environmental audit of santacruz - borivali...

67
E507 Volume 5 ENVIRONMENTAL AUDIT OF SANTACRUZ - BORIVALI 5 TH RAILWAY LINE PROJECT (Submitted to Mumbal Metropolitan Region Development Authorit, Govt. of Maharashtra) a-- Serene Environmenl Svics 509, 'Devavrata', Plot No. 63, Sector 17, Vashl, Nav Mumbal 400705 Telebx - 7896926 E Mail: sereneffvsni.com Web sie: www.serenenviro.com JUNE 2002 FlI r efiv Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: lexuyen

Post on 05-Jun-2018

233 views

Category:

Documents


4 download

TRANSCRIPT

E507Volume 5

ENVIRONMENTAL AUDIT OF SANTACRUZ - BORIVALI5TH RAILWAY LINE PROJECT

(Submitted to Mumbal Metropolitan Region DevelopmentAuthorit, Govt. of Maharashtra)

a--

Serene Environmenl Svics509, 'Devavrata', Plot No. 63,

Sector 17, Vashl, Nav Mumbal 400705Telebx - 7896926

E Mail: sereneffvsni.comWeb sie: www.serenenviro.com

JUNE 2002

FlI r efiv

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Environmental-Audit of Santacruz- Bonvali Serene Environmental Services5Eh Railway line

TABLE OF CONTENTS

Sr. No. Description Page NumberExecutive Summary

1.0 Introduction 11.1 Background 11.2 Statement Of Purpose 1

2.0 Project Details 22.1 Project Need And Details 22.2 Project Components and Status 2

3.0 Scope And Methodology 43.1 Scope and Methodology 43.2 Legal Requirements 5

4.0 Baseline Environmental Status And Impacts 84.1 Terrain and Geology 84.2 Climate 84.3 Ambient Air Quality 84.4 Noise Levels 94.5 Ground and Surface Water Quality 94.6 Natural Habitats and Ecology 104.7 Landuse 104.8 Resettlement and Rehabiliation 104.9 Archaeological and Cultural Property 11

5.0 Assessment of Environmental Mitigation Measures 145.1 Introduction 145.2 EHS Mitigation Measures 14

6.0 Environmental Monitoring And Reporting 216.1 Environmental Monitoring Program 216.2 Institutional Setup 25

6.2.1 institutional strengthening 26

6.3 Estimated Cost of EMP Implementation 27

Environmental Audit of Santacruz- Bonvaii Serene Environmental Services5h Railway line

LIST OF TABLES

Table Description PageNumber Number

1.1 Project Components 31.2 Project Implementation Status 32.0 Detailed Scope and Methodology 43.0 Day time Noise Monitoring Results 94.0 Impact Matrix 125.1 EHS Mitigation Measures (Pre-Construction / Design Stage) 155.2 . EHS Mitigation Measures (Construction Stage) 165.3 EHS Mitigation Measures (Operation Stage) 196.0 Monitoring Program during Operation Phase 247.0 Training Program for Institutional Strengthening 26

LIST OF FIGURES

Figure Description Page NumberNumber

1.0 Existing Organization Framework For Western Railway 25

LIST OF ANNEXURES

Annex DescriptionNumberl.A Terms of Reference for carrying out Environmental Audit of Railway Projects11.B Legal Requirements2. Site Photographs3. Public Consultation Details4. Environment/ Health/ Safety Inspection Sheet5. Documentation to be maintained by contractor or railway site engineer on site6. Format for survival reporting for tree plantation

Environmental Audit of Santacruz -Bonivali Serene Environmental Services5Eh Railway line.

LIST OF ABBREVIATIONS

AAQ: Ambient Air Quality

CPCB: Central Pollution Control Board

CEMP: Community Environment Management Plans

EA: Environmental Assessment

EMP: Environmental Management Plan

EHS Environment, Health and Safety

FOB: Foot over-bridges

GOM: Government of Maharashtra

MMR: Mumbai Metropolitan Region

MOEF: Ministry of Environment and Forests

MGGM: Municipal Corporation of Greater Mumbai

MMRDA: Mumbai Metropolitan Regional Development Authority

MLEA: Micro-Level Environmental Assessment

MRVC: Mumbai Rail Vikas Corporation

MSEB: Maharashtra State Electricity Board

MUTP: Mumbai Urban Transport Project

PIA: Project Implementation Agency

PUC Pollution Under Control

RAP: Rehabilitation Action Plan

ROW: Right of Way

R&R Resettlement and Rehabilitation

SES: Serene Environmental Services

WR: Westem Railway

Environmental Audit of Santacruz- Bonval: Serene Environmental ServiceS'51h Railway line Project

EXECUTIVE SUMMARY

1.0 INTRODUCTIONThe Mumbai Urban Transport Project (MUTP) has identified a number of sub-projects tostrengthen the suburban rail transport and road transport in Greater Mumbai and MumbaiMetropolitan Region (MMR) as a whole. MUTP places considerable emphasis on improvingpublic transport including the railway capacity.

As per requirement of The World Bank, Environmental Assessments (EA) was done for someof these sub-projects in the years 1996 to 1998. Also, a consolidated EA was prepared forthe entire MUTP project. Environmental Management Plans (EMP) was prepared as a partof these EAs, which included mitigation measures for minimising adverse environmentalimpacts. Currently, several of these sub-projects are in different stages of construction andMMRDA desires to carry out an assessment of the relevant EMPs.

This assignment pertains to the EMP assessment/audit for the 5 th line construction betweenSantacruz and Borivali stations on Westem Railway (WR). This project is being implementedby the Western Railway (WR).

Mumbai Metropolitan Region Development Authority (MMRDA) has retained the services ofSerene Environmental Services (SES) to carry out Environmental Audit for railway projects ofMUTP.

2.0 OBJECTIVES OF THE STUDYThe objectives of the Environmental Audit are as follows:

o Assess the status of environmental impacts during ongoing construction and futureplanned activities.

0 Assess whether any environmental mitigation measures are required based on on-goingcompleted works, if any. i

o Environmental mitigation measures for planned works, if required.O Document lessons that can be useful for future projects.O Mitigate environmental impacts on the marine water quality, water flow due to

construction of bridges and other possible impacts as identified in the MLEA report bfBorivali - Virar Quadrupling Project prepared by Montgomery Watson Consultants,Mumbai.

3.0 PROJECT COMPONENTSThe Santacruz - Borivali 5 th railway line is necessary to improve the reliability of Suburbantrains, which are working beyond saturation level of line capacity. The scope of projectincludes construction of 5 th railway line between Santacruz to Borivali covering about 15 kms.Four additional 9-car rakes or 12-car rakes service could be introduced on this line toenhance the capacity of suburban section of Western Railway.

The broad components of the project can be grouped under the following heads:. Earthwork for laying of rail tracks between stations

Environmental Audit of Santacruz- Bonvali Serene Environmental Services;5"h Railway line Project

* Construction of additional infrastructure at various stations such as New Plafforms andextension of existing platforms, Station building and Booking office, Foot over-bridges(FOB), Extension of level crossings, etc.

* Construction of major and minor bridges at various locations* Construction of miscellaneous structures such as drainage, boundary walls etc.The implementation status of the project is given below:

No. Section Current Status1. Santacruz to Andheri Project Completed and Operating2. Andheri to Goregaon Work completed - Ready for Operation

3. Goregaon to Borivali Only track-linking work is remaining

3.1 Applicable Legal Requirements

The applicable Indian environmental regulations, World Bank policies/directives and GOMdirectives for all MUTP projects are given in detail in Annex lB. This EMP's for the

Santacruz-Borivali project have been prepared within the framework of the ConsolidatedEnvironmental Assessment (CEA), Report for MUTP, 2002. The legal requirementsapplicable to the Santacruz-Borivali project are as follows:

Indian Environmental and Other Requlationso Environmental (Protection) Act, 1986, associated Rules and Notifications under the Act.0 The Maharashtra (Urban Areas) Preservation of Trees Act, 1975g Land Acquisition Act 1894 (LA Act):0 Maharashtra Regional and Town Planning Act, 1966 (MR&TP Act):D Development Control Regulations for Greater Mumbai 1991 (DCRs):

World Bank Policieso Environmental Assessment (OP 4.01)O Involuntary Resettlerpent (OD 4.30)

4.0 BASELINE ENVIRONMENTAL STATUS and IMPACTS

For this project Environmental Assessment has not been carried out earlier and baselineenvironmental data is not available. As discussed earlier, construction work for the project isfully complete. Thus, impacts during construction phase of the project cannot be assessed.However, residual impacts, if any, due to completed activities and ongoing activities havebeen evaluated and are presented below. A summary of Impacts is presented in Table A.

4.1 Ambient Air Quality

Current AAO Monitorin' DataBaseline data for the project site is not available. AAQ is being monitored by MunicipalCorporation of Greater Mumbai (MCGM) at several locations in Mumbai. Monitoring is doneas per the methodology prescribed by Ministry of Environment and forests (MOEF), NewDelhi. One of the locations where monitoring is conducted regularly is near the Khar railwaystation. Although this station does not lie between Santacruz and Borivali, it is on the sameline and located adjacent to Santacruz to the south. This location is considered as anexample of area near the railway stations, having high density of vehicular traffic includingauto-rickshaws, buses, private vehides etc. The annual average values for the year 2000 for

ii

Environmental Audit of Santacruz- Borivali Serene Environmental Services5h Railway line Project

SO2 , NOx and SPM reported at,Khar was 16.16 ILg/m 3, 69.25 jig/M3 and 290 tW/M3 . These

values may not represent the MQ levels at other stations, but may be taken as an example.The values for NOx and SPM exceed the MO annual average standards for residential areas.These MQ annual average MQ standards for residential areas are as follows: S02 (60jig/m3); NOx (60 .g/m3); SPM (140 gg/m3).

AAQ near commercial and residential areas near railway stations, typically have elevatedAAQ levels due to sluggish traffic and highly built-up area with poor dispersion conditions.However, areas between stations have much lower values.

Impacts During Construction PhaseConstruction work is completed. Thus impacts on air quality due to construction activitycannot be assessed.Impacts During Operation PhaseDuring the operation stage, there will be no impact on air quality, as electric trains will beoperated on the proposed track.

4.2 Noise Impacts

Baseline data for the project site is not available. However, spot monitoring of noise wasdone near the 5 th line between Santacruz and Andheri to assess noise impacts.Durinq Construction PhaseConstruction work is completed. Thus impacts on noise levels due to construction activitycannot be assessed.Durinq Operation PhaseExisting baseline noise levels in this area exceeds the CPCB noise standards for residentialarea. This is typically found near the railway stations, where residential areas are locatedquite close (30 to 50 m) to railway tracks.

Boundary wall have been constructed along the railway land, however this is not expected tohave much potential for noise attenuation, as residential building are located very close to thetracks and are 3 to 4 storey high. Providing a barTier all along the track to this height may notbe feasible. Source reduction techniques by providing better track/wheel interface and trackmodification may be more appropriate for noise reduction.

4.3 Ground and Surface Water Quality

Construction work is completed. Thus impacts on any water body, due to construction activitycannot be assessed. However, there are no water bodies of any significance (lakes, rivers,creek etc.) present in the Santacruz-Borivali rail corridor. In fact most of the area is denseBuilt-up area. Thus there would not have been any adverse environmental impact on waterbodies.

Impacts During Operation PhaseThe operation of the project is not likely to have a significant impact on water bodies due tothe following reasons:

Wastewater generated at platforms and the new railway quarters will be treated inseptic tank and discharged via soak pits or discharged into existing seweragenetwork.

Environmental Audit of Santacruz- Borivali Serene Environmental Servicesth Railway line Project

* Drains are constructed at locations near stations likely to be flooded duringmonsoons.

* There is no other activity which generates effluent and which can adversely affectany water body.

4.4 Natural Habitats and EcologyManagement and conservation of natural habitats likely to be affected by the SantacruzBorivali project is required by The World Bank Operational Policy OP 4.04. There are nonatural habitats along this route such as forests, mangroves, which require protection.

ImPacts Durina Construction PhasePermission for felling of these trees were obtained from the Tree Officer of MCGM. Area fortree plantation is limited due to dense built-up area on this route (See Photo 1- in Annex 2).However, WR is carrying out track-side and other plantation for enhancement of the areawherever feasible. This activity is proactive and plantation targets are normally set for variousWR managers.

Impacts During Oneration PhaseImpacts on ecology is not expected during the operation stage as the project is coming upalongside the existing tracks and there is-no forest and other sensitive ecological reservesnear the tracks that can be affected due to operation of additional rakes.

4.5 LanduseThis rail corridor is large built-up area with no significant ecological resources, water bodiesetc. There are mixed use and residential areas immediately adjacent to the corridorboundary. At Malad and Goregaon few patches of vacant land are seen in between stations.

The land-use pattern has not change significantly due to the implementation of the project asit has come up alongside the existing tracks.

4.6 Resettlement and RehabilitationThere are 515 project-affected households (PAHs) which need resettlement. Resettlementand rehabilitation of the project-affected households is being done by MMRDA as per theRehabilitation Action Plan (RAP) of Govt. of Maharashtra. Site specific CommunityEnvironment Management Plans (CEMP) are being prepared separately by MMRDA fortransit and permanent locations.

4.7 Archaeological and Cultural PropertyRehabilitation of Cultural Property such as archaeological and historical sites, religious(temples, mosques etc.) affected by project activities is required by The World BankQperational Policy 4 11 on Cultural Property Preservation.

As per survey conducted by MMRDA, there were no such structures present on this route.

A summary of the impacts during construction and operation phases of the project in given inTable A

iv

Environmental Audlt of Santacruz- Borivalh Serene Environmental Services5Zh Railway line Project

Table A Impact Matrix

No. Parameter Impacts During Construction phase Impacts During operation phase

1. Air Quality Construction work is completed. Thus impacts on air No negative impacts durng operation phase.quality due to construction activity cannot be assessed.

2. Noise Construction work is completed. Thus impacts on noise Existing baseline noise levels in this area exceeds the CPCBlevels due to construction activity cannot be assessed. noise standards for residential area. This is typically found

near the railway tracks where residential areas are locatedquite close (30 to 50 m) to railway tracks.

Boundary wall have been constructed along the railway land,however this is not expected to have much potential fornoise attenuation, as residential building are located veryclose to the tracks and are 3 to 4 storey high. Providing abarrier all along the track to this height may not be feasible.Source reduction techniques by providing better track/wheelinterface and track modification may be more appropriate fornoise reduction.

Environmental Audit of Santacruz- Bonvali Serene Environmental Servicese" Railway line Project

Table A Cont..

No. Parameter Impacts During Construction phase Impacts During operation phase

3 Water Quality No water bodies of any significance such as lakes, rivers, No significant adverse impacts as effluent fromcreek etc. present in the Santacruz-Borivali rail corridor. platforms will be treated in septic tanks andNo adverse environmental impact on any water body. discharged via soak pits/ or into existing sewers.

No other source of effluent during operation.4. Natural Permission for felling of trees had been obtained from the No adverse impacts on ecology during operation

Habitats and Tree Officer. Area for tree plantation is limited due to phase. No forest and other sensitive ecologicalEcology dense built-up area on this route (See Photo 1 in Annex reserves located in the rail corridor.

2). However, WR is carrying out track-side and otherplantation for enhancement of the area wherever feasible.(Photo 3 in Annex 2 shows plantation and fencing atAndheri station)

5. Landuse The land-use pattern has not change significantly due to No adverse impacts expected.the implementation of the project as it has come upalongside the existing tracks.

There are 515 project-affected households (PAHs) whichneed resettlement. Resettlement and rehabilitation of thePAH done by MMRDA as per the Rehabilitation ActionPlan (RAP) of Govt. of Maharashtra.

6. Archaeological As per survey conducted by MMRDA, there were no such No adverse impacts expected.and Cultural structures present on this route. More details are given inProperty. the Rehabilitation Action Plan (RAP) for MUTP and

Rehabilitation Implementation Plan (RIP) for the Project.

"I

Environmental Audit of Santacruz- Bonvali Serene Environmental Servicesdh Railway line Project

5.0 Assessment of Environmental Mitigation Measures

The entire construction work for the project is complete and thus EHS measures cannot beaudited/assessed for the construction phase. Also, as seen from the previous section, sitevisits have not revealed any significant adverse environmental impact caused due the alreadycompleted activity.

Thus, as far as this project is concerned, recommendations for EMP implementationinclude the following:• EHS mitigation measures that could be included as a requirement for contractors

for future works in this area.* EMP monitoring and reporting during operational stage.* Institutional mechanism for EMP implementation

The EHS issues are addressed for the components given below

* Ecological impacts such as tree cutting and destruction of mangroves.* Resettlement and rehabilitation* Utility relocation* Generation of Dust due to construction activity* Construction Vehicle /equipment exhaust emissions* Noise from vehicles, plants and equipment*. Contamination of water bodies* Ecological impacts such as tree cutting and destruction of mangroves* Soil erosion* Debris disposal* Soil contamination by construction wastes, fuel etc.* Land degradation in quarry area.* Health and hygierqe at construction labour camps* Delays and congestion on tracks* Traffic Control and Safety* Occupational Health and Safety

Critical EHS recommendations for the project are given below, more details on audit findings andrecommendations are available in Tables 5.1 to 5.3 of this reporL

Pre-construction and desiqn stage:

1. Resettlement is currently being carried out by MMRDA as per RAP of GOM. SeparateTransit and permanent accommodations for project affected households should be audited atleast 6 monthly.

2. All necessary permissions to be taken for cutting trees/vegetation3. Along with design of noise barriers, technology with low noise should be incorporated.

vii

Environmental Audit of Sentacruz- Bonvali Serene Environmental Seivicesdh Railway line Project

Construction Phase

1. Road wetting for earth-working operations to be done regularly for dust suppression..2. All contractors to make sure that all dumpers and other vehicles being used at site have been

checked for vehicle emissions and have a valid PUC certificate.3. A clear documented procedure to be made part of the tender documents for future projects,

requirng contractors to dispose debris in low-lying areas away from water bodies, as fillmaterial only.

4. Documentation such as quarry release receipt issued by the District Revenue officer at thequarry site to be available at construction site.

5. Safety and hazard posters and signs should be clearly displayed at locations such as plafformworks, level crossings, Station building construction areas etc.

6. W.R. to assure that procedure for work permit is followed at all construction sites.7. WR to assure that all contractors make available safety shoes, face masks, earplugs etc. as

applicable to the labourers. Such PPE's should be available on site and assessment shouldbe made during scheduled inspections.

WR to make sure that all above requirements (given in more detail in EMP tables 5.1 to 5.3)should be made part of tender documents for future projects.

ODeration Phase1. Regular maintenance of track side plantation.2. Noise monitoring on Santacruz-Borvali route as given in Table 6.

6.0 Environmental Monitoring and Reporting

Ste visits and interviews have revealed the following facts related to environmentalmanagement organisation:

. In the consolidated EA report for MUTP, MRVC was reported to be the ProjectImplementation Agency (PIA). However, Westem Railway '/VR) is the PIA for thisproject. MRVC is the coordinating agency to facilitate communication between MMRDAand WR.

o WR has not been involved in any of the earlier EA efforts. Environmental mitigationmeasures identified in the earlier EA for this project and also identified in the consolidatedEA are not available with WR. However, WR has incorporated certain EHS elements inthe tender documents.

o Environmental monitoring is currently not required to be done by the contractors. Apartfrom periodic safety inspections, currently there is no feedback mechanism for EHSelements of the project.

The construction phase is completed and site observations have not revealed any significantresidual impacts on the site due to construction phase. Major significant impacts would bethe displacement of project affected people and cutting of vegetation along the ROW. Themonitoring of R&R components is being covered separately as a part of another study andpermissions have been taken earlier for cufting of vegetation

viii

Environmental Audit of Santacnuz- Borivali Serene Environmental Servicesh Railway line Project

Comprehensive periodic site inspection programs for EHS elements and a regularenvironmental monitorng program will best achieve the objectives of monitoring describedabove for this project.

The recommended EMP monitoring and reporting mechanism, inspection schedule - format -responsibilities, current institutional mechanism, training requirements etc. are given in detailin Section 6.1 of this report. The cost for EMP for Santacruz-Borvali line is estimated at Rs.1346000 (See Table 8).

ix

Environmental Audit of Santacruz- Borivali Serene Environmental Servicesdh Railway line Project

1.0 INTRODUCTION

1.1 Background

The Mumbai Urban Transport Project (MUTP) has identified a number of sub-projects tostrengthen the suburban rail transport and road transport in Greater Mumbai and MumbaiMetropolitan Region (MMR) as a whole. MUTP places considerable emphasis on improvingpublic transport including the railway capacity.

As per requirement of The World Bank, Environmental Assessments (EA) was done for someof these sub-projects in the years 1996 to 1998. Also, a consolidated EA was prepared forthe entire MUTP project. Environmental Management Plans (EMP) was prepared as a partof these EAs, which included mitigation measures for minimising adverse environmentalimpacts. Currently, several of these sub-projects are in different stages of construction andMMRDA desires to carry out an assessment of the relevant EMPs.

This assignment pertains to the EMP assessment/audit for the 5th line construction betweenSantacruz and Borivali stations on Western Railway (WR). This project is being implementedby the Western Railway (WR).

1.2 Statement of purpose

Mumbai Metropolitan Region Development Authority (MMRDA) has retained the services ofSerene Environmental Services (SES) to carry out Environmental Audit for railway projectsof MUTP. The scope of work is as per TOR given in the RFP no. PD/MUTP/EA/701/2001dated October 16, 2001 (Annex 1). The work was awarded to SES on November 7, 2001,after final negotiations on November 6, 2001.

Objectives of the study:

*' Assess the status of environmental impacts during ongoing construction and futureplanned activities.

0 Assess whether any environmental mitigation measures are required based on on-goingcompleted works, if any.

l' Environmental mitigation measures for planned works, if required.0- Document lessons that can be useful for future projects.*' Mitigate environmental impacts on the marine water quality, water flow due to

construction of bridges and other possible impacts as identified in the MLEA report ofBorivali - Virar Rail Quadrupling Project (BVQR), prepared by Montgomerry WatsonConsultants, Mumbai, 1998.

Environmental Audit of Santacruz- Borivah Serene Environmental Services5e Railway line Project

2.0 PROJECT DETAILS

2.1 Project Need and Details

The Santacruz - Borvali 5th railway line is necessary to improve the reliability of Suburbantrains, which are working beyond saturation level of line capacity. The scope of projectincludes construction of 5th railway line between Santacruz to Borivali covering about 15 kms.Four additional 9-car rakes or 12-car rakes service could be introduced on this line toenhance the capacity of suburban section of Western Railway.

Benefits of the 5th line between Santacruz - Borivali:

1. Segregation of suburban and non-suburban traffic between Santacruz and Borivali, thusreleasing capacity on through lines to allow more suburban trains and create new routefor passenger trains to new passenger terminus at Bandra.

2. Provision of 5th line will provide additional three suburban 12-car rake paths from Borvalito Churchgate.

2.2 Project Components and Status

The broad components of the project can be grouped under the following heads:

* Earthwork for laying of rail tracks between stations* Construction of additional infrastructure at various stations such as New Platforms and

extension of existing platforms, Station building and Booking office, F?ot over-bridges(FOB), Extension of level crossings, etc.

* Construction of major and minor bridges at various locations* Construction of miscellaneous structures such as drainage, boundary walls etc.

The broad project components and implementation status of the same are given below inTable 1.1 and 1.2 respectively. Santacruz to Andheri line has started operating and track-linking work is in progress in case of Goregaon to Borvali railway line. Photo I (Annex 2)shows the completed 5th line with boundary wall. Photo 2 shows a view of a minor bridge(subway extension).

2

Environmental Audit of Santacruz- Borivali Serene Environmental Serviceseh Railway line Project

Table 1.1 Project ComponentsNo. Description Unit Scope1. Land Acquisition Sq.m. 968

2. Earth Work Cum 1500003. Major Bridge (12 to 18 m) Nos. 44. Minor Bridge (< 12m) Nos. 235. Level Crossing extensions Nos. 66. F.O.B extensions Nos. 87. Quarters to be dismantled Nos. 1058. Quarters to be constructed Nos. 1059. Hoarding Nos. 7210. Ballast Cum 5500011. Booking office at Kandivali, Nos. 1

Plaffomm shed at Vileparle andMalad.

12. New Plafform at Andheri Nos. 113. Construction of Boundary wall, Boundary wall near residential areas,

drains, fencing etc. at different encroachment areas. Drainagestations provided at stations and areas prone to

flooding.

Table 1.2 Project Implementation StatusNo. Section Current Status

1. Santacruz to Andheri Work Completed - Ready for Operation2. Andheri to Goregaon Work completed - Ready for Operation

3. Goregaon to Borivali Only track-linking work is remaining

3

Environmentl Audit of Santacruz- Bonvali Serene Environmental Services5 h Railway line Project

3.1 SCOPE AND METHODOLOGY

As described earlier the construction of project is completed. An assessment of AltemativeSites for the Santacruz - Borvali project was not carred out since the lines will be coming upadjacent to the existing lines with a view to enhancing the capacity of these lines. Publicconsultation have also been conducted for MUTP and its various components. The details ofwhich are given in Annex 3.

The various tasks and methodology followed for completing these objectives are given belowin Table 2.0. Methodology followed is as per the Inception Report of the project.

Table 2.0 Detailed Scope and MethodologyScope MethodologyTask IReview of previous reports such as These reports were reviewed for understanding the projectengineering design, MUTP background.consolidated EA report etc.Task 2Determination of significant impacts on Site visits along ROW of the proposed tracks and facilitiesthe air, noise and ecological such as stations etc.environment that have occurred due to Ambient Air Qualitycurrent construction works and future Ambient air quality impacts during construction stages ofplanned activities. the project cannot be assessed, as the construction work is

over and tracks are largely operational. Residual impactsthat could have been caused due to construction /modification of infrastructure such as plafforms etc. wereassessed during site visits. Ambient air monitoring is notenvisaged for the project.Noise ImpactsSpot monitoring of Noise levels at the following locationwil Ibe done:* Near 5 line between Santacruz to Andheri - This line

is operational and noise levels due to operation of thisline were measured.

Water QualityConstruction of the project is complete and no impact onsurface or ground water quality expected. No watermonitoring envisagedImpacts on water quality due to planned construction ofplatforms, sanitary facilities etc will be assessed. No watermonitoring envisaged.Soil QualityAll earthwork and construction of bridges etc are completeSoil analysis is not envisaged.

4

Environmental Audit of Santacnrz- Borivali Serene Environmental Services5e Railway line Project.

Table 2.0 ContScope Methodology

Ecological ImpactsArea alongside the tracks is largely built-up and noecological resources of any significance are present in thiscorridor. However, stock is taken of the number of treescut in the ROW and track- side plantation efforts.

TASK 3 Construction work is fully complete for this project. Thus* Preparation of EMPs for adverse implementation status of EMPs during construction stage

environmental impacts identified cannot be assessed. However, it can be safely said thatfor the completed and planned measures implemented durng the construction stage wasworks. Preparation of EMP matrix, similar to those currently being implemented at the Borivali-specific EMPs, responsibilities and Virar Rail Quadrupling project. Both these projects areauthorities for implementation and being implemented by Westem Railways.the cost implications for the EMP * To assess any residual impacts that may have beenimplementation. caused during construction, site visits were conducted

* Assess the adequacy of current along tracks and at Andheri Station.institutional arrangements and * Organization structure and chain of command betweensuggest measures for contractors, Railway and MRVC was reviewed.strengthening the same if required. * A representative EMP matrix consisting of measures

* Suggest improvements in that should be incorporated in the tender documents forimplementation of mitigation any future projects are included.measures in future activities. * Environmental Monitoring protocols are defined for

operation stage.* EMP implementation framework, reporting

requirements etc. have been firmed up afterdiscussions with MRVC, Westem Railway andMMRDA.

Environmental Audit of Santacruz- Borivali Serene Environmental Services5e Railway line Project

3.2 Applicable Legal Requirements

The applicable Indian environmental regulations, World Bank policies/directives and GOMdirectives for all MUTP projects are given in detail in Annex lB. This EMP's for theSantacruz-Borivali project have been prepared within the framework of the ConsolidatedEnvironmental Assessment (CEA), Report for MUTP, 2002. The legal requirementsapplicable to the Santacruz-Borivali project are as follows:

Indian Environmental and Other Regulations*' Environmental (Protection) Act, 1986, associated Rules and Notifications under the Act.*' The Maharashtra (Urban Areas) Preservation of Trees Act, 1975*' Land Acquisition Act 1894 (LA Act):

*' Maharashtra Regional and Town Planning Act, 1966 (MR&TP Act):* Development Control Regulations for Greater Mumbai 1991 (DCRs):

World Bank Policies*' Environmental Assessment (OP 4.01)

*' Involuntary Reseftlement (OD 4.30)

Relevant compliance action for these policies has been covered in the following Section 4.6

6

Environmental Audit of Santacruz- Bonvali Serene Environmental Services5eh Railway line Project

4.0 BASELINE ENVIRONMENTAL STATUS and IMPACTS

For this project Environmental Assessment has not been carried out earlier and baselineenvironmental data is not available. As discussed earlier, construction work for the project isfully complete. Thus, impacts during construction phase of the project cannot be assessed.However, residual impacts, if any, due to completed activities and ongoing activities havebeen evaluated and are presented below. A summary of Impacts is presented in Table 3.

4.1 Terrain and Geology

Santacruz - Borvali tracks run over almost a level terrain in the area. The area through out isbuilt-up. Some open areas are observed between Malad and Goregaon. Geology is typicalof the westem coast i.e. Basalt rocks overlain by alluvial soils / clays.

4.2 Climate

The climate of the area is characterized by high humidity nearly all year round, oppressivesummers season and well-distributed and heavy rainfall during the southwest monsoonseason. This suburban district receives heavy rainfall during the southwest monsoon seasonbetween June and August.

4.3 Ambient Air Quality

Current AAQ Monitoring Data

Baseline data for the project site is not available. AAQ is being monitored by MunicipalCorporation of Greater Mumbai (MCGM) at several locations in Mumbai. Mronitoring is doneas per the methodology prescribed by Ministry of Environment and forests (MOEF), NewDelhi. One of the locations where monitoring is conducted regularly is near the Khar railwaystation. Although this station does not lie between Santacruz and Borivali, it is on the sameline and located adjacent to Santacnrz to the south. This location is considered as anexample of area near the railway stations, having high density of vehicular traffic includingauto-rickshaws, buses, private vehicles etc. The annual average values for the year 2000 forS02, NOx and SPM reported at Khar was 16.16 t1g/M 3, 69.25 jig/M3 and 290 hig/M3. Thesevalues may not represent the AAQ levels at other stations, but may be taken as an example.The values for NOx and SPM exceed the AAQ annual average standards for residential areas.These AAQ annual average AAQ standards for residential areas are as follows: S02 (60[Lg/M 3); NOx (60 jig/m3); SPM (140 jig/rn3).

AAQ near commercial and residential areas near railway stations, typically have elevatedAAQ levels due to sluggish traffic and highly built-up area with poor dispersion conditions.However, areas between stations have much lower values.

Environmental Audit of Santacruz- Borivali Serene Environmental Services5 h Railway line Project

Impact Assessment

Durina Construction PhaseConstruction work is completed. Thus impacts on air quality due to construction activitycannot be assessed.

Durnnq Operation PhaseDurng the operation stage, there will be no impact on air quality, as electric trains will beoperated on the proposed track.

4.4 Noise Levels

Baseline DataBaseline data for the project site is not available. However, spot monitoring of noise (daytime) was done near the 5e line between Santacnrz and Andheri to assess noise impacts.Photo 1 in Annex 2 shows a section of the completed 5th line with boundary wall andresidential areas next to it. Noise monitoring was done at a similar locations. The noisemonitoring locations and values are given below in Table 4.0

Table 4.0 Day time Noise Monitoring ResultsNo. Location Noise levels CPCB Noise

dB(A) Standards forresidential area

1. Baseline noise level 30 m from railway track at 65 - 70 Day time - 55dB(A)Santacruz - no train movement (behind Night time - 45boundary wall) dB(A)

2. Baseline noisb level 30 m from railway track at 83 - 87Santacruz - with train movement (behindboundary wall)

Impact Assessment

During Construction PhaseConstruction work is completed. Thus impacts on noise levels due to construction activitycannot be assessed.

During ODeration PhaseExisting baseline noise levels in this area exceeds the CPCB noise standards for residentialarea. This is typically found near the railway stations, where residential areas are locatedquite close (30 to 50 m) to railway tracks.

Boundary wall have been constructed along the railway land,-however this is not expected tohave much potential for noise attenuation, as residential building are located very close to thetracks and are 3 to 4 storey high. Providing a barrier all along the track to this height may notbe feasible. Source reduction techniques by providing better track/wheel interface and trackmodification may be more appropriate for noise reduction.

8

Environmental Audit of Santacruz- Borivali Serene Environmental Services5e' Railway line Project

4.5 Ground and Surface Water Quality

Impact AssessmentDurinq Construction PhaseConstruction work is completed. Thus impacts on any water body due to construction activitycannot be assessed. However, there are no water bodies of any significance (lakes, rivers,creek etc.) present in the Santacnrz-Borivali rail corridor. In fact most of the area is denseBuilt-up area. Thus there would not have been any adverse environmental impact on water

bodies.

During Operation PhaseThe operation of the project is not likely to have a significant impact on water bodies due tothe following reasons:* Wastewater generated at platforms and the new railway quarters will be treated in septic

tank and discharged via soak pits or discharged into existing sewerage network.* Drains are constructed at locations near stations likely to be flooded during monsoons.* There is no other activity which generates effluent and which can adversely affect any

water body.

4.6 Natural Habitats and Ecology

Management and conservation of natural habitats likely to be affected by the SantacruzBorivali project is required by The World Bank Operational Policy OP 4.04. There are nonatural habitats along this route such as forests, mangroves, which require protection.

Imoacts During Construction PhasePermission for felling of these trees were obtained from the Tree Officer of MCGM. Area fortree plantation is limited due to dense built-up area on this route (See Photo I in Annex 2).However, WR is carrying out track-side and other plantation for enhancement of the areawherever feasible. Photo 3 in Annex 2 shows plantation and fencing done at AndheriStation. Photo 4 shows the completed 5th line with track-side vegetable plantation which isgiven on contract. This activity is proactive and plantation targets are normally set for variousWR managers.

Impacts Durina Operation PhaseImpacts on ecology is not expected during the operation stage as the project is coming upalongside the existing tracks and there is no forest and other sensitive ecological reservesnear the tracks that can be affected due to operation of additional rakes.

4.7 Land UseThis rail corridor is large built-up area with no significant ecological resources, water bodiesetc. There are mixed use- and residential areas immediately adjacent to the corridorboundary. At Malad and Goregaon few patches of vacant land are seen in between stations.

Impacts

The land-use pattern has not change significantly due to the implementation of the project asit has come up alongside the existing tracks.

9

Environmental Audit of Santacruz- Bonrvali Serene Environmental ServiCeS5lh Railway line Project

4.8 Resettlement and RehabilitationThere are 515 project-affected households (PAHs) which need resettlement. Resettlementand rehabilitation of the project-affected households is being done by MMRDA as per theRehabilrtation Action Plan (RAP) of Govt of Maharashtra. Site specific Community

Environment Management Plans (CEMP) are being prepared separately by MMRDA fortransit and permanent locations.

4.9 Archaeological and Cultural PropertyRehabilitation of Cultural Property such as archaeological and historical sites, religious(temples, mosques etc.) affected by project activities is required by The World BankOperational Policy 4.11 on Cultural Property Preservation.

As per survey conducted by MMRDA, there were no such structures present on this route.

Table 4.0 presents summarized impacts during construction and operation phase of project.

I(

Environmental Audit of Santacnrz- Bonvali Serene Environmental Servicesh"' Railway line Project

Table 4.0 Impact Mjatrix

No. Parameter Impacts During Construction phase Impacts During operation phase

1 Air Quality Construction work is completed. Thus impacts on air No negative impacts during operation phase.quality due to construction activity cannot be assessed.

2. Noise Construction work is completed. Thus impacts on noise Existing baseline noise levels in this area exceeds the CPCBlevels due to construction activity cannot be assessed. noise standards for residential area. This is typically found

near the railway tracks where residential areas are locatedquite close (30 to 50 m) to railway tracks.

Boundary wall have been constructed along the railway land,however this is not expected to have much potential fornoise aKtenuation, as residential building are located veryclose to the tracks and are 3 to 4 storey high. Providing abarrier all along the track to this height may not be feasible.Source reduction techniques by providing beKter track/vheelinterface and track modification may be more appropriate fornoise reduction.

Environmental Audit of Santacruz- Borivali Serene Environmental Serviceseh Railway line Project

Table 4.0 Cont..

No. Parameter Impacts During Construction phase Impacts During operation phase

3. Water Quality No water bodies of any significance such as lakes, rivers, No significant adverse impacts as effluent fromcreek etc. present in the Santacruz-Borivali rail corridor. plafforms will be treated in septic tanks andNo adverse environmental impact on any water body. discharged via soak pits/ or into existing sewers.

No other source of effluent during operation.4. Natural Permission for felling of trees had been obtained from the No adverse impacts on ecology during operation

Habitats and Tree Officer. Area for tree plantation is limited due to phase. No forest and other sensitive ecologicalEcology dense built-up area on this route (See Photo I in Annex reserves located in the rail corridor.

2). However, WR is carrying out track-side and otherplantation for enhancement of the area wherever feasible.(Photo 3 in Annex 2 shows plantation and fencing atAndheri station)

5. Landuse The land-use pattern has not change significantly due to No adverse impacts expected.the implementation of the project as it has come upalongside the existing tracks.

There are 515 project-affected households (PAHs) whichneed resettlement. Resettlement and rehabilitation of thePAH done by MMRDA as per the Rehabilitation ActionPlan (RAP) of Govt. of Maharashtra.

6. Archaeological As per survey conducted by MMRDA, there were no such No adverse impacts expected.and Cultural structures present on this route. More details are given inProperty. the Rehabilitation Action Plan (RAP) for MUTP and

Rehabilitation Implementation Plan (RIP) for the Project.

12

Environmental Audit of Santacnuz-Bonvali Serene Environmental Servicesdh Railway Line Project

5.0 Assessment of Environmental Mitigation Measures

5.1 Introduction

The previous sections described the changes observed in baseline environmental status andthe environmental impacts during construction and operation stages of the project. Thissection is dedicated to evaluating the Environment, Health and Safety (EHS) mitigation needsand institutional mechanisms for their implementation. EHS mitigation measures, monitoringprograms and reporting structure are required to be a part of an Environmental ManagementPlan.

As discussed earlier, the entire construction work for the project is complete and thus EHSmeasures cannot be audited/assessed for the construction phase. Also, as seen from theprevious section, site visits have not revealed any significant adverse environmental impactcaused due the already completed activity.

Thus, as far as this project is concemed, recommendations for EMP implementation includethe following:* EHS mitigation measures that could be included as a requirement for contractors for

future works in this area.* EMP monitoring and reporting during operational stage.* Institutional mechanism for EMP implementation

5.2 EHS Mitigation Measures

EMP measures are presented in Table 5.1 to 5.3 for the design, construction and operationstages. Tables 5.1 and 5.2 will be applicable only for future projects. Table 5.3 isapplicable to the operating stage of the current Santacruz-Borivali 5th line project.

The mitigation requirements mentioned should be complied by the WR by assigningresponsibilities for the same to various WR departments and making it a part of contractorrequirements where relevant.

14

Environmental Audit of Santacruz-Borivali Serene Environmental Servicesdh Railway Line Project

TABLE 5.1 EHS Mitigation Measures (PRE-CONSTRUCTION I DESIGN STAGE)

Environmental EHS Mitigation Measures To be taken* Responsibility **Impact Implementation SupervisionEcological impacts Trees to be removed before commencement of construction, with prior permission from Forestsuch as tree cutting Officer as required by the The Maharashtra (Urban Areas) Preservation of Trees Act, 1975. WR - Site Engineer WR - Dy. Chiefand destruction of with contractor Engineer (Construction)mangroves.Utility relocation All utilities, such as electrical installations, telephone lines etc. to be shifted after prior approval of

agencies. WR - Site Engineer WR - Dy. Chiefwith contractor Engineer (Construction)

Noise pollution Construction of noise barriers at appropriate locations. Barriers as mentioned above may providethe noise attenuation to some extent, however, it is doubfful that any attenuation will be possible WR - Site Engineer WR - Dy. Chiefover the ground floor of existing structures. Also, the effect will be variable to a large extent as with contractor Engineer (Construction)residential and sensitive receptors will be located at variable distances from the boundary wall.

Noise reduction at source appears to be a more practical approach to address the noise impacts.These should be implemented by WR.

A variety of sources are responsible for both the total environmental noise pollution of a passingtrain and its interior noise. These sources are the wheel, the rail, the track components - sleepers,ballast etc. Some of the measures which are being introduced in all new rail lines are:

a. Use of continuous welded railsb. Rubber pads between rail and sleepers.c 30-cm stone ballast cushion below sleeper seat, which will reduce noise by providing elasticity.d. Construction of concrete bridges instead of steel bridges.

o T/e EMP Measures given above for pre-construction and construction phases are applicable for Future Railway Projects on this andotlier routes of WR.

** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting inSection 6 and the inspection sheet and formats in Annex 4 and 5.

15

Environmental Audit of Santacruz-Borivali Serene Environmental Services5th Railway Line Project

TABLE 5.2 EHS Mitigation Measures (CONSTRUCTION STAGE)Environmental EHS Mitigation Measures To be taken* Responsibility **Impact Implementation SupervisionGeneration of Dust Construction site to be watered periodically to minimize fugitive dust generation. WR - Site Engineer &due to construction Site contractor Dy. Chief Engineeractivity (Construction)

All Earthwork and construction material should be protected in such a manner so as to minimize WR - Site Engineer &generation of dust. All dumpers should be covered by tarpaulin sheets to minimise spillage of sand Site contractor Dy. Chief Engineerand soil. (Construction)

Construction Vehicle Exhaust emissions from all construction vehicles shall adhere to vehicle emission norms. WR - Site Engineer &/equipment exhaust Site contractor Dy. Chief Engineer

(Construction)Noise from vehicles, All vehicle and construction equipment shall be fitted with exhaust silencers. Damaged silencers WR - Site Engineer &plants and to be promptly replaced by contractor. Vehicles to be maintained and services regularly. Site contractor Dy.. Chief Engineerequipment . (Construction)Contamination of Silt fencing shall be provided at the base of the embankment for the entire perimeter of any water WR - Site Engineer &water bodies such as body (including wells). A documented procedure to be made by all contractors clearly prohibiting Site contractor Dy. Chief Engineerwells and discharge/dumping of waste material into any water body. Checks on the same shall be kept as (Construction)lakes/ponds.dicag/upnofwsemtrainoaywtrbd.Cekontesmshlbekpas(otuto)

per format given in Inspection Sheet in Annex 4Construction material containing fine particles shall be stored in an enclosure such that sediment- WR - Site Engineer &laden water does not drain into nearby watercourses. Site contractor Dy. Chief Engineer

(Construction)Siltation of soil into water bodies shall be prevented as far as possible by adapting soil erosioncontrol measures as per MoST (Ministry of Surface Transport) guidelines Site contractor WR - Site Engineer &

Dy. Chief Engineer(Construction)

Construction work close to water bodies shall be avoided during monsoon.Site contractor WR - Site Engineer &

Dy. Chief Engineer(Construction)

In sections along water courses and close to cross drainage channels, earth, stone or any otherconstruction material shall be properly disposed so as not to block the flow of water. Site contractor WR - Site Engineer &

Dy. Chief Engineer(Construction)

* The EMP Measures given above for pre-construction and construction phases are applicable for Future Railway Projects on this and otherroutes of WR

** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting -inSection 6 and the inspection sheet and formats in Annex 4 and 5.

16

Environmental Audit of Santacruz-Borivali Serene Environmental Services5th Railway Line Project

TABLE 5.2 Cont.Environmental Impact EHS Mitigation Measures To be taken* Responsibility **

Implementation SupervisionEcological impacts such as tree All works shall be carried out in such a fashion that damage to flora is minimum WR - Site Engineercutting and destruction of mangroves Site contractor & Dy. Chief

EngineerTrack - side plantation shall be done as per the Tree cutting permission from Tree WR - Site EngineerOfficer Site contractor & Dy. Chief

EngineerSoil erosion On road/track embankments, slopes shall be stabilized. The work shall consist of WR - Site Engineer

measures as per design, or as directed by the engineer to control soil erosion, Site contractor & Dy. Chiefsedimentation and water pollution, through use of berms, dikes, sediment basin, Engineermulches, grasses and other devices.

Debris disposal Debris generated due to dismantling of existing structures shall be suitably reused in WR - Site Engineerproposed construction. Un-utilised debris shall be suitably disposed either as fill Site contractor & Dy. Chiefmaterial or at pre-designated dump locations, approved by engineer. Care should be Engineertaken that the material does not block natural drainage or contaminate water bodies.

A clear documented procedure to be made part of the tender documents, requiringcontractors to dispose debris in low-lying areas away from water bodies, as fill materialonly. Monitoring the same to be done by use of inspection sheet in Annex 4 and 5

Slurry or similar debris generated from pile driving or other construction activities shall WR - Site Engineerbe disposed such that it does not flow into surface water bodies or form mud puddles in Site contractor & Dy. Chiefthe area. Engineer

Loss of top soil The topsoil from all areas of cutting and all areas to be permanently covered shall be WR - Site Engineerstripped to a specified depth of 150 mm and stored in stockpiles. Site contractor & Dy. Chief

EngineerThe topsoil from the stockpile shall be used to cover disturbed areas and cut slopesand also for re-development of borrow areas, landscaping and road side plantation.

Soil contamination by construction Oil and fuel spills from construction equipment shall be minimized by good O&M WR - Site Engineerwastes, fuel etc. practices. Soils contaminated by such spills shall be disposed as per MOEF Site contractor & Dy. Chief

requirements. I_Engineer* The EMP MYeasures given aboveforpre-construction and construction phases are applicablefor Future Railway Projects on this and other

routes of WR** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting in

Section 6 and the inspection sheet and formats in Annex 4 and 5.

17

Environmental Audit of Santacruz-Borivali Serene Environmental Services5"' Railway Line Project

Table 5.2 Cont.

Environmental Impact EHS Mitigation Measures To be taken * Responsibility **Implementation Supervision

Land degradation in quarry Sand and stones shall be sourced from only and licensed quarries. Documentation such as WR - Site Engineerarea quarry release receipt issued by the District Revenue officer at the quarry site to be available Site contractor & Dy. Chief

at construction site. Engineer

Health and hygiene at Construction labour camps shall be located away from the nearest habitation to avoid WR - Site Engineerconstruction labour camps conflicts and stress over infrastructure facilities. Site contractor & Dy. ChiefHealth and hygiene at Engineerconstruction labour camps The contractor will provide, erect and maintain necessary (temporary) living accommodation WR - Site Engineer

and ancillary facilities such as toilet blocks, potable water supply etc. for labour as per the Site contractor & Dy. Chiefstandards set by various labour Act. Engineer

On completion of the works, all temporary structures shall be cleared away along with all WR - Site Engineerwastes. All excreta and other disposal pits should be filled in and effectively sealed. The site Site contractor & Dy. Chiefshould be left clean and tidy to the satisfaction of the engineer. Engineer

Delays and congestion on The construction plan shall be discussed in advance with Western Railway Authorities to WR - Site Engineertracks avoid delays in existing train schedules. Site contractor & Dy. Chief

EngineerTraffic Control and Safety The contractor shall take all necessary measures for the safety of existing train traffic during WR - Site Engineer

construction and provide, erect and maintain such barricades, including signs, markings, Site contractor & Dy. Chiefflags, lights and flagmen as may be required by the engineer for the information and Engineerprotection of traffic. All such measures should as per requirement of Western Railway.

Special consideration shall be given in preparation of traffic control plan to the safety ofpedestrians (at railway crossings) and workers at night.

* Tie EMP Measures given abovefor pre-construction and construction phases are applicablefor Future Railway Projects on this andother routes of KR

** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting inSection 6 and the inspection sheet and formats in Annex 4 and 5.

18

Environmental Audit of Santacruz-Borivali Serene Environmental Services5" Railway Line Project

Table 5.2 Cont.

Environmental Impact EHS Mitigation Measures To be taken * Responsibility **Implementation Supervision

Occupational Health and The contractor is required to comply with all the precautions as required for the safety of WR - Site EngineerSafety workmen. Site contractor & Dy. Chief

EngineerThe contractor shall supply all necessary safety appliances such as safety goggles, helmets, WR - Site Engineersafety belts, earplugs, masks etc. to the worker and staff. All laws related to safe scaffolding, Site contractor & Dy. Chiefladders, working plafform, gangway, stairwells, excavations, safety entry and exit etc. shall be Engineercomplied with. This requirement should be made part of the tender documentation.Adequate precautions shall be taken to prevent danger from electrical equipment. All WR - Site Engineermachines/equipment used shall confirm to the relevant Indian Standards (IS) codes and shall Site contractor & Dy. Chiefbe regularly inspected by the engineer. EngineerA readily available first aid unit including an adequate supply of sterilized dressing material WR - Site Engineerand appliances shall be provided as per the requirements under the Factory Act. Site contractor & Dy. Chief

_______________________________________________________________ ____________ EngiEnineeAll anti-malarial measures as prescribed by the engineer shall be complied with, including WR - Site Engineerfilling up of burrow pits. Site contractor & Dy. Chief

Engineer

* The EMP Measures given aboveforpre-construction and construction phases are applicablefor Future Railway Projects on this and otherroutes of WR

** A follow-up mechanism for regular monitoring of mitigation measures to be followed as per EMP monitoring and reporting inSection 6 and the inspection sheet and formats in Annex 4 and 5.

19

Environmental Audit of Santacruz-Bonvali Serene Environmental Servicesdh Railway Linre Project

TABLE 5.3 EHS MITIGATION MEASURES (OPERATION STAGE)

Environmental EHS Mitigation Measures To be taken Responsibility **Impact Implementation SupervisionNoise pollution To track the benefits accrued from noise reduction WR- Dy. Chief

at source from installing improved track, wheel and WR - Site Engineer Engineerother mechanism, regular noise monitoring should with contractor (Construction)be done as per monitoring plan in Table 6.

Land and water Contingency plans to be in place for spill clean-up.contamination from Contingency plan needs to be made for the entire District District Collector MMRDAaccidental spills from by the District Collector. Emergency situations will need agoods trains. combined response from many agencies and a specific

plan as a part of this project is not envisaged.Rail traffic and safety Unauthorised building development to be checked. Slum WR- Dy. Chief

encroachments to be discouraged. WR - Site Engineer Engineerwith contractor (Construction)

Surveillance along railway boundary to be increased tocheck encroachment and breach of boundary wall.

Loss of plantation. Regular maintenance of the mandatory track-side and WR- Dy. Chiefother plantation should be done. WR - Site Engineer Engineer

with contractor (Construction)Monitoring of plantation to be done as per format inAnnex 6.

20

Environmental Audit of Santacruz -Borivali Serene Environmental Services5th Railway line.

6.0 Environmental Monitoring and Reporting

Ste visits and interviews have revealed the following facts related to environmentalmanagement organisation:

. In the consolidated EA report for MUTP, MRVC was reported to be the ProjectImplementation Agency (PIA). However, Westem Railway (WR) is the PIA for thisproject. MRVC is the coordinating agency to facilitate communication between MMRDAand WR.

* Environmental monitoring is currently not required to be done by the contractors. Apartfrom periodic safety inspections, currentiv there is no feedback mechanism for EHSelements of the project.

6.1 Environmental Monitoring Program

The main objectives of a monitoring program are:* To evaluate the effectiveness of the mitigation measures during the construction and

operation phases.* To satisfy the legal and community obligations* To respond to the unanticipated environmental issues at an early stage and to verify the

accuracy of environmental impact prediction.

The monitoring of R&R components is being covered separately as a part of another studyand permissions have been taken earlier for cutting of vegetation.

Comprehensive periodic site inspection programs for EHS elements and a regularenvironmental monitoring program will best achieve the objectives of monitoring describedabove for this project. This is covered in Section below.

6.1.1 EMP Monitoring and Reporting during Construction Phase

6.1.1.1 Environmental Monitoring

The construction of this line is complete and hence monitoring during construction phase isnot being provided. For future works, monitoring of air quality, noise levels etc. will need to bedefined based on actual location and site conditions of the project.

6.1.1.2 Monitoring of EHS mitigation measures implementation

In the context of Railway projects of MUTP, an effective inspection program will go a longway to assure implementation of various EHS mitigation measures for this project. Theprogram given here could be used for future construction activities on this line. The inspectionprogram needs to be dove-tailed into existing programs followed by WR and, the parametersfor inspection, inspection schedules etc. need to be clearly defined. The EHS parameters tobe monitored depend upon factors such as:

21

Environmental Audit of Santacruz -Borivali Serene Environmental Services5 Railway line.

* EHS components affected* Construction schedule of the project

* Environmental Mitigation measures suggested

Based on the site observations, level of awareness of contractor and WR staff, the followingprogram and procedure is suggested for effective monitoring of EHS implementation at futureconstruction sites covered by MUTP:

a. Monthly inspection program by WR for all project construction sites. Theinspection will be carried out by DCE (Construction) In-charge of the constructionsite, or his representative. The format for inspection will be as per Annex 4. Theinspection will be carried out during the entire period of construction activityincluding before start of construction and immediately after construction iscomplete.

The completed inspection checklist shall be submitted by the concemed DCE tothe Chief Engineer (WR). Correctve action plan with time frame for implementationfor any non-compliance to be also submitted.

(Separate checklists need to be filled in for separate works. However, a group ofsimilar activites could be inspected using the same checklist . E.g.- Findings ofinspection of construction of station building, FOB, platform extension work at astation could be entered in the same checklist).

b. All site contractors to maintain log books and other documentation specified inAnnex 5.

c. Copy of the completed monthly inspectfon checklist should be sent by the ChiefEngineer (WR) to MMRDA every month for review. The Inspection checklist for amonth along with the corrective actfon plan, if any, shall reach MMRDA no laterthan the 1?m day of the next month.

d. MMRDA to carry out independent 3rd - party inspection of various construction sites(the sample sites indicated in this report could be visited at a minimum) everyquarter during the constructfon activity and also after construction is completed toassess any residual environmental Impact A Project Management Consultant(PMC) should be appointed for this purpose by MMRDA. Review checklist given inAnnex 4 could be used for this purpose.

22

Environmental Audit of Santacruz -Bonvalh Serene Environmental Services5e Railway line.

6.1.2 EMP Monitoring and Reporting during Operation Phase

Operation phase monitoring for this project is required mainly for the following:

* Ambient noise levels to determine baseline levels and track improvements accrued due toimplementation of source noise reduction. Ambient air monitoring is not suggested sincethe operation will not contribute to air pollution (Electricity driven trains). Also no impactsduring operation stage expected on water quality and soil quality.

* Health and survival rates of the compensatory and other plantation done by WR.* Monitoring of Rehabilitation and Resettlement (R&R) sites for the people displaced due to

the project. This will be done as a separate exercise not covered in this audit report.

The monitoring program suggested is given in Table 6 below.

23

Environmental Audit of Santacruz -Borivali Serene Environmental Services5 th Railway line

Table 6 Monitoring Program During Operation Phase.

Compone Parameters Locations Duration Frequency ResponsibilityntNoise Leq (day) * At residential Continuous Once every PIA (Deputylevels and Leq location 200 m 24 hour season Chief Engineer-

(night) North of reading with (Summer, WR) throughSantacruz a frequency Winter, Post- extemalstation, facing of 10 minutes monsoon). agencythe 5t line for 2 non-tracks. (At consecutivefront of and days perbehind week for 2boundary wall) weeks.

* At residentialarea near newplatformconstructed atAndheristation

* At residentialarea behindboundary wall200 m south ofBorivalistation.

Tree As per At plantaton 6-monthly for PIA (Deputyplantaton Format in locatons 3 years. Chief Engineer-survival Annex 6. WR) throughrates. external

agency

24

Environmental Audit of Santacnrz -Borivali Serene Environmental Serviceseh Railway line.

6.2 INSTITUTIONAL SETUP

The construction activities of the project are being implemented by WR. The existing organisationalstructure of Railways for operation phase is given below in Figure 1.

FIGURE 1.0 EXISTING ORGANISATION FRAMEWORK FOR WESTERN RAILWAY(Santacruz-Borivali 5h Line)

|World Ban MMD_ DxAec

| RVtr. - Cnrtlinntinn Anpnr

Chief Engineer (WR)

Dy. ChiefEngineer(Construction)Borivali to Virar

Assistant Engineers

In the consolidated EA report for MUTP, it was envisaged that the monitoring and reportingprocess for mitigation measures during construction should initiate from the contractor at thelowest rung who will report to the Project Implementation Agency (PIA) through the ProjectManagement Consultant (PMC). PMC could be appointed for periodic 3r party review of theEHS elements for the operating stages and for construction phases of any future projects.

25

Environmental Audit of Santacruz -Borivali Serene Environmental Services5 h Railway line.

6.2.1 Institutional Strengthening

For carrying out regular inspection for the EHS elements, the WR staff needs training forappreciation of various EHS elements. The training program proposed is given in Table 7below.

Table 7. Training Program for Institutional Strengthening

Module Topic and Contents Duration1 Environmental Awareness Class Room

Appreciation of Environment, Health and Safety Training of Iissues - Fundamentals of Air Pollution, Noise, dayWater Pollution, Solid and Hazardous Wastesgeneration and handling etc.

2 Environmental Impact Assessment Class RoomEIA fundamentals. Consequences of adverse Training of Ienvironmental impacts on various ecosystems. dayTypical environmental impacts of railway projects

3 Environmental Legislation Class RoomIndian Environmental Laws and their application to Training of 1/2

_Railway Projects. day4 EHS Management System Class Room

Components of EHS Management System in Training of 1/2general and as applicable to Railway projects. dayMethodology of environmental monitoring for airquality, noise etc. Site visit to any

one railwayEnvironmental monitoring and inspection programs constructionas suggested in this report should be discussed. site for

appreciation ofReview of existing tender conditions and its variousmodification to include EHS elements for better EHS environmentalmanagement. components.

(1/2 day)

The training should be provided at a minimum to the following personnel:* Deputy Chief Engineers (Construction)* Westem Railway Site In-charge of various construction sites* Contractor Site In-charge of various construction sites.

1 training program of 4 days as given above should be conducted every quarter to cover allconcemed WR staff. The training program can also be integrated into the WR induction-training program.

Visits to country's having similar railway projects and with established and demonstrated EHSMahagement System, including demonstrated measures for noise attenuation could be visitedby concemed officials of WR. This will help in increasing awareness with WR and improvetechnical skills for EHS management.

26

Environmental Audit of Santacruz -Borivali Serene Environmental Services5 h Railway line.

6.3 Estimated Cost of EMP ImplementationAs seen in the Tables 5.1 to 5.3, several EHS elements are already induded in the currentconstruction operation. The construction phase is complete and hence construction phaseEMP costs are not applicable.

Table 8 Cost of EMP ImplementationComponent Unit cost (Rs) Units Total Cost (Rs)EnvironmentalMonitoring(Operation Phase)Noise Levels (Leq 2000 per 24-hr Leq 16 samples per season x 96000day and night) (1 sample) 3 seasons = 48 samplesTree plantation 15000 per survey 1 survey every 6 months 90000survival rates. for 3 years = 6 surveys

Training Program 40000 per program 4 programs per year 160000*of 4 days each.

Visit abroad to 200000 per person 5 persons 1000000*Railway Project sitewith demonstratedMeasures forEnvironmentalProtection andestablished EHSManagement Systemincluding noiseattenuation.Total Cost 1346000*

* Cost of Training has already been included for WR in BVQR project The staff ofWR for this 2 lines will be included under the same training program. The actualcost for EMP for Santacruz-Borivali line will be Rs. 1,86,000.

27

Environmental Audit of Santacruz- Borivali Serene Environmental Services5th Railway line

ANNEX-1A

TERMS OF REFERENCE

MUMBAI URBAN TRANSPORT PROJECT

TERMS OF REFERENCE FOR CARRYING OUT ENVORONMENTALASSESSMENT/ AUDITING OF RAILWAY PROJECTS

1 ASSIGNMENT:

The purpose of this assignment is to assist Mumbai Metropolitan RegionDevelopment Authority (MMRDA) in carrying out an environimlental audit ofvarious ongoing railways projects to determine how environmental Issues. if any,can be addressed at this staae of project implementation.

2 BACKGROUND:

2.1 MMRDA had appointed Montgonmery-Watson Consultanlts (India) IPvt Ltd toundertake the preparation of the Environmental Assessment (EA) for the MUTP.This EA process resulted in the preparation of Sectoral-Level EnvironmentalAssessment (SLEA), Programmatic Level Environmental Assessiment (PLEA)and Micro-Level Environmental Assessment (MLEA) The SLEA was a strategicdocument, the PLEAs were prepared for small generic sub-projects like flyovers.ROBs and RUBs while MLEAs were prepared for larger sub-projects like roadwideening and extenisionis This study was undertaken between 1996 and 1998and resulteCd In several outp)uts including a syntlhesized final epoit

2 2 Consequently, almost all of these railway projects except DC to AC conversionhave been started and are in varying stages of implementation As thecoInstruction work of the project is already underway coIIsullants slhould assessthe cUrrent and residual requiremenits of environmiiiental manlagement practiceEnvironimental Studies, whict have been carried oult for railway projects, are asunder

a) Report of MLEA of Borivali-Virar Quadrupling prepared by Montgomery-Watson Consultants (India) Pvt. Ltd in 1998,

b) Report of Initial Environmental Examination for Thane- Kurla 5th and 6th linesprepared by MMRDA in 2000-01.

The Consultant should use these reports as the basis to carry out the proposedenvironmental audit

2 3 Somie of the projects may also involve construGtion in aieas. wlhichi are classifiedas restricted areas unfder Coastal Regulation Zone (CRZ) Rules H-lence,permiission needs to be obtained under CRZ FRules fromil thie Ministry ofEiviroinilent and Forests. Governimlenit of Ildia for SUCIl projectS

MUMBAI URBAN TRANSPORT PROJECT

TERMS OF REFERENCE FOR CARRYING OUT ENVORONMENTALASSESSMENT/ AUDITING OF RAILWAY PROJECTS

I ASSIGNMENT:

The purpose of this assignm1ent is to assist Mumbai Metropolitan RegionDevelopment Authority (MMRDA) in carrying Out an environmental audit ofvarious ongoing railways projects to determine how environmental Issues, if any.can be addressed at this stage of project implementation.

2 BACKGROUND:

2 1 MMRDA had appointed Montgomery-Watson Consultantis (India) l vt Ltd toulidertake the preparation of the Environmental Assessment (EA) for the MUTPThis EA process resulted in the preparation of Sectoral-Level EnvironmentalAssessment (SLEA). Programmatic Level Environmental Assessmelnt (PLEA)and Micro-Level Environmental Assessment (MLEA) Tlhe SLEA was a strategicdocument, the PLEAs were prepared for small generic sub-piojects like flyovers.ROBs and RUBs while MLEAs were prepared for larger sub-projects like roadwicdenin1g and extensionis This study was undertaken between 1996 and 1998and ICcsullCd in several outputs includinig a syntlesized final i epolt

2 2 Consequently, almost all of these railway projects except DC to AC conversionhiave been started and are in varying stages of implementntion As tIheconistiuctioni work of the project is already underway consultalits sh ouldl assessthe currenit and residual requirenienits of enviionimental management practice

'Enviionnmental stLidies, whichi lhave been carried out for railway projects. are asunder

a) Report of MLEA of Borivali-Virar Quadrupling prepared by Montgomery-Watson Consultants (India) Pvt Ltd in 1998.

b) Report of Initial Environmental Examination for Thane- Kurla 5th and 6th linesprepared by MMRDA in 2000-01.

The Consultant should use these reports as thie basis to carry out thie proposedenvironmental audit

2 3 Som1e of the projects m1ay also involve coristruGlior) In areas, which are classifiedas restricted areas un1der Coastal Regulation Zone (CRZ) Rules I-fence,perinission needs to be obtained under CRZ FPules from tire Ministry ofEiivironment and Forests. Government of Indis foI SUCIn proJeCts

Assessnicut has not Iben cairied out for this project as unider the scrcereeing ofMUTP carried otit by Montigomlery Watson, it was placed in the category ofsu)bproject w;thl possibly negligible un rpacts on the environmilent

3 2 2 hlle puIpose of the Audit will be to

- asscss teic status of enviroririiental liznpacts duringl onigoil( iColnstitictior0 ar rIopet atio!n

- assess wNiletlir aiiy environimilental miiitigation imeasuLres are e(ltiireid basedon the on- golilg and comipleted works

OUtlin1e enviroinmienital rnitigation measures for planned works if required

CdocuIMent l^ssons that can be useful for future projects

LSuggest MiltigalIon m1easures for environimilental impacts on the mllarine watelquality, water flow due to construction of bridges and othier possible impactsas identified in the MLEA reporl of Borivali-Virar Quadrupling projectprepared by Montgomery Watson Consultants, Munmbai

.' :.3 *rlie detailed scope of woIk will be as follows

Task 1: Pr eviouis oitap)it arl(l stti(iies

I1 Ile conl0staLINlt s' oiol1l alaniiliatize hliiiiself with

- MLEA report of Borivali-Virar Quadrupling project prepared by MontgomeryWatson Consu'm.AaWts, Mumnbai

- Final report on Environmental Assessmerit for the MUTP project prepared byMontgo iney Watson Consultants. Murimbam

- Project Design/Enigineering and Techno-economic Feasibility Reportsprepared by MRVC.

Task 2: Assessment of Impacts

Consultanl sho-ld undertake site visits to Construction and Operationsites to chleck whether any significant impacts on the air, noise andecolo,:ical envi onmenit, have occurred, if any due to the alreadycomi,;c ted works

-Cor .-.:;r: shoijlcd identify significant envircnmental impacts dLue to 6ni-goin( anca i).oo)csed activities, if any,

CCorII-ltcat shouuld develop a matrix of poss'Ie envtionmierntal impactsarid 'ssues for assessment of the cumulati%. e impacts due to ongoirigcons t: uctioi anrd operation activities

AssessmIcerit lias not l)ben camiied out for this project aS Under th1e screenillng ofMUTP carnted out by Monitgomiiery Watson, it was placed in the category ofsubproject w;thi possibly negligible unipacts on the environmilent

3 2 2 1 hle pLi pose of tlie Audit will be to

- assess tIic status of ciiviioninilenital imlpacts (ILJIiig oriqoilr(; (C.tnStr ii0o am metopei ati o!

- assess whiethier any environmental mnitigation miieasures are we(qitirecd basedon the on- going and coimpleted works

- Outline environillenital mitigationi mieasures for planned works if required

- docuLiveii llcosos tllat can be useful for futLire projects

- Suggest miltKi1ation mieasures for enviroiinmental inipacts on the mlarine waterquality, watCl flow due to construction of bridges and othier possible 1impactsas identilfed in the MLEA reporl of Borivali-Virar Quadrupling projectprepared by Montigomery Watson Consultants, Munmbai

2 :3 The detailed scope of woik will be as follows

Task 1: Pre; iOIIS oultiht anrd st i(lies

I he cOIISLilhif1t s'Iould familiarize liiiiiself wvith

- MLEA report of Borivali-Virar Quadrupling project prepared by MontgomaeryWatson Co.su':amits, Munmbam

- Final ret Slt ole Environmental Assessmaerit for the MUTP project prepared byMontgo riery Watson Consultanits, Mumbai

- Project Design/Enginieering and Techno-econornic Feasibility Reportsprepared by MRVC

Task 2: Assessnient of Impacts

CIComIsultani slhojld undertake site visits to Constructioni arid Operationsites to chleck whether any significant impacts on the air, noise andecoloiical envioniment. have occurred, if any due to the alreadycoii:;c ted %vorks

Con,.,;;tan: slioi Id idenitify significant envirormiental impacts dLIe to on-goin( ancli propcsed activities, if ani

Conn;wlt,Inl sliuuld develop a matrix of posslt!e environiiienital impacts* and ssues for assessment of the cumulat .e impacts due to ongolingcons t: ctil ci and operation activities

sulg9e ;t (!Ivii iicllial m1itigallon niieastires for planlnied ViOlKs. if aiiy asdelinclte(l in tIhe IFS iepoit as well as based on the MLEA repoil of BoDtvall-V1i.1a 01Qil(1 Iiidi'ilii pli ct'(1 p1 epale d by Mol)toolli\ly W;at'.4m (,o i';i il-,;f,it;

I Ie detailcd scope of woi k will be as follows

Task 1 : Previous output anid studies

TI'he consultant shoLild famliliarize hIimiself witlh

- Initial Environmental Assessment Report prepared bv MMRDA and MRVC

- MLEA iepoit of Bomivali-VWiar QuaCilupling project prepaied by lorollgomeryWatson Consultants, Mumbai

- Final iepoit on lEnvironmental Assessmicnt for the MUITP project pilepalCd byMontgonllely Watson Conesultants, Mumitbai

- Project Design/Enigineerincg and Techno-economilc Fren-ibllty Reportsprepaiedcl by MPRVC

Task 2: Assessmilenit of Impacts

Consultant shiould undertake site visits to Construction arid Operationsites to clheck whethler any significant impacts on tI-E' air, noise andecological environimienit, iave occurred, if any due to flhe alreadycoiiipletecl woiks

1Consultallt should identify significant environmental impacts dLie to on-4o9ing and lpioposeCd activities. if any

CConsultant sliould develop a matrix of possible environmilenital imlpactsand Issues for assessment the cuMIulative impacts due to ongoingconstiuction and operation activilties.

Task 3: Enviroiinienital Mitigation Measures

Consultant should undertake visits to Construction and Operation sites toidentify if any environmental mitigation measures are recquired based onconm,pletecl and planned works and delineate environniental mzlanagcmenitplan fol- tillIs puipose. An EMP matrix giving t[e environmental11mpactsS/ssUes. -thie mitigation measures, the impienlentatior andsupeivision authlority for tIe EMiP (whIicth inay e t.o dil'ere1nt ageicies),and the cost iiplications for each mitigationi miieasure s 1o.ld be pl ovided

The l-MI's and their imiiplemlentation plans shIould )e pmepaled in(:oisuIllatiol ar 1(d aq lceiCllet withl thl MRPVC .r1(id ti1(, . (1 rh , c d

stiggjel et iviionnieital imitigation miieasures for planned V,OIK-s, if aiiy asdIclihncŽte( in tlhe IES iIp)oit as well as based on the MLEA iepoit of l3Drivali-Viill a; Quld,II III !I pol'o(ct ptlep.iled by Moitqolliely W:11.'il Coii'.t11t11il';.M~UM?bai

II e detailed scol)e of woi k will he as follows

Task 1: Previous output anid studies

Ilhe consultant shIould familiarize Ihimself with

- Initial Environmrental Assessment Report prepared bv MMRDA qnd MRVC

- MLEA icpoit of Bor ivali-Vuiar Quadiup[lilg project prepaied i y MonltigolielyWatson Consulltants, Muimbai

- Final iepoit on l-nvironiunental Assessiment for Ille MUI'P project pi epaied b)yMontgonllcy Watson Consultants, Mumbai

- Pr oject Design/Enginee riig and Techinio-econorlic f:e.,silility Reportspreparedcl by MRVC

Task 2 : Assessimcint of Impacts

Consultant slhould undertake site visits to ConstruCtion arid Operationsites to chieck whetlher any significant impacts on thE air, noise anidecological environment, lave occurred, if any dire to the alreadycorpletecd works

Consultant should identify significant environmental imprincts dLue to on-oiirg and pi oposcd activilies, if any

IConsullanit slhould develop a m1atrix of possib'e environmental imlpactsand Issues for assessmient the cum1ulative Iimpacts rlnLe to onigoingconstiuction and operation activities.

Task 3: Envirotinierital Mitigation Measures

- Consultant should undertake visits to Construction and Operation sites toidentify if any environmental mitigation measures are reFquired based oncomiipletecd and planned works and delineate environmental mnragellientplall fol tIlIs pir pose An EMP mzatrix giving tte environmentalinpacts/issues, -the mnitigation measures, the impieillentation andsupeIvisioll autthoity for tI,e EMP (which may 'e two cil'i elut age.rcles),and tle cost irmiplications for eacth mllitigation nieaSLure slhouild hcE pr ovicded

- TThe EMPs andcl their iiiplermienitation plans should Ibe prepared In(onscillatiir arIl( anclieinil,nt withl tl)e MR\./(; aId( tiii' ,I I,(II( rCii(lSIJ(jCi ii i 's

Task 2 Assessmicint of Impacts

- Consultant should undeitake visits to the proposed sub-station sites to clieckwhiellter any significanit impacts during constiuction and opeiation especiallyon ecological environmienit, would occur, if any due to the proposed activitiesSonie of the impacts likely to occur relate to construction works. accessroads, ImIpact on suLioUlndilng flora and fauna, and imi pact oni thc coastalecology (CRZ violation)

- Consultant shouild identify impacts during construction due to laying ofundergrouLid cables for replacement of L T. overhiead lines

- Consultants should identify whether the DC transformers to be replacedcontain l'oly Chloiinated 3i-plienyls (PCB3s) anl dlll( diqlit the 1n iii ipa(. ofdisposal of old DC tiansforimers,

- Consultants slIoLild review the Project Design Report and EnviionmentalAssessmienit Report prepaied by M/s Rl-l ES and identify imipacts oii air,noise -and ecological environlmenit due to various othier activities of theproject

Task 3: Environmiental Mitigation Measures

- Consultant shlould identify measures durnglg construction anld Operation, ifaiiy reqilleed to mi itigate eiiviroiniienital impacts anrd delineate i -lviiorio nmidllmariagemerit plan for this purpose

- Consultant should identify ilitigation measures for minimiiizinig thie impacts ofold DC tiansforniefs and delineate EMP incorporatinig thle n easures for safedisposal of old tianisformers, arid prepare a PCB mianiagenietit plan in casePCBs are likely to be found in old transforniers

- The EIVIPs aiid tIlicir iniipleniientationi plan s shoul ce prepared iii GOiISilS1iato101

and agreemient with the MRVC and other concerned agencies

Task 4: Environmenital Assessment Report

- Prepare an Environimlental Assessment report based on the above tasks

4 DOCUMENTS:

r:ie coosultants shIould review the following documenits

Final ieport on Eiivironiental Assessmaerit for the M1UTP project plepared byMontgloiielry Watsoni Con sultants.l Munibai

ii Project Design Report for Borivali-Virar Quadrup',ng. Santacruz-Borivall 5tilline, Klula-Tlharie 5thi and 6th lines and DC to AC conversionl piolectspiepar ecl by MRVC

Task 4: Enviroinmental Assessment Report

Prepare Environmental Audit report for the present exercise based on theabove tasks

3.4 To perforn Environmenital Assessment of DC to AC Traction ConversionProject (1500 V DC to 25000 V AC)

3.4.1 The MRVC has proposed to undertake the conversion of DC to AC Tractioni sothat the sub-urban trains in Mumnbai would be converted to traction of 25000 VAC from the present 1500 V DC. The project would involve the provision of 18DC sub-stations (5 substationis on Western Railway and 13 sub-stations onCentral Railway) in place of existing 69 DC suib-slalions Jlle delailedFnviio0ni enlal Assessmtenit was not carried out as ni1rder JlC ret r sii(:(i mj ol MLJ icarried out by Montigomiiery Watson, it was identified to have least impacts on theenvironm1enit. M/s RITES as a part of feasibility study have identified variousenvironmental benefits of the project. The project will have 10 to 15 %Yo lowerconsumption of energy and lesser use of insulation materials such as copper andAluminum whichi would have least impact on environment as compared to DCtraction/ disposal of old DC transformers.

3.4.2 The objectives of the environm1ental assessment will be to

-assess whiether any activity of tihe project will have imnpacts on theenvironimaenit such as construction of sub-stations withinl coastal regulationzone.

propose proper disposal mleasures for the old DC tiansformers

Lsuggest enviroiinmental management plans if required for riiitigatingenvirotnmenital imlpact.

3.4.3 The detailed scope of work will be as follows

Task 1: Previous output and studies

The consultant should familiarize himself with the:

- Components of the Project

- Final report on Environmienital Assessm1ent for the MUI1P proiect prepaireld byMontgomlery Watson Consultanits. Mumbal

- Project Qesign Reports prepared by Mls RITES and MRVC.

iii. MLEA report of Borivali-Virar Quadrupling project prepared by MontgomeryWatson Consultants, Mumbai.

Iv Initial Environmllenital Report prepared by MMRDA and MRVC

v Environnienital Status Reports piepared by MCGI3 for tile yea.I; 19916-2001

vi. Guidelines available (from the World Bank and elsewhere) oni environmentalissues related to electrical substation / transformers.

5 REPORTING REQUIREMENTS

The Consultanit will report to MMRDA and the following is tthe output schedule foreach ot' the four projects. The draft reports submitted by the Consultant will bereviewed and monitored by a Technical Working Group (TWG) constituted byMMRDA comprising of the representatives of MMRDA, MRVC, MCGM, andNGO.

Inception Report 1st week1i Interimr, Report I 4th weekiii DDiaft final Report 7th weekiv. Final Report 8th week

6 DURATION: '

The study should be cornpleted within a period of 8 weeks The total Consultant inputsfor the above assioniment is expected to be 6 person weeks.

7 CONSULTANT'S QUALIFICATIONS:

The Consultant for the assignment shall have acquired a post graduate degree inEnvironmental Engineering with at least 7 to 10 years experience in preparingEnvironmental Assessment reports, conducting Environmental Audits and good workingknowledge of environmental management in related projects.

Environmental Audit of Santacruz- Borivali Serene Environmental Services5h Railway line

ANNEX- 1B

LEGAL REQUIREMENTS

LEGAL AND POLICY FRAMEWORK

1 The project will be implemented within the Indian legal framework and will also complywiththe safeguard policies of the World Bank. The applicable legal and policy framework isdescfibed below.

Applicable Indian Legal Requirements2. The applicable Indian legal provisions are described in two groups one related to

environment and the other related to resettlement.

Legislation related to Environment:

3. There are various Acts, Rules and Notifications applicable for different environmentalcomponents such as Air Polluton, Water Pollubon, Noise Pollution, Coastal Areas,Hazardous Matefials Handling and Transpoit, Forest and Wildlife. In additon, regulatoryprovisions by way of environmental clearance also exist. The applicable acts andregulabons are listed below.

Environmental (Protectfon) Act, 19864. This is an umbrella act for environmental protection. Various rules and notifications are

issued from bme to time under the provisions of this Act. Environmental Protection Rules(2000) specify standards for ambient air quality whereas Noise Pollution (Regulation andControl) Rules, 2000 provide for the ambient noise standards in public places. Howeverlegal mechanism to achieve these are not explicit in terms of emission at source intransport sector except for the vehicle emission norms like Euro II or Bharat II that havebeen prescribed. The Environmental Impact Assessment Notification. 1994 (as amended inMay 1997) make environmental clearance mandatory for 29 categores of developmentalprojects listed in Schedule 1 of the notification. Railways are not listed in schedule 1 andhence do not need environmental clearance. For other components under MUTP, MoE_Fhas confirmed that environmental qlearance EIA notfication is not required.

Coastal Regulation Zone Notfication, 19915. The notification provides for determining certain areas between the Low Tide Line

(LTL) and High Tide Line (HTL) and adjacent land ward area as the CoastalRegulation Zone and its classification into CRZ I -ecologically sensitive and coastalwetland between HTL and LTL, CRZ II - where development has already occurredand CRZ IlIl - the residual area largely rural in character. The notification alsoprescribes prohibited activities in CRZ and activities that can be taken up with theapproval of MoEF. Reclamation being a prohibited activity cannot be undertaken inCRZ I.

The Maharashtra (Urban Areas) Preservabon of Trees Act. 19756 GOM legislation requires every local authority to constitute a Tree Authority. No tree can be

felled without the permission of this authority. The Road development agencies will have toobtain the permission of the Tree Authority for felling of trees in the right of way and followthe Tree Authorities stipulations in respect of transplantng or compensatory plantation.

Legislation related to R & R.

Land Acquisition Act 1894 (LA Act):7. This act provides for compulsory acquisition of land for public purposes by paying

compensation at the market rate with 30% solatium for the compulsory nature of acquisitonand interest at 12 percent per annum from the date of notificabon of land for acquisition.

Maharashtra Regional and Town Planning Act, 1966 (MR&TP Act):8. The act provides for preparation of Regional Plan for the MMR as a whole and preparabon

of Development Plans (Master Plans) for-the local jurisdiction of individual municipalauthority like MCGM. The Regional Plan of MMR has been sanctioned in 1999whereastheDevelopment Plan of Greater Mumbai was sanctioned in 1991. The Regional Plan is policyoriented and strategic in nature whereas Development Plan is more specificand prescribesdetailed land use zoning including designation of land required for public purposes, whichcan then be acquired in conjuncton with the provisions of Land Acquisition Act. The actalso provides a statutory framework for formulation and enforcement of DevelopmentControl Regulations. The sub-projects are required to be consistentwith the Regional Planand the Development Plan.

Develooment Control Regulations for Greater Mumbai 1991 (DCRs):9. The DCRs set out the standards for building design and construction, provision of services

like water supply, sewerage, site drainage, access roads, elevators, fire fighting etc. Aseparate set of regulabons is included for the redevelopment or resettlement of slums,which are administered by the Slun, Rehabilitabon Authority (SRA). Buildings procured forR & R have to conform to these DeRs. Up-front clearance of the entre project is howevernot required under the DCR. Approvals are to be obtained for individual scheme, as it getsprepared.

10. These regulations prepared under the MR & TP Act offer an alternatve to acquisibon underLA Act by way of Transfer of Development Rights (TDR). The permissible Floor SpaceIndex (FSI) defines the development rights of every parcel of land in Mumbai. If a partcularparcel of land is designated for a public purpose the landowner has an option of acceptingmonetary compensabon under the LA Act 1894 or accept TDR (equivalent to the plot areatimes the permissible FSI), which can be sold in the market for use elsewhere in Mumbai.The DC Regulations have been amended to provide incentives for rehabilitation (includingresettlement of slum dwellers) in 1997. For landowners prepared to provide 225 sq.ft.dwelling units free of cost to slum dwellers, the incentve is in the form of right to build andsell floor space equivalent to that required for slum rehabilitation subject to the maximumin-situ utirization of FSI of 2.5. The remainder of the total development rights can be usedas TDR. In case of land designated for resettlement of slum dwellers affected byinfrastructure projects, the land owner has an option of offering dwelling unitsto the projectimplementing agency free of cost and getting the benefit of maximum of TDR equivalenttofloor area calculated at FSI of 3.5 (1 for land and 2.5 for the built-up area).

The Maharashtra Co-operative Societies Act 1960:11. This act provides for establishing, registering and administering the co-operative societies.

Housing co-operative is a special form of co-operative society, where the land and building

is owned by the co-operative and its members have occupancy rights of apartmentoccupied by them. Sale and purchase of such units can take place only with the consent ofthe society. This is a common form of tenure in Mumbai's apartment buildings and iswdelyunderstood.

Applicable World Bank Policies12. Given that MUTP has been developed with the intention of mobilizing financial resources

from the World Bank, project preparation has included a number of studies andassessments which have sought to address and meet the requirements of the WorldBank's environmental and social policies, often referred as the 'safeguard' policies. Thenext paragraphs provide a summary overview of how these guidelines have beenconsidered.

Environmental Assessment (OP 4.01)13. In the context of the Bank's Operational Policy (OP) 4.01 on Environmental Assessment,

MUTP has been classified as category "A" project, largely on the basis of the large numberof people requiring resettlement and rehabilitation. Because of the large-scale resettlementand the triggering of more than one safeguard policy the project is also classified as 'S1 " interms of safeguard issues. A consolidated EA including SEA has been prepared thatprovides the framework for preparing sub-project specific EA and EMPs in compliance withthe World Bank policy.

Cultural Property (OP 4.11):14. The United Nations term "cultural property" includes sites having archeological

(prehistoric), paleontological, historical, religious, and unique natural values. Culturalproperty, therefore, encompasses both remains left by previous human inhabitants (forexample, middens, shrines, and battlegrounds) and unique natural environmentalfeaturessuch as canyons and waterfalls. The World Bank's general policy regarding culturalproperties is to assist in their preservation, and to seek to avoid their elimination.

15. Mumbai with its history of- nearly three hundred years is rich in cultural propertyparticularly in the form of built herTtage. GOM and MCGM are acutely aware of the need toconserve such heritage. GOM in 1995 with the involvement of NGOs listed over 600buildings and precincts as of heritage significance. DCR 67 govems the development ofthese listed buildings and precincts. GOM has also constituted a Heritage ConservationCommittee in 1995 to advise the Municipal Commissioner regarding developmentpermission to be granted in case of listed buildings and precincts. No developmentpermission can be granted of the listed buildings or within the precincts without the consentof the Heritage Committee.

16. During the execution of works, if a 'chance find "of archaeological significance occurs, thecontract requires the contractor to immediately inform the employer and stop furtherwork.Employer will in turn inform the state Archaeology Department for further investigation.

17. The only cultural properties that are directly affected by the sub projects are smallplaces of worship established by the community of squatters within the right ofway. These hav7e been created by the affected communities for their own use.Such places of worship do not possess any historical or architectural significanceand may not therefore strictly qualify to be treated as cultural property.Nevertheless they are treated as an integral part of preparation of RIPs. Theplaces of worship and other community assets are identified dunng the BSES.Their rehabilitation is being implemented as a part of the R & R process inconsultation with the community The impact on these properties and the manner inwhich such impacts can be identified can be classified in three categones. Firstly the

buildings that are only partially affected can be helped to add equivalent area elsewhereadjacent to the building. Secondly structures that are fully affected by the right of way butare patronized by the community that is not affected by the project could be rebuilt outsidethe right of way in consultation with the community and with assistance of the NGO. Insome cases the entrance to the structure could be reoriented to ensure safety of thedevotees visiting the place. Thirdly the affected structuresthat patronized by the communitybeing resettled could be relocated in consultation with the community. In addition, thecommunity may agree to forego some places without insisting upon their resettlement

Natural Habitat (OP 4.04):

18. Natural habitats are defined as land and water areas where (i) the ecosystems' biologicalcommunities are formed largely by native plant and animal species, and (ii) human activityhas not essentfally modified the area's primary ecological functions. All natural habitatshave important biological, social, economic, and existence value. Important natural habitatsmay occur in tropical humid, dry, and cloud forests; temperate and boreal forests;Mediterranean-type shrub lands; natural arid and semi-arid lands; mangrove swamps,coastal marshes, and other wetlands; estuaries; sea grass beds; coral reefs; freshwaterlakes and rivers; alpine and sub alpine environments, including herb fields, grasslands, andparamos; and tropical and temperate grasslands. Criticalnaturalhabitats include exisfingprotected areas and areas officially proposed by governments as protected areas (e.g.,reserves that meet the criteria of the World Conservation Union [IUCN] classifications i.e.Strict Nature Reserve/Wilderness Area: protected area managed for science or wildernessprotecton; Il-Nabonal Park: protected area managed mainly for ecosystem protection andrecreation; Ill-Natural Monument: protected area managed mainly for conservation ofspecific natural features; IV-HabitatVSpecies Management Area: protected area managedmainly for conservation through management intervention; V-ProtectedLandscape/Seascape: protected area managed mainly for landscape/seascapeconservation and recreation; and VI-Managed Resource Protected Area: protected areamanaged mainly for the sustainable use of natural ecosystems. The conservabon of naturalhabitats, like other measures that protect and enhance the environment, is essential forlong-term sustainable development. The Bank therefore supports the protection,maintenance, and rehabilitation of natural habitats and their functions in its economic andsector work, project financing, and policy dialogue. The Bank supports, and expectsborrowers to apply, a precautionary approach to natural resource management to ensureopportunities for environmentally sustainable development.

19. From this perspective one of Mumbai's notable natural habitat is limited to the 103 sq.km.Nabonal Park at Borivaii, which is located in the northern part of the peninsula between thetwo rail corridors. The National Park is protected underthe Indian Forest Act. None of thesub-projects passes through the National Park. The other important Natural Habitat is thecoastal wetlands in the eastern and western suburbs and along the Vasai creek. These areprotected by the Coastal Regulation Zone (CRZ) Notification of 19 February 1991.

Involuntary Resettlement (OD 4.30)

20. The Operational Directve 4.30 describes Bank policy and procedures oninvoluntary resettlement, as well as the conditions that borrowers are expected tomeet in operations involving involuntary resettlement. Planning and financingresettlement of projects are an integral part of preparation for projects that causeinvoluntary displacement MUTP will require resettlement of about 19000households (68000 persons) The World Bank Policy on Involuntary Resettlement

is therefore applicable to the project. In compliance with to this policy an R & RPolicy has been prepared and adopted by GOM for MUTP. RAP providing theoverall framework of policy, entitlements, consultative processes, grevanceredressal mechanism, component costs and monitoring and evaluation mechanismhas already been prepared. Sub-project specific RIPs are being prepared.

Indigenous People (OD 4.20)

21. This operabonal directive describes Bank policies and processing procedures for projectsthat affect indigenous peoples. It sets out basic definitions, policy objectves, and guidelinesfor the design and implementabon of project provisions or components for indigenouspeoples. The terms "indigenous peoples," "indigenous ethnic minorities," "tribal groups,"and "scheduled tribes" describe social groups with a social and cultural identty distinct fromthe dominant society that makes them vulnerable to being disadvantaged in thedevelopment process. For the purposes of this directive, "indigenous peoples" is the termthat will be used to referto these groups. Indigenous peoples can be identified in particulargeographical areas by the presence in varying degrees of the following characteristics: (a)a close attachment to ancestral territories and to the natural resources in these areas; (b)self-identfication and identification by others as members of a distinct cultural group; (c) anindigenous language, often different from the national language;(d) presence of customarysocial and political insttutions; and (e) primarily subsistence-oriented production.

22. About 1% of the PAHs of MUTP belong to the Scheduled Tribes. A field-based review wasundertaken to determine if these PAHs were subject to application of this Policy since theymight have originally belonged to tribal communities in the distant past. As of now they areintegrated with the city life and do not have their traditional habitat or follow traditional waysof life. More particularly, (a) they no longer have close attachment to ancestral territories;(b) they do not identify themselves or are identified by others as distinct cultural group; (c)they do not speak an indigenous language; and (d) they no longer belong to customarysocial and political institutions. There is also a general reluctance to reveal the caste ortribe particularly pronounced when data is to be kept in public domain. It wasdetermined bythe review that the social impact of the project on such people is therefore similar to thatonother PAHs and thus the policy does not apply. No separate Indigenous PeoplesDevelopment Plan (IPDP) has therefore been prepared.

Other Safeguard Policies

23. World Bank has other safeguard policies dealing with Pest Management, Forestry, Safetyof Dams and Projects in International Waterways or in Disputed Areas These are howevernot applicable to MUTP.

Environmental Audit of Santacruz- Borivali Serene Environmental Services5 h Railway line

ANNEX- 2

SITE PHOTOGRAPHS

Environmental Audit of Santacruz- Borivali Serene Environmental Servicesdh Railway line

F~~~~~~ i * A ~ ~ ~ ~ V

1. The Completed 5 th Line With Boundary Wall And Residential Areas Next To It

2.Sba Exenio WrkAtSataru -BoiaiTck5tLne

o_R~~~~~~~~L -S*

- - ~. -; _~

B- -. X

2. Suwa Exftenion Wor At S'tcu '' oiv' rak(ie

Environmental Audit of Santacruz- Bonvali Serene Environmental Services5h Railway line

+,'~~~~~~~~~~~~~~j

3. Plantation And Fencing At Andheri Station

4 . TeCmlt cgi

/ f /

! * \/.* - f7>4_ > /

4. ~ Th Copee Lin Wit Trc Sid Veea le Plataio

Environmental Audit of Santacruz- Bonivali Serene Environmental Serviceseh Railway line

ANNEX-3

PUBLIC CONSULTATION DETAILS

SUMMARY OF PUBLIC CONSULTATIONS

DATE VENUE TARGET AUDIENCE MEANS OF RECORDSCOMMUNICATION MAINTAINED

During CTS1993 Conference Representatives of the Letters of Invitations List of

Room, govemment along with Executive participants,MMRDA departments, local Summary of draft CTS Minutes of the

authorities, project report. Meetingimplementationagencies, consultants inthe transport

DuringSectoral EAJune 2, 1997 Yashwantrao Representatives of the Letters of Invitations List of

Chavan government along with Executive participants,Centre departments, local Summary of EA report Minutes of the

authorities, project were sent to individuals. Meetingimplementation Telephonic Confirmationsagencies, academia and about individualsthe consultants in the participationtransport andenvironment field.

During R&R1996 to 2002 All Sub-Project Project Affected Personal visits, List of

Sites, Households, Local discussions, Meetings in participants,MMRDA Leaders, etc. MMRDA Photographs,

etc.DuringUpdated EANovember 20, Conference Environmental experts, Letters of Invitations List of2000 Room, Consultants, Academia, along with Executive participants,

MMRDA representatives of Summary of EA report Minutes of thegoverment were sent td individuals. Meetingdepartments, NGOs Telephonic Confirmationsand of project about individualsimplementing agencies participationand the World Bank

December 13, Office of Project Affected Public Notices to leading Public Notices,2000 Divisional Households (PAHs), English and Marathi List of

Engineer, NGOs newspapers, Draft participants,Mankhurd Updated EA report, Minutes of the

Executive Summary made Meeting,available at Public Photographs,Information Centres (PIC), Pamphlets,Pamphlets, Non technical Updated EASummary of EA report in reports,English and Marathi were Executivedistributed to PAHs Summary, Nonthrough NGOs well in Technicaladvance. Summary at PIC

DATE VENUE TARGET AUDIENCE MEANS OF RECORDSCOMMUNICATION MAINTAINED

December 14. Yashwantrao The Cross section of Public Notices to leading List of2000 Chavan Society, NGOs, English and Marathi participants,

Centre Journalists newspapers, Draft Minutes of theUpdated EA report, Meeting,Executive Summary made Photographs,available at Public Pamphlets,Information Centres (PIC), Updated EAPamphlets, Non technical reports,Summary of EA report in ExecutiveEnglish and Marathi were Summary, Nondistributed to participants Technical

Summary at PIC

ConsolidatedEANovember 23, Mumbai Cross section of Public Notices in English, List of2001 Marathi Society, NGOs, Marathi and Hindi to participants,

Patrakar Representatives of the leading English and Minutes of theSangh, CST govemment Marathi newspapers, Meeting,Mumbai departments, local Draft Consolidated EA Photographs,

authorities, project report, Executive Pamphlets,implementation Summary in English and Consolidatedagencies, World Bank Marathi made available at EA reports,academia and the PICs at MMRDA and Executiveconsultants in the Mankhurd well in Summary, Nontransport and advance. Pamphlets each Technicalenvironment field, in English, Hindi and Summary atJoumalists Marathi were distributed PiC. Records of I

amongst the general writtenpublic and in the project comments,affected areas through e.mailenvironmental and social messages etcNGOs. Public Notice and mesges,netExecutive Summary kept maitaiedon MMRDA's web sitewell in advance.

November 24, Goregaonkar Project Affected Public Notices in English, List of2001 English Households (PAHs), Marathi and Hindi to participants,

School, NGOs, Representatives leading English and Minutes of theGoregaon of the project Marathi newspapers, Meeting,(West) implementation Draft Consolidated EA Photographs,Mumbai agencies, World Bank, report, Executive Pamphlets,

Joumalists, etc. Summary and Non ConsolidatedTechnical Summary in EA reports,English and Marathi made Executiveavailable at PICs at Summary, NonMMRDA and Mankhurd Technicalwell in advance. Summary atPamphlets each in PIC. Records ofEnglish, Hindi and Marathi writtenwere distributed amongst comments,the general public and in e.mailthe project affected areas messages, etc

through environmental maintainedand social NGOs. PublicNotice and ExecutiveSummary kept onMMRDA's web site well in

I advance.

Environmental Audit of Santacruz -Borivali Serene Environmental Services5 h Railway line.

ANNEX 4 ENVIRONMENT / HEALTH I SAFETY'INSPECTION SHEET

Nature of Work: Earth working operations / Civil construction (platform extension, bridgeconstruction etc.) / Subways / FBOI other(Tick as applicable)

Location:Contractor Name: SignName of Westem Railway - Site incharge: SignInspected by: . SignReviewed by Dy. Chief Engineer: SignReviewed by Chief Engineer (WR): SignReport to JPD (Env.) - MUTP (MMRDA): Sign

Environment / Health / Safety Elements Compliance Status Comments I Remarksf6r improvement

AIR POLLUTION -

1) Watering of service / Haul roads, earthworking stretch, construction site. No. of times / day:

Source of Water:2) PUC certificate for all construction vehicles

used, avail with contractor Yes No

NOISE -3) All vehicles / DG sets have working silences

Yes No_4) High noise generating operations in NA

residential areas limited to daytime only. (eg.DG sets, drilling, fabrication etc.) Yes No_

NA _WATER POLLUTION -

5) Log book of construction waste generated &disposed available Yes No

NA6) Any signs of contamination of nearby water

bodies due to construction operation. Yes _ NoIf yes, method employed by contractor for its NAcontrol - dyke / embankment etc.

7) Any construction material stored near waterbodies with a possibility of water Yes_ No_contamination NA

ECOLOGICAL ISSUES8) Have any tree > 1 Om girth or sensitive

vegetation such as mangroves cut at Yes No_construction site and stretch NA

9) Copy of NOC from forest Dept. or relevantauthority available at site for the trees to be Yes No_cut. NA

10) Track embankments have been stabilized bysuitable techniques Yes No_

NA

Environmental Audit of Santacruz -Bonvali Serene Environmental Services5 Railway line.

Annex 4 Cont.Environment I Health I Safety Elements Compliance Status Comments I

Remarks forimprovement

LAND POLLUTION / DEGRADATION -

11) Waste Logbook of debris generated and Yes_ Nodisposal available on site. NA

12) Any indication of land contamination by oil Yes Nospills, dumping of garbage etc. on NAconstruction site.

13) Log book of quarry material brought to site, Yes No -quarry location and related receipts of NA_District Collector available on sie

14) Temporary structures, wastes dumps, Yes No -material etc. been cleared adequately after NAcompleton of construction activity

LABOUR CAMP HEALTH AND HYGIENE -

15) Adequate drinking water and toilet facilKies Yes No_in labour camps NA

Are general sanitation conditions Yes Noadequate? NA

TRAFFIC CONTROL & SAFETY

16) Have all safety precaubons been taken as Yes No_per Annex 3 of engineering work permi of NAWestem Railway

17) Copy of endorsed work permit for the Yes No_amount period available at site. NA _

18) Safety and hazard sign boards at critical Yes_ No_locations such as earthworks sites, NAplafform modification, level crossingextension etc. been installed

OCCUPATIONAL HEALTH AND SAFETY-

19) Are Personal protection equipments Yes No(PPEs) such as safety helmets, safety NAshoes, safety belts, safety goggles etcavailable for all workers?

20) Are law related to safe scaffolding, ladder Yes No_working, working on plafforms etc. NA_complied with. (IS codes for safety forvarious equipmenVoperations given inAttachment A)

21) Any unsafe condition observed during Yes Noinspection? NA _

Environmental Audit of Santacruz -Bonvali Serene Environmental Services5e Railway line.

Annex 4 Cont

Environment / Health I Safety Elements Compliance Status Comments I Remarksfor improvement

(22) Is adequate First Aid available at site? Yes No_ _First Aid to consist of antiseptic solution. NA_lAspinn, sterlized gauze, bum ointmentetc. I

(ATTACHMENT A for Annex 4)IS CODES FOR SAFETY

1. Code of practice for pre-stressed concrete IS 1343:19802. Wire Ropes Slings & Sling legs IS 2762:19863. Safety Code of scaffold and ladders IS 3696: 19914. Excavation Work - code of safety IS 3764: 19925. Safety code for blasting and related drilling operations IS 4081: 19866. Stacking and storage of construction materials and IS 4082: 1996

components at site7. Safety code for use of hot bituminous material s IS 5916: 19708. Safety code for working in compressed air IS 4138: 19779. Safety code for tunnelling work IS 4756: 197710. Concrete batching and mixing plant IS 4925: 196811. Ready I Mixed concrete IS 4926: 197612. Safety code for piling and other deep foundations IS 5121: 196913. Safety code for erection of structural steel work IS 7205: 197414. Safety code for working with construction machinery IS 7293: 197415. Wire rope slings - safety criteria and inspection procedure IS 12735: 199416. Code of safety for protective barriers in and around IS 13415: 1992

buildings

17. Industrial safety gloves IS 6994: 197318. Safety helmets IS 2925: 198419. Safety in electric and gas welding IS 818: 196820. Safety procedure in hand operated tools IS 8235: 1976

Environmental Audit of Santacruz -Borivalh Serene Environmental Services5' Railway line.

ANNEX 5 DOCUMENTATION TO BE MAINTAINED BYCONTRACTOR OR RAILWAY SITE ENGINEER ON SITE

1) Road watering daily schedule and source of water in the following format:

Date of Location No. of times Source of waterroad watering waswatering done

2) Daily records of Nature and quantity of waste generated

Type of Waste Date Quantity Disposal Method I(Waste oil, debris, generated (in Kg, Number, LocationmetaVelectric scrap and Truck Loadetc.) etc.)

3) List of trees to be cut or planned to be cut.

Tree Type Number Location

4) Copy of permission for tree felling from Tree officer / Forest Dept.

5) Amount of material taken from quarry, quarry location, copy of permit by District collectoretc.

Type of Quantity Date Quarry Name Copy ofMaterial and Address OfficialBought Royalty paid

Receipt

6) Number of personnel protective equipment (PPE) avail at site (safety helmets, safetybelts, shoes, belts etc.)

7) List of First Aid available at site

8) Log book of fatal accidents on site.

Environmental Audit of Santacruz -Borivali Serene Environmental Services.h Railway line.

ANNEX 6

FORMAT FOR SURVIVAL REPORTING FOR TREE PLANTATION

Date of Survey:Name of Surveyor:

Sr. Location of Tree / Mangrove PlantationNo. Plantation Species Total trees Total %

Planted Planted surviving survival(numbers) (numbers) (%)