  • EMMA

    24th February 2009

    ALICE Stakeholder Meeting

    ALICE Stakeholder meeting - Feb 2009

    IOTRacksEMMA Layout

    ALICE Stakeholder meeting - Feb 2009

    EMMA Infrastructure upgrade in progress in ALICE Accelerator Hall

    ALICE Stakeholder meeting - Feb 2009

    Injection Line Assembly in progress in S Block

    ALICE Stakeholder meeting - Feb 2009

    IntegrationIOT RackALICEDiagnosticsBeamlineRF Distribution

    ALICE Stakeholder meeting - Feb 2009

    Aims & Objectives of EMMA ProjectWorlds first NS-FFAG (non-scaling Fixed Field Alternating Gradient) acceleratorFFAG: Field fixed in time but varies across pipe

    Nonscaling: Dipole field scales with momentum but focussing quadrupole fields do not Optics changes during accelerationBetatron Tune changes during accelerationResonances unavoidableBut rapid acceleration means this is not fatal. (We hope)

    ALICE Stakeholder meeting - Feb 2009

    CONFORMCONFORM ( COnstruction of a Nonscaling FFag for Oncology, Research, and Medicine ) www.conform.ac.uk/ Total funds 6.9m over 4 year project lifecycle from RCUK Basic Technology from 1st April 2007Led by University of Manchester and The Cockcroft Institute including RAL, JAI, and others. Also FNAL, Brookhaven, Grenoble EMMA design and construction PAMELA design study for hadron therap machine Applications study for other applicationsBASROC (British Accelerator Science and Radiation Oncology Consortium) umbrella group of academic, medical and industry specialists in accelerator and medical technology with the aim of promoting the use of accelerators in science, industry and medicine. www.basroc.org.uk/

    ALICE Stakeholder meeting - Feb 2009

    EMMA Basic Parameters

    Energy range10 20 MeVLatticeF/D DoubletCircumference16.6 mNo of cells42Normalised transverse acceptance3 mm-mradFrequency (nominal)1.3 GHzNo of RF cavities19Average beam current13 A Repetition rate1, 5, 10, 20 HzBunch charge16-32 pC single bunch

    ALICE Stakeholder meeting - Feb 2009

    RequirementsFull aperture injection and extraction at all energies 10 20 MeV

    Many lattice re-tunings (vary ratio of dipole to quadrupole fields)

    Vary frequency, amplitude and phase of RF cavities

    Non-accelerated operation to map closed orbits and tunes vs momentum

    Map longitudinal and transverse acceptances with probe beam

    To be heavily instrumented with beam diagnostics, etc.

    ALICE Stakeholder meeting - Feb 2009

    Ring MagnetsRequirements / SolutionAdjust dipole & quadrupole components independently - Mount magnets on independent radial linear slidesFields identical in every cell despite kickers and septum - Field clamps at cell entrance face of QD & exit face of QF. Adjusted at the factory Very large good field region for range of closed orbits - Optimised pole profile implemented Due to extreme compactness of lattice, D & F magnets Are in very close proximity. Consequence: field computation and measurement with both magnets in place has been essential. Results from the prototype measurements have been implemented in the lattice simulations Are short compared with aperture. Consequence: integrated strength is dominated by end-field contributionsAll magnets scheduled to be delivered from TESLA by 10th April 2009

    ALICE Stakeholder meeting - Feb 2009

    RF Cavities20 (19 + spare) production cavity construction in progress give fast acceleration 4 of 5 batches delivered to DL 5th batch scans awaiting approval by DL

    ALICE Stakeholder meeting - Feb 2009

    Injection/Extraction Septum DesignIn house design of septum and vacuum chamber in progressWire eroding of lamination stacks is in progress. Delivery scheduled for Feb Mar 2009Manufacture Misc. septum components Apr May 2009Magnet measurements scheduled for Jun 2009Plan view of septum in vacuum chamberSection view of septum in vacuum chamberISO view of septum with vacuum chamber removed

    ALICE Stakeholder meeting - Feb 2009

    Kicker Magnet DesignFerrite CDM5005C core(Ceramic Magnetics, New Jersey)100 mmKicker component manufacture by Brite Precision, NewburyFerrite blocks manufactured by Ceramic Magnetics, New JerseyPrototype kicker magnet complete. Four production devices to follow subject to successful testingDelivery to APP in early March to be used as the test load for the kicker power supplies

    ALICE Stakeholder meeting - Feb 2009

    Standard Ring Vacuum ChamberBPM BlockContract placed for BPM pickups with Testbourne. Delivered November 2008Contract placed with VG Scienta for the vacuum chambers. Manufacture in progress Batch Delivery March 2009Clean vacuum testing & RGA cleanliness tests at the factory before delivery to DaresburyParticle processing at Daresbury

    ALICE Stakeholder meeting - Feb 2009

    RF DistributionContact placed with Q-Par Angus in Oct. 2008Manufacture and testing in progressDelivery due end of March 2009

    ALICE Stakeholder meeting - Feb 2009

    RF SourceInductive Output TubeVIL409 90 kW Transmitter Contact placed with CPI in Sep. 2008Full testing at CPI before deliveryDelivery due end of March 2009Commissioning at Daresbury in late April early May

    ALICE Stakeholder meeting - Feb 2009

    INJECTION LINE ALICE to EMMANew Dipoles x 2 (33) & BPMs at dipole entrancePosition measurementNew Dipole 30& BPMs at dipole entrancePosition measurementBPMPositionmeasurement Wall Current Monitor New Quadrupoles x 13Ion PumpVacuum valveTomography SectionScreens x 3(emittance measurement)SRS Quadrupoles x 3Screen &Vert. SlitBeam DirectionSRS Quadrupoles x 2ScreenVacuum valveScreenEmittance measurementCombined H and V Steering Magnet x 4 EMMARingALICEMatch the probe beam to the requirements of EMMAMeasure the properties of the probe beamVertical Steering Magnet x 2 Beam DumpNew Dipole 30

    ALICE Stakeholder meeting - Feb 2009

    DIAGNOSTICS BEAMLINE LAYOUTSpectrometer BPM @ dipole entranceScreenFaraday Cup

    E-O Monitor

    Screen x 3Tomography Section

    Wall Current Monitor

    BPM & ValveSRS Quadrupoles x 6New Quadrupoles x 4ALICENew Dipole (43) & BPMs at dipole entrance

    Current measurementLongitudinal profilePosition measurementNew Quadrupoles x 4Screen& Vert. Slit Emittance measurementExtracted momentumScreenLocation for Transverse Deflecting Cavity(NOT IN BUDGET)Combined Horizontal and Vertical Steering Magnets x 4Vertical Steering Magnet x 2

    ALICE Stakeholder meeting - Feb 2009

    Timescale for InstallationALICE shutdown25 Oct - 21 Nov 2008CompleteDiamond drilling of ALICE wall, cable tray installation

    EMMA off line build of modules in S blockNov 2008 - Jul 20099 months

    ALICE shutdown (In progress now)23nd Feb - 29th Mar 20095 weeksEMMA Cable pull (90%) through external labyrinth, ALICE Dipole installation, Injection line girders through equipment access doorway

    EMMA installation in Accelerator HallMar - Aug 2009 6 months

    ALICE shutdown (dates to be confirmed) 8th Jun - 13th Jul 20095 weeksEMMA Cable pull through external labyrinth (10%), Controls cable pull through the control room labyrinth, Ring girder installation through equipment access doorway (except Injection & Extraction girders)

    Injection line complete ready for commissioning with electrons19th Jul 2009

    Test IOTMay 2009Install RF waveguide distributionAug 2009Commission RF Sep 2009

    EMMA Injection & extraction septum girder available for installation through equipment access doorwayend of Aug 2009

    ALICE shutdown (dates to be confirmed)15th Sep - 15th Oct 20094 weeks

    Test systems in Accelerator HallSep - Oct 20092 months

    Ring and phase 1 diagnostic beamline complete31st Oct 2009

    Commission with electrons starting1st Nov 2009

    ALICE Stakeholder meeting - Feb 2009

    SummaryDesign phase and Procurement is well advanced with major contracts placedMajor components started to arrive in November 2008, off-line build is in progressAccess to ALICE accelerator Hall required for installation workShutdowns required to ALICE to open the cable route labyrinthWe aim to have the ALICE to EMMA Injection line ready for commissioning with electrons by 19th July 2009We aim to be ready for commissioning the EMMA ring with electrons by 1st November 2009

    *