emgt 501 hw #3 chapter 10 - self test 7 chapter 10 - self test 18 due day: oct 3
DESCRIPTION
EMGT 501 HW #3 Chapter 10 - SELF TEST 7 Chapter 10 - SELF TEST 18 Due Day: Oct 3. Ch. 10 – 7 A project involving the installation of a computer system comprises eight activities. The following table lists immediate predecessors and activity times (in weeks). Immediate Predecessor. - PowerPoint PPT PresentationTRANSCRIPT
EMGT 501
HW #3Chapter 10 - SELF TEST 7
Chapter 10 - SELF TEST 18
Due Day: Oct 3
Ch. 10 – 7A project involving the installation of a computer system comprises eight activities. The following table lists immediate predecessors and activity times (in weeks).
ActivityImmediate
Predecessor Time
ABCDEFGH
--A
B,CDE
B,CF,G
36254393
a. Draw a project network.b. What are the critical activities?c. What is the expected project completion time?
Ch. 10 – 18The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows.
ActivityImmediatePredecessor
ABCDEFGHI
-AA
B,CBADG
E,H,F
Description
Meet with boardHire coachesReserve poolAnnounce programMeet with coachesOrder team suitsRegister swimmersCollect feesPlan first practice
Optimistic
142121111
Time (weeks)Most Probable
164232221
Pessimistic
286343331
a. Draw a project network.b. Develop an activity schedule.c. What are the critical activities, and what is the expected
project completion time?d. If the club manager plans to start the project on
February1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks)? Should the manager begin planning the swimming program before February 1?
EMGT 501
HW #3
SolutionsChapter 10 - SELF TEST 7
Chapter 10 - SELF TEST 18
Ch. 10 – 7
a.
Start
A
B
C D
G
E
H
F
Finish
b. B-D-E-F-H
Ch. 10 – 7
c. 21 weeks
ActivityLatestStart
ABCDEFGH
EarliestStart
EarliestFinish
0036
11156
18
LatestFinish
466
1115181821
CriticalActivity
10100030
1046
11159
18
365
1115181521
Slack
Yes
YesYesYes
Yes
Ch. 10 – 18
Start
C
F
D G
E
H
I FinishA B
b.
Activity Variance
ABCDEFGHI
Expected Time
1.176.004.002.003.002.002.002.001.00
0.030.440.440.110.110.110.110.110.00
ActivityLatestStart
ABCDEFGHI
EarliestStart
EarliestFinish
0.001.171.177.177.171.179.17
11.1713.17
LatestFinish
1.177.177.179.17
13.1713.1711.1713.1714.17
CriticalActivity
0.000.002.000.003.00
10.000.000.000.00
0.001.173.177.17
10.1711.179.17
11.1713.17
1.177.175.179.17
10.173.17
11.1713.1714.17
Slack
YesYes
Yes
YesYesYes
c. Critical Path: A-B-D-G-H-I Expected Project Completion Time=1.17+6+2+2+2+1 =14.17 weeks
d. Compute the probability of project completion in 13 weeks or less.
With this low probability, the manager should start prior toFebruary 1.
0951.04049.05000.0)weeks13(4049.0
31.180.0
17.1413)(E13z
80.000.011.011.011.044.003.0
2I
2H
2G
2D
2B
2A
2