elizabeth nolan's presentation: nuts and bolts of marcellus shale
TRANSCRIPT
![Page 1: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/1.jpg)
Nuts and Bolts of Marcellus Shale Drilling and Fracking
Elizabeth A. NolanOffice of Chief Counsel
Bureau of Regulatory CounselDepartment of Environmental Protection
![Page 2: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/2.jpg)
Marcellus Shale Development Overview
Major Stages: Site developmentWell drilling, hydraulic fracturing, productionWater withdrawalsWater and wastewater storageWaste managementProcessing and transmission
Potential Environmental Impacts: Surface waterGroundwaterAir
![Page 3: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/3.jpg)
Laws and RegulationsLaws and Regulations
Oil and Gas ActOil and Gas Act25 Pa. Code Chapter 78 (relating to Oil and Gas Wells)25 Pa. Code Chapter 78 (relating to Oil and Gas Wells)
Coal and Gas Resource Coordination ActCoal and Gas Resource Coordination ActOil and Gas Conservation LawOil and Gas Conservation LawClean Streams LawClean Streams Law
25 Pa. Code Chapter 91 (relating to General Provisions)25 Pa. Code Chapter 91 (relating to General Provisions)25 Pa. Code Chapter 93 (relating to Water Quality Standards)25 Pa. Code Chapter 93 (relating to Water Quality Standards)25 Pa. Code Chapter 95 (relating to Wastewater Treatment 25 Pa. Code Chapter 95 (relating to Wastewater Treatment Requirements)Requirements)25 Pa. Code Chapter 102 (relating to Erosion and Sediment 25 Pa. Code Chapter 102 (relating to Erosion and Sediment Control)Control)
![Page 4: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/4.jpg)
Laws and Regulations (continued)
Dam Safety and Encroachments ActDam Safety and Encroachments Act25 Pa. Code Chapter 105 (relating to Dam Safety and 25 Pa. Code Chapter 105 (relating to Dam Safety and Waterway Management)Waterway Management)
Waterways Planning ActWaterways Planning Act25 Pa. Code 110 (relating to Water Resources Planning)25 Pa. Code 110 (relating to Water Resources Planning)
Solid Waste Management ActSolid Waste Management ActStorage Tank and Spill Prevention ActStorage Tank and Spill Prevention ActAir Pollution Control ActAir Pollution Control ActEnvironmental Laboratory Accreditation ActEnvironmental Laboratory Accreditation Act
![Page 5: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/5.jpg)
Well PermitWell Permit
Notice to surface landowner, users of water supplies within 1,000 feet Well location restrictions:
100 feet from streams and other bodies of water identified on topographic map100 feet from wetlands greater than 1 acre200 feet from buildings and water supplies
Consideration of impacts to public resources
![Page 6: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/6.jpg)
Erosion and Sediment ControlErosion and Sediment Control
Erosion and Sediment Control General PermitErosion and Sediment Control General Permit5 Acres or more of earth disturbance.5 Acres or more of earth disturbance.E&S planE&S planPost construction stormwater management Post construction stormwater management plan and well site restorationplan and well site restoration
![Page 7: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/7.jpg)
Water WithdrawalWater Withdrawal
Single water management plan covers multiple Single water management plan covers multiple well sites.well sites.Applies in Ohio, Susquehanna and Delaware Applies in Ohio, Susquehanna and Delaware basins.basins.Required to protect existing and designated uses Required to protect existing and designated uses –– 25 Pa. Code Chapter 93.25 Pa. Code Chapter 93.
![Page 8: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/8.jpg)
Spill Prevention
PPC Plan: Preparedness, Prevention, and Contingency Plan
Operators must review their operations and identify all pollutional substances and wastes that will be used or generated, as well as identify the methods for control and disposal of these substances or wastes.Operators are required to identify potential risks and plan for the possibility of an accident occurring at the well site during hydraulic fracturing operations.
![Page 9: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/9.jpg)
Pits, Tanks and Centralized Pits, Tanks and Centralized ImpoundmentsImpoundments
All pits and impoundments must be impervious and structurally All pits and impoundments must be impervious and structurally sound.sound.Low impact centralized impoundments that store wastewater are Low impact centralized impoundments that store wastewater are permitted by regional oil and gas staff.permitted by regional oil and gas staff.High impact impoundments permitted by dam safety.High impact impoundments permitted by dam safety.
Impact wetlands, on streams, breach threatens Impact wetlands, on streams, breach threatens welfare/property.welfare/property.
![Page 10: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/10.jpg)
Groundwater ProtectionGroundwater Protection
Gas migrationProtection of water suppliesFinal rulemaking – 25 Pa. Code Chapter 78
Oil and Gas Well Cementing and CasingEffective February 5, 2011
![Page 11: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/11.jpg)
25 Pa. Code Chapter 78Overview
CementCasingWell controlInspectionsGas migration Response
![Page 12: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/12.jpg)
25 Pa. Code Chapter 78: Reporting Requirements
Requires mandatory electronic production reporting to DEP. New well record and completion reporting requirements submitted by the operator as part of the stimulation record include pump rates, pressure, total volume and list of hydraulic fracturing chemicals used, the volume of water used, and the identification of water sources used pursuant to an approved water management plan.
![Page 13: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/13.jpg)
Hydraulic Fracturing Wastewater Hydraulic Fracturing Wastewater ManagementManagement
Follow Residual Waste Regulations.Follow Residual Waste Regulations.Generator, transporter and treatment facility Generator, transporter and treatment facility regulatory and recordregulatory and record--reporting requirements.reporting requirements.
Annual Well and Waste Production ReportAnnual Well and Waste Production ReportChemical characterization of frac waste required.Chemical characterization of frac waste required.
Reporting mechanism: Reporting mechanism: Form 26R, Chemical Form 26R, Chemical Analysis of Residual Waste, Annual Report by the Analysis of Residual Waste, Annual Report by the GeneratorGenerator. .
![Page 14: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/14.jpg)
Hydraulic Fracturing Wastewater Hydraulic Fracturing Wastewater ManagementManagement
TDS strategyTDS strategyNew and Expanded Sources OnlyNew and Expanded Sources Only
500 Mg/l TDS500 Mg/l TDS250 Mg/l Chlorides250 Mg/l Chlorides10 Mg/l Barium and Strontium 10 Mg/l Barium and Strontium
Underground Injection Control ProgramUnderground Injection Control ProgramEPA administersEPA administersOnly 7 Class II UIC disposal wells in PA.Only 7 Class II UIC disposal wells in PA.
![Page 15: Elizabeth Nolan's presentation: Nuts and Bolts of Marcellus Shale](https://reader031.vdocuments.mx/reader031/viewer/2022021508/584dd6551a28ab857391da5d/html5/thumbnails/15.jpg)
Thank you!
Elizabeth A. NolanAssistant Counsel
Office of Chief CounselBureau of Regulatory Counsel
Pennsylvania Department of Environmental Protection400 Market Street
Harrisburg, PA 17101-2301(717) 787-9373
The views and positions expressed in this presentation and its materials are those of the author and do not necessarily reflect those of the Commonwealth or the Governor’s Office of General Counsel or the Department of Environmental Protection.