entergy transmission planning summit new orleans, la july 29, 2008

14
1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

Upload: darcie

Post on 19-Jan-2016

43 views

Category:

Documents


0 download

DESCRIPTION

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects. Entergy Transmission Planning Summit New Orleans, LA July 29, 2008. ELL-South/ENOI Transmission Reliability Projects. Loblolly-Hammond: Build 230kV line. DSG: Phase III ( Postponed ). - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

1

Entergy Louisiana, LLC (South) &

Entergy New Orleans, Inc.

Proposed TransmissionReliability Projects

Entergy Transmission Planning Summit

New Orleans, LA

July 29, 2008

Page 2: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

2

ELL-South/ENOITransmission Reliability Projects

DSG: Phase III (Postponed)

Improve ASI Capability:Phase II- Panama-Dutch Bayou Phase III- Coly-Vignes Conway-Bagatelle

ELL-South

Loblolly-Hammond:Build 230kV line

SELA Phase #2Peters Rd-Oakville :

Build 230kV line & Station

SELA Phase #3Oakville-Alliance:

Build 230kV line & Auto

Houma:Install Cap Bank

Paterson:• Restore 4 breakers

Page 3: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

3

Paterson:Restore 4 Breakers

Scenario:• Paterson substation was flooded during Hurricane Katrina resulting in all major

transmission equipment being damaged. Prior to Katrina, Paterson 115kV bus terminated four 115kv transmission lines and operated as a hub for the transmission system in the New Orleans area. Presently, the Paterson 115kV bus has been temporarily restored to operate in a split, east / west bus configuration. The east bus is in series with the Chalmette 115kV and the Sherwood Forest 115kV substations.

• The west bus is in series with the Claiborne 115kV and the Pontchartrain Park 115kV substations. Various single contingencies in the New Orleans area now could result in overloads on portions of this west bus circuit.

Recommended Solution: • Re-build the Paterson 115kV substation to terminate four 115kV transmission lines

from Pontchartrain Park, Sherwood Forest, Chalmette and Claiborne. The bus configuration should be configured in a double bus with shared breaker configuration (breaker and a 1/2). This arrangement will allow for station expansion, including power transformer additions and potentially the addition of a 230/115kV auto transformer as system conditions dictate.

• Proposed In-Service Date: 2008

• Estimated Cost: $3 MM

ENOI

Page 4: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

4

Paterson: Restore 4 Circuit Breakers

Restore Breakers

Page 5: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

5

Houma:Install Capacitor Bank

Scenario:• This project was identified as required as part of a transmission service

request

Recommended Solution: • Install a 40MVAr capacitor bank at Houma 115kV substation.• Proposed In-Service Date: 2008

Estimated Cost: $850 k

ELL-South

Page 6: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

6

Houma:Install Capacitor Bank

Install Cap Bank

Page 7: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

7

Loblolly-Hammond:Construct 230 kV Substation and Line

Scenario:• Entergy’s transmission system north of Lake Pontchartrain is primarily

supported from the ELL 230kV system between Willow Glen and Waterford. – Loss of the Franklin-McKnight 500kV line, or certain other transmission

contingencies, result in overloads to occur on the underlying transmission system, primarily on the Gypsy-Madisonville 230kV line.

– Adding another 230kV source from a location north of Willow Glen reduces loading on the existing system and improves load serving capability north of Lake Pontchartrain and into south Mississippi.

Recommended Solution: • Construct 230 kV line from Loblolly to Hammond using existing Coly–

Hammond 69 kV line (constructed for 230kV). • Proposed In-Service Date: 2012

Estimated Cost: $75 MM

ELL-South

Page 8: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

8

McKnight

ToFranklin

To SOCO’sPlant Daniel

To Coly

To FancyPoint

Loblolly

Loblolly-Hammond: Build 230 kV Line

Construct new 230kV line

ELL-South / EGSI-LA

Coly

Page 9: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

9

Scenario:• When generation in the Amite South area is low, loss of the Waterford–Willow

Glen 500 kV line is the most severe contingency that establishes the Amite South Import (ASI) capability.

• The ASI capability improved to approximately 2,450 MW upon completion of Phase 1 of the ASI Improvement Plan (Conway-Panama) in 2005.

• Phase 2 (Panama-Dutch Bayou) and Phase 3 (Coly-Vignes, Conway-Bagatelle) were expected to provide economic benefits and were to be completed by 2007 prior to Hurricane Katrina.

• Post Hurricane Katrina and the subsequent loss of load within southeast LA, Phases 2 and 3 were determined to be needed for reliability by 2015 or by 2010 for economics.

• Based on the 2006 Transmission Study, Entergy determined that accelerating Phases 2 & 3 could yield economic benefits sufficient enough to advance the in-service dates to earlier than 2010.

Recommended Solution:• Construction of Phases 2 & 3. • Proposed In-Service Date: 2009 (Phases 2 & 3)

Estimated Project Costs:• Phase 2: $38 MM• Phase 3: $20 MM

ASI Improvement Plan - Phases 2 & 3

ELL-South / EGSI-LA

Page 10: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

10

Panama

ELL-South

ASI Improvement Plan - Phase 2

Build 230kV

line

Page 11: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

11

Coly

Vignes

Panama

ELL-South / EGSI-LA

ASI Improvement Plan - Phase 3

Upgrade 230kV line

Upgrade 230kV line

Page 12: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

12

Scenario: • The primary transmission sources to lower Lafourche, Lower Jefferson, and

Plaquemines Parishes are the Ninemile and Valentine substations. Although lower Plaquemines Parish experienced heavy damage during Hurricane Katrina, it is expected that oil refining and pumping facilities in the area will be restored.

• Additionally, upper Plaquemines Parish, including Belle Chasse and the Naval Air Support facility, is experiencing growth.

• For the contingency loss of the Ninemile-Barataria 115kV or the Valentine-Clovelly 115kV lines, potential low voltages and line overloads exists.

Recommended Solution:• Peters Road-Oakville 230kV

– Build a new 230kV substation at Oakville and a new radial 230kV line from Peters Road to Oakville Substation.

– Proposed In-Service Date: 2010– Estimated Cost: $21.3 MM

• Oakville-Alliance 230 kV– Construct a new 230kV transmission line from Oakville substation to Alliance

substation. Add a 150MVA 230/115kV auto at Alliance substation. This project also provides support for the Fourchon area.

– Proposed In-Service Date: 2010– Estimated Cost: $35 MM

Southeast Louisiana Coastal Improvement Plan:Construct New Peters Road-Oakville-Alliance 230 kV Line

ELL-South

Page 13: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

13 ELL-South

Peters Road-Oakville 230kV: Build new line and substation Oakville-Alliance 230 kV: Build new line

Build 230kV Line & Auto

Peters Rd.Oakville

Build 230kV Line & Auto

Build 230kV

Line & Sub

Page 14: Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

14

ELL-South and ENOI Identified Target Areas Beyond 2011

Paterson:Install 230/115kV auto

Belle Point – Little Gypsy:Reconductor 230kV Line

DSG: Phase III

Napoleonville – Add capacitor bank