MV SWITCHGEAR SITE ACCEPTANCE TEST (SAT) REPORTS CLIENT ADDC PROJECT D10590/B2- Al Sila’a Al Gharbia Emarati Housing Project –Infrastructural Works CONSULTANT PB POWER SUB-CONTRACTOR AL HUSAM GEN. CONTR. CONTRACTOR PIVOT SUBSTATION Energisation Check List Sl No PANEL REFERENCE OK NOT OK 1 Existing permit for the Installation and testing Job is cancelled. (if applicable) 2 All Open point Earth switch are removed. 3 Switchgear Room is clean and all unwanted materials are Removed 4 All the tools and Testing equipments are removed from site. 5 HSE Clearance Obtained for Energisation 6 Fire Extinguishers are available 7 Substation Earthing done as per specification. 8 All Feeders Disconnector switch in OFF position. 9 Main source feeder MV cable tested and connected to 11 KV switchgear. 10 Final Relay setting is uploaded for all protection relays and trip test done 11 All CT Circuits are through and shorting links opened 12 All MCB in ON position 13 Emergency Light Available at site Tested By Witnessed By Approved By Approved By Signature Name Date Company AL HUSAM KEO PB POWER ADDC 2

Upload: strider0710

Post on 15-Nov-2015

18 views

Category:

Documents


1 download

DESCRIPTION

Energization Check List Rev 1

TRANSCRIPT

INSPECTION AND TEST PLAN

MV SWITCHGEAR SITE ACCEPTANCE TEST (SAT) REPORTS

CLIENTADDCPROJECTD10590/B2- Al Silaa Al Gharbia Emarati Housing Project Infrastructural Works

CONSULTANTPB POWERSUB-CONTRACTORAL HUSAM GEN. CONTR.

CONTRACTORPIVOTSUBSTATION

Energisation Check ListSl NoPANEL REFERENCEOKNOT OK

1Existing permit for the Installation and testing Job is cancelled. (if applicable)

2All Open point Earth switch are removed.

3Switchgear Room is clean and all unwanted materials are Removed

4All the tools and Testing equipments are removed from site.

5HSE Clearance Obtained for Energisation

6Fire Extinguishers are available

7Substation Earthing done as per specification.

8All Feeders Disconnector switch in OFF position.

9Main source feeder MV cable tested and connected to 11 KV switchgear.

10Final Relay setting is uploaded for all protection relays and trip test done

11All CT Circuits are through and shorting links opened

12All MCB in ON position

13Emergency Light Available at site

14Emergency Exit Way is Clear

15Substation Red Marked Drawings and SLD is available at site

16Substation SAT report is available at site

17All sites are cleared and Danger Boards displayed

18Ensure padlocks available for locking all switchgear positions and Doors

Tested ByWitnessed ByApproved ByApproved By

Signature

Name

Date

CompanyAL HUSAMKEOPB POWERADDC