emoc project presentation...2009/07/20  · emoc project presentation montgomery county, maryland...

40
EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD01 Baker and Associates July 20, 2009 1

Upload: others

Post on 11-Jun-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

EMOC Project Presentation

Montgomery County, MarylandContract No. 7504510027  Task Order WD‐01

Baker and AssociatesJuly 20, 2009

1

Page 2: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Project Team

Montgomery CountyRassa Davoodpour – Manager

Department of General Services, Office of Planning and Development

Hamid Omidvar – ChiefDepartment of General Services, Office of Planning and Development

Baker & Design TeamPeter Schmidt, AIA, LEED AP – Project Manager

Greg Shipley, AIA, LEEP AP – Project Architect

Steve Radomski, AIA, LEED AP – Facilities Architect

Shawn Benjaminson, PE, LEEP AP – Civil Engineer

Michele Monde, PE, PMP – Environmental Manager

John F. Parker, CMLI – Landscape Architect 2

Page 3: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Project Scope 3June 29, 2009

EMOC Facility – Casey 7 Proposed Location200 Bus Capacity

Heavy Equipment Fleet

Approximately 110,000 SF

Highway Service Facilities – Casey 6 & R.O. Proposed Location

Salt Storage

Covered Equipment Sheds

Materials, Soil & Gravel Storage

3

Page 4: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Project Major Goals 4June 29, 2009

Design a functional, state of the art facility

Design a Green/Sustainable facility

Design a project that fits best in the fabric of community

Traffic

Sound

Pollution

Architecture

Deliver the project on time and within budget

4

Page 5: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Schedule 5June 29, 2009

Two Projects – Schedule OverviewEMOC – Casey 7

Design Complete – June 9, 2010

Construction Complete – January 18, 2012

Highway Services – Casey 6Design Complete – March 3, 2010

Construction Complete – June 1, 2011

5

Page 6: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Design Considerations 6June 29, 2009

Sustainable Design – LEED Silver or betterIntegrated Design Process

Environmental and Energy Quality Improvements

Site ConstraintsRelationship to Surrounding Developments

Terrain, Wetlands, Noise & Odor Control

Access & Traffic (Equipment, Automobile, Pedestrian)

Aesthetic ConsiderationsVisibility

Washington Grove

6

Page 7: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Roberts Oxygen – Aerial Photo 7June 29, 2009

7

Page 8: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

8

Sector Plan June 29, 2009 8

Page 9: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

9

Site Area June 29, 2009 9

Page 10: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Site Elevation 10June 29, 2009

10

Page 11: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Site Slope Analysis 11June 29, 2009

11

Page 12: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

12

Proposed Site AllocationWashington 

Grove Highway Services‐ Laydown Area‐ Intermittent Use & Movements

Highway Services‐ Salt Storage‐Covered Equipment‐Materials / Soil / Gravel

CASEY 6

CASEY 7

Roberts Oxygen

EMOC Facility‐200 Buses‐Heavy Equipment Fleet‐Employee Parking‐Fleet, Transit & Hwy. Offices

State Hwy

I‐370

Crabbs Branch Way

Shady Gro

ve Rd.

June 29, 2009 12

Page 13: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Summary of June 29th Discussions

Refer to handout

13

Page 14: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Summary of June 29th Discussions

Heat Islands

Location of Fuel

Noise Generation and Mitigation

Community Benefits

Access to I‐370

Discussion Points for the Department of Transportation

Access to Roberts Oxygen

14

Page 15: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Designs

15

Page 16: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 6A

16

Page 17: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

17

Concept Design 6B

Page 18: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 6C

18

Page 19: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 7A

19

Level 2

Level 1LOWER LEVEL

Page 20: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 7B

Level 2

20

Level 1LOWER LEVEL

Page 21: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 7C

21

Level 2

Level 1LOWER LEVEL

Page 22: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 7D

Level 2

22

Level 1LOWER LEVEL

Page 23: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 7F

Level 2

Level 1LOWER LEVEL

23

Page 24: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Design response to community requests

24

Page 25: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Heat Islands

How will the project account for minimizing the heat island effect due to increased hardscape?

SS‐7.1: Heat Island Effect:  Non‐RoofMin. of 50% parking under cover with roof to have SRI of at least 29.

25

Page 26: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Heat Islands (cont.)

SS Credit 7.2:  Heat Island Effect:  RoofOption 1: Roofing Material with Solar Reflectance Index (SRI) equal to or great than table for 75% of roof surface.

Roof Type Slope SRI

Low‐Sloped Roof ≤2:12 78

Steep‐Sloped Roof >2:12 29

Option 2: Install vegetated roof for at least 50% of roof area.

Option 3: Install high albedo and vegetated roof surfaces that, in combination, meet criteria:

(Area of SRI Roof/0.75) + (Area of vegetated roof / 0.5) >= Total Roof Area

26

Page 27: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Location of Fuel

Where will the fueling locations be?

Public Fueling (Unleaded, Diesel, E85, and CNG)

Fueling Tanks

CNG Yard

Fueling

27

Page 28: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Noise Generation and Mitigation

What are the proposed noise mitigation strategies? Earth Berm with 6‐ft Board Fence

Public Fueling

CNGReceiving & Relinquishment

Trailer and Equipment Storage

Salt Barns

Volume AND Frequency

Volume OR Frequency

Low Volume and Frequency

28

Page 29: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Noise Generation and Mitigation

What are the proposed noise mitigation strategies? Earth Berm

Potential Covered storage area

Enclosed CNG compressor

I‐370 acts as a major sound block for bus operationMaintenance bay areas are enclosed

29

Page 30: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Noise Generation and Mitigation

What are the proposed noise mitigation strategies?

I‐370 and ICC Berm

Admin. Bldg.

Fleet Maintenance

Vehicle Parking

CNG YardVolume AND Frequency

Volume OR Frequency

Low Volume and Frequency

30

Page 31: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Discussion Points for Dept. of Transportation

31

Can a traffic calming device be located between Crabbs Branch Way, which is more commercial, and Amity Drive, which is residential?

Can the Crabbs Branch Way extension be realigned to retain the existing break in the mature treeline north of Casey 6?

Road terminus

Page 32: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Access to Roberts Oxygen

Q: Will there be an access driveway to Roberts Oxygen?  If so, where? 

A: Under investigation – Not in the green buffer area

32

Page 33: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Access to Roberts Oxygen

Option A

Option B

Q: Will there be an access driveway to Roberts Oxygen?  If so, where? 

A: Under investigation – Not in the green buffer area

33

Page 34: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Community Benefits

How will the community benefit?Increased Green Buffer

Tree Lined Pedestrian Walk/Bike Trail to Shopping Center and Metro

Preserved Wetlands and Reforestation Areas

Improved Shady Grove streetscape

34

Page 35: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Access to I-370Could the project incorporate an access directly to I‐370?

•Review period for an additional ramp would be between 3‐5 years.

•Ramps are typically 2 miles apart.

•Site is too small for access ramp requirements (acceleration / deceleration.)

35

Page 36: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 7E

Level 2

Level 1LOWER LEVEL

36

Page 37: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Concept Design 6D

37

Page 38: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Enlarged Plan of Pedestrian Walkway

38

Page 39: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Detail Section of Pedestrian Walkway

39

Page 40: EMOC Project Presentation...2009/07/20  · EMOC Project Presentation Montgomery County, Maryland Contract No. 7504510027 Task Order WD‐01 Baker and Associates July 20, 2009 1 Project

Discussion

40