EMA tracking tool: relocation to Amsterdam Main milestones Permanent Building Temporary Building Financial, governance, legal EMA Staff 20.11.2017 EU27 decision on Amsterdam as new EMA seat 31.12 Staff relocation to permanent building finalised 30.03 Staff relocation to temporary building finalised 01.07 Seat agreement signed by EMA and NL 01.01 SPARK building fully operational 22.02 Approval of permanent building by Budgetary Authority as initially expected 15.11 Permanent building fully operational 2018 2019 2020 Nov Feb Feb Feb Nov Nov Aug Aug May May May Jan Jan Jan Oct Oct Jul Jul Apr Apr Apr Dec Mar Mar Mar Dec Dec Sep Sep Jun Jun Jun 15.01 Joint governance structure implemented 26.01 Final decision on temporary building Please click on the icons to be directed to the related work streams. EMA stands for European Medicines Agency and NL stands for the Netherlands. progress on track progress delayed but overall still on track progress at risk *last updated on 30 April 2018

Upload: duongtuong

Post on 08-May-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: EMA tracking tool: relocation to Amsterdam - Main milestones · ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun 30.03 Staff relocation to temporary

EMA tracking tool: relocation to AmsterdamMain milestones

PermanentBuilding

TemporaryBuilding

Financial,governance,

legal

EMA Staff

20.11.2017EU27 decision on Amsterdam as new EMA seat

31.12 Staff relocation to permanent building finalised

30.03 Staff relocation to temporary building finalised

01.07 Seat agreementsigned by EMA and NL

01.01 SPARK building fully operational

22.02 Approval of permanent building by Budgetary Authorityas initially expected

15.11 Permanent buildingfully operational

2018 2019 2020Nov Feb Feb FebNov NovAug AugMay May MayJan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun

15.01Joint governance structure implemented

26.01Final decision ontemporary building

Please click on the icons to be directed to the related work streams.EMA stands for European Medicines Agency and NL stands for the Netherlands.

progress on trackprogress delayed but overall still on trackprogress at risk*last updated on 30 April 2018

Page 2: EMA tracking tool: relocation to Amsterdam - Main milestones · ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun 30.03 Staff relocation to temporary

completedongoingdeadline missednot started

EMA+NLin charge

Legend:

EMA in charge

NL in charge

EUin charge

EMA tracking tool: relocation to AmsterdamPermanent building

Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun

15.11 Permanent building fully operational

22.02 Approval of permanent building by Budgetary Authority as initially expected

*last updated on 30 April 2018

Page 3: EMA tracking tool: relocation to Amsterdam - Main milestones · ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun 30.03 Staff relocation to temporary

completedongoingdeadline missednot started

EMA+NLin charge

Legend:

EMA in charge

NL in charge

EUin charge

EMA tracking tool: relocation to AmsterdamTemporary building

Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun

26.01Final decision ontemporary building

01.01 SPARK building fully operational

*last updated on 30 April 2018

Page 4: EMA tracking tool: relocation to Amsterdam - Main milestones · ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun 30.03 Staff relocation to temporary

completedongoingdeadline missednot started

EMA+NLin charge

Legend:

EMA in charge

NL in charge

EUin charge

EMA tracking tool: relocation to AmsterdamEMA Staff

Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun

30.03 Staff relocation to temporary buildingfinalised

31.12 Staff relocation to permanent buildingfinalised

*last updated on 30 April 2018

Page 5: EMA tracking tool: relocation to Amsterdam - Main milestones · ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun Jul Sep ct ec Jan Mar Apr Jun 30.03 Staff relocation to temporary

completedongoingdeadline missednot started

EMA+NLin charge

Legend:

EMA in charge

NL in charge

EUin charge

Feb Feb FebNov NovAug AugMay May May2018 2019 2020Jan Jan JanOct OctJul JulApr Apr AprDec Mar Mar MarDec DecSep SepJun Jun Jun

01.07Seat agreementsigned

15.01Joint governance structure implemented

EMA tracking tool: relocation to AmsterdamFinancial, governance, legal

*last updated on 30 April 2018