entso-e’s “guidelines on dynamics ”. the path towards ... power system analysis tools using...
TRANSCRIPT
ENTSO-E’s “Guidelines on Dynamics Modelling”. The path towards exchange of models between different Power System Analysis tools using Common Information Model (CIM)
1st Wind Integration Symposium:Models of Wind Power Plants and their Use in System Wide Power System Analysis Studies in EuropeFrankfurt, 16-17 June 2011
Chavdar Ivanov, PhD
Research and Development Advisor, ENTSO-E Secretariat
Content
ENTSO-E brief overview
Guidelines on Dynamics Modelling
ENTSO-E and CIM
CIM for Dynamics
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 2 of 29
ENTSO-E is THE European TSO platform
• Founded 19 December 2008 and
fully operational since 1 July 2009
• Represents 41 TSOs from 34
countries
• 532 million citizens served
• 880 GW net generation
• 305,000 Km of transmission lines managed by the TSOs
• 3,200 TWh/year demand
• 380 TWh/year exchanges
• Replaces former TSO organisations:
ATSOI, BALTSO, ETSO, NORDEL,
UCTE, UKTSOA
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 3 of 29
Key activities set out in Regulation 714/2009 (on cross-border electricity
trade, part of the 3rd Internal Energy Market Package)
• Deliver network codes
• Deliver network plans European / regional view of system needs (Ten-Year
Network Development Plan “TYNDP”)
• Deliver crucial aspects of market integration (“market coupling”)
• R&D Plan (fully included in EEGI – European Electricity
Grid Initiative, part of the SET Plan)
Through its members deliver the infrastructure to:
• enable markets to function,
• secure energy supply,
• meet climate change objectives through connecting RES
ENTSO-E has significant role in delivering
European energy and climate change objectives
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 4 of 29
ENTSO-E: Organised to deliver a range of services
1- Research & Development Plan
2- Monitoring and Knowledge Sharing
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 5 of 29
Guidelines on Dynamics Modelling
The work triggered by ENTSO-E System Development
Committee
An internal ENTSO-E document still under development
Part of the document has informational character on stability
phenomena
The document points out the main challenges on dynamics
modelling and studies
The document suggests CIM extensions related to dynamics
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 6 of 29
Guidelines on Dynamics Modelling – main challenges
TSOs need to deal with dynamics problems not only to
ensure feasibility of future investments but also to cope with
requests for extensions of existing synchronous areas
Utilization of a harmonized approach to optimize the
execution of different studies is required
Data exchange format, data exchange platform,
confidentiality
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 7 of 29
From a circular to a linear process: Are we still far from
this change?
Study requirements
Models availability
Data exchange
formatTools
Analyses and results
Models of the
components
(excitation
systems,
wind,
turbines, etc)
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 8 of 29
Linear
process - the
ideal
situation:
more time for
analyses than
preparation
effort
Th
e s
olu
tio
n is p
erh
ap
s i
n b
etw
een
Different needs – different requirements
Pan-European studies
Regional studies
TSO studies
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 9 of 29
Guidelines towards better studies
Clarity on needs; harmonization when possible
Common data exchange format – ENTSO-E Common
Information Model (CIM) Profile
IEC, IEEE Standards
Tools ready to fully support standards
Equipment vendors fully open to provide models for system
studies
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 10 of 29
ENTSO-E and CIM
• ENTSO-E needs and wants to have only one data exchange format
• ENTSO-E decisions towards CIM data exchange
• ENTSO-E organizes yearly Interoperability tests to ensure right and stable development
• The Roadmap for the implementation of next updates of the ENTSO-E CIM Profile avoids frequent changes in the ENTSO-E CIM Profile
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 11 of 29
ENTSO-E CIM/XML Profiles
Current ENTSO-E Profile is the profile tested in UCTE IOP in March 2009 in Paris.
THIS IS THE PROFILE THAT MUST BE IMPLEMENTED BY ENTSO-E MEMBERS.
It is named 1st edition of ENTSO-E CIM Profile
The draft version of the 2nd edition on the ENTSO-E CIM Profile will be tested in July 2011 – under development
Updates of this profile should follow the approved Roadmap
Proposals for changes are welcome and will be discussed within ENTSO-E, IEC and will be tested in the ENTSO-E IOP once agreed among IOP participants.
ENTSO-E CIM/XML Profiles
1st edition of ENTSO-E CIM Profile is published on ENTSO-E web site (CIM part: http://www.entsoe.eu/index.php?id=237)
ENTSO-E Boundary Set is available here: https://www.entsoe.eu/resources/cim/profiles/
A draft version of the 2nd edition of the ENTSO-E CIM/XML profile was developed for the ENTSO-E interoperability test in July 2010. It is also available on the ENTSO-E web site (https://www.entsoe.eu/fileadmin/user_upload/_library/resources/CIM/Interoperability_Tests/ENTSO-E_CIM_Model_Exchange_Profile_v2_draft_7_IOPversion_12July2010.zip)
The profile files for IOP 2011 – new draft of the 2nd edition of the ENTSO-E CIM Profile are available in CIM user group site.
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 13 of 29
IOPs and ENTSO-E CIM/XML Profiles
IOP July 2011, Draft version of the 2nd edition on the ENTSO-E CIM Profile - IEC CIM 15v25 (current version)
IOP July 2010, Draft version of the 2nd edition of the ENTSO-E CIM Profile - IEC CIM 14v15
IOP Dynamic, Nov 2009 – 1st edition on ENTSO-E CIM Profile + dynamics
IEC CIM 14v02
IOP March 2009 - 1st edition of ENTSO-E CIM Profile
IEC CIM 14v02 Migration
Not to be
implemented
Not to be
implemented
Decision expected
in Oct-Nov 2011
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 14 of 29
ENTSO-E exchanges in CIM – migration process to CIM
Two main ENTSO-E processes are subject to CIM migration
System development • Still in migration period.
• First data exchanges in CIM
started in February 2010.
DACF process• The goal is to complete migration stage
by the end of 2011
• First test exchanges started on 8 June
2010 and finished in the end of August
2010
• Now the second stage of tests for DACF
is running. TSOs are exchanging 6 files
per day in CIM (one day in a week) . The
goal is to verify the procedures and test
Communication channels.
• TSOs are building their converters to CIM
(operational systems to CIM)
“Planning exchanges” –
required for TYNDP,
regional initiatives, i.e. EU
3rd Energy Package
Day-Ahead Congestion
Forecast process – stable
exchange needed to
support system operation
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 15 of 29
Roadmap for future implementation of CIM
The aim: to structure the implementation effort. No yearly implementation. An exception could be only if a change is introduced which is critical for ENTSO-E processes
The implementation process is foreseen to last one year.
On regular basis the implementation effort is foreseen every three years, if necessary.
Next versions of the ENTSO-E Profile have to be approved by System Development Committee (SDC). In case of changes that affect operational data, System Operations Committee (SOC) decision is also required.
SDC or SDC&SOC decision ensures one year implementation period. Coming into force date is fixed and mandatory for TSOs
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 16 of 29
Roadmap for future implementation of CIM – example
of implementation
If the updated version of the 2nd ENTSO-E Profile for IOP 2011 is OK:
Approval by SDC and SOC in Oct-Nov 2011
2012 implementation year
Jan 2013 ENTSO-E switches mandatory to 2nd edition of the profile for all exchanges.
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 17 of 29
ENTSO-E IOP Report 2010
Finalized and published in mid August 2010
Available on the ENTSO-E web site:
https://www.entsoe.eu/index.php?id=240
Identified CIM issues were listed in the final report and submitted to
IEC WG13 for further discussion. CIM15 resolves most of the issues
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 18 of 29
ENTSO-E CIM Interoperability Tests – 11 July 2011 (5 days)
Registered vendors BCP Busarello + Cott + Partner AG (NEPLAN)
Open Grid Systems (Cimphony)
Intercompro AG (ISPEN)
TIBCO (IntelliEDGE)
SISCO (UIB Adapter for PI-AF and UIB Core)
Siemens Power Technologies International (PSS/ODMS)
GE Energy (PSLF)
EKC&DMS (Transmission Network Analyzer)
RTE (Convergence)
FGH (INTEGRAL7)
Tractebel and RTE (EUROSTAG)
Ventyx/ABB (Network Manager SCADA/EMS)
CESI (SPIRA; CRESO; SICRE)
EPS (Power System Analyzer, PSA)
PSI AG (PSIcontrol)
DIgSILENT GmbH (PowerFactory 14.1)
EDF R&D (GEDEON Database; CIMclipse; CIM-ENTSO-E Converters)
Alstom Grid (e-terrasource)
GE Energy Services (Enterprise Gateway)
Nexant
In addition to the above vendors, ABB (BMS CIM Explorer) requested to participate in the preparation leading up to the
interoperability test. Zemiren (CimContextor) will participate in the test and will support preparation of profiles to be used
in the test.
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 19 of 29
CIM and ENTSO-E web site (www.entsoe.eu)
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 20 of 29
ENTSO-E CIM in the CIMug web site
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 21 of 29
CIM for Dynamics
• Started as EPRI project: ENTSO-E, General Electric, Siemens, DIgSILENT, Tractebel/RTE, US and Canada utilities
• CIM for Dynamics IOP held in November 2009; Tests repeated in ENTSO-E IOP 2010. IOP 2011 in preparation – no change for dynamics
• EPRI Reference Manual for Exchanging Standard Power System Dynamic Models is available: http://my.epri.com/portal/server.pt?Abstract_id=000000000001020200
• Models integrated in the IEC CIM15. Work in progress to extend the dynamics package
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 22 of 29
CIM exchange and Dynamics
2nd edition of the ENTSO-E CIM Profile – draft version
IEC Standards: 61970-552, 452, 301, 456, (part 457 -
dynamics – under development)
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 23 of 29
CIM for Dynamics – Simple connection; Cross compound
connection possible as well
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 24 of 29
CIM for Dynamics – Example PSS2B model
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 25 of 29
CIM for Dynamics – CIM UML model
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 26 of 29
CIM for Dynamics – CIM UML model
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 27 of 29
CIM for Dynamics – Next steps
• Include additional standard models in the CIM. No complete data exchange is possible without this.
• Update the Standard models reference manual and prepare user-defined models and proprietary models manual. It is needed for proper documentation and IEC standards.
• Include all manuals in IEC standards
• Create a process to update the standards and UML; model repository; gather models from TSOs, manufacturers and harmonise between IEC and IEEE
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 28 of 29
Conclusion remarks
Challenges in dynamics modelling are obvious; complexity increases
with the scale
IEC CIM Standards (and derived CIM Profiles such as ENTSO-E one)
are important for the interoperability and ensure smooth data exchange
Vendors and manufactures involvement as well as utility involvement is
very important to keep models up to date covering various needs
Standard models/user-defined models/proprietary model exchange
allows flexible exchange between parties keeping confidentiality as
agreed
Vendors’ commitment is very important to have IEC CIM standards
implemented as soon as possible.
ENTSO-E and CIM | Chavdar Ivanov | 16 June 2011 | Page 29 of 29