engineering& consulting ltd. com. · 2019-07-23 · since its foundation in 1987, piramit...

32
PİRAMİT ENGINEERING& CONSULTING LTD. COM.

Upload: others

Post on 03-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

PİRAMİT ENGINEERING& CONSULTING

LTD. COM.

Page 2: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing

engineering and consultancy services in various fields:

• Infrastructure

- Water supply and Distribution Network

- Sewerage System

- Wastewater Treatment Plant (WWTP)

- Deep Sea Disposal

- Stormwater Drainage

- Solid waste and storage

- Natural Gas

• Building

- Hotel

- Residence

- Mass Housing

• Industrial Plant

• Bridge and Roads

• Map and Expropriation

• Landscaping

• Geotechnical Surveys

PIRAMIT ENG. CONS. LTD. COM.

Page 3: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

ORGANIZATION CHART

General Manager

Structure

Business Development& Tender Manager

Administration & Finance ManagerTechnical Manager

Legal Adviser

Road Sewerage Drinking Water

ProcurementPersonalAccounting

Geology/ Geotechnical

Mapping City Planning

Waste Water Deep Sea Dispo. Solid Waste

Technical Support Group

ITCAD OperatorsTechniciansEngineers Secretary

CONSULTINGENGINEERING

Page 4: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Key personnel list:

Name Occupation Position Education

Adnan Bilgin Civil Engineer General Manager B.S., METU, 1986

Murat Bilge Civil Engineer Technical Manager B.S., METU, 1986

M.S., METU, 1988

Mevlüt Genç Aytekin Civil Engineer Civil Engineer B.S., Yıldız Tek. Ün.1974

İlker Bilgin Civil Engineer Civil Engineer B.S., METU, 2011

Sait Cetin Environmental Engineer Treatment Plant & Solid Waste Expert 19 Mayıs, 1989

Fahrettin Üstün Mechanical Engineer Mechanical Engineer B.S., ADMMA, 1981

Mehmet Uyanık Mechanical Engineer Mechanical Engineer B.S., KTÜ, 2003

Selçuk Çayırezmez Mechanical Engineer Design Engineer ( Natural Gas) B.S., KTU, 1997

Vedat Göktürk Survey Engineer Survey Engineer B.S.,Selçuk Ün, 1987

Emre Şirazi Survey Engineer Survey Engineer B.S., 19 Mayıs Ün., 2009

Mustafa Yıldız Electrical Engineer Electrical Engineer B.S., ADMMA, 1979

Tanju Ökten Geological Engineer Geological Engineer B.S., Ege Un., 1982

Ünal Hügül Architect Architect B.S., ITU, 1959

PIRAMIT ENG. CONS. LTD. COM.

Page 5: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Total Number of Personal:

Civil Engineer 4

Mechanical Engineer 3

Environmental Engineer 1

Survey Engineer 2

Electrical Engineer 1

Geology Engineer 1

Architect 1

CAD Operator 4

Other personal 4

T O T A L 21

Page 6: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Piramit is providing service for var ious government associat ion and pr ivate organizat ions:

1 STATE WATER WORKS (DSİ)

2 ILLER BANK (ILLER BANKASI)

3 MINISTRY OF FORESTRY AND WATER WORKS DEPARTMENT OF EUROPEAN UNION INVESTMENTS ( ORMAN VE SU İŞLERİ BAKANLIĞI AB YATIRIM DAİRESİ BAŞKANLIĞI)

4 THE MINISTRY OF SCIENCE, INDUSTRY AND TECHNOLOGY (BİLİM, SANAYİ VE TEKNOLOJİ BAKANLIĞI)

5 MINISTRY OF ENVIRONMENT AND URBAN PLANNING (ÇEVRE VE ŞEHİRCİLİK BAKANLIĞI)

6 GENERAL DIRECTORATE OF HIGHWAYS (TCK)

7 SOUTHEASTERN ANATOLIA PROJECT REGIONAL DEVELOPMENT ADMINISTRATION (BAŞBAKANLIK GAP İDARESİ BAŞKANLIĞI)

8 HOUSING DEVELOPMENT ADMINISTRATION (TOKI)

9 MUNICIPALITIES

10

ANKARA WATER SEWERAGE ADMINISTRATION (ASKİ), ISTANBUL WATER SEWERAGE ADMINISTRATION (İSKİ), IZMIR WATER SEWERAGE ADMINISTRATION (İZSU), SAMSUN WATER SEWERAGE ADMINISTRATION (SASKİ)

11 HOLDİNG COMPANIES (GAMA, TEPE, GÜNTEKİN, ORYATAŞ, AKTÜRK, ALARKO, BAYINDIR, CEYLAN)

PIRAMIT ENG. CONS. LTD. COM.

Page 7: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

INTERNATIONAL PROJECTS

PIRAMIT ENG. CONS. LTD. COM.

Page 8: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Ref - No: Int - 06 Project Title: ELBISTAN DRINKING WATER PROJECT

Country

Overall project Value

(EUR)

Proportion carried by

Piramit (%)

Number of staff provided

Name of the client Dates (start-end)

Name of Partners

if any

Turkey 362.000 50% 4 ELBİSTAN BELEDİYESİ/ILLER BANKASI

2008 - ongoing

ILF Engineers (Austria)

DETAILED DESCRIPTION OF DESIGN TYPE OF SERVICES PROVIDED

▪ Consultancy Service for Drinking Water pipeline, Pump stations, storage etc. Project has been financed

by World Bank. ▪ General Consultancy and Project Management

▪ Tender Document Preperation - Detailed BOQ ▪ Project Characteristics: - Cost Estimation

- Pipeline network: 90 km - PUmp stations: 2 nos

▪ Pump line: 5 km

▪ Storage Tank capacity: 4000,1000,300 m3

▪ Construction Cost: 4.100.000 EUR

PiRAMiT

Page 9: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Ref - No: Int - 05 Project Title: ADEN (YEMEN) FREEZONE INFRASTRUCTURE PROJECT

Country

Overall project Value (EUR)

Proportion carried by

Piramit (%)

Number of staff provided

Name of the client Dates (start-end)

Name of Partners

if any

YEMEN 215.000 50% 12 ADEN FREEZONE DIRECTORATE 2006-2007 -

DETAILED DESCRIPTION OF DESIGN TYPE OF SERVICES PROVIDED ▪ Design of infrastructures; Drinking Water, Sewerage, stormwater, Road, Electrical,

Telecominication, Surveying, Geotechnical Report, ▪ Design and Project

▪ Tender Document Preperation ▪ - Detailed BOQ ▪ Project Characteristics: - Cost Estimation - Area: 400 ha - Natural Gas Pipeline Length: 23 Km ▪ Site visit and consultancy service at critical stages.

▪ Construction Cost: 2.650.000 EUR

PiRAMiT

PRIVATEAREA

PRIVATEAREA

IAIA1

ELECTRONICS AND ELECTRICAL EQUIPMENTS, WOODEN AND METALLIC INDUSTRIES GROUP

IA2 FOOD, READY MADE CLOTHES, TRICOTPRINTING AND PUBLISHING GROUP

IA3 BUILDING MATERIALS, LABORATORIES ANDWORKSHOPS GROUP

IIAIIA1

PAPER, LEATHER AND TEXTILE INDUSTRIESGROUP

IIA2 BUILDING MATERIALS, LABORATORIES ANDWORKSHOPS GROUP

IIA3 FOOD, READY MADE CLOTHES, TRICOTPRINTING AND PUBLISHING GROUP

IIIAIIIA1 PLASTIC AND CHEMICAL INDUSTRIES GROUP

IIIA2PAPER, LEATHER AND TEXTILE INDUSTRIESGROUP

SUB REGION

A LIGHT INDUSTRY AREAS B WARE HOUSES

D1ADMINISTRATION AND INFORMATION

B2 VENTILATED STORAGE

B3 COLD STORAGE

C COMMERCIAL AND PUBLICSERVICES

D UTILITIES FACILITIES AREAS

CENTER

D2 BANKS AND COMPANIES COMPLEX

D3CUSTOM AREA, POLICE STATION, POSTOFFICE AND TELECOMMUNICATION MOSQUEAND MEDICAL CENTER

B1 DRY STORAGE

D4 ELECTRICAL TRANSFORMING STATION

D5 WATER SANITISATION STATION AND WATERSTORAGE TANKS

D6 WALLS AND WATCHING TOWERSSUB REGION

SUB REGION

B4 WAREHOUSES

PRIVATEAREA

(MENHOLE NUMBER)

(LENGTH) (SLOPE)

PUMP LINE

PUMP STATION

PRIVATEAREA

PRIVATEAREA

IIIA

PRIVATEAREA

Administration Area

IIIA1

IIIA2

IIAIIA1IIA2 IIA3

B3

B1

B2

IA

D1

D3

D - 4

D - 5

D2

IA1

IA2

IA3

D 6

A

A

B

B4

CALTEXISLAND

A

C

C

C

D

G

SEA SHORE

SEA SHORE (NATURAL PRESERVATION AREA)

YATCH HARBOUR

Tele

-Com

.Cen

tral

Bui

ldin

g

Surrounded Area (Fence)

Surrounded Area (Fence)

...... Ø1/....

............

(..........)

L=.....

(GROUND LEVEL)(INVERT LEVEL) (DIAMETER) (INVERT LEVEL)

STRET LINE (CONCRETE PIPE)

PARCELS CONNECTION (PVC PIPE)

DROPPED MANHOLE

EXISTING LINE

INSPECTION CHAMBER

Quç.......... INFLOW

(NATURAL PRESERVATION AREA)

TECHNICALINFRASTRUCTURE

AREA

POWERSTATION

TECHNICALINFRASTRUCTURE

AREA

TECHNICALINFRASTRUCTURE

AREA

PIRAMIT ENG. CONS. LTD. COM.

Page 10: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Ref - No: Int - 04 Project Title: SANAA NORTHERN REGION STORMWATER PROJECT

Country

Overall project Value (EUR)

Proportion carried by

Piramit (%)

Number of staff provided

Name of the client Dates (start-end)

Name of Partners

if any

Yemen 180.000 50% 10 Sanaa Municipality 2005-2006 -

DETAILED DESCRIPTION OF DESIGN TYPE OF SERVICES PROVIDED

▪ Design of infrastructures; stormwater, Road, Surveying, Geotechnical Report ▪ Design and Project ▪ Tender Document Preperation ▪ - Detailed BOQ ▪ Project Characteristics: - Cost Estimation - Area: ▪ Site visit and consultancy service at critical stages.

PiRAMiT

PIRAMIT ENG. CONS. LTD. COM.

Page 11: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Ref - No: Int - 03 Project Title: SAMARA MASS HOUSING INFRASTRUCTURE PROJECTS

Country

Overall project Value (EUR)

Proportion carried by

Piramit (%)

Number of staff provided

Name of the client Dates (start-end)

Name of Partners

if any

Russia 80.000 100% 10 TEKFEN CONSTRUCTION 2003 - 2004 -

DETAILED DESCRIPTION OF DESIGN TYPE OF SERVICES PROVIDED

▪ Design of infrastructures; Natural Gas pipeline, Drinking Water, Sewerage,

stormwater, Road, Electrical, Surveying, Geotechnical Report ▪ Design and Project

▪ Tender Document Preperation - Detailed BOQ ▪ Project Characteristics: - Cost Estimation - Area: ▪ Site visit and consultancy service at the end of construction

PiRAMiT

PIRAMIT ENG. CONS. LTD. COM.

Page 12: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Ref - No: Int - 02 Project Title: Turkmenbashi Rafinary Lub Oil Plants

Country

Overall project value (EUR)

Proportion carried by

Piramit (%)

Number of staff provided

Name of the client Dates (start-end)

Name of partners

if any

Turkmenistan 119.500 100% 12 GAMA Endüstri Tes. İml. Ve Montaj Inc. 2000- 2001 -

DETAILED DESCRIPTION OF DESIGN TYPE OF SERVICES PROVIDED

▪ Preparation of Architectural, Civil, Infrastructure Projects and Consultancy services for Main Building, Administrating Building, Canopy,Transformer Building, Laboratory, Workshop, Control Building and Truck Loding Station, Tank Foundadion, Piping and Cable Supporting Structures

▪ Design and Project

▪ Site visit and consultancy service on constructor request

PiRAMiT

PIRAMIT ENG. CONS. LTD. COM.

Page 13: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Ref - No: Int - 01 Project Title: Kremenchuk Hospital and Cafeteria

Country

Overall project value (EUR)

Proportion carried by

Piramit (%)

Number of staff

provided Name of the client Dates (start-end)

Name of partners

if any

Russia (Ukraine) 50.000 100% 12 TEPE Wood, Metal and

Construction Int. Inc. 1991- 1992 -

DETAILED DESCRIPTION OF DESIGN TYPE OF SERVICES PROVIDED

▪ Design of Hospital and Cafeteria Building. Design of all infrastructure (road-sewerage-stormwater and drinking water) Preparation of calculations, method statements and projects.

▪ Design and Project

▪ Tender Document Preparation - Detailed BOQ

- Cost Estimation ▪ Site visit and consultancy service on constructor request

PiRAMiT

PIRAMIT ENG. CONS. LTD. COM.

Page 14: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

LIST OF PROJECTS

Page 15: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

1 - Infrastructure

• Water Supply and Distribution Network

• Sewerage

• WWTP

• Drinking Water TP

• Deep Sea Disposal

• Stormwater

• Solid Waste Disposal

• Natural Gas

pp ii rr a m i t m ü h

PIRAMIT ENG. CONS. LTD. COM.

Page 16: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

1- INFRASTRUCTURE

WATER SUPPLY & DISTRIBUTION NETWORKS

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Technical Assistance and Supervision for Nizip Water and Wastewater Project

Department of Europen Union Investments Apr - 13 On going

Giresun Drinking Water Project Construction DSİ Oct-12 On going

Saray Ayvacik Pond Construction Project DSİ Feb-12 On going

Cizre Drinking Water Project Construction DSİ Feb-12 On going

Ergani Drinking Water Project Construction DSİ Dec-10 Oct - 13

Kulp Drinking Water Project Construction DSİ Dec-10 Oct - 13

Sivas - Erzincan irrigation Project UNDP United Nations Nov-10 May-11

Adjacent Area North Towns and Villages of Ankara Metropolitan Municipality Neighborhood Network, Transmission Line, Reservoir, Pump Station, Construction of Drinking Water Facilities Project

ASKİ Aug-10 Mar-12

Construction of Potable Water Transmission Line Project Corum I.Stage Koçhisar Dam DSİ Apr-10 Sept –

13 Çankırı Drinking Water Project 3rd Part Transmission Line Storage and SACADA Construction Projects

State Water Works (DSI) Aug-09 Nov-09

Bodrum (Muğla) Peninsula Drinking Water Transmission Line Revision Projects " Dec-08 Apr-10

Consultancy services (ILF-Piramit JV) for Elbistan Drinking Water Project Iller Bank/ World Bank Apr-08 Jan-10

Anamur (Mersin) Iller Bank Apr – 07 Jun-08

Hereke World Bank Housing Prime Ministry PIU , Garanti Balfour Beaty Construction Jan-01 Aug-01

Düzce Disaster Victim Settlement Invesco / The Ministry of Public Work and Settlement/ Iller Bank Oct-00 Apr-01

Bolu Disaster Victim Settlement " Jun-00 Apr-01

Kumburgaz - Selimpaşa Oryataş İnşaat Jun-00 Oct-00

Seydiler (Kastamonu) Iller Bank Mar-99 Nov-99

Yıldızeli (Sivas) " Sep-98 Oct-99

Kavaklıdere (Muğla) İKA Altyapı / Iller Bank Mar-98 Nov-98

Bahçeşehir 2nd Etape Housing Emlak Bank Dec-97 Jun-99

Mavişehir 3.Etape Emlak Bank / Ceylan İnşaat Nov-97 Oct-98

Silivri Municipality Iller Bank Sep-97 Nov-98

Yozgat KSS Ministry of Science, Industry and Technology Nov-96 Mar-97

Ankara City (various) ASKİ / İKA Altyapı Jun-96 Jun-97

Bizimkent Housing Emlak Bank/Ceylan İnşaat May-95 Jun-95

Aratol (Aksaray) Iller Bank May-95 Dec-95

PIRAMIT ENG. CONS. LTD. COM.

Page 17: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Eraslan (Amasya) " May-95 Apr-96

Sancaklı Bozköy (Manisa) " Apr-95 Oct-95

Mavişehir 2.Etape Emlak Bank / Ceylan İnşaat Mar-95 May-96

Mavişehir 1.Etape " Jun-94 May-95

Yeşilova (Aksaray) İKA Altyapı / Iller Bank Feb-94 Apr-94

Şarköy (Tekirdağ) " Feb-94 May-94

Armutalan (Muğla) Iller Bank Jun-93 Jan-94

Senirkent (Isparta) " Jun-93 Apr-94

Çamlıyayla (İçel) " May-93 Jun-94

Kuyuluk (İçel) " Mar-93 Dec-93

Bilkent 2 Housing Emlak Bank/Tepe İnşaat Aug-92 Jan-93

Bilkent Plaza " May-92 Dec-92

Beylikova (Eskişehir) Iller Bank Dec-91 Aug-92

Bilkent 1 Housing Emlak Bank/Tepe İnşaat Aug-91 Oct-91

SEWERAGE

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Sivrihisar Sivrihisar Municipality July-13 Sept-13

Tekmen (Mersin) Iller Bank Jun-11 Feb-14

Karaağaç (Balıkesir) " Feb-11 Mar-12

Beypazarı (Ankara) " Jan-11 Mar-12

Kumbağ (Tekirdağ) " Dec-10 Nov-11

Ahmetbey (Kırklareli) – Sağlamtaş (Tekirdağ) " Apr-10 Oct-11

Kavaklı (Kırklareli) " Mart-10 Apr-10

Bekirpaşa Adapazarı Metropolitan Municipality Mar-08 Apr-11

Kazımpaşa " Mar-08 Dec-10

Gücücek " Mar-08 Dec-10

Mahmudiye " Mar-08 Dec-10

Yanık " Mar-08 Dec-10

Çaybaşı " Mar-08 Dec-10

Yeşilyurt " Mar-08 Dec-10

Nehirkent " Mar-08 Dec-10

Hereke World Bank Housing Prime Ministry PIU , Garanti Balfour Beaty Construction Jan-01 Dec-10

Kargıpınarı (İçel) 110 km Iller Bank Oct-00 Aug-01

Arpaçbahşiş (İçel) 80 km " Oct-00 Sep-01

Tömük (İçel) 100 km " Oct-00 Jun-01

PIRAMIT ENG. CONS. LTD. COM.

Page 18: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Düzce Disaster Victim Settlement Invesco / The Ministry of Public Work and Settlement/ Iller Bank Oct-00 Aug-01

Bolu Disaster Victim Settlement " Jun-00 Apr-01

Sakarya III Organized Industry Region Ministry of Science, Industry and Technology Mar-00 Apr-01

Akşehir Organized Industry Region " Nov-99 Jun-00

Sakarya II. Organized Industry Region " Dec-98 Jun-00

Karataş (Adana) 400 km İller Bank Oct-98 Dec-99

Mavişehir 3.Etape Emlak Bank / Ceylan İnşaat Nov-97 Nov-00

Sivas Organized Industry Region Ministry of Science, Industry and Technology Sep-97 Oct-98

Besni (Adıyaman) GAP, Southeastern Anatolia

Project Regional Development Administration

Jan-97 Sep-98

Kayseri (İncesu) Organized Industry Region Ministry of Science, Industry and Technology Nov-96 Oct-01

Yavuzeli (Gaziantep) GAP, Southeastern Anatolia

Project Regional Development Administration

Nov-96 Nov-99

Osmaniye Organized Industry Region Ministry of Science, Industry and Technology Mar-96 Nov-99

Adıyaman Organized Industry Region " Jul-95 Jan-98

Bandırma Organized Industry Region " Jun-95 Nov-98

Bizimkent Housing Emlak Bank/Ceylan İnşaat May-95 Nov-97

Mavişehir 2.Etape " Mar-95 Jun-95

Mavişehir 1.Etape " Jun-94 May-96

Uşak Deri Organized Industry Region Ministry of Science, Industry and Technology Feb-94 May-95

Kahramanmaraş Organized Industry Region " Dec-93 Feb-95

Karlıova (Bingöl) (150 km) İller Bank Sep-93 Sep-94

Nazimiye (Tunceli) (70 km) " Sep-93 Apr-94

Bilkent 2 Housing Emlak Bank/Tepe İnşaat Aug-92 Apr-94

Bilkent Plaza " May-92 Jan-93

Bilkent 1 Housing " Aug-91 Dec-92

Elvankent KonutlarıI Emlak Bank/Ceylan İnşaat Aug-91 Oct-91

Saraykent (Yozgat) ( 200 km.) İller Bank May-91 Dec-91

PIRAMIT ENG. CONS. LTD. COM.

Page 19: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

WASTE WATER TREATMENT PLANTS (WWTP)

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Sivrihisar (Eskişehir) Serinhisar Municipality July – 13 Oct – 13

Tomarza (Kayseri) Iller Bank Dec – 13 Apr 14

Karamürsel, Körfez, Kullar, Yeniköy ve 42 Evler Kocaeli İSU Oct-12 On going

Kırklareli – Merkez DSİ Oct-11 Sept-12

Edirne – Uzunköprü DSİ Oct-11 Aug-12

Çobanlar – Işıklar – Sülümenli – Kocaöz (Afyonkarahisar) Iller Bank Oct-11 Aur- 13

Ortaköy (Aksaray) “ Oct-11 Aug – 13

Sazlı (Aydın) “ Dec-10 July-12

Özalp (Van) “ Apr-10 May – 13

Atasu (Trabzon) Dam WWTP and Sewerage Line Project State Water Works (DSI) Dec-09 May-11

Çakmak (SAMSUN) Dam WWTP Engineering Services SASKİ Dec-09 Mar-10

19 Mayıs (SAMSUN) Iller Bank Jun-09 July-11

Biga (ÇANAKKALE) “ Jun-09 Dec-10

Serinhisar (Denizli) " Jul-07 Jan-09

Tatvan (Bitlis) " Sep-06 Dec-07

Okurcalar (Antalya) Turkish Development Bank Jul-05 Apr-06

Kepez (Çanakkale) Iller Bank May-04 Dec-04

İzogün İzalasyon İzogün İzalasyon Nov-99 Apr-00

SAKARYA II. Organized Industry Region Ministry of Science, Industry and Technology Dec-98 Dec-99

HE-CE İnşaat HE-CE İnşaat May-98 Nov-98

Akçaabat (Trabzon) Güntekin İnşaat / İller Bank Feb-97 Apr-97

Besni (Adıyaman) GAP, Southeastern Anatolia

Project Regional Development Administration

Jan-97 Oct-01

Yavuzeli (Gaziantep) " Nov-96 Nov-99

Ortaç Boya Ortaç Boya Jan-95 Jun-95

S.S. Gökçekent Housing Cooperative S.S. Gökçekent Housing Cooperative Dec-94 Feb-95

Uşak Deri Organized Industry Region (2570 decar)

Ministry of Science, Industry and Technology Feb-94 Jun-95

PIRAMIT ENG. CONS. LTD. COM.

Page 20: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

DEEP SEA DISPOSAL

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Rize 3. (Merkez) Iller Bank Apr 14 On going

Rize (Merkez) “ Sep-11 Feb-12

Kemalpaşa (Artvin) “ Sep-11 Dec-12

Amasra (Bartın) “ May-11 Apr-12

Beşikdüzü (Trabzon) “ Nov-10 Feb-12

19 Mayıs (Samsun) “ Aug-10 July-11

Bulancak (Giresun) “ Jul-07 Jul-08

Okurcalar (Antalya) Turkish Development Bank Aug-05 Apr-06

Sürmene (Trabzon) Iller Bank May-05 Jul-06

Of (Trabzon) " May-04 Nov-04

Mapping, City Planning and All Infrastructure Projects (Drinking Water, Sewerage, Stormwater,Road, Natural Gas, Electricity and

Telecommunication)

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Milas Organized Industry Region (135 ha) Ministry of Science, Industry and Technology Jun-14 On going

Adıyaman Organized Industry Region (200 ha) “ Jun-14 On going

Alaplı Organized Industry Region (100 ha) “ Oct -13 On going

Boyabat Organized Industry Region (100 ha) “ July-13 Jan 14

Şanlıurfa Organized Industry Region (150 ha) Bilim Sanayi ve Teknoloji Bakanlığı Haz.13 Mart 14

Irak Al – Tuz City İntaş Co. July 12 Mar 14

Gerede leather Organized Industry Region (150 ha) “ Jun-10 Sept 12

Konya Organized Industry Region (400 ha) “ Sep-09 Dec 11

Anadolu Organized Industry Region (400 ha) " Mar-08 Sep-09

Kemalpaşa İzmir Organized Industry Region (1300 ha) " Mar-05 Dec-09

PIRAMIT ENG. CONS. LTD. COM.

Page 21: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Osmaneli Bilecik Organized Industry Region (60 ha) " May-07 Sep-09

Bozüyük Organized Industry Region (600 ha) " Aug-06 Jul-07

Kırklareli Organized Industry Region (300 ha) " Apr-05 Jun-06

Sakarya 3. Organized Industry Region (240 ha.) " Mar-00 Jun-00

Akşehir Organized Industry Region (240 ha.) " Nov-99 Jun-00

Sakarya 2 Organized Industry Region (320 ha.) " Dec-98 Dec-99

Sivas OSB (100 ha. additional ) " Sep-97 Sep-98

Kayseri 2. Organized Industry Region (600 ha.) " Nov-96 Nov-99

Osmaniye 1-2-3 Stages Organized Industry Region (400 ha.) " Mar-96 Jan-98

Adıyaman Organized Industry Region (150 ha.) " Jul-95 Nov-98

Bandırma Organized Industry Region (150 ha.) " Jun-95 Nov-97

Uşak Organized Industry Region (310 ha.) " Feb-94 Feb-95

Ardeşen Small Industry Site " Feb-94 Aug-94

Kahramanmaraş Organized Industry Region (286 ha.) " Dec-93 Sep-94

STORMWATER DRAINAGE

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Kutlukent River Improvement Project SASKİ Dec-09 Nov-10 Sabanoglu Kirazlık and Rivers Improvement Project “ Dec-09 Nov-10

Kurupelit River Improvement Project “ Dec-09 Nov-10

Hasköy Stream Improvement and Arrangement Project “ Dec-09 Nov-10

Infrastructure projects in 48 different locations State Railways - 2nd District Diractorate

Aralık 08 Nov-10

SOLID WASTE DISPOSAL

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Solid Waste Association of Troas Solid (Çanakkale) Waste Storage Plant Design Project Iller Bank Sept-14 On going

Ortaca (Muğla) Solid Waste Storage Plant Design Project The Ministry of Environment Sept-10 Nov-10

Foça (İzmir) Solid Waste Storage Plant Design Project The Ministry of Environment Aug-09 Dec-09

Beypazarı (Ankara) Solid Waste Storage Plant Design Project Iller Bank Apr-08 May-09

PIRAMIT ENG. CONS. LTD. COM.

Page 22: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

2 - Structure

• Hotel • Mass Housing • Gymnasium • School • Hangar and Depot

3 – Industrial Building

Refinery Steel Silo

pp ii rr a m i t m ü ü h

PIRAMIT ENG. CONS. LTD. COM.

Page 23: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

2- STRUCTURE

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Type 12.6 Terminal Building Static and RC Projects Iller Bank Apr-00 Oct-00

Dinar (Afyon) Fire Brigade Building RC and Mechanical Projects " Mar-99 Nov-99

Type 05.16 Municipaility Building Static and RC Projects " Apr-95 Oct-95

Type 05.12/1 Municipaility Building Static and RC Projects " May-95 Dec-95

Type 05.31Municipaility Building Static and RC Projects " Jun-93 Jan-94

Type 05.16/1 Municipaility Building Static and RC Projects " Mar-93 Dec-93

Type 05.12/2 Municipaility Building Static and RC Projects " Jun-93 Apr-94

Type 05.12/1, 05.12/2, 05.16/1, 05.31Municipaility Building Static and RC Projects " Apr-00 Oct-00

Mamak Municipality Service Buildings; (30000 m2) RC and Mechanical Projects " Oct-95 Nov-96

Gökçekent construction cooperative- architectural, RC project and calculations

S.S. Gökçekent Housing

Coorperative Nov-96 Nov-98

Elvankent Retaining Wall Projects Ceylan İnşaat / Emlak Bank Jan-95 Jun-95

Cizre KSS, RC Project Ministry of

Science, Industry and Technology

Mar-98 Aug-98

Trabzon Gymnasium for 500 person capacity,- static calculation and RC projects,

The ministry of youth and sport May-96 May-97

Giresun Covered Swimming Pool - pile foundation calculation and projects, " Jan-96 Jul-96

Niğde Covered Swimming Pool - pile foundation calculation and projects, " Dec-93 Apr-94

Edirne Stadium- static calculation and RC projects, " Nov-95 Mar-96

Simav Gymnasium for 250 person capacity,- static calculation and RC projects, " Feb-94 May-95

Dörtdivan (BOLU) Gymnasium for 250 person capacity,- static calculation and RC projects, " Jun-93 Mar-94

Yeniçağ (BOLU) Gymnasium for 250 person capacity,- static calculation and RC projects, " Jul-94 Mar-95

Bilecik Gymnasium for 500 person capacity- static calculation and RC projects, " Nov-95 Jun-96

Dinar (Afyon) Gymnasium for 1500 person capacity,- static calculation and RC projects, " Jun-96 Oct-96

Izmit Gymnasium for 1500 person capacity,- static calculation and RC projects, " Jul-95 Jan-96

Gemlik Gymnasium for 1500 person capacity,- static calculation and RC projects, " Jul-93 Jan-94

Kocaeli Gymnasium for 5000 person capacity,- static calculation and RC projects, " Dec-98 Aug-99

Gümüşhane Gymnasium Extension Construction " Dec-98 Jun-99

İmla İşletmesi Resteurant Static RC Projects MKE Oct-98 Dec-98

Konya District OilI Depot Extension Petrol Ofisi May-93 Jul-93

İzmir Aliağa Plant Laboratory Building- Static Calculation " May-93 Jul-93

Trabzon District Directorate tin factory static calculation and RC " May-93 Jul-93

PIRAMIT ENG. CONS. LTD. COM.

Page 24: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

projects

Type 2 and 6 Station Sale Buildings- Static Calculations and RC Projects " May-93 Jul-93

Bahçeşehir 2. Etape 2. Part Static, RC Project Emlak Bank Dec-97 Jun-98

Ankara Municipality, steel foot bridge with cafe between SSK Maternity Hospital – Gülhane, RC calculations and projects

Doruk İnşaat / Ankara

Metropolitan Municipality

Apr-94 May-95

3- INDUSTRIAL BUILDING

PROJECT CLIENT CONTRACT DATE

FINISH DATE

ETİBANK General Directorate Bigadiç Raw Boron Grinding Depots; Architectural and Steel Application Project

Etibank Dec-02 May-03

Doğalgaz Kojenerasyon Plant (Erdemir); Architectural and Steel Application Projects

Erdemir - Ereğli Dec-01 May-02

Brisa Tyre Factory (İzmit), II. Extension Building (İZMİT) BRİSA Oct-01 Mar-02

Soda Sanayi A.Ş. Kromsan (Şişecam-Mersin), Chrome Integral Plant; Steel application project

Şişecam Oct-01 Mar-02

Türkmenbaşı CCR Platform Petroleum Refinery Control Building Electric Detail and Application Project

GAMA İnşaat Apr-00 Apr-01

Kardemir Steel Plant (Karabük) – Steel Fabrication Project Kardemir A.Ş Dec-98 May-99

Coca-Cola Factory Boiler , Water Treatment , Steel Floor Platforms (Ekaterinburg); Steel construction application project

Coca Cola - İzmir Jan-98 Jun-98

Rize-Çayeli bakır işletmeleri A.Ş. ; Copper Tank Platforms Tüsraş A.Ş Jan-97 Jun-97

PIRAMIT ENG. CONS. LTD. COM.

Page 25: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

4 – Road and Bridge

• Highway

• Bridge and Viaduct

• Interchange

• Overpass

• Footbridge

• Service Roads

pp ii rr a m i t m ü h

PIRAMIT ENG. CONS. LTD. COM.

Page 26: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

4 - BRIDGE AND ROADS

PLACE OF PROJECT

EMPLOYER

CONTRACT DATE

FINISH DATE

KILOMETRES

Samsun - Ankara State Highway Ankara Metropolitan Municipality Jun-01 Oct-01 14.500

Düzce Disaster Victim Settlement Invesco / The Ministry of Public Work and Settlement/ Iller Bank Oct-00 Apr-01

54.555 Bolu Disaster Victim Settlement " Jun-00 Apr-01 7.281

Sakarya III. O.S.B. Ministry of Science, Industry and Technology Mar-00 Jun-00

7.783

Akşehir O.S.B. " Nov-99 Jun-00 7.866

Sakarya II. O.S.B. " Dec-98 Dec-99 11.876

Sivas O.S.B. " Sep-97 Sep-98 3.814

Silivri Municipality Iller Bank Sep-97 Nov-98 10.709

Kayseri (İncesu) O.S.B. Ministry of Science, Industry and Technology Nov-96 Nov-99

19.733

Yozgat KSS " Nov-96 Mar-97 6.568 Samsun - Ünye State Road Kerimbey Bridge

The Ministry of Public Work and Settlement / Tubin İnşaat May-96 Oct-96

N/A AŞTİ-Ümitköy Ankara Metropolitan Municipality May-96 May-

97 8.500

Osmaniye O.S.B. Ministry of Science, Industry and Technology Mar-96 Jan-98

4.660

Adıyaman O.S.B. " Jul-95 Nov-98 8.829

Bandırma O.S.B. " Jun-95 Nov-97 9.645

Çayyolu Ankara Metropolitan Municipality Mar-95 Nov-95 13.368

Denizbostanlısı (İzmir) 2.Etape Housing Emlak Bank / Ceylan İnşaat Jan-95 Feb-96 3.800

Beylikdüsü " Jan-95 Jun-95 12.809 Kızlarpınarı - Dr. Besim Ömer Street Interchange RC and Pile Calculations and Project

Doruk İnşaat / Ankara Metropolitan Municipality Apr-94 May-

95 N/A

Ardeşen KSS Ministry of Science, Industry and Technology Feb-94 Aug-94

1.436 Uşak Deri O.S.B. " Feb-94 Feb-95 23.202 Rize İspir State Road Avalanche Tunnel Static and RC Project Güntekin İnşaat Feb-94 Jun-94

5 nos.

Kahramanmaraş O.S.B. Ministry of Science, Industry and Technology Dec-93 Sep-94

19.620

Denizbostanlısı (İzmir) 1.Etape Housing Emlak Bank / Ceylan İnşaat Jan-93 Sep-94 4.500

Bilkent 2 Housing Emlak Bank/Tepe İnşaat Aug-92 Jan-93 8.175 Bilkent Plaza " May-92 Dec-92 2.100 Bilkent 1 Housing " Aug-91 Oct-91 8.600

PIRAMIT ENG. CONS. LTD. COM.

Page 27: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

5- Maping and Expropriation

• Development plan

• Piecemeal plan

• Plan investigation study • Landscaping and regulatory development plan

• Urban development

pp ii rr a m i t m ü h

PIRAMIT ENG. CONS. LTD. COM.

Page 28: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

5- MAPPING and EXPROPRIATION

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Atasu WWTP and Sewerage project, surveying of complete basin area

State Water Works (DSI)

Dec-09 May-1

Çakmak Dam, surveying of complete basin area SASKİ Dec-09 Mar-10

Bodrum (Muğla) Peninsula Drinking Water Transmission Line Revision Projects DSİ Dec-08 Apr-10

Mapping of various Organized Industrial rEGİON :Gaziantep, Bandırma, Osmaniye, Kayseri 2

Ministry of Science,

Industry and Technology

Çerkezköy (Tekirdağ), Kapaklı (Tekirdağ), Karaağaç (Tekirdağ) Zorlu Holding

Nehirkent , Bekirpaşa, Kazımpaşa, Gücücek , Mahmudiye, Yanık, Çaybaşı, Yeşilyurt (Adapazarı)

Adapazarı Metropolitan Municipality

PIRAMIT ENG. CONS. LTD. COM.

Page 29: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

6 - LANDSCAPING

PROJECT CLIENT CONTRACT DATE

FINISH DATE

Bahçeşehir 2. Stage, 2. Part, 62 Island; Landscaping, Boundary Lighting and Automatic Irrigation Application Project

Emlak Bank Dec-97 Jun-99

Primary Schools, Southeast Anatolia District, 99 School, Landscaping and Infrastructure Project

UBM Inc, Ministry of National Education

İzmir Mavişehir Housing, 3. Stage Landscaping and Application Project

Emlak Bank , Ceylan İnşaat Nov-97 Oct-98

Vatan Street Landscaping and Complete Infrastructure Project

Ankara Metropolitan Municipality

7 - GEOTECHNICAL STUDIES

PROJECT CLIENT

STATE ROADS Sinop -Boyabat-Durağan State Road Geological – Geotechnical Etude General Directorate of Highways

Cide-İlyasbey State Road Geological – Geotechnical Etude "

Kastamonu –Araç-Safranbolu State Road Geotechnical Etude "

Sinop-Ayancık State Road Geotechnical Etude (with borehole) "

Çayeli-Hemşin State Road Geological – Geotechnical Etude (with borehole) "

Cide-İlyasbey State Road Geological – Geotechnical Etude "

Afyon-Kütahya State Road Geological – Geotechnical Etude (with borehole) "

Cide-İlyasbey State Road – Geological – Geotechnical Etude (with borehole) "

Balıkesir-Akhisar State Road Geological – Geotechnical Etude "

Balıkesir-Dursunbey State Road Geological – Geotechnical Etude "

İvrindi-Havran State Road Geological – Geotechnical Etude "

Balıkesir-Kepsut State Road Geological – Geotechnical Etude "

Antalya-Korkuteli State Road Geological – Geotechnical Etude "

Refahiye-Sivas State Road Geological – Geotechnical Etude "

PIRAMIT ENG. CONS. LTD. COM.

Page 30: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Kalecik State Road Geological – Geotechnical Etude "

Burdur-Tefenni State Road Geological – Geotechnical Etude "

Rize-İkizdere State Road Geological – Geotechnical Etude "

Erzurum-İspir State Road Geological – Geotechnical Etude "

Karasu-Kocaali State Road Geological – Geotechnical Etude "

Uşak Peripheral Road Geotechnical Etude "

LANDSLIDE REHABILITATION PROJECTS

Hatay OSB Landslide Rehabilitation Project

Ministry of Science, Industry and Technology

Kahramanmaraş OSB Landslide Rehabilitation Consultancy "

Giresun OSB Landslide Rehabilitation (bored pile) and Application Projects "

Yalova-Çınarcık State Road Landslide Rehabilitation Studies General Directorate of Highways

DAM and HEPP

Bodrum Varil Small Dam Geotechnical Etude

Electrical Power Resources Survey and Development

Admin. (EIE)

Çoruh Basin Muratlı – Borçka – Definer - Artvin and Yusufeli Dam Geotechnical Etude " Y. Çoruh Basin Laleli- İspir- Güllübağ- Çetinboğaz Aksu Dams and Tunnel Alignement, Geotechnical Studies " Y.Karasu Basin Fındıklı Mercan Dam Tunnel Aignement, Geotechnical Studies " Tek Gökova-Ören Thermic Plant General Survey " Y. Çoruh Basin Arkun Dams and Tunnel Alignement Geotechnical Survey " Y. Çoruh Basin Dams and Tunnel Alignement Getechnical Survey " Kepez HEPP Yeni Su Kay. Araş. and Plant Location Studies " A. Karasu Basin Dumanlı HEPP, Kemah, Elmalı ve Erinç Dams and Tunnel Alignement Getechnical Survey " Y. Körkün Basin Kamışlı ve Karakuz Dams and Tunnel Alignement Getechnical Survey " Zapsuyu Basin Hakkari, Doğanlı ve Çukurca Dam Reservoir Geotechnical survey "

PIRAMIT ENG. CONS. LTD. COM.

Page 31: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

RAILWAY DDY Ankara Haydarpaşa Railway Track Turkish State Railways

DDY Irmak-Zonguldak Railway Track Rehabilitation Project "

DDY Irmak-Zonguldak Railway Track Geotechnical etude "

DDY Ankara-Kayseri Railway Track Geotechnical etude "

TUNNEL

Zapsuyu Basin Doğanlı Dam State Water Works Anamur Drinking Water Plant Transmission Tunnel Iller Bank Bozüyük Mekece Road Borehole Works Limak İnşaat Bozüyük-Bilecik-Osmaneli,Mekece State Road Kaletepe and Kocatepe Tunnels Alignment and Portal Geotechnic Design State Highways Taşucu Ovacık Road Tunnel Geotechnic Etude and Boreholes State Highways Ermenek Barajı Access Tunnel Geotechnic Etude State Water Works DDY Elmadağ Tunnel Portal Design Turkish State Railways

BRIDGE – VIADUCT BORED PILE FOUNDATION ETUDES

Interchange and Underpass Bored Pile Geotechnical etude (with borehole) Konya MetropolitanMunicipality

Um-Haraz Bridge over Sudan-Hartum Nile River, Geotechnical Etude and pile design

Sudan State Highways

Ozuzab Bridge over Sudan-Hartum Nile River, Geotechnical Etude and pile design

"

Soba Bridge over Sudan-Hartum Nile River, Geotechnical Etude and pile design

"

Al-Halfaia Bridge over Sudan-Hartum Nile River, Geotechnical Etude and pile design

"

Tuti Bridge over Sudan-Hartum Nile River, Geotechnical Etude and pile design

"

Sudan-Hartum Multi Interchange Underpass and Overpass Geotechnical Etude and pile design

"

OTHER (WWTP, DRINKING WATER, DEEP SEA DISPOSAL, SOLID WASTE DISPOSAL and MARINA EST.)

Beypazarı Waste Disposal Plant Project Iller Bank

Sürmene Deep Sea Disposal Line Geotechnical Etude Pal-Planş Project "

PIRAMIT ENG. CONS. LTD. COM.

Page 32: ENGINEERING& CONSULTING LTD. COM. · 2019-07-23 · Since its foundation in 1987, Piramit Engineering Consultancy Co. Ltd. has been providing engineering and consultancy services

Derebağ-Kayseri Sewerage Project " Tatvan WWTP Project " Samsun WWTP Project " Biga WWTP Project " Kalkınma Bank Alanya Ortacalar Deep Sea Disposal Project Turkish Development Bank

Naval Construction Dock Project Erdemir Marina Project Doğuş Holding Didim Marina Project Bodrum Yat İşl. A.Ş.

PIRAMIT ENG. CONS. LTD. COM.