EN-CV status
EHN1 Extension Project
Jérôme Rodary EN-CV-PJ 2015/08/06
![Page 2: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/2.jpg)
Contents 1. Works in progress
• Cold boxes works (Vertex 1&2, CMS, ATLAS H8)
• Fan coil for barrack HNA 494
2. North wall dismantling • Dismantling works (water networks, ventilation,…)
3. Future design activities• Future design activities : GAr extraction system, general
ventilation
• User requirements missing
4. Schedule – CV activities
![Page 3: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/3.jpg)
1. Works in progress
• Cold boxes Vertex & CMS-RD5 • piping networks completed
• components & instrumentation installed
• next step : pressure tests (before 2015/08/14)
• final step : functional tests with the CB connected !
https://edms.cern.ch/document/1527243/0.1
![Page 4: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/4.jpg)
1. Works in progress
• Cold box ATLAS H8 (Saleve side) • piping & components supply in progress
• VIC done on 2015/08/05
• works will be done until end of august 2015
• New fan coil for barrack HNA 494 • cooling power 6,3 kW
• procurement launched
• installation in September 2015
![Page 5: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/5.jpg)
2. North wall dismantling
• Works completed : • firefighting network interception
• chilled water disconnected barrack HNA 910
• mixed water station removed (north wall)
• old fan coil removed from barrack HNA 494
• raw water network interception (several places)
• Works to be scheduled before end of 2015 : • To be removed:
• ventilation ducts
• CW pipes & equipments
• drinking water loop
• To be rerouted: • compressed air loop
• demi water network
• raw water network
Specific care to asbestos !
![Page 6: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/6.jpg)
3. Future design activities
• GAr extraction system : • pre-study in progress
• extraction flowrate to be frozen
• technical meeting scheduled on
friday 2015/08/07 regarding GAr system
GAr preliminary 3D model including extraction units & ducts
![Page 7: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/7.jpg)
3. Future design activities
• Building general ventilation: • adding of 2 new ventilation units
• total flowrate: 210 000 m3/h
• total heating power: 2 440 kW
WP will be edited
Existing ventilation unit inside EHN1 building
![Page 8: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/8.jpg)
3. Future design activities
• User requirements missing EN-CV needs technical data & requirements for designing the future extended networks as listed below:
• chilled water (for HVAC purposes)
• chilled water (for cooling down other some equipments)
• compressed air
• raw water
• demineralized water
• domestic water (hot and cold)
• fire fighting system
• gas extraction (other gases except GAr ?)
• ventilation for cryostat assembly clean room
• other… ?
![Page 9: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/9.jpg)
4. Schedule – CV activities
Task Start DurationInstall new cooling system Barrack BE-BI in progress Mon 04.09.15 1 day
Reroute CMS cold box to raw water in progress Mon 20.07.15 1 week
Reroute Vertex cold boxes to raw water in progress Mon 27.07.15 1 week
Reroute Atlas cold box to raw water in progress Mon 28.09.15 1 week
Install scaffolding on Jura side (EN-MEF-SI?) to be advanced ? Thu 01.10.15 2 days
Cut drinking water (pipe loop already drained) to be advanced ? Mon 05.10.15 2 days
Cut Ventilation duct and pipe on Jura side Wed 07.10.15 1 day
Remove drinking water from NW (Asbestos) Thu 08.10.15 2 days
![Page 10: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/10.jpg)
4. Schedule – CV activities
Task Start DurationDisconnect cooling system from CMS Barrack 902 Mon 02.11.2015 1 day
Install scaffolding on Saleve side (EN-MEF-SI?) Mon 02.11.2015 1 day
Cut and remove chilled water pipe Wed 04.11.15 1 week
Cut Ventilation duct and pipe on Saleve side Wed 11.11.15 1 day
Install new Chilled water pipe (Gallery + Barrack BE-BI) Thu 12.11.15 3 days
Connect the new cooling system for Barrack BE-BI Tue 17.11.15 1 day
Rerouted Gallery Pipes (2 demi water, 2 raw water, 1 compressed air) Mon 04.01.16 2 weeks
![Page 11: EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06](https://reader035.vdocuments.mx/reader035/viewer/2022062422/56649ecf5503460f94bdc01a/html5/thumbnails/11.jpg)
Thank you for your attention