elevating the quality of life in the district. agenda site view sections construction strategy ...
TRANSCRIPT
![Page 1: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/1.jpg)
Elevating the Quality of Life in the District
![Page 2: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/2.jpg)
Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY
TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE – AUGUST 2015 TO APRIL 2016 TIMELINE – EASTER BREAK 2016 TIMELINE – APRIL 2016 TO JULY 2016
ACCESS & FLOW Foundation to Grade Building Permit Building Permit
NEXT STEPS 18th Nov. to 2nd Dec. Activities two week look ahead. Construction Images in Courtyard Construction Milestone Frequently Asked Questions.
Q & A
Elevating the Quality of Life in the District
![Page 3: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/3.jpg)
Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District
RULES OF THE ROAD RESPECT EACH OTHER
CELLPHONES OFF OR ON VIBRATE
Q&A WILL BE TAKEN AT THE END OF THE PRESENTATION
![Page 4: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/4.jpg)
Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District
SITE VIEW
![Page 5: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/5.jpg)
Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District
COURTYARD
AFTER RENOVATION AFTER RENOVATIONBEFORE RENOVATION
BEFORE RENOVATION
![Page 6: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/6.jpg)
Elevating the Quality of Life in the District
MEDIA CENTERAFTER RENOVATIONBEFORE RENOVATION
![Page 7: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/7.jpg)
Elevating the Quality of Life in the District
BEFORE RENOVATION AFTER RENOVATION
SOUTH ELEVATION
![Page 8: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/8.jpg)
Elevating the Quality of Life in the District
AFTER RENOVATIONBEFORE RENOVATION
REAR ELEVATION
![Page 9: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/9.jpg)
Elevating the Quality of Life in the District
BEFORE RENOVATION AFTER RENOVATION
MAIN ENTRANCE
![Page 10: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/10.jpg)
Elevating the Quality of Life in the District
SECTIONS
![Page 11: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/11.jpg)
Elevating the Quality of Life in the District
COURTYARD
![Page 12: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/12.jpg)
Elevating the Quality of Life in the District
FIVE STOPS ELEVATOR
![Page 13: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/13.jpg)
Elevating the Quality of Life in the District
CONSTRUCTION STRATEGY
TIMELINE – JUNE 2013 TO JULY 2015
![Page 14: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/14.jpg)
Elevating the Quality of Life in the District
GROUND FLOOR PLAN
SECOND FLOOR PLAN
FIRST FLOOR PLAN
![Page 15: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/15.jpg)
Elevating the Quality of Life in the District
CONSTRUCTION STRATEGY
TIMELINE – AUGUST 2015 TO APRIL 2016
![Page 16: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/16.jpg)
Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District
SITE VIEW
![Page 17: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/17.jpg)
Elevating the Quality of Life in the District
GROUND FLOOR PLAN
SECOND FLOOR PLAN
FIRST FLOOR PLAN
TIMELINE AUGUST 2015 – APRIL 2016
UNDER CONSTRUCTIONEGRESS DURING
CONSTRUCTION
LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE
![Page 18: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/18.jpg)
Elevating the Quality of Life in the District
CONSTRUCTION STRATEGY
TIMELINE – EASTER BREAK 2016
![Page 19: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/19.jpg)
Elevating the Quality of Life in the District
TIMELINE EASTER BREAK 2016
UNDER CONSTRUCTION
LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE
![Page 20: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/20.jpg)
Elevating the Quality of Life in the District
CONSTRUCTION STRATEGY
TIMELINE – APRIL 2016 TO JULY 2016
![Page 21: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/21.jpg)
Elevating the Quality of Life in the District
SITE VIEW
![Page 22: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/22.jpg)
Elevating the Quality of Life in the District
GROUND FLOOR PLAN
SECOND FLOOR PLAN
FIRST FLOOR PLAN
TIMELINE APRIL 2016 – JULY 2016
UNDER CONSTRUCTIONEGRESS DURING
CONSTRUCTION
LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE
![Page 23: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/23.jpg)
Elevating the Quality of Life in the District
SITE VIEW
TWO CREPE MYRTLE TREES WILL BE RELOCATED
1
2
![Page 24: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/24.jpg)
Excavation & Demo in Courtyard
![Page 25: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/25.jpg)
Excavation & Demo in Courtyard
![Page 26: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/26.jpg)
Excavation & Demo in Courtyard
![Page 27: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/27.jpg)
Installation of Foundation System & Elevator Pit in Courtyard
![Page 28: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/28.jpg)
Erection of Structural Steel in Cafeteria & Roof of 1956 Building
![Page 29: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/29.jpg)
Elevating the Quality of Life in the District
SITE VIEW
TWO CREPE MYRTLE TREES WILL BE RELOCATED
1
2
![Page 30: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/30.jpg)
Infiltration System Impact Crepe Myrtle Trees in Images
![Page 31: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/31.jpg)
Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District
CONSTRUCTION MILESTONE COMMENCEMENT OF CONCRETE WORK; OCTOBER
COMMENCEMENT OF ELEVATOR SHAFT; NOVEMBER
COMMENCEMENT OF COURTYARD STRUCTURAL STEEL; DECEMBER
![Page 32: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/32.jpg)
Shepherd ES Logoin Courtyard
![Page 33: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/33.jpg)
Frequently Asked Questions
1. Will the asphalt area on theplayground be repaired or replaced?Answer:- The asphalt will be repaired.
2. The Mural on the concrete wall will not be impacted by the construction Activities.
![Page 34: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/34.jpg)
Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District
NEXT STEPS TWO WEEK LOOK AHEAD EXCAVATION IN COURTYARD
FORMING & INSTALLATION OF FOUNDATION SYSTEM IN COURTYARD
ERECTION OF STRUCTURAL STEEL IN THE 1956 BUILDING
![Page 35: Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –](https://reader036.vdocuments.mx/reader036/viewer/2022062409/5697c0291a28abf838cd7a0c/html5/thumbnails/35.jpg)
Kenneth DiggsDGS Associate Director
DGS Government Affairs & [email protected]
(202) 580-9361