Energy Storage System Add Value on Energy
International Perspective on Energy Storage
2014. 12. 4
International Policy
1
Definition of ESS
2 Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
BESS(Battery Energy Storage System), so-called ESS, is a system used for storing electrical energy to
secondary battery for timely use.
Concept Summary
Principle Storing electrical energy to Secondary batteries
(Li-ion, Lead-acid, NaS, etc)
Composition Role
PMS: Control PCS, BMS
PCS: Convert AC/DC, Power quality control
BMS: Control and Monitoring batteries
Battery: Store electrical energy
Life Expectancy
10 years
Efficiency More than 85%
Benefits
Reserving Power electricity
Frequency Regulation
Improving Power quality
Supporting Renewables
Supporting Users for efficient power usage
Voltage control
T&D investment Deferral
Construction Period
Less than 1 year
Applications of ESS
3
ESS is applicable to entire power system area starting from generation to end user and has multiple
benefits such as improving & stabilizing power quality, supporting renewables and off-grids.
Improving Generation efficiency
– Load leveling: Aiding generators by smoothing load fluctuation
– Peak Shaving: Decentering peak load
– Spinning reserve: Supplying seconds-scale reserve
– Frequency Regulation: Improving power quality
A Generation
Ancillary services
– T&D Deferral: Defer additional investments by reduce load
– Voltage Support: Responding sharp drop of voltage in a grid
B T&D
Controlling Renewable output
–Output smoothing: Smoothing irregular output power
– Constant power control: Controlling peak generation
C Renewables
Supporting Effective Power usage
– Time of Use response: Charge at off-peak, discharge at on-peak
– Power Quality & Reliability: Prevent blackout & voltage drop
– Energy Management: Power usage management and UPS
D End User
Supply power to the grid insufficient area through renewables integration –Power storing: Store produced electricity through renewable energy in the areas of power does not reach such as island and desert
E Off-grid
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Environment of Korea
4
88GW of Power Plants are operating isolated. Semi conductors, Chemicals, Shipbuilding, Steel
industries are strong. Korea has 494 islands occupied within 3,736 islands
Korea, North
China
Russia
Korea, South
Dokdo
* Map from DOE Global Energy Storage Database
Japan Jejudo
<Key Statistics>
•Area: 100,210km2
•Population: 50 million
• # of Islands: 3,736
• Island occupied: 494
• Installed Capacity: 88GW
•Peak Demand: 76GW
•Nuclear: 20GW
•Coal: 25GW
• LNG: 27GW
•Renewable: 5.6GW
•PHES: 4.7GW
• Frequency: 60±0.2 Hz
•Voltage: 220V-380V-6.6kV-
22.9kV-154kV-345kV-765kV
as of Apr 2014
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Governmental Drive
5
Ms. Park’s government support ESS deployment in many ways. Subsidy program, R&D support, and
Regulatory Reformation for electricity market and grid.
Remarks by President Park Geun-hye
“We will try new ways to
site incineration plants and
landfills, which local
communities tend to reject.
Those communities will
receive real benefits in the
form of clean technology-
based energy - energy that
will come from biomass co-
generation plants or
Energy Storage
Systems.”
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Introduction of KSGA
6
The Korea Smart Grid Association(KSGA) was established on May 21st, 2009 for the purpose of
developing Smart Grid.
ESS Committee
The Korea Smart Grid Association(KSGA) was established
for the purpose of developing Smart Grid
Date of establishment : May 21st, 2009
Number of Member Companies : 152 companies(2014)
KSGA
KSGA operate Smart Grid Committee. And ESS Committee
is affiliated with the Smart Grid committee
Organizations operating: May, 2012 ~
Standardization project
Projects for the establishment on Smart Grid infra
Research and analysis on Smart Grid
Role as a mediator between the government and private-sector stakeholders
Smart Grid Expert Training Program
Business Registration
1
2
3
4
5
6
Smart Grid Committee
Advisory Committee
EVCI Infra AMI Micro Grid
ESS Security xEMS
council
ESS Standards development
- ES-PCS(SGSF-04-2012-07) - 10kW↓ ESS(SGSF-04-2013-02) - 10~150kW ESS(SGSF-04-2013-03)
- 150kWA↑ ESS(SGSF-045-1-3)
Role as a mediator between the government and private-sector stakeholders(ESS) - Support to enact Governmental ESS Policies.
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Policies of Korea
7
Korean Government has a lot of interest for the ESS and enacted many ESS related policies.
MOTIE (Ministry Of
Trade, Industry & Energy)
January 2014 『2nd Energy Master Plan』
『The sixth Electricity
Supply Plan (2013~2027)』
『K-ESS 2020』
ESS related policies in Korea
Policy name Announcement
Time Main Content
Korean Government starts to focus on
changing their energy policies from
supply-side to demand-side management.
For this reason, Korean ESS market will
be expanded.
February 2013
May 2011
Target accumulated capacity of ESS is 500MW
in 2015
Target accumulated capacity of ESS is 2,000MW
in 2020
Korean Government set the goal to occupy
30% of the world market and makes on effort to
achieve Global Top3 ESS leading country by
2020
Supply 1,700MW ESS by 2020
Government department
May 2014
『Creative Korea
Flagship Project』
Korean Government will support
demonstration of 3 types(FR/RI/DR)
of ESS Business.
MSIP (Ministry of Science,
ICT & Future Planning)
Energy Storage System policies
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Major ESS Projects in Korea
8
Demonstration, R&D programs, smart grid promotion programs are major business opportunities in
Korea. Nowadays KEPCO and large power users lead the ESS market.
Projects Period Contents
Jeju smart grid Demonstration ‘09~’11 Smart Renewable, Smart Place, Smart Transporation with ESS, AMI, EVCI, etc
Daegu PV connected ESS for 100 household
‘10~’14 PV connected ESS for Household
Chochun S/S Renewable Integration(4MW)
’11~’14 Substation level renewable integrated ESS
Industrial Energy Management ESS(1MW)
‘13~’16 Factory energy management with ESS
Frequency Regulation with ESS(8MW)
‘13~’16 Develop frequency regulation market
Projects Period Organization Contents
Smart grid Promotion
‘12~ KSGI
ESS, AMI, EMS 75% subsidy for end user 2012 \3B > 2013 \20B > 2014 \17B
Hybrid Renewable
Energy ‘13~ KEMCO
50% from KEMCO, Renewable Energy with ESS for island
KEPCO FR ‘14~ KEPCO 500MW, ~2017
Large Power User Energy
Management ’13~
Samsung SDI LG Chemical
Kiheung/Ulsan Plant Ochang/Iksan Plant
Jeju Wind Power
‘14~ SK, Hanwha, GS,
etc
Jeju province are reviewing wind power regulation 10%/min variation
Smart grid City Projects
‘15~’17 KSGI 8 Consortiums are being evaluated for EVCI, AMI, ESS, EMS
R&D Demonstration and Promotion
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Multi-functional ESS for Substations
9
Hyosung supported multiple projects of power grid integration ESS for performance verification on
a variety of features and for Research on Utilization.
• Period: 2011.07~2014.06
• End-customer: KEPCO
•Description: ESS is linked with substation for
Renewables output smoothing
Active & Reactive power Controlling
Black start
• Integrator: HYOSUNG
• Rated power: 4MW (4 units of 1MW PCS, HYOSUNG)
• Energy: 8MWh (Li-ion Battery, Samsung SDI)
Jocheon Substation (4MW/8MWh)
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
ESS for Frequency Regulation
10
Hyosung participates in the project for study of how to adapt ESS for frequency regulation with KPX
• Period: 2013.06~2016.06
• End-customer: KPX
•Description:
• Integrator: HYOSUNG
• Rated power: 4MW (4 units of 1MW PCS, HYOSUNG)
• Energy: 2MWh (Li-ion Battery, SK Innovation)
Frequency regulation ESS (4MW/2MWh)
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Peak Shaving and Load Leveling ESS for Electricity users(1/2)
11
Hyosung supported multiple ESS projects for electricity users to reduce electricity charge.
• Period: 2012.08~2012.12
• End-customer: KT, Korea Smart Grid Institute
•Description: ESS is installed for separate outdoor
building and linked with KEPCO’s 22.9kV Power grid
• Effect: Reduce power electricity demand charge (max
$23 mil/year) and power electricity rate charge (max
$12 mil/year) by peak reduction.
• Integrator: HYOSUNG
• Rated power: 250kW (HYOSUNG)
• Energy: 500kWh (Li-ion Battery, LG Chemical)
Guri Agricultural Market (250kW/500kWh)
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
12
Peak Shaving and Load Leveling ESS for Electricity users(2/2)
Hyosung supported multiple ESS projects for electricity users to reduce electricity charge.
• Period: 2013.08~2013.12
• End-customer: Duzon Bizon, Korea Smart Grid
Institute
•Description: ESS is installed inside the building to
reduce power electricity demand charge and power
electricity rate charge by peak reduction.
• Integrator: HYOSUNG
• Rated power: 500kW(2 units of 250kW PCS,
HYOSUNG)
• Energy: 1,600kWh(Li-ion Battery, Samsung SDI)
Duzon Bizon (500kW/1,600kWh)
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Off Grid Solution(1/3)
13
Hyosung constructed Carbon Free Island in Gapado island, Korea
• Period: 2013.08~2014.01
• End-customer: Government of Jeju Island
•Description: Electricity supply using wind power
and ESS to over 200 residents in Gapado
island
• Integrator: HYOSUNG
• Rated power: 1MW (HYOSUNG)
• Energy: 1MWh (Li-ion Battery, Samsung SDI)
ES-PCS
Li Battery
Gapado Renewable & Off-grid Integration (1MW/1MWh)
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
14
Off Grid Solution(2/3)
Hyosung supplies the installation of 1.25MW/3MWh ESS solutions on Gasado by September 2014
the Republic of Korea
Jindo-gun
ES-PCS Li Battery
• Period: 2014.03~2014.09
• End-customer: KEPRI
•Description: Carbon free island using Renewables
and ESS for off-grid integration
• Integrator: HYOSUNG
• Rated power: 1,250kW (1 unit of 250kW and 2
units of 500kW, HYOSUNG)
• Energy: 3MWh (Li-ion Battery, Kokam)
Gasado Stand-alone micro-grid ESS (1.25MW/3MWh)
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
Multi-functional ESS for Substations
15
Hyosung supported multiple projects of power grid integration ESS for performance verification on
a variety of features and for Research on Utilization.
• Period: 2013.09~2014.08
• End-customer: CLP
•Description: ESS is linked with substation for
Load leveling
Peak shifting
PV power generation quality improving
• Integrator: HYOSUNG
• Rated power: 500kW (2 units of 250kW PCS,
HYOSUNG)
• Energy: 350kWh (Li-ion Battery, Samsung SDI)
Hong Kong CLP (CLP, 500kW/350kWh)
Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
16
Off Grid Solution(3/3)
Hyosung constructed the Off-Grid system based on PV generator in Mozambique
• Period: 2013.01 ~ 2013. 12
• End-customer: FUNAE
•Description: Electricity supply using PV generator and
ESS in Mozambique - Mavago(550kW),
Mecula(400kW), Muembe(350kW) - under
contemplation of grid-connected photovoltaic system
• Integrator: HYOSUNG
• Rated power: 900kW (single phase 5kW x 180, SMA)
• Energy: 20MWh (2V, 2,000Ah x 5,105, SEBANG
BATTERY)
Mozambique Off-grid PV generator-ESS (900kW/20MWh)
Author: Junill Yoon Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
17
Demand Variability
One of KEPCO’s large customer has over 250MW variability within 1GW peak. Also Wind and Solar
can make challenges against the grid operator
Demand Variability(MW)
725.00
775.00
825.00
875.00
925.00
975.00
1,025.00
00
15
00
45
01
15
01
45
02
15
02
45
03
15
03
45
04
15
04
45
05
15
05
45
06
15
06
45
07
15
07
45
08
15
08
45
09
15
09
45
10
15
10
45
11
15
11
45
12
15
12
45
13
15
13
45
14
15
14
45
15
15
15
45
16
15
16
45
17
15
17
45
18
15
18
45
19
15
19
45
20
15
20
45
21
15
21
45
22
15
22
45
23
15
23
45
250MW
24h
Author: Junill Yoon Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
18
PV Output
PV output can fluctuate 80% of its nameplate capacity.
80%
PV power plant in Korea(kW)
Author: Junill Yoon Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
19
Wind Output
Wind can fluctuate 90% through 24hour/365day operation.
Wind Power Output(MW)
90%
Author: Junill Yoon Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung
20
Conclusion
▪ In Korea, Demonstration projects have been ongoing from 2009, and several ESS site have been
installed and operated. Commercial ESS PJT is under review by government and utilities.
▪ Technology is important for adopting ESS, but political factors, such as support program and
regulation reform and etc., is also important for driving ESS.
▪ Subsidy program, R&D support and regulation changing is conducted and under review for
driving ESS business by government in Korea.
▪ ESS is a key element for renewable energy policies of India by contributing grid stabilizing and
enhancing energy efficiency in renewable energy grid.
Author: Junill Yoon Author: Junill Yoon ESS Committee Chair, KSGA/General Manager, Hyosung