SN Scenario
ID Description of scenario
Leak Size in
mm
Flammable distances in m
Conc. 2F 5D
1 IS01 Piping from LPG Bullets to suction of compressors
5
UFL 0.31 0.32
LFL 1.57 1.47
0.5 LFL
2.89 2.45
25
UFL 1.53 1.54
LFL 7.56 6.51
0.5 LFL
15.72 11.49
100
UFL 6.08 5.97
LFL 40.45 39.65
0.5 LFL
88.24 97.75
FBR
UFL 9.24 9.02
LFL 66.71 70.66
0.5 LFL
110.12 129.97
2 IS02 Piping from discharge of compressors to vapour
arm
5
UFL 0.35 0.36
LFL 1.75 1.63
0.5 LFL
3.22 2.73
25
UFL 1.7 1.71
LFL 8.45 7.28
0.5 LFL
18.32 14.03
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 84
SN Scenario
ID Description of scenario
Leak Size in
mm
Flammable distances in m
Conc. 2F 5D
100
UFL 6.72 6.64
LFL 46.59 46.14
0.5 LFL
88.08 102.09
FBR
UFL 6.84 6.73
LFL 47.89 47.08
0.5 LFL
88.76 103.6
3 IS03 Piping from liquid
Loading & unloading arm to inlet of LPG Bullets
5
UFL 1.61 1.58
LFL 6.82 5.47
0.5 LFL
13.52 8.16
25
UFL 7.87 7.38
LFL 54.02 49.84
0.5 LFL
123.87 105.88
100
UFL 39.39 38.9
LFL 250.27 303.56
0.5 LFL
369.63 428.38
FBR
UFL 66.09 65.56
LFL 299.69 371.04
0.5 LFL
417.64 490.24
4 IS04 Piping from outlet of
tanks to suction of LPG filling pumps
5
UFL 0.32 0.32
LFL 1.6 1.49
0.5 LFL
2.94 2.49
25
UFL 1.55 1.56
LFL 7.67 6.61
0.5 LFL
16.09 11.81
100
UFL 6.18 6.08
LFL 41.26 40.49
0.5 99.04 105.45
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 85
SN Scenario
ID Description of scenario
Leak Size in
mm
Flammable distances in m
Conc. 2F 5D
LFL
FBR
UFL 16.59 16.46
LFL 118.08 131.98
0.5 LFL
179.17 211.45
5 IS05
Piping from discharge of LPG filling to filling hall
(LPG Cylinder filling operation)
5
UFL 2.01 1.97
LFL 8.55 6.72
0.5 LFL
19.14 11.91
25
UFL 9.91 9.17
LFL 70.57 69.25
0.5 LFL
153.74 141.49
100
UFL 51.66 51.02
LFL 257.24 316.5
0.5 LFL
360.07 424.44
FBR
UFL 85.42 84.56
LFL 303.07 383.64
0.5 LFL
404.71 479.29
6 IS06 Piping from LPG Bullets to suction of LPG tanker
loading pump
5
UFL 0.33 0.34
LFL 1.68 1.56
0.5 LFL
3.07 2.6
25
UFL 1.63 1.64
LFL 8.04 6.91
0.5 LFL
17.18 12.8
100
UFL 6.48 6.37
LFL 44.01 43.31
0.5 LFL
97.6 112.02
FBR UFL 9.85 9.61
LFL 73.24 76.62
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 86
SN Scenario
ID Description of scenario
Leak Size in
mm
Flammable distances in m
Conc. 2F 5D
0.5 LFL
121.03 142.44
7 IS07 Piping from discharge of LPG tanker loading pump
tanker loading arm
5
UFL 1.83 1.78
LFL 7.37 5.72
0.5 LFL
15.92 8.68
25
UFL 8.94 8.15
LFL 63.92 58.65
0.5 LFL
164 108.6
100
UFL 47.09 46.37
LFL 264.13 312.74
0.5 LFL
571.25 461.15
FBR
UFL 123.66 180.36
LFL 706.25 1133.53
0.5 LFL
1643.72 1817.43
8 IS08 Loss of containment of
LPG from 600MT Mounded Bullets 1
5
UFL 0.83 0.62
LFL 8.6 5.6
LFL Frac
12.55 11.1
25
UFL 4.11 3.08
LFL 40.08 26.64
LFL Frac
57.49 46.53
100
UFL 16.13 12.32
LFL 137.39 98.73
LFL Frac
247.3 162.31
FBR
UFL 83.13 95.08
LFL 226.78 359.59
LFL Frac
440.25 729.3
9 IS09 Loss of containment of 5 UFL 0.83 0.62
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 87
SN Scenario
ID Description of scenario
Leak Size in
mm
Flammable distances in m
Conc. 2F 5D
LPG from 600MT Mounded Bullets 2
LFL 8.6 5.6
LFL Frac
12.55 11.1
25
UFL 4.11 3.08
LFL 40.08 26.64
LFL Frac
57.49 46.53
100
UFL 16.13 12.32
LFL 137.39 98.73
LFL Frac
247.3 162.31
FBR
UFL 83.13 95.08
LFL 226.78 359.59
LFL Frac
440.25 729.3
10 IS10 Loss of containment of
LPG from 300MT Mounded Bullets 1
5
UFL 0.664 0.496
LFL 6.88 4.48
LFL Frac
10.04 8.88
25
UFL 3.288 2.464
LFL 32.064 21.312
LFL Frac
45.992 37.224
100
UFL 12.904 9.856
LFL 109.912 78.984
LFL Frac
197.84 129.848
FBR
UFL 66.504 76.064
LFL 181.424 287.672
LFL Frac
352.2 583.44
11 IS11 Loss of containment of
LPG from 300MT Mounded Bullets 2
5
UFL 0.664 0.496
LFL 6.88 4.48
LFL Frac
10.04 8.88
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 88
SN Scenario
ID Description of scenario
Leak Size in
mm
Flammable distances in m
Conc. 2F 5D
25
UFL 3.288 2.464
LFL 32.064 21.312
LFL Frac
45.992 37.224
100
UFL 12.904 9.856
LFL 109.912 78.984
LFL Frac
197.84 129.848
FBR
UFL 66.504 76.064
LFL 181.424 287.672
LFL Frac
352.2 583.44
12 IS12 Loss of containment of
LPG from 300MT Mounded Bullets 3
5
UFL 0.664 0.496
LFL 6.88 4.48
LFL Frac
10.04 8.88
25
UFL 3.288 2.464
LFL 32.064 21.312
LFL Frac
45.992 37.224
100
UFL 12.904 9.856
LFL 109.912 78.984
LFL Frac
197.84 129.848
FBR
UFL 66.504 76.064
LFL 181.424 287.672
LFL Frac
352.2 583.44
13 IS13 Loss of containment of
Diesel form Diesel Tank
5
UFL 2.16 1.89
LFL 3.43 3.98
0.5 LFL
3.46 3.98
25
UFL 6.18 6.02
LFL 6.34 6.38
0.5 6.35 6.4
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 89
SN Scenario
ID Description of scenario
Leak Size in
mm
Flammable distances in m
Conc. 2F 5D
LFL
100
UFL 8.7 8.72
LFL 8.8 8.83
0.5 LFL
8.8 8.84
FBR
UFL 16.02 18
LFL 16.18 18.15
0.5 LFL
16.21 18.18
14 IS14 Loss of containment of
Diesel from Diesel Tank Transfer pump
5
UFL 7.12 6.96
LFL 7.47 7.57
0.5 LFL
7.5 7.61
25
UFL 9.22 9.29
LFL 9.27 9.38
0.5 LFL
9.28 9.39
FBR
UFL 11.16 11.25
LFL 11.24 11.35
0.5 LFL
11.24 11.36
Notes: NR: Not Reached FBR: Full Bore Rupture It can be noted that the flammable cloud dispersion distances (LFL) are more in case of full bore rupture of LPG Mounded Bullets. It goes up to approximately 450m for5Dwind condition. Radiation Distances due to Jet Fire A jet or spray fire is a turbulent diffusion flame resulting from the combustion of a fuel continuously released with some significant momentum in a particular direction or directions. The properties of jet fires depend on the fuel composition, release conditions, release rate, release geometry, direction and ambient wind conditions. Radiation due to jet fire are given in the table below –
Table 7.8: Jet fire radiation distances
SN Scenario Description of scenario Leak Jet Fire distances in m
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 90
ID Size in mm
Radiation
kw/m2 2F 5D
1 IS01 Piping from LPG Bullets to suction of compressors
5
4 NR NR
12.5 NR NR
37.5 NR NR
25
4 14.92 15.51
12.5 11.36 12.42
37.5 NR NR
100
4 61.58 61.73
12.5 46.3 49.68
37.5 35.47 40.2
FBR
4 90.79 89.24
12.5 66.47 70.32
37.5 50.05 55.65
2 IS02 Piping from discharge of compressors to vapour
arm
5
4 NR NR
12.5 NR NR
37.5 NR NR
25
4 17.04 17.61
12.5 13.3 14.42
37.5 NR NR
100
4 69.67 69.54
12.5 52.3 55.67
37.5 40.04 44.81
FBR
4 70.71 70.53
12.5 53.02 56.41
37.5 40.57 45.37
3 IS03 Piping from liquid
Loading & unloading arm to inlet of LPG Bullets
5
4 15.73 13.6
12.5 12.57 10.36
37.5 10.57 8.33
25
4 68.66 59.68
12.5 54.6 45.43
37.5 46.19 36.97
100
4 239.28 207.78
12.5 188.06 156.95
37.5 157.64 126.76
FBR 4 348.64 293.67
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 91
SN Scenario
ID Description of scenario
Leak Size in
mm
Jet Fire distances in m
Radiation
kw/m2 2F 5D
12.5 273.13 222.73
37.5 228.28 180.4
4 IS04 Piping from outlet of
tanks to suction of LPG filling pumps
5
4 NR NR
12.5 NR NR
37.5 NR NR
25
4 15.19 15.79
12.5 11.58 12.66
37.5 NR NR
100
4 62.59 62.7
12.5 47.02 50.42
37.5 36.02 40.77
FBR
4 146.89 141.27
12.5 104.23 108.41
37.5 77.46 83.78
5 IS05
Piping from discharge of LPG filling to filling hall
(LPG Cylinder filling operation)
5
4 19.7 17.05
12.5 15.78 13.03
37.5 13.34 10.57
25
4 85.63 74.38
12.5 67.97 56.56
37.5 57.44 46.01
100
4 297.86 253.16
12.5 233.76 191.91
37.5 195.71 155.45
FBR
4 433.7 355.78
12.5 339.34 271.12
37.5 283.3 220.45
6 IS06 Piping from LPG Bullets to suction of LPG tanker
loading pump
5
4 NR NR
12.5 NR NR
37.5 NR NR
25
4 16.01 16.62
12.5 12.31 13.43
37.5 NR NR
100 4 65.55 65.53
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 92
SN Scenario
ID Description of scenario
Leak Size in
mm
Jet Fire distances in m
Radiation
kw/m2 2F 5D
12.5 49.14 52.57
37.5 37.58 42.41
FBR
4 96.52 94.63
12.5 70.45 74.32
37.5 52.97 58.64
7 IS07 Piping from discharge of LPG tanker loading pump
tanker loading arm
5
4 16.52 14.32
12.5 13.21 10.91
37.5 11.12 8.78
25
4 71.74 62.48
12.5 56.97 47.47
37.5 48.11 38.55
100
4 249.18 216.8
12.5 195.49 163.42
37.5 163.54 131.64
FBR
4 NR NR
12.5 NR NR
37.5 NR NR
8 IS08 Loss of containment of
LPG from 600MT Mounded Bullets 1
5
4 3.07 3.07
12.5 2.75 2.75
37.5 NR NR
25
4 16.34 16.93
12.5 13.48 14.64
37.5 11.27 12.84
100
4 66.45 66.29
12.5 50.17 53.51
37.5 38.65 43.44
9 IS09 Loss of containment of
LPG from 600MT Mounded Bullets 2
5
4 3.07 3.07
12.5 2.75 2.75
37.5 NR NR
25
4 16.34 16.93
12.5 13.48 14.64
37.5 11.27 12.84
100 4 66.45 66.29
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 93
SN Scenario
ID Description of scenario
Leak Size in
mm
Jet Fire distances in m
Radiation
kw/m2 2F 5D
12.5 50.17 53.51
37.5 38.65 43.44
10 IS10 Loss of containment of
LPG from 300MT Mounded Bullets 1
5
4 2.456 2.456
12.5 2.2 2.2
37.5 NR NR
25
4 13.072 13.544
12.5 10.784 11.712
37.5 9.016 10.272
100
4 53.16 53.032
12.5 40.136 42.808
37.5 30.92 34.752
11 IS11 Loss of containment of
LPG from 300MT Mounded Bullets 2
5
4 2.456 2.456
12.5 2.2 2.2
37.5 NR NR
25
4 13.072 13.544
12.5 10.784 11.712
37.5 9.016 10.272
100
4 53.16 53.032
12.5 40.136 42.808
37.5 30.92 34.752
12 IS12 Loss of containment of
LPG from 300MT Mounded Bullets 3
5
4 2.456 2.456
12.5 2.2 2.2
37.5 NR NR
25
4 13.072 13.544
12.5 10.784 11.712
37.5 9.016 10.272
100
4 53.16 53.032
12.5 40.136 42.808
37.5 30.92 34.752
13 IS13 Loss of containment of
Diesel from Diesel Tank
5
4 NR NR
12.5 NR NR
37.5 NR NR
25 4 2.43 2.34
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 94
SN Scenario
ID Description of scenario
Leak Size in
mm
Jet Fire distances in m
Radiation
kw/m2 2F 5D
12.5 NR 0.98
37.5 NR NR
100
4 NR NR
12.5 NR NR
37.5 NR NR
FBR
4 NR NR
12.5 NR NR
37.5 NR NR
14 IS14 Loss of containment of
Diesel from Diesel Tank Transfer pump
5
4 1.31 0.76
12.5 NR NR
37.5 NR NR
25
4 1.37 1.84
12.5 NR NR
37.5 NR NR
100
4 3.3 3.18
12.5 1.96 1.98
37.5 NR NR
Notes: NR: Not Reached FBR: Full Bore Rupture Jet fire is a credible scenario for gas facility, in the event of loss of containment from LPG pump discharge, the jet fire radiation distances for 4kW/m2 radiation goes up to approx. 433m for 2F wind condition. Radiation Distances due to Pool Fire A pool fire involves a horizontal, upward-facing, combustible fuel. When spilled, the Flammable/combustible liquid may form a pool of any shape and thickness, and may be controlled by the confinement of the area geometry such as a dyke or curbing. Once ignited, a pool fire spreads rapidly over the surface of the liquid spill area. When a spilled liquid is ignited, a pool fire develops. Provided that an ample supply of oxygen is available, the amount of surface area of the given liquid becomes the defining parameter. The diameter of the pool fire depends upon the release mode, release quantity (or rate), and burning rate. Liquid pool fires with a given amount of fuel can burn for long periods of time if they have a small surface area or for short periods of time over a large spill area.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 95
Following table gives radiation distances for pool fire scenario where it is assumed that the dyke will contain leaked material and would not allow it to flow beyond the restricted bund area.
Table 7.9: Pool fire radiation distances
SN Scenario ID Description of
scenario Leak Size in
mm
Pool Fire distances in m Radiation
kw/m2 2F 5D
1 IS13 Diesel Tank
5 4 84.30 98.39
12.5 42.97 43.60 37.5 NR NR
25 4 97.31 112.92
12.5 51.34 52.14 37.5 NR NR
100 4 33.97 37.70
12.5 19.19 23.48 37.5 11.61 12.15
FBR 4 90.52 108.29
12.5 44.58 47.52 37.5 NR NR
2 IS14 Diesel Tank
Transfer pump
5 4 42.15 49.195
12.5 21.485 21.8 37.5 NR NR
25 4 48.655 56.46
12.5 25.67 26.07 37.5 NR NR
100 4 16.985 18.85
12.5 9.595 11.74 37.5 5.805 6.075
FBR 4 45.26 54.145
12.5 22.29 23.76 37.5 NR NR
NR: Not Reached FBR: Full Bore Rupture The above results show that the pool fire radiation distances are in case of Diesel tank which goes up to 108 m for 4kW/m2 radiationfor 5D wind Condition. Radiation Distances due to Fireball
Table 7.10: Fireball Radiation Distances
SN Scenario
ID Description of scenario
Leak Size in
mm
Fireball distances in m
Radiation kw/m2
2F 5D
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 96
SN Scenario
ID Description of scenario
Leak Size in
mm
Fireball distances in m
Radiation kw/m2
2F 5D
1 IS1 Piping from LPG Bullets to suction of compressors
100
4 44.98 42.51
12.5 20.49 18.89
37.5 NR NR
2 IS2 Piping from discharge of compressors to vapour
arm
100
4 40.78 38.61
12.5 18.98 17.62
37.5 NR NR
FBR
4 40.78 38.61
12.5 18.98 17.62
37.5 NR NR
3 IS3
Piping from liquid Loading & unloading arm to inlet of LPG
Bullets
FBR
4 269.17 247.76
12.5 136.72 124.05
37.5 16.2 NR
4 IS4 Piping from outlet of
LPG Bullets to suction of LPG filling pumps
100
4 74.03 69.54
12.5 34.9 32.09
37.5 NR NR
FBR
4 74.03 69.54
12.5 34.9 32.09
37.5 NR NR
5 IS5
Piping from discharge of LPG filling pumps to
filling hall (LPG Cylinder filling
operation)
100
4 268.22 247.55
12.5 142.07 130.35
37.5 50.2 39.36
FBR
4 268.22 247.55
12.5 142.07 130.35
37.5 50.2 39.36
6 IS6 Piping from LPG Bullets to suction of LPG tanker
loading pump
100
4 52.18 49.24
12.5 24.29 22.44
37.5 NR NR
FBR
4 52.18 49.24
12.5 24.29 22.44
37.5 NR NR
7 IS7 Piping from discharge of
LPG tanker loading pump to LPG tanker
FBR
4 1484.53 1299.07
12.5 796.87 690.66
37.5 269.58 147.03
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 97
SN Scenario
ID Description of scenario
Leak Size in
mm
Fireball distances in m
Radiation kw/m2
2F 5D
loading arm
20 IS8 600MT Mounded Bullets FBR
4 1366.03 1199.02
12.5 728.14 631.92
37.5 230.06 103.13
21 IS9 600MT Mounded Bullets FBR
4 1366.03 1199.02
12.5 728.14 631.92
37.5 230.06 103.13
22 IS10 300MT Mounded Bullets FBR
4 819.618 719.412
12.5 436.884 379.152
37.5 138.036 61.878
23 IS11 300MT Mounded Bullets FBR
4 819.618 719.412
12.5 436.884 379.152
37.5 138.036 61.878
24 IS12 300MT Mounded Bullets FBR
4 819.618 719.412
12.5 436.884 379.152
37.5 138.036 61.878
Notes: NR: Not Reached FBR: Full Bore Rupture In case of Fireball for gas facility, in the event of loss of containment of LPG from 600MT Mounded Bullets, the Fireball radiation distances for 4kW/m2 radiation goes up to approx. 1350 m for 5D wind condition.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 98
7.2.7 Likelihood Estimation Frequency analysis was conducted for each of the release scenarios identified based on the number of potential leak sources contained within each isolatable section. Leaks may occur from various components such as tanks, pumps, pipes, valves and flanges. Each component has a generic historical leak frequency per single item such as a leak frequency per flange-year or per meter of pipe per year. Generic failure data for equipment and piping items is derived from historical leak frequency data compiled by the International Association of Oil & Gas Producers (OGP). For components other than Tanks, Report No. 434 – 1 – Process Release Frequencies dtd March 2010 has been used and for storage tanks, Report No. 434 – 3 – Storage incident frequencies dtd March 2010 has been referred to. Failure Frequencies This scenario is considered only for floating roof type of tank. Under section 2 of Report No. 434 – 3 the failure frequency of sunken roof in case of floating roof tank is 1.1 × 10-3/avg year. For other scenarios, the failure frequency has been estimated using parts count approach. The total leak frequency for any scenario is estimated by counting the number of each type of component in the section. This process is called “Parts Count”. The generic leak frequencies are then multiplied by the number of corresponding components in each isolatable section to obtain the overall leak frequency for that section. The calculated frequencies are given here below
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 99
Table 7.11: Estimated failure frequency
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 100
7.2.8 Risk Analysis This section deals with the risk assessment of Terminal installed at LPG Bottling Plant, Una. The risk of LPG Bottling Plant, Una is calculated based on consequences, parts count, failure frequency, ignition sources etc. A Quantitative Risk Analysis (QRA) is used to determine the risk caused by the use, handling, transport and storage of hazardous substances. The results of the QRA are, for example, used to assess the acceptability of the risk in relation to the benefits of the activity, to evaluate new developments on and off-site, to estimate the benefit of risk-reducing countermeasures and to determine zoning distances around an activity for land-use planning. QRAs are used to demonstrate the risk caused by the activity and to provide the competent authorities with relevant information to enable decisions on the acceptability of risk related to developments on site, or around the establishment or transport route. 7.2.9 Risk Contours Location specific individual risk (LSIR) is a measure of the risk exposure of an individual who is continuously present at a particular location for the whole year. This is a graphical representation of the risk estimated. Individual risk estimated for LPG Bottling Plant, Una is superimposed on layout and has illustrated below,
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 101
It can be seen that the risk level of 1E-03/avg year is surrounded to the LPG Bulltes. Above figure shows the risk impact of the entire facility. It can be seen easily that though the risk contour goes beyond the facility is 10E-06/avgyear, there is no other populated facility which will get affected. FN Curve The FN Curve shows the frequency (F) with which events cause N or more fatalities. F-N curve for risk posed by LPG Bottling Plant, Una on public surrounding is given here below. The risk is well within ALARP limits
IRPA and PLL Individual Risk per Annum (IRPA) and Potential Loss of Life (PLL) are estimated based on the LSIR at the locations. Figure above shows that the risk at the office building is less than 1E-07/avg year. Therefore the IRPA and PLL also fall under broadly acceptable region.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 102
7.2.10 Conclusion The risk analysis shows that the risk is below 1E-04/avg year. After benchmarking the risk against PNGRB’s Individual Risk Acceptance criteria, the risk is within ALARP or Tolerable Region – (Risk is tolerated only – High, investigate alternatives)region which means that normal precautions shall be maintained. However, in case of emergency there should be availability of the fire fighting system to control fire and also the vehicles to escape from hazardous area. 7.2.11 Recommendations The facility handles storage and handling of LPG which is highly inflammable in nature. Considering the hazard associated with storage and handling of LPG, state-of-art safety and security system has to be conceived to eliminate the hazard. 1. Safety as a consideration; the whole Tank Farm must be automated in order to avoid delays
in mitigating the risks unlike in manual operations. 2. Periodic preventive maintenance of pumps, valves, flanges, nozzles, flame arrestors,
breather valves etc. must be done. This preventive maintenance includes: a. Regular inspection of all pumps checking for mechanical seal to prevent leakages and
fugitive emission. b. Regular inspection of storage tanks checking for leaks due to cracks, spillages,
corrosion/erosion etc. c. Regular inspection of flame arrestors and breather valve checking for corrosion. d. Periodic functional tests of all valves ( isolation valves or any other valves installed along
the pipeline) e. Checking of storage areas for accumulation of any hazardous or combustible material. f. Safety devices and control instruments to be calibrated once in a year. 3. Fire & Gas detection system must be installed within one meter radius of tank farm area. 4. Flameproof Motors for unloading near flammable storage tank should be provided with
double earthing. 5. At every tank farm its license number, storage capacity & name of the chemicals should be
displayed at the entrance. 6. There should be good communication system available near tank farm area to the control
room, and it should be flameproof. 7. Periodic On Site Emergency Mock Drills and occasional Off Site Emergency Mock Drills
must be conducted, so that the staff is trained and are in a state of preparedness to tackle any emergency.
8. Safe operating procedure to be prepared for hazardous processes and material handling process.
9. Operating personnel should be adequately trained. 10. Work permit system must be implemented mandatorily for hazardous work in the plant.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 103
11. Safety manual and Public awareness manual needs to be prepared and distributed to all employees and nearby public.
12. Fire & Safety organization setup to be planed and implemented for better plant process safety.
13. Security circuit containing fusible plugs to detect heat/fire and thereby closing ROVs in vase of fire.
14. Fire water deluge and sprinkler system for spheres and mounded vessels. 15. LPG Storage vessel pressure safety valves designed for fire case. 16. Gas detectors at vantage points near LPG Storage vessel to detect any gas leak and give
alarm. 17. Dyke of small height at the LPG storage to collect LPG spillage with the floor at the
bottom of LPG Storage vessel sloping away from Storage vessels so that LPG will not form a pool below the Storage vessel itself.
18. All the ROVs should be fire safe certified and CCOE certified for SOV. 19. Emergency push buttons should be provided in LPG control room and also in field at safe
location for manual actuation of emergency shutdown interlock by the operator. 20. LPG transfer pumps should have double mechanical seal type with low level indication and
high pressure indication in field at seal pot. Low level alarm and high pressure alarm should be available in LPG control room for monitoring the status of level and high pressure for pump operation, accordingly action should be initiated for running of LPG Pump.
21. For additional safety, in case of any rupture in the discharge line of LPG Transfer Pump, alarm should be received in the control room and LPG pumps should automatically stop running.
22. Water sprinkler arrangement should be always in working condition at the Bullet top exposed domes / structure, Horton LPG Storage vessels and pumps area.
23. Entire storage and handling facility should be covered under fire hydrant and monitor loop. 24. In case of flame detection in pump house and LPG Storage area, action should be initiated
through various interlocks for closing of all ROVs located in LPG mounded vessels outlet line, inlet line, vapour balance line, saturation line and pump minimum flow line. Sequentially, Deluge Valve will open, Marcaptan Dosing Pump will trip and also LPG pumps will trip. Accordingly, fire water sprinkler system will actuate automatically as per logic.
25. Actuation of pressure switch due to quartzoid bulb failure on any of fire detection loop should give audio-visual alarm at the LPG control room, fire station and security gate indicating fire.
26. ROV should be manually auto reset type. All DV’s should be ready for taking next signal immediately after one operation is over, without any further interruption or manual reset. The Deluge valve position (Opened/Closed) should be indicated by proximity sensor.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 104
27. Suitable corrosion protection for internal and external surface of mounded storage vessel should be provided.
28. Cathodic protection should be provided for mounded storage vessels on the external surface.
29. In order to reduce the frequency of failures and consequent risk, codes, rules and standards framed e.g. OISD 144, SMPV rules (Unfired), gas cylinder rules etc. should be strictly followed with respect to construction of new facilities.
30. There should be no depression or low lying areas in the plant in order to avoid accumulation of LPG vapour and consequent hazard.
31. Safety valves located on the storage vessels and other places must be tested regularly. The block valves before safety valve must always be kept in open condition when safety valves are in position. It is desirable to provide a chain and lock to ensure that the block valve is not inadvertently kept closed when safety valve is in position.
32. Vehicular traffic as well as entry of personnel inside the plant area must be restricted. 33. Smoking within the premises should be strictly prohibited. Use of naked light or hot work must be
restricted to the areas designated for the purpose. 34. The sprinkler system including quartzoid bulbs, heat detectors and remote operated valves must be
checked regularly for timely actuation of the safety system. LPG gas detection system should be checked regularly.
35. The DG sets must be periodically tested on load to ensure that it remains always in operating condition.
36. Training of all the employees for fire fighting and use of safety apparatus must be conducted regularly. Mock drills should be conducted at regular intervals keeping liaison with local administration and fire-fighting facilities available in the area.
37. Safety Audits must be regularly done as per norms & recommendations of OISD. 38. Inspection and testing of the major equipments e.g. LPG storage, LPG pumps and compressors etc.
should be done at regular intervals for ensuring their health and condition monitoring. 39. Mutual aid agreement should be done with nearby industries. Also agreement shall be made with
hospitals, fire services, nursing homes for help during emergency. 40. Procurement of materials, construction & erection of the plant should be done as per international
codes & practices. 41. Proper lighting system should be done in the plant so that plant personnel can approach in any part
of the plant during night. 42. Disaster Management plan which has been prepared for the plant should be updated to cover the
proposed refrigerated LPG storage and handling facilities along with proposed mounded vessels.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 105
CHAPTER 8. ENVIRONMENT MANAGEMENT AND MONITORING
PLAN
8.1 Introduction
The Environmental Management Plan (EMP) provides an essential link between predicted impacts and mitigation measures during implementation and operational activities. EMP outlines the mitigation, monitoring and institutional measures to be taken during project implementation and operation to avoid or mitigate adverse environmental impacts, and the actions needed to implement these measures.
The likely impacts on various components of environment due to the project during developmental activities have been identified and measures for their mitigation are suggested.
The EMP lists all the requirements to ensure effective mitigation of every potential biophysical and socio-economic impact identified in the EIA. For each attribute, or operation, which could otherwise give rise to impact, the following information is presented:
A comprehensive listing of the mitigation measures
Parameters that will be monitored to ensure effective implementation of the action
Timing for implementation of the action to ensure that the objectives of mitigation are fully met
The EMP comprises a series of components covering direct mitigation and environmental monitoring, an outline waste management plan and a project site restoration plan. Therefore, environmental management plan has been prepared for each of the above developmental activities.
8.2 EMP during Construction Phase
Environmental pollution during construction stage will be limited and for a temporary period during the construction activity. Construction shall be planned in such a way that excavated material shall be disposed safely. The manpower required for these activities shall preferably be employed from nearby villages so that avenues of employment will be open to local people. Directly or indirectly all the environmental components get affected due to the construction activity. The following environmental protection and enhancement measures are suggested for implementation by the contractor or the authority during the construction as applicable.
8.2.1 Air Environment
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 106
During the construction phase, gaseous emissions are expected from the heavy machineries deployed for construction. All other emission sources are intermittent. Though the gaseous emissions are not expected to contribute significantly to the ambient air quality, some generic measures to reduce fugitive and gaseous pollutants emissions during construction phase from point area and line sources shall include the following:
All equipment used during construction shall have valid PUC certificate.
The storage and handling of soil, sub-soils, top-soils and materials will be carefully managed to minimize the risk of wind-blown material and dust
To avoid generation of air borne dust, water sprinkling shallbe done.
There will be no on-site burning of any waste arising from any construction activities
All vehicles delivering construction materials or removing soil will be covered to prevent escape of dust
Engines and exhaust systems of all vehicle and equipment will be maintained so that exhaust emissions do not exceed statutory limits and that all vehicles and equipment are maintained in accordance with manufactures’ manuals. Periodic monitoring of this shall be undertaken to ensure compliance
Exhausts of other equipment used for construction (e.g. generators) will be positioned at a sufficient height to ensure dispersal of exhaust emissions and meet the standards set by HPPCB.
8.2.2 Noise Environment
The following environmental management measures are recommended to mitigate adverse impacts on noise environment during construction phase:
Earth movers and construction machinery with low noise levels shall be used
Periodic maintenance of construction machinery and transportation vehicles shall be undertaken
Onsite workers shall be provided with noise protection devices such as ear plugs/ muffs wherever necessary
Periodic monitoring for the noise levels within the project site shall be undertaken to ensure compliance per HPPCB set standards
8.2.3 Water Environment
Drinking water requirements during the construction phase by the contractors shall be met from existing borewells on site. Construction labourersshall be provided with adequate quantity of drinking water of potable quality.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 107
Sufficient and appropriate sanitary facilities shall be provided in order to maintain hygienic conditions in the camps of construction labourers. The wastes, such as, sanitary wastes shall be treated in Septic Tank along with Soak Pit. The solid waste generated shall be collected and disposed in an appropriate manner either at a landfill site or used as compost to be used in lawns/gardening purpose.
8.2.4 Land Environment
On completion of construction works all temporary structures, surplus materials and wastes shall be completely removed. Dumping of construction waste on agricultural land will be prohibited and used appropriately.
The solid wastes such as paints, lubricants, oil or any other non-biodegradable wastes that have leachable constituents will be disposed to authorized recyclers.
A waste management plan shall be prepared or integrated with existing plan before the commissioning, implemented and monitored. In areas, where soil quality for natural vegetation is of critical concern, loosening of soil in such areas will be done to mitigate soil compaction caused due to operation of heavy machinery.
8.2.5 Biological Environment
The region does not have dense vegetation and landuse is dominated by agriculture activities. Following environmentalmanagement measures are recommended to mitigate adverse impacts on biological environment during construction phase:
Native species will be preferred for plantation in addition to beautification plants/species.
8.2.6 Socio-economic Environment
Given that the project and related developments like construction camps will not be dependent on local resources (power, water), during both construction and operations, the only likely impact on infrastructure would be on the roads, during the construction phase. Considering the high traffic emanating during construction phase an effective traffic management scheme will be put in place to avoid congestion on the nearby and local roads.Local persons will get employment during Construction phase.
8.2.7 Health and Safety
The movement of heavy equipment will be undertaken with proper precaution to prevent any accidents on the road. Occupational risk shall be minimized at the project site through
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 108
implementation of a full proof safety system. Speed limit set for movement of vehicles with 20 km/hr on village roads to reduce risks of accidents or injuries.
Safety training shall be provided to all construction workers on operation of equipment. Security shall also be extended during non-working hours to ensure there is controlled access to the machinery and equipment.
The contractors shall also be vigilant to detect workers showing symptoms of communicable diseases. Health check up of the contract labors shall be done/ recorded at times. All illness and incidents shall be reported and recorded.
8.3 EMP during Operation Phase
In order to mitigate the impacts due to capacity expansion of facility on various environmental components, the following environmental management measures are recommended:
8.3.1 Air Environment
Leak detection and repair (LDAR) program has been implemented in the facility and shall be extended for the proposed Mounded Storage Bullets system
Ambient air quality with respect to SPM, RPM, SO2, NOx, H2S, CO and HC monitoring shall be continued in the impact zone as per regulations
To minimize occupational exposure/hazards, the present practice of using personal protective equipmente.g. helmets, safety (gas) mask/safety dress, safety harness for working at heights, safety shoes, safety goggles, low temperature hand gloves & shock resistant hand glovesetc. shall be continued for workers engaged in operation of process units within the facility complex
Stacks of adequate height (CPCB norms) for DG Sets to ensure adequate dispersal of pollutants has already been provided
Waste Lube oil will not be incinerated and will be continued to sold to HPPCB authorised waste oil recyclers
All access roads (internal as well as external) to be used by the project authorities have been paved (either with WBM, concrete or bitumen) to suppress the dust generation along the roads
8.3.2 Noise Environment
Similar measures as proposed in the construction phase for noise making machinery, to ensure practicably low noise levels within the work environment.
The major areas of concern for noise generation have already been adequately addressed by considering it during procurement of the machinery from vendors, project implementation stage. Further feedback from the monitored noise levels at sensitive locations will be taken to ensure that the impact due to high noise levels is practically minimized.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 109
Monitoring job and location specific noise levels for compliance with HSE regulations by verifying acceptability of noise levels caused by the project activities and comparison with noise criteria
Conducting periodic audiometric tests for employees working close to high noise levels, such as compressors, DG sets, etc
Provision of PPE’s shall be continued to be done and their proper usage will be ensured for eardrum protection of the workers as well as visitors
Acoustic barriers and silencers shall be used in equipment wherever necessary
Sound proofing/ glass panelinghave been provided at critical operating stations/ control rooms, etc
Monitoring of ambient noise levels shall also be continued to be carried out regularly both inside the facility area as well as outside the peripheral greenbelt
8.3.3 Water Environment
For domestic sewage, Septic Tank along with Soak Pithas been provided.
There are/will be no industrial effluent generated in this plant. However, waste water being generated during plant operations (during washing of empty cylinders) shall be re-circulated/ re-used.
There shall be no increase in quantity of waste water generation from operation of proposed Mounded Bullets.
Rain Water Harvesting: The rain water harvesting program has been implemented in LPG bottling plant. The system has been developed around the admn. Building, Truck Parking area, Cold Repair shed, Empty cylinder shed in the plant. The practice shall be continued and extended further.
8.3.4 Land Environment
Greenbelt in and around the facility will be strengthened/maintained
A record w.r.t quantity, quality and treatment/management of solid/hazardous waste shall be continued to be maintained at environmental monitoring cell
Solid/Hazardous Waste Management
No solid hazardous waste will be generated in the operation of LPG Bottling Plant.
8.3.5 Biological Environment
Development of green belt with carefully selected plant species is of prime importance due to their capacity to reduce noise and air pollution impacts by attenuation/assimilation and for providing food and habitat for local micro fauna.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 110
8.3.6 Socio-economic Environment
In order to mitigate the impacts likely to arise out of the proposed project and also to maintain good will of local people, steps will be taken for improving the social environment. Necessary social welfare measures by the industry shall be undertaken in gaining public confidence and to meet local area development requirement. The following measures are suggested:
IOCL shall continue to undertake social welfare programs for the betterment of the Quality of Life of villages around in collaboration with the local bodies
Some basic amenities, viz. education, safe drinking water supply to the nearby villages may be taken up
Regular medical checkup shall be continued at times in the villages around the facility
Focus shall be on to educate villagers regarding safety measure provided in the plant.
8.4 Environmental Monitoring Programme
Introduction
Environmental Management is nothing but resource management and environmental planning is just the same as development planning. They are just the other side of the same coin. The resource management and development planning look at the issue from narrow micro-economical point of view while environmental management views the issue from the broader prospective of long term sustained development option, which ensures that the environment is not desecrated. For the effective and consistent functioning of the project, proper environmental monitoring programmeshall be continued to be carried out at the LPG Bottling Plant. The programme includes the following:
Environmental Monitoring
Personnel Training
Regular Environmental audits and Correction measures
Documentation–standards operation procedures Environmental Management Plan and other records
Environmental Monitoring
Work of monitoring shall be carried out at the locations to assess the environmental health in the post period. A post study monitoring programme is important as it provides useful information on the following aspects.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 111
It helps to verify the predictions on environmental impacts presented in this study.
It helps to indicate warnings of the development of any alarming environmental situations, and thus, provides opportunities for adopting appropriate control measures in advance.
The monitoring programmes in different areas of environment, outlined in the next few sections, have been based on the findings of the impact assessment studies described in Chapter 4. Post study monitoring programme have been summed up in Table 8.1.
Table 8.1: Post Study Environmental Monitoring Program
Area of Monitoring
Sampling locations
Frequency of Sampling
Parameters to be Analysed
Ambient Air Quality
Station within premises.
Twice in a year PM10, PM2.5,SO2, NOx, HC, VOCs and other parameters as specified by HPPCB consents
Stack monitoring of DG Set
Once in three months
TPM, SO2, NOx and other parameters as specified by HPPCB consents
Water Ground water sample within the Plant
Twice in a year Physical and Chemical parameters
Bacteriological parameters
Heavy metals and toxic constituents
Noise Within Plant shed for bottling operations
Twice a year Sound Pressure Levels (Leq) during Plant operations.
Solid Waste Records of generation of used drums, bags and records of their dispatch to suppliers for refilling
As & when required
--
Environmental Audit Statement
Environmental statement under the EP (Act) 1986
Once in a year --
8.4.1 Ambient Air Quality
Monitoring of ambient air quality at the LPG Bottling Plant site shall be continued to be carried out on a regular basis to ascertain the levels of hydrocarbons in the atmosphere; ambient air quality shall be monitored as per Table 8.1.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 112
8.4.2 Surface Water Quality
Water quality constitutes another important area in the post study monitoring programme. There are no major streams or perennial sources of surface water in the study area. Contamination of surface water in the vicinity of LPG Bottling Plant area during the operation is possible only in one form.
8.4.3 Noise Level
Ambient noise levels have been monitored at 8 stations inside and outside the plant during baseline season for day time and night time.
8.5 Environmental Management Cell
The Locattion-in-charge of the LPG Bottling Plantwith the assistance of operation and maintenance engineers at respective stations presently look after environmental management. Technical officers of the LPG Bottling Plantstation shall regularly carry out the following:
Sampling and analysis of noise and water samples.
Systematic and routine housekeeping at the LPG Bottling Plant
Apart from the regulatory requirements, officials conduct inter station environment auditing to improve the performance. As part of company’s endeavour, the IOCL has been accredited with national and international certification of repute such as ISO: 14001 and ISO: 9002. Under this following aspects are covered.
Following the changes/amendments to central/state legislation pertaining to environment management.
Assessing the level of experience, competence and training to ensure the capability of personnel, especially those carrying out specialized environmental management functions.
Conducting environmental awareness programme for the employees at LPG Bottling Plantsite.
Measurement of pollution emissions and levels at LPG Bottling Plantthrough an external agency approved by HPPCB.
8.6 Budgetary Allocation for Environmental Protection Measures
IOCL has proposed a capital investment of Rs42lacs and a recurring cost of Rs. 10.2 lacs per annum for environmental protection measures. The details of investment for procuring the equipment for efficient control and monitoring of pollution along with annual recurring cost are given in Table 8.3.
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 113
Table 8.3: Cost of Environmental Protection Measures
Sr. No.
Particulars Capital Proposed Cost (Rs. Lacs)
Recurring Proposed Cost (Rs. Lacs)
1 Dust suppression 5 1.7 2 Water quality monitoring &
management 15 2
3 Air quality and noise monitoring
20 6
4 Greenbelt / Plantation 2 0.5 Total 42 10.2
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 114
CHAPTER 9. DISCLOSURE OF CONSULTANTS ENGAGED
9.1 Consultants Engaged
This EIA report is prepared on behalf of the proponents, taking inputs from proponent’s office staff, their R and D wing, Architects, Project Management Professionals etc. by Environmental Consultants M/s. Ultra-Tech Environmental Consultancy and Laboratory, Thane.
M/s Ultra-Tech Environmental Consultancy and Laboratory:
Ultra-Tech Environmental Consultancy and Laboratory [Lab Gazetted by MoEF – Govt. of India] not only give environmental solutions for sustainable development, but make sure that they are economically feasible. With innovative ideas and impact mitigation measures offered, make them distinguished in environmental consulting business. The completion of tasks in record time is the key feature of Ultra-Tech. A team of more than hundred environmental brigadiers consists of engineers, experts, ecologists, hydrologists, geologists, socio-economic experts, solid waste and hazard waste experts apart from environmental media sampling and monitoring experts and management experts , strive hard to serve the clients with up to mark and best services.
Ultra-Tech offers environmental consultancy services to assist its clients to obtain environmental clearance for their large buildings, construction, CRZ, SEZ, high rise buildings, township projects and industries covering sugar and distilleries from respective authorities.
Ultra-Tech also provide STP/ETP/WTP project consultancy on turn-key basis apart from Operation and Maintenance of these projects on annual contract basis. Also, having MoEF approved environmental laboratory, Ultra-Tech provide laboratory services for monitoring and analysis of various environmental media like air, water, waste water, stack, noise and meteorological data to its clients all over India and abroad.
The EIA team involved for the proposed EIA Report is as mentioned in Table 9.1.
Table 9.1: EIA Team
SN Name of the expert Area of functional Expert(NABET Accredited) 1 Mr.Timir Shah EIA Coordinator 2 Mr.Timir Shah Air Pollution 2 Mr.Timir Shah Water Pollution 3 Mr. Santosh Gupta Solid Hazardous Waste 5 Dr. T. K. Ghosh Ecology and Biodiversity 6 Dr. Kishore Wankhede Socio Economic 7 Mr.Ajay Patil Team Member
EIA Report for LPG Bottling Plant Una, Himachal Pradesh 115
Functional area experts and assistance to FAE involved in the EIA study for “M/s.Indian Oil Corporation Ltd.” is as shown in Table 9.2:
Table 9.2: Functional Area Experts Involved in the EIA
S.N. NAME OF SECTOR
NAME OF PROJECT
NAME OF CLIENT
FUNCTIONAL AREA EXPERTS INVOLVED FA NAME/S
1. Schedule 6 (b) Category ‘B’
Proposed augmentation in LPG Bulk Storage capacity at LPG Bottling Plant at Mehatpur, Una, Himachal Pradesh
M/s.Indian Oil Corporation Limited.
AP Mr.Timir Shah
WP Mr.Timir Shah Associate: Mr.Ajay Patil
EB Dr. T. K. Ghosh Associate: Ms.BhartiKhairnar
SE Dr. Kishore Wankhede
SHW Mr. Santosh Gupta Associate: Mr.Timir Shah
LU Mr.SwapnilAvghade Associate: Mr. Prasad Khedkar
RH
Mr.Subhash L. Bonde Associate: Mr.Ajay Patil
9.2 Laboratory for Analysis
NAME OF LABORATORY SCOPE OF SERVICES ACCREDITATION STATUS
ENVIRON-TECH
Monitoring and Analysis of: Ambient Air Monitoring Stack Emission Monitoring Bore Water(Analysis) Domestic and Potable
Water(Analysis) Waste Water(Analysis)
VALIDITY 23.04.2019
ANNEXURE - I
Site Layout
ANNEXURE 2
Ambient Air Quality Results
Site 1
Date PM10
PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
80 40 4 8 ND ND ND ND ND ND ND ND
3 75 42 3 7 ND ND ND ND ND ND ND ND 9 78 44 5 5 ND ND ND ND ND ND ND ND 10 82 45 4 7 ND ND ND ND ND ND ND ND 16 88 48 3 3 ND ND ND ND ND ND ND ND 17 90 38 5 8 ND ND ND ND ND ND ND ND 23 79 35 7 9 ND ND ND ND ND ND ND ND 24 85 39 5 10 ND ND ND ND ND ND ND ND 30 92 31 6 8 ND ND ND ND ND ND ND ND 31 89 35 4 9 ND ND ND ND ND ND ND ND 6 feb 80 34 5 08 ND ND ND ND ND ND ND ND 7 81 30 6 4 ND ND ND ND ND ND ND ND 13 86 34 4 5 ND ND ND ND ND ND ND ND 14 83 38 3 7 ND ND ND ND ND ND ND ND 20 86 35 5 8 ND ND ND ND ND ND ND ND 21 88 37 7 9 ND ND ND ND ND ND ND ND 27 80 34 5 7 ND ND ND ND ND ND ND ND 28 79 42 4 7 ND ND ND ND ND ND ND ND 6 march
87 41 6 8 ND ND ND ND ND ND ND ND
7 80 37 7 9 ND ND ND ND ND ND ND ND 13 86 35 4 8 ND ND ND ND ND ND ND ND 14 81 39 5 7 ND ND ND ND ND ND ND ND 20 88 33 6 8 ND ND ND ND ND ND ND ND 21 92 34 6 9 ND ND ND ND ND ND ND ND 27 95 31 3 5 ND ND ND ND ND ND ND ND 28 90 37 4 5 ND ND ND ND ND ND ND ND
Site 2
Date PM10
PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
80 35 4 7 ND ND ND ND ND ND ND ND
3 85 30 5 7 ND ND ND ND ND ND ND ND 9 79 32 3 5 ND ND ND ND ND ND ND ND 10 83 34 4 6 ND ND ND ND ND ND ND ND 16 85 35 2 5 ND ND ND ND ND ND ND ND 17 88 37 3 5 ND ND ND ND ND ND ND ND 23 92 39 4 8 ND ND ND ND ND ND ND ND 24 90 40 5 7 ND ND ND ND ND ND ND ND 30 88 42 6 8 ND ND ND ND ND ND ND ND 31 80 35 4 6 ND ND ND ND ND ND ND ND 6 feb 87 34 2 5 ND ND ND ND ND ND ND ND 7 89 33 3 8 ND ND ND ND ND ND ND ND 13 80 35 4 7 ND ND ND ND ND ND ND ND 14 85 31 5 8 ND ND ND ND ND ND ND ND 20 89 30 6 9 ND ND ND ND ND ND ND ND 21 83 37 4 8 ND ND ND ND ND ND ND ND 27 87 35 5 7 ND ND ND ND ND ND ND ND 28 89 36 4 8 ND ND ND ND ND ND ND ND 6 march
90 37 5 8 ND ND ND ND ND ND ND ND
7 91 32 3 5 ND ND ND ND ND ND ND ND 13 92 30 2 7 ND ND ND ND ND ND ND ND 14 88 34 5 8 ND ND ND ND ND ND ND ND 20 85 36 6 7 ND ND ND ND ND ND ND ND 21 87 38 4 5 ND ND ND ND ND ND ND ND 27 83 36 3 5 ND ND ND ND ND ND ND ND 28 80 32 4 6 ND ND ND ND ND ND ND ND
Site-3
Date PM10
PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
72 34 2 4 ND ND ND ND ND ND ND ND
3 85 30 3 5 ND ND ND ND ND ND ND ND 9 88 34 4 6 ND ND ND ND ND ND ND ND 10 81 31 5 7 ND ND ND ND ND ND ND ND 16 86 34 6 8 ND ND ND ND ND ND ND ND 17 89 32 5 7 ND ND ND ND ND ND ND ND 23 80 34 7 9 ND ND ND ND ND ND ND ND 24 83 38 5 7 ND ND ND ND ND ND ND ND 30 85 40 4 6 ND ND ND ND ND ND ND ND 31 81 39 3 5 ND ND ND ND ND ND ND ND 6 feb 86 29 5 7 ND ND ND ND ND ND ND ND 7 91 37 4 6 ND ND ND ND ND ND ND ND 13 82 34 3 5 ND ND ND ND ND ND ND ND 14 86 39 5 7 ND ND ND ND ND ND ND ND 20 88 40 4 6 ND ND ND ND ND ND ND ND 21 83 38 2 5 ND ND ND ND ND ND ND ND 27 81 36 3 5 ND ND ND ND ND ND ND ND 28 90 37 5 7 ND ND ND ND ND ND ND ND 6 march
84 31 4 6 ND ND ND ND ND ND ND ND
7 86 35 2 5 ND ND ND ND ND ND ND ND 13 87 36 3 5 ND ND ND ND ND ND ND ND 14 85 37 4 5 ND ND ND ND ND ND ND ND 20 80 35 5 7 ND ND ND ND ND ND ND ND 21 84 33 3 5 ND ND ND ND ND ND ND ND 27 90 36 7 9 ND ND ND ND ND ND ND ND 28 87 31 5 7 ND ND ND ND ND ND ND ND
Site-4
Date PM10
PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
82 40 3 5 ND ND ND ND ND ND ND ND
3 81 38 5 7 ND ND ND ND ND ND ND ND 9 83 37 3 5 ND ND ND ND ND ND ND ND 10 85 35 4 7 ND ND ND ND ND ND ND ND 16 87 36 3 5 ND ND ND ND ND ND ND ND 17 89 30 5 7 ND ND ND ND ND ND ND ND 23 82 37 3 5 ND ND ND ND ND ND ND ND 24 80 35 4 9 ND ND ND ND ND ND ND ND 30 85 38 6 7 ND ND ND ND ND ND ND ND 31 88 40 5 7 ND ND ND ND ND ND ND ND 6 feb 84 30 4 6 ND ND ND ND ND ND ND ND 7 90 35 5 6 ND ND ND ND ND ND ND ND 13 93 36 6 8 ND ND ND ND ND ND ND ND 14 95 38 7 9 ND ND ND ND ND ND ND ND 20 96 39 8 9 ND ND ND ND ND ND ND ND 21 90 40 5 8 ND ND ND ND ND ND ND ND 27 85 42 6 7 ND ND ND ND ND ND ND ND 28 87 44 7 9 ND ND ND ND ND ND ND ND 6 march
80 38 6 9 ND ND ND ND ND ND ND ND
7 86 35 5 8 ND ND ND ND ND ND ND ND 13 84 37 7 10 ND ND ND ND ND ND ND ND 14 80 32 6 8 ND ND ND ND ND ND ND ND 20 79 30 5 7 ND ND ND ND ND ND ND ND 21 72 35 7 9 ND ND ND ND ND ND ND ND 27 79 34 5 8 ND ND ND ND ND ND ND ND 28 82 38 6 9 ND ND ND ND ND ND ND ND
Site-5
Date PM10
PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
82 32 2 5 ND ND ND ND ND ND ND ND
3 84 35 4 6 ND ND ND ND ND ND ND ND 9 86 32 5 7 ND ND ND ND ND ND ND ND 10 80 27 6 8 ND ND ND ND ND ND ND ND 16 87 36 5 7 ND ND ND ND ND ND ND ND 17 86 31 4 8 ND ND ND ND ND ND ND ND 23 82 30 6 7 ND ND ND ND ND ND ND ND 24 80 35 8 9 ND ND ND ND ND ND ND ND 30 84 33 6 8 ND ND ND ND ND ND ND ND 31 86 31 4 6 ND ND ND ND ND ND ND ND 6 feb 87 35 5 7 ND ND ND ND ND ND ND ND 7 82 34 7 9 ND ND ND ND ND ND ND ND 13 86 36 6 7 ND ND ND ND ND ND ND ND 14 83 37 7 9 ND ND ND ND ND ND ND ND 20 80 38 6 7 ND ND ND ND ND ND ND ND 21 84 35 5 8 ND ND ND ND ND ND ND ND 27 83 33 7 9 ND ND ND ND ND ND ND ND 28 81 38 8 10 ND ND ND ND ND ND ND ND 6 march
86 37 7 9 ND ND ND ND ND ND ND ND
7 82 35 6 8 ND ND ND ND ND ND ND ND 13 83 34 7 9 ND ND ND ND ND ND ND ND 14 80 30 6 8 ND ND ND ND ND ND ND ND 20 86 20 7 9 ND ND ND ND ND ND ND ND 21 89 18 5 7 ND ND ND ND ND ND ND ND 27 90 30 4 5 ND ND ND ND ND ND ND ND 28 92 28 5 7 ND ND ND ND ND ND ND ND
Site-6
Date PM10
PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
16 march
80 30 4 7 ND ND ND ND ND ND ND ND
17 83 32 5 5 ND ND ND ND ND ND ND ND 23 85 35 6 7 ND ND ND ND ND ND ND ND 24 87 31 3 7 ND ND ND ND ND ND ND ND 30 86 33 4 6 ND ND ND ND ND ND ND ND 31 march
80 34 5 7 ND ND ND ND ND ND ND ND
6 April
83 36 4 8 ND ND ND ND ND ND ND ND
7 84 37 6 7 ND ND ND ND ND ND ND ND 13 86 39 5 7 ND ND ND ND ND ND ND ND 14 82 34 6 8 ND ND ND ND ND ND ND ND 20 80 35 5 7 ND ND ND ND ND ND ND ND 21 86 36 4 8 ND ND ND ND ND ND ND ND 27 87 38 6 7 ND ND ND ND ND ND ND ND 28 April
86 40 5 8 ND ND ND ND ND ND ND ND
4 May 82 37 4 6 ND ND ND ND ND ND ND ND 5 84 38 6 8 ND ND ND ND ND ND ND ND 11 86 40 5 7 ND ND ND ND ND ND ND ND 12 82 42 4 6 ND ND ND ND ND ND ND ND 18 86 38 6 8 ND ND ND ND ND ND ND ND 19 84 39 5 7 ND ND ND ND ND ND ND ND 25 87 43 4 6 ND ND ND ND ND ND ND ND 26 May
89 42 6 7 ND ND ND ND ND ND ND ND
1 June 81 41 5 7 ND ND ND ND ND ND ND ND 2 84 38 4 8 ND ND ND ND ND ND ND ND 8 86 39 4 6 ND ND ND ND ND ND ND ND 9 June 88 34 6 7 ND ND ND ND ND ND ND ND
Site-7
Date PM10
PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
83 32 2 6 ND ND ND ND ND ND ND ND
3 84 34 3 5 ND ND ND ND ND ND ND ND 9 86 35 4 7 ND ND ND ND ND ND ND ND 10 82 38 4 8 ND ND ND ND ND ND ND ND 16 78 34 6 7 ND ND ND ND ND ND ND ND 17 83 38 4 8 ND ND ND ND ND ND ND ND 23 84 35 3 6 ND ND ND ND ND ND ND ND 24 86 37 4 8 ND ND ND ND ND ND ND ND 30 82 40 5 6 ND ND ND ND ND ND ND ND 31 78 39 6 8 ND ND ND ND ND ND ND ND 6 feb 92 42 4 6 ND ND ND ND ND ND ND ND 7 84 40 5 7 ND ND ND ND ND ND ND ND 13 86 38 6 8 ND ND ND ND ND ND ND ND 14 82 39 4 6 ND ND ND ND ND ND ND ND 20 84 37 5 7 ND ND ND ND ND ND ND ND 21 86 38 6 8 ND ND ND ND ND ND ND ND 27 88 35 4 6 ND ND ND ND ND ND ND ND 28 81 37 5 7 ND ND ND ND ND ND ND ND 6 march
83 34 4 5 ND ND ND ND ND ND ND ND
7 80 35 5 7 ND ND ND ND ND ND ND ND 13 81 37 4 8 ND ND ND ND ND ND ND ND 14 78 38 5 7 ND ND ND ND ND ND ND ND 20 72 36 7 7 ND ND ND ND ND ND ND ND 21 78 34 6 8 ND ND ND ND ND ND ND ND 27 75 38 5 7 ND ND ND ND ND ND ND ND 28 80 39 4 8 ND ND ND ND ND ND ND ND
Site-8
Date PM10
PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
80 34 3 5 ND ND ND ND ND ND ND ND
3 82 36 4 7 ND ND ND ND ND ND ND ND 9 84 38 3 8 ND ND ND ND ND ND ND ND 10 86 39 4 8 ND ND ND ND ND ND ND ND 16 87 32 5 8 ND ND ND ND ND ND ND ND 17 88 37 4 7 ND ND ND ND ND ND ND ND 23 82 38 3 5 ND ND ND ND ND ND ND ND 24 89 32 5 6 ND ND ND ND ND ND ND ND 30 92 38 4 78 ND ND ND ND ND ND ND ND 31 81 37 3 5 ND ND ND ND ND ND ND ND 6 feb 83 38 5 8 ND ND ND ND ND ND ND ND 7 84 39 4 6 ND ND ND ND ND ND ND ND 13 86 35 3 5 ND ND ND ND ND ND ND ND 14 87 37 4 7 ND ND ND ND ND ND ND ND 20 90 35 3 5 ND ND ND ND ND ND ND ND 21 91 30 4 7 ND ND ND ND ND ND ND ND 27 87 37 5 7 ND ND ND ND ND ND ND ND 28 86 37 4 6 ND ND ND ND ND ND ND ND 6 march
81 34 3 5 ND ND ND ND ND ND ND ND
7 85 38 4 6 ND ND ND ND ND ND ND ND 13 89 34 5 7 ND ND ND ND ND ND ND ND 14 81 34 4 8 ND ND ND ND ND ND ND ND 20 83 36 3 7 ND ND ND ND ND ND ND ND 21 84 37 5 6 ND ND ND ND ND ND ND ND 27 86 38 4 5 ND ND ND ND ND ND ND ND 28 87 39 5 7 ND ND ND ND ND ND ND ND
Site-9
Date PM10 PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
84 35 4 6 ND ND ND ND ND ND ND ND
3 86 37 5 7 ND ND ND ND ND ND ND ND 9 80 35 4 6 ND ND ND ND ND ND ND ND 10 81 38 6 8 ND ND ND ND ND ND ND ND 16 83 39 5 6 ND ND ND ND ND ND ND ND 17 80 40 4 6 ND ND ND ND ND ND ND ND 23 83 42 6 8 ND ND ND ND ND ND ND ND 24 87 37 5 8 ND ND ND ND ND ND ND ND 30 89 39 4 6 ND ND ND ND ND ND ND ND 31 92 41 4 9 ND ND ND ND ND ND ND ND 6 feb 90 43 5 10 ND ND ND ND ND ND ND ND 7 83 40 3 5 ND ND ND ND ND ND ND ND 13 88 34 4 6 ND ND ND ND ND ND ND ND 14 82 38 5 8 ND ND ND ND ND ND ND ND 20 87 40 4 7 ND ND ND ND ND ND ND ND 21 83 38 3 6 ND ND ND ND ND ND ND ND 27 88 39 4 8 ND ND ND ND ND ND ND ND 28 87 35 5 8 ND ND ND ND ND ND ND ND 6 march
86 34 3 7 ND ND ND ND ND ND ND ND
7 84 30 4 7 ND ND ND ND ND ND ND ND 13 83 34 5 8 ND ND ND ND ND ND ND ND 14 80 35 4 6 ND ND ND ND ND ND ND ND 20 83 36 3 7 ND ND ND ND ND ND ND ND 21 84 37 5 8 ND ND ND ND ND ND ND ND 27 86 38 4 7 ND ND ND ND ND ND ND ND 28 89 40 3 5 ND ND ND ND ND ND ND ND
Site-10
Date PM10 PM2.5
SO2
NO2
NH3
O3 CO Arsenic
Lead Banzene Benzo(a) pyrene
Nickel
2 January
83 35 3 5 ND ND ND ND ND ND ND ND
3 85 71 4 6 ND ND ND ND ND ND ND ND 9 88 38 5 7 ND ND ND ND ND ND ND ND 10 87 36 3 8 ND ND ND ND ND ND ND ND 16 89 37 4 7 ND ND ND ND ND ND ND ND 17 80 38 6 8 ND ND ND ND ND ND ND ND 23 90 35 5 6 ND ND ND ND ND ND ND ND 24 86 36 7 9 ND ND ND ND ND ND ND ND 30 88 39 6 8 ND ND ND ND ND ND ND ND 31 90 40 5 7 ND ND ND ND ND ND ND ND 6 feb 84 38 4 5 ND ND ND ND ND ND ND ND 7 86 32 6 7 ND ND ND ND ND ND ND ND 13 89 38 5 7 ND ND ND ND ND ND ND ND 14 81 40 4 6 ND ND ND ND ND ND ND ND 20 85 37 5 7 ND ND ND ND ND ND ND ND 21 83 38 4 6 ND ND ND ND ND ND ND ND 27 80 32 6 8 ND ND ND ND ND ND ND ND 28 83 38 4 6 ND ND ND ND ND ND ND ND 6 march
81 37 3 5 ND ND ND ND ND ND ND ND
7 83 39 6 8 ND ND ND ND ND ND ND ND 13 88 40 4 6 ND ND ND ND ND ND ND ND 14 87 41 5 7 ND ND ND ND ND ND ND ND 20 90 43 4 6 ND ND ND ND ND ND ND ND 21 80 35 6 8 ND ND ND ND ND ND ND ND 27 91 43 5 6 ND ND ND ND ND ND ND ND 28 92 37 4 6 ND ND ND ND ND ND ND ND