EMMA 24 th February 2009 ALICE Stakeholder Meeting. EMMA Layout. IOT Racks. EMMA Infrastructure upgrade in progress in ALICE Accelerator Hall. Injection Line Assembly in progress in S Block. Integration. ALICE. Diagnostics Beamline. IOT Rack. RF Distribution. - PowerPoint PPT PresentationTRANSCRIPT
-
EMMA
24th February 2009
ALICE Stakeholder Meeting
ALICE Stakeholder meeting - Feb 2009
IOTRacksEMMA Layout
ALICE Stakeholder meeting - Feb 2009
EMMA Infrastructure upgrade in progress in ALICE Accelerator Hall
ALICE Stakeholder meeting - Feb 2009
Injection Line Assembly in progress in S Block
ALICE Stakeholder meeting - Feb 2009
IntegrationIOT RackALICEDiagnosticsBeamlineRF Distribution
ALICE Stakeholder meeting - Feb 2009
Aims & Objectives of EMMA ProjectWorlds first NS-FFAG (non-scaling Fixed Field Alternating Gradient) acceleratorFFAG: Field fixed in time but varies across pipe
Nonscaling: Dipole field scales with momentum but focussing quadrupole fields do not Optics changes during accelerationBetatron Tune changes during accelerationResonances unavoidableBut rapid acceleration means this is not fatal. (We hope)
ALICE Stakeholder meeting - Feb 2009
CONFORMCONFORM ( COnstruction of a Nonscaling FFag for Oncology, Research, and Medicine ) www.conform.ac.uk/ Total funds 6.9m over 4 year project lifecycle from RCUK Basic Technology from 1st April 2007Led by University of Manchester and The Cockcroft Institute including RAL, JAI, and others. Also FNAL, Brookhaven, Grenoble EMMA design and construction PAMELA design study for hadron therap machine Applications study for other applicationsBASROC (British Accelerator Science and Radiation Oncology Consortium) umbrella group of academic, medical and industry specialists in accelerator and medical technology with the aim of promoting the use of accelerators in science, industry and medicine. www.basroc.org.uk/
ALICE Stakeholder meeting - Feb 2009
EMMA Basic Parameters
Energy range10 20 MeVLatticeF/D DoubletCircumference16.6 mNo of cells42Normalised transverse acceptance3 mm-mradFrequency (nominal)1.3 GHzNo of RF cavities19Average beam current13 A Repetition rate1, 5, 10, 20 HzBunch charge16-32 pC single bunch
ALICE Stakeholder meeting - Feb 2009
RequirementsFull aperture injection and extraction at all energies 10 20 MeV
Many lattice re-tunings (vary ratio of dipole to quadrupole fields)
Vary frequency, amplitude and phase of RF cavities
Non-accelerated operation to map closed orbits and tunes vs momentum
Map longitudinal and transverse acceptances with probe beam
To be heavily instrumented with beam diagnostics, etc.
ALICE Stakeholder meeting - Feb 2009
Ring MagnetsRequirements / SolutionAdjust dipole & quadrupole components independently - Mount magnets on independent radial linear slidesFields identical in every cell despite kickers and septum - Field clamps at cell entrance face of QD & exit face of QF. Adjusted at the factory Very large good field region for range of closed orbits - Optimised pole profile implemented Due to extreme compactness of lattice, D & F magnets Are in very close proximity. Consequence: field computation and measurement with both magnets in place has been essential. Results from the prototype measurements have been implemented in the lattice simulations Are short compared with aperture. Consequence: integrated strength is dominated by end-field contributionsAll magnets scheduled to be delivered from TESLA by 10th April 2009
ALICE Stakeholder meeting - Feb 2009
RF Cavities20 (19 + spare) production cavity construction in progress give fast acceleration 4 of 5 batches delivered to DL 5th batch scans awaiting approval by DL
ALICE Stakeholder meeting - Feb 2009
Injection/Extraction Septum DesignIn house design of septum and vacuum chamber in progressWire eroding of lamination stacks is in progress. Delivery scheduled for Feb Mar 2009Manufacture Misc. septum components Apr May 2009Magnet measurements scheduled for Jun 2009Plan view of septum in vacuum chamberSection view of septum in vacuum chamberISO view of septum with vacuum chamber removed
ALICE Stakeholder meeting - Feb 2009
Kicker Magnet DesignFerrite CDM5005C core(Ceramic Magnetics, New Jersey)100 mmKicker component manufacture by Brite Precision, NewburyFerrite blocks manufactured by Ceramic Magnetics, New JerseyPrototype kicker magnet complete. Four production devices to follow subject to successful testingDelivery to APP in early March to be used as the test load for the kicker power supplies
ALICE Stakeholder meeting - Feb 2009
Standard Ring Vacuum ChamberBPM BlockContract placed for BPM pickups with Testbourne. Delivered November 2008Contract placed with VG Scienta for the vacuum chambers. Manufacture in progress Batch Delivery March 2009Clean vacuum testing & RGA cleanliness tests at the factory before delivery to DaresburyParticle processing at Daresbury
ALICE Stakeholder meeting - Feb 2009
RF DistributionContact placed with Q-Par Angus in Oct. 2008Manufacture and testing in progressDelivery due end of March 2009
ALICE Stakeholder meeting - Feb 2009
RF SourceInductive Output TubeVIL409 90 kW Transmitter Contact placed with CPI in Sep. 2008Full testing at CPI before deliveryDelivery due end of March 2009Commissioning at Daresbury in late April early May
ALICE Stakeholder meeting - Feb 2009
INJECTION LINE ALICE to EMMANew Dipoles x 2 (33) & BPMs at dipole entrancePosition measurementNew Dipole 30& BPMs at dipole entrancePosition measurementBPMPositionmeasurement Wall Current Monitor New Quadrupoles x 13Ion PumpVacuum valveTomography SectionScreens x 3(emittance measurement)SRS Quadrupoles x 3Screen &Vert. SlitBeam DirectionSRS Quadrupoles x 2ScreenVacuum valveScreenEmittance measurementCombined H and V Steering Magnet x 4 EMMARingALICEMatch the probe beam to the requirements of EMMAMeasure the properties of the probe beamVertical Steering Magnet x 2 Beam DumpNew Dipole 30
ALICE Stakeholder meeting - Feb 2009
DIAGNOSTICS BEAMLINE LAYOUTSpectrometer BPM @ dipole entranceScreenFaraday Cup
E-O Monitor
Screen x 3Tomography Section
Wall Current Monitor
BPM & ValveSRS Quadrupoles x 6New Quadrupoles x 4ALICENew Dipole (43) & BPMs at dipole entrance
Current measurementLongitudinal profilePosition measurementNew Quadrupoles x 4Screen& Vert. Slit Emittance measurementExtracted momentumScreenLocation for Transverse Deflecting Cavity(NOT IN BUDGET)Combined Horizontal and Vertical Steering Magnets x 4Vertical Steering Magnet x 2
ALICE Stakeholder meeting - Feb 2009
Timescale for InstallationALICE shutdown25 Oct - 21 Nov 2008CompleteDiamond drilling of ALICE wall, cable tray installation
EMMA off line build of modules in S blockNov 2008 - Jul 20099 months
ALICE shutdown (In progress now)23nd Feb - 29th Mar 20095 weeksEMMA Cable pull (90%) through external labyrinth, ALICE Dipole installation, Injection line girders through equipment access doorway
EMMA installation in Accelerator HallMar - Aug 2009 6 months
ALICE shutdown (dates to be confirmed) 8th Jun - 13th Jul 20095 weeksEMMA Cable pull through external labyrinth (10%), Controls cable pull through the control room labyrinth, Ring girder installation through equipment access doorway (except Injection & Extraction girders)
Injection line complete ready for commissioning with electrons19th Jul 2009
Test IOTMay 2009Install RF waveguide distributionAug 2009Commission RF Sep 2009
EMMA Injection & extraction septum girder available for installation through equipment access doorwayend of Aug 2009
ALICE shutdown (dates to be confirmed)15th Sep - 15th Oct 20094 weeks
Test systems in Accelerator HallSep - Oct 20092 months
Ring and phase 1 diagnostic beamline complete31st Oct 2009
Commission with electrons starting1st Nov 2009
ALICE Stakeholder meeting - Feb 2009
SummaryDesign phase and Procurement is well advanced with major contracts placedMajor components started to arrive in November 2008, off-line build is in progressAccess to ALICE accelerator Hall required for installation workShutdowns required to ALICE to open the cable route labyrinthWe aim to have the ALICE to EMMA Injection line ready for commissioning with electrons by 19th July 2009We aim to be ready for commissioning the EMMA ring with electrons by 1st November 2009
*