DIRECTORATE GENERAL OF ELECTRICTY

MINISTRY OF ENERGY AND MINERAL RESOURCES

REPUBLIC OF INDONESIA

ELECTRICTY DEVELOPMENT IN

INDONESIA

CONTENTS

OVERVIEW OF INDONESIAN ELECTRICITY

POLICY ON POWER SECTOR DEVELOPMENT

NEW REGULATIONS ON POWER SECTOR

Total installed capacity: 39,193 MW

− PLN : 75%

− IPP : 21%

− PPU : 4%

Current electrification ratio: 72.95%

Electricity Growth: 9% / year

Energy mix for power generation in 2012 to be

targeted as:

− Coal : 51.40%

− Gas : 23.18%

− Oil : 13.83%

− Hydro : 6.29%

− Geothermal : 4.79%

Total investment in Power Sector (2011):

– Power Generation : USD 1,671 Million

– Transmission : USD 3,100 Million

– Distribution : USD 318 Million.

OVERVIEW OF INDONESIAN ELECTRICITY (Current Condition)

PLN 29,447

75%

IPP 8,366 21%

PPU 1,380

4%

INDONESIA POWER SECTOR

INFRASTRUCTURE (Current Condition)

SUMATERA : • Generation: 5.909 MW • 275 kV : 1.011 kms • 150 kV : 8.382 kms • 70 kV : 332 kms • MV : 75.382 kms • LV : 83.827 kms

JAMALI : • Generation: 29.231 MW • 500 kV : 4.923 kms • 275 kV : 8.494 kms • 150 kV : 12.126 kms • 70 kV : 3.437 kms • MV : 137.354 kms • LV : 256.156 kms

Nusa Tenggara: • Generation: 282 MW • MV : 7.836 kms • LV : 7.794 kms

KALIMANTAN : • Generation: 1.602 MW • 150 kV : 1.568 kms • 70 kV : 123 kms • MV: 23.487 kms • LV : 22.540 kms

SULAWESI : • Generation: 1.625 MW • 150 kV : 2.304 kms • 70 kV : 833 kms • MV : 24.482 kms • LV : 29.722 kms

MALUKU : • Generation: 233 MW • MV : 4.722 kms • LV : 2.717 kms

PAPUA : • Generation: 311 MW • MV : 2.351 kms • LV : 3.393 kms

: Existing transmission

: Planned transmission

: Generation

TOTAL

• GENERATION CAPACITY : 39.193 MW

• TRANSMISSION LINE : - 500 KV : 4.923 kms - 275 KV : 9.505 kms - 150 KV : 24.380 kms - 70 KV : 4.724 kms

• DISTRIBUTION LINE : - MV : 275.613 kms - LV : 406.149 kms

POLICY ON POWER SECTOR DEVELOPMENT

Objective of electricity development: to ensure the

availability of electricity in sufficient quantity, good quality

and reasonable price in order to improve the welfare of the

people.

Primary energy sources from domestic and overseas shall

be used optimally in accordance with National Energy

Policy to ensure a sustainable supply of electricity.

Utilization of domestic energy sources will be prioritized for

national interests

Continuously to increase new and renewable energy usage

in primary energy composition for electricity generation.

To increase the electrification ratio, 80% in 2014 (72,95% in

2011).

To reduce oil share in power generation (5% in 2015):

replacing existing Diesel Power Plant with other power

plant (coal, geothermal and renewable);

To improve private participation in the power sector.

To improve electricity efficiency in the demand and the

supply side.

To increase the local content (TKDN).

To enforce safety regulations.

POLICY ON POWER SECTOR DEVELOPMENT

(2)

Establishing of more efficient and transparent investment

climate.

Private Investments should comply with Indonesian’s law and

regulations.

Providing fiscal and non-fiscal incentives for investors to

accelerate electricity development, such as:

- Free import tax for power plant’s capital goods that

producing energy for public use.

- Attractive energy sale price generated from geothermal or

other renewable power plant.

- Simplifying power purchase mechanism between PLN and

IPP for certain terms and conditions.

INVESTMENT POLICY

NEW REGULATIONS ON POWER SECTOR

Law 30/2009 on Electricity.

Government Regulation 14/2012 on Activity of Electricity Provision Business.

Government Regulation 42/2012 on Cross-Border Power Sale and Purchase.

MEMR Regulation No 1/2012 (amendment of No. 15/2010) on Project List of Accelerate Power Plant Projects using renewable energy, gas and coal.

MEMR Regulation 2/2011 on Assignment to PLN for purchasing geothermal electricity and ceiling price of electricity purchase from geothermal.

MEMR Regulation 04/2012 on Electricity Purchase from Small and Medium Scale Renewable Energy & Excess Power.

MEMR Regulation 12/2012 on Controlling of oil utilization.

Director General of Electricity Regulation 553-12/20/600.3/2012 on Criteria for Mine Mouth Power Plants, Purchasing of excess power and Electricity Crisis Conditions.

Tender Direct

Selection

Direct

Appointment

• Power purchase from power

generation which utilize renewable

energy, marginal gas, mine-mouth coal

and other local energy sources;

• Purchasing of excess power;

• Local electricity system in the crisis

condition or emergency of electricity

supply; or.

• Expansion of IPP which has already

operation at the same location:

o Capacity ≤ existing

o Capacity > existing:

− more efficient technology

− environmental friendly

− accordance with the requirement

of local electricity system

• In the frame of energy

diversification for power

generation to non oil

fuel.

• Addition of generation

capacity on the power

plant which has already

operation in the same

location, in terms of in

the same location there

are more than one of

holder of electricity

provision business

license which is

interested.

• Basically, entire

of power

purchase by the

holder of

electricity

provision

business license

conducted

through Tender,

except fulfill

condition of

Direct Selection

and/or Direct

Appointment.

INVESTMENT PROCEDURE (Government Regulation No. 14/2012 on Activity of Electricity Provision Business)

ELECTRICITY PRICE OF GEOTHERMAL (MEMR Regulation No. 02/2011)

Ceiling price for purchasing electricity from geothermal power plant

by PLN is 9.70 cent USD/kWh (in high voltage side)

PLN shall purchase electricity from the winner of geothermal

working area tender with the price based on the tender it self.

The price is used for Power Purchase Agreement, shall be final and

without negotiation

The electricity price as the result of tender before this MEMR

regulation is stipulated remain in force, except for the electricity price

more than 9.70 cent USD/kWh shall negotiate based on PLN’s

estimate and shall obtain the approval from MEMR

In case of failure on the exploration and the feasibility study, then the

risk shall be bear by developer

In case of failure on the exploration and the feasibility study that

cause the license of geothermal business activity has revoked, the

Power Purchase Agreement shall be automatically terminated.

ELECTRICITY PRICE OF SMALL AND MEDIUM

SCALE

RENEWABLE ENERGY AND EXCESS POWER (MEMR Regulation No. 04/2012)

PLN shall purchase electricity from renewable energy up to 10 MW and

excess power from state owned enterprise, regional owned enterprise,

private, cooperation and society to strengthen the local electricity system,

without price negotiation and approval from MEMR

The purchasing may be more than the own electricity use according to

condition or local electricity demand

In case of electricity supply crisis, PLN may purchase the excess power

with the price higher than mention above

Electricity purchasing with the price higher than mention above is based

on the PLN’s estimate and its shall obtain the approval from Director

General of Electricity on behalf of MEMR

The contract of the excess power purchase is maximum for 1 year and

may be extended

PRICE FOR EXCESS AND RENEWABLES ≤

10 MW (MEMR Regulation No. 04/2012)

Note:

No negotiation

No need Minister Approval.

Energy HV

(Rp/ kWh)

LV

(Rp/ kWh)

Renewable and Excess Power 656 x F 1.004 x F F = 1 Java, Bali

F = 1.2 Sumatera, Sulawesi

F = 1.3 Kalimantan, Nusa

Tenggara

F = 1.5 Maluku, Papua

Biogas/Biomass 975 x F 1,325 x F F = 1 Java, Bali, Sumatera

F = 1.2 Sulawesi, Kalimantan,

Nusa Tenggara

F = 1.3 Maluku & Papua

City Waste (zero waste

technology)

City Waste (sanitary landfill)

1,050

850

1,398

1,198

THE CRITERIA OF MINE-MOUTH POWER

GENERATION Director General of Electricity Regulation 553-12/20/600.3/2012 on Criteria for Mine

Mouth Power Plants,

Purchasing of Excess Power and Electricity Crisis Conditions

1. Mine mouth coal fired power plant utilize coal which

economically more feasible for mine mouth power

plant;

2. Mine mouth coal fired power plant must be

guaranteed by the coal availability during operation

based on contract;

3. The power plant site is near by the coal mining;

4. Coal transportation cost would not be considered.

2012 2020

Coal64%

Gas17%

Geothermal12%

Oil1%

Hydro6%

*Source: RUPTL PLN 2011-2020

Target Planned

THE TARGET OF ENERGY MIX ON POWER

GENERATION

Until 2020, the oil consumption are reduce until 1%. Fuel utilization for power

generation specifically for isolated/remote areas, and prioritizing local new and

renewable resources.

Utilization of coal are significantly increasing to 64% at 2020. following the CFPP

operational in FTP Phase I and II all over Indonesia, operational of CFPP 1.000 MW

ultra super critical at Jawa-Bali, and high capacity CFPP Mine Mouth at Sumatera.

Indonesia has a huge potential of geothermal for power generation, until 2020 has

planned 12% of geothermal power plant or increase 10% since 2011.

Coal 51.40%

Gas 23.18%

Oil 13.83%

Hydro 6.29%

Geothermal 4.79%

Engineering Procurement and Construction (EPC) Contract

The owner of project is PLN. Engineering, Procurement, and Construction

(EPC) of project will be offered to private sector through bidding. In this model

PLN provides 15% financing and private provides 85%. Example: Fast Track

10,000 MW Phase I and some projects in Fast Track 10,000 MW Phase II.

Independence Power Producer (IPP) Project

The owner and implementer of EPC is private. 100% financing source of the

project comes from private and it is passed through to electricity selling price.

Example: most of IPP projects and some projects in Fast Track 10,000 MW

Phase II.

Public Private Partnership (PPP) Project

The government project that offer to private entity through bidding. The

government could provide either the government support or the government

guarantee. If private as the initiator of the project, the government will provide

some compensation. Example: CFPP Central Java 2 x 1,000 MW.

PRIVATE SECTOR PARTICIPATION SCHEME

CONCLUDING REMARKS

Government has committed to increase electricity supply by 9% growth

per year and to increase electrification ratio from currently 72,95% (2011)

to 80% (2014) by creating a conducive investment climate to attract

private sector involvement.

Some efforts are continued to be done such as providing policies to

support the use of alternative energy and efficient energy technology.

Pricing policies give major influence for better energy efficiency and

energy diversification.

Undoubtedly, there is a need for private sector participation in power

sector development.

Energy diversification in electricity sector should be encouraged in order to

reduce electricity production cost, secure electricity supply and preserve

the environment.

To accelerate rural electrification ratio the Government promotes the

utilization of locally available energy resources, like mine mouth coal and

renewable energy.

Pulau Sumatera 5 Proyek (531 MW)

1. PLTU Pangkalan Susu 3 dan 4 (2x200 MW)

2. PLTU Nias (2x7 MW)

3. PLTU Tj. Balai Karimun (2x10 MW)

4. PLTU Tj. Pinang (2x15 MW)

5. PLTU Bangka (2x30 MW)

Pulau Jawa-Bali 3 Proyek (1.600 MW)

6. PLTU Indramayu (1x1.000 MW)

7. PLTU Madura (2x200 MW)

8. PLTU Bali Timur (2x100 MW)

Pulau Nusa Tenggara 2 Proyek (70 MW)

9. PLTU Sumbawa (2x10 MW)

10.PLTU Lombok (2x25 MW)

Pulau Kalimantan 8 Proyek (612 MW)

11.PLTU Parit Baru (2x50 MW)

12.PLTU Ketapang (2x10 MW)

13.PLTU Sampit (2x25 MW)

14.PLTU Kalsel (2x100 MW)

15.PLTU Kotabaru (2x7 MW)

16.PLTU Melak (2x7 MW)

17.PLTU Kaltim (2x100 MW)

18.PLTU Nunukan (2x7 MW)

Pulau Sulawesi 6 Proyek (360 MW)

19.PLTU Luwuk (2x10 MW)

20.PLTU Mamuju (2x25 MW)

21.PLTU Takalar 2x100 MW)

22.PLTU Kolaka (2x10 MW)

23.PLTU Kendari (2x25 MW)

24.PLTU Bau-Bau (2x10 MW)

Pulau Maluku 1 Proyek (14 MW)

25.PLTU Tidore (2x7 MW)

Pulau Papua 6 Proyek (116 MW)

26.PLTU Klalin/Sorong (2x15 MW)

27.PLTU Andai (2x7 MW)

28.PLTU Biak (2x7 MW)

29.PLTU Nabire ((2x7 MW)

30.PLTU Jayapura (2x15 MW)

31.PLTU Merauke (2x7 MW 8

1

2 3

4

5

6

7

9

10

11

12

13

14 15

16

17

18

19

20

21

22 23

24

25

26

27

28

29

30

31

LOCATION OF FTP 10.000MW PHASE II (COAL FPP)

Pulau Sumatera 12 Proyek (1.767 MW)

1. PLTP Seulawah Agam (1x55 MW)

2. PLTP Jaboi (1x7 MW)

3. PLTP Sarulla 1 (3x110 MW)

4. PLTP Sarulla 2 (2x55 MW)

5. PLTP Sorik Merapi (1x55 MW)

6. PLTP Muara Laboh(2x110 MW)

7. PLTP Sungai Penuh (2x55 MW)

8. PLTP Hululais (2x55 MW)

9. PLTP Lumut Balai (4x55 MW)

10. PLTP Rantau Dadap (2x110 MW)

11. PLTP Ulubelu 3 & 4 (2x55 MW)

12. PLTP Rajabasa (2x110 MW)

Pulau Jamali 19 Proyek (1.970 MW)

13. PLTP Rawa Dano (1x110 MW)

14. PLTP Tangkuban Perahu I (2x55 MW)

15. PLTP kamojang 5 &6 (1x40 MW & 1x60 MW)

16. PLTP Cibuni (1x10 MW)

17. PLTP Cisolok-CIsukarame (1x50 MW)

18. PLTP Darajat (2x55 MW)

19. PLTP Karaha Bodas (1x30 MW & 2x55 MW)

20. PLTP Patuha (3x60 MW)

21. PLTP Salak (1x40 MW)

22. PLTP Tampomas (1x45 MW)

23. PLTP Tangkuban Perahu II (2x30 MW)

24. PLTP Wayang Windu (2x120 MW)

25. PLTP Baturaden (2x110 MW)

26. PLTP Dieng (1x55 MW & 1x60 MW)

27. PLTP Guci (1x55 MW)

28. PLTP Ungaran (1x55 MW)

29. PLTP Wilis/Ngebel (3x55 MW)

30. PLTP Iyang Argopuro (1x55 MW)

31. PLTP Ijen (2x55 MW)

Pulau Nusa Tenggara 4 Project (50 MW)

32. PLTP Sembalun (2x10 MW)

33. PLTP Hu’u (2x10 MW)

34. PLTP Sukoria (2x2,5 MW)

35. PLTP Atadei (2x2,5 MW)

Pulau Sulawesi 5 Proyek (145 MW)

36. PLTP Lahendong 5 & 6 (2x20 MW)

37. PLTP Kotamobagu 1 & 2 (2x20 MW)

38. PLTP Kotamobagu 3 & 4 (2x20 MW)

39. PLTP Bora (1x5 MW)

40. PLTP Merana/Maaaingi (2x10 MW)

Pulau Maluku 3 Proyek (35 MW)

41. PLTP Jailolo (2x5 MW)

42. PLTP Songa Wayaua (1x5 MW)

43. PLTP Tulehu (2x10 MW)

6

7

8 9

10

11 12

13

18

19 20

21 22

25

27

26

23 24

28

29 30 14

15 16

17

31 32 33 34 35

36 37

38

39

40

41

42

43

1

2

3 4

5

LOCATION OF FTP 10.000MW PHASE II (GEOTHERMAL PP)

Pulau Sumatera 2 Proyek (16 MW)

1. PLTGB Sabang (2x4 MW)

2. PLTGB Tj. Batu (2x4 MW)

Pulau Nusa Tenggara 2 Proyek (16 MW)

3. PLTGB Waingapu (2x4 MW)

4. PLTGB Larantuka (2x4 MW)

Pulau Kalimantan 1 Proyek (8 MW)

5. PLTGB Putussibau (2x4 MW)

Pulau Sulawesi 3 Proyek (24 MW)

6. PLTGB Tahuna (2x4 MW)

7. PLTGB Moutong (2x4 MW)

8. PLTGB Selayar (2x4 MW)

Pulau Maluku 3 Proyek (24 MW)

9. PLTGB Tual (2x4 MW)

10.PLTGB Masohi (2x4 MW)

11.PLTGB Tobelo (2x4 MW)

1

2

3

4

5

6

7

8

9

10

11

LOCATION OF FTP 10.000MW PHASE II (GAS PP)

Proyek PLTA

Pulau Sumatera 1 Proyek (204 MW)

1. PLTA Asahan 3 (2x87 MW)

2. PLTA Simpang Aur (2x6 MW) +

(2x9 MW)

Pulau Jawa 1 Proyek (1000 MW)

3. PLTA Upper Cisokan (4x250 MW)

Proyek PLTG

Pulau Kalimantan 1 Proyek (100 MW)

4. PLTG Kaltim (Peaking)

Proyek PLTGU

Pulau Jawa 1 Proyek (500 MW)

5. PLTGU Muara Tawar Add-On Blok 2

(1x500 MW

Pulau Kalimantan 1 Proyek (120 MW)

6. PLTGU Bangkanai (1x120 MW)

Pulau Sulawesi 1 Proyek (240 MW)

7. PLTGU Senoro (2x120 MW)

1

2

3

4

6

7

5

LOCATION OF FTP 10.000MW PHASE II (HYDRO, GAS, CG PP)

PROGRESS SUMMARY OF FTP 10,000MW PHASE

II (status May 2012) Project of PLN: 26 project (3,757 MW)

- FS 6 Project (405 MW)

- Establishment Process of WKP 1 Project (20 MW)

- Bidding Process 12 Project (958 MW)

- Financing Process 1 Project (1,000 MW)

- Exploration 1 Project (20 MW)

- Pre-Construction 5 Project (1,354 MW)

Project of IPP: 72 Project (6.290 MW)

- FS Process 1 Project (20 MW)

- Establishment Process of WKP 4 Project (225 MW)

- Bidding Process of CFPP 9 Project (206 MW)

- Bidding Process of WKP 9 Project (580 MW)

- Negotiations Process 7 Project (403 MW)

- PPA Process 27 Project (3,060 MW)

- Government Guarantee Process 2 Project (241 MW)

- Exploration 9 Project (1,180 MW)

- Exploitation 3 Project (330 MW)

- Construction 1 Project (45 MW)

PROJECT LIST OF FAST TRACK PROGRAM 10,000 MW PHASE II

(MEMR Regulation No. 01/2012 Amandement to MEMR Regulation No. 15/2010)

1 GeoPP Tangkuban Perahu I 2 x 55 IPP JAWA Jawa Barat

1 x 30 IPP JAWA Jawa Barat

1 x 60 IPP JAWA Jawa Barat

3 GeoPP Ijen 2 x 55 IPP JAWA Jawa Timur

4 GeoPP Iyang Argopuro 1 x 55 IPP JAWA Jawa Timur

5 GeoPP Wilis/Ngebel 3 x 55 IPP JAWA Jawa Timur

6 GeoPP Gunung Endut 1 x 55 IPP JAWA Banten

7 GeoPP Rawa Dano 1 x 110 IPP JAWA Banten

8 GeoPP Cibuni 1 x 10 IPP JAWA Jawa Barat

9 GeoPP Cisolok-Cisukarame 1 x 50 IPP JAWA Jawa Barat

1 x 30 IPP JAWA Jawa Barat

2 x 55 IPP JAWA Jawa Barat

11 GeoPP Patuha 3 x 60 IPP JAWA Jawa Barat

12 GeoPP Tampomas 1 x 45 IPP JAWA Jawa Barat

13 GeoPP Tangkuban Perahu II 2 x 30 IPP JAWA Jawa Barat

14 GeoPP Wayang Windu Unit 3 dan 4 2 x 110 IPP JAWA Jawa Barat

15 GeoPP Gunung Ciremai 2 x 55 IPP JAWA Jawa Barat

16 GeoPP Baturaden 2 x 110 IPP JAWA Jawa Tengah

1 x 55 IPP JAWA Jawa Tengah

1 x 60 IPP JAWA Jawa Tengah

18 GeoPP Guci 1 x 55 IPP JAWA Jawa Tengah

19 GeoPP Ungaran 1 x 55 IPP JAWA Jawa Tengah

20 GeoPP Seulawah Agam 1 x 55 IPP SUMATERA Nanggroe Aceh Darussalam

21 GeoPP Jaboi 2 x 5 IPP SUMATERA Nanggroe Aceh Darussalam

22 GeoPP Sarulla 1 3 x 110 IPP SUMATERA Sumatera Utara

23 GeoPP Sarulla 2 2 x 55 IPP SUMATERA Sumatera Utara

PROVINCECAPACITY (MW)

2 GeoPP Kamojang 5 dan 6

NO. OWNER ISLAND

10 GeoPP Karaha Bodas

17 GeoPP Dieng

PROJECT

PROJECT LIST OF FAST TRACK PROGRAM 10,000 MW PHASE II

(MEMR Regulation No. 01/2012 Amandement to MEMR Regulation No. 15/2010)

24 GeoPP Umbul Telomoyo 1 x 55 IPP JAWA Jawa Tengah

25 GeoPP Simbolon Samosir 2 x 55 IPP SUMATERA Sumatera Utara

26 GeoPP Sipoholon Ria-Ria 1 x 55 IPP SUMATERA Sumatera Utara

27 GeoPP Sorik Marapi 240 (Total) IPP SUMATERA Sumatera Utara

28 GeoPP Muaralaboh 2 x 110 IPP SUMATERA Sumatera Barat

29 GeoPP Bonjol 3 x 55 IPP SUMATERA Sumatera Barat

30 GeoPP Lumut Balai 4 x 55 IPP SUMATERA Sumatera Selatan

31 GeoPP Rantau Dadap 2 x 110 IPP SUMATERA Sumatera Selatan

32 GeoPP Rajabasa 2 x 110 IPP SUMATERA Lampung

33 GeoPP Ulubelu 3 dan 4 2 x 55 IPP SUMATERA Lampung

34 GeoPP Suoh Sekincau 4 x 55 IPP SUMATERA Lampung

35 GeoPP Wai Ratai 1 x 55 IPP SUMATERA Lampung

36 GeoPP Danau Ranau 2 x 55 IPP SUMATERA Lampung

37 GeoPP Lahendong 5 dan 6 2 x 20 IPP SULAWESI Sulawesi Utara

38 GeoPP Bora 1 x 5 IPP SULAWESI Sulawesi Tengah

39 GeoPP Marana/Masaingi 2 x 10 IPP SULAWESI Sulawesi Tengah

40 GeoPP Hu’u 2 x 10 IPP NUSA TENGGARA Nusa Tenggara Barat

41 GeoPP Atadei 2 x 2,5 IPP NUSA TENGGARA Nusa Tenggara Timur

42 GeoPP Sokoria 3 x 5 IPP NUSA TENGGARA Nusa Tenggara Timur

43 GeoPP Mataloko 1 x 5 IPP NUSA TENGGARA Nusa Tenggara Timur

44 GeoPP Jailolo 2 x 5 IPP MALUKU Maluku Utara

45 GeoPP Songa Wayaua 1 x 5 IPP MALUKU Maluku Utara

46 HEPP Rajamandala 1 x 47 IPP JAWA Jawa Barat

47 HEPP Peusangan 4 1 x 83 IPP SUMATERA Nanggroe Aceh Darussalam

48 HEPP Wampu 3 x 15 IPP SUMATERA Sumatera Utara

49 HEPP Hasang 40 (Total) IPP SUMATERA Sumatera Utara

PROVINCECAPACITY (MW)NO. OWNER ISLANDPROJECT

PROJECT LIST OF

FAST TRACK PROGRAM 10,000 MW PHASE II (MEMR Regulation No. 01/2012 Amandement to MEMR Regulation No. 15/2010)

50 HEPP Simpang Aur 23 (Total) IPP SUMATERA Bengkulu

51 HEPP Semangka 2 x 28 IPP SUMATERA Lampung

52 HEPP Bonto Batu 2 x 50 IPP SULAWESI Sulawesi Selatan

53 HEPP Malea 2 x 45 IPP SULAWESI Sulawesi Selatan

54 CFPP Madura 2 x 200 IPP JAWA Jawa Timur

55 CFPP Nias 3 x 7 IPP SUMATERA Sumatera Utara

56 CFPP Tanjung Pinang 2 x 15 IPP SUMATERA Kepulauan Riau

57 CFPP Tanjung Balai Karimun 2 x 10 IPP SUMATERA Kepulauan Riau

58 CFPP Bangka 2 x 30 IPP SUMATERA Bangka Belitung

59 CFPP Nunukan 2 x 7 IPP KALIMANTAN Kalimantan Timur

60 CFPP Kaltim 2 x 100 IPP KALIMANTAN Kalimantan Timur

61 CFPP Kalsel 2 x 100 IPP KALIMANTAN Kalimantan Selatan

62 CFPP Luwuk 2 x 10 IPP SULAWESI Sulawesi Tengah

63 CFPP Mamuju 2 x 25 IPP SULAWESI Sulawesi Barat

64 CFPP Kendari 2 x 25 IPP SULAWESI Sulawesi Tenggara

65 CFPP Kolaka 2 x 10 IPP SULAWESI Sulawesi Tenggara

66 CFPP Sumbawa 2 x 10 IPP NUSA TENGGARA Nusa Tenggara Barat

67 CFPP Biak 2 x 7 IPP PAPUA Papua

68 CFPP Jayapura 2 x 15 IPP PAPUA Papua

69 CFPP Nabire 2 x 7 IPP PAPUA Papua

70 CFPP Merauke 2 x 7 IPP PAPUA Papua

71 CFPP Klalin 2 x 15 IPP PAPUA Papua Barat

72 CFPP Andai 2 x 7 IPP PAPUA Papua Barat

TOTAL 10,047

PROVINCECAPACITY (MW)NO. OWNER ISLANDPROJECT

Note:

HEPP : Hydro Electric Power Plant

GeoPP : Geothermal Power Plant

CFPP : Coal Fired Power Plant

CGPP : Coal Gasification Power Plant

GTPP : Gas Turbine Power Plant

PROJECT LIST OF

FAST TRACK PROGRAM 10,000 MW PHASE II (MEMR Regulation No. 01/2012 Amandement to MEMR Regulation No. 15/2010)

1 GeoPP Sungai Penuh 2 x 55 PLN SUMATERA Jambi

2 GeoPP Hululais 2 x 55 PLN SUMATERA Bengkulu

3 GeoPP Kotamobagu 1 dan 2 2 x 20 PLN SULAWESI Sulawesi Utara

4 GeoPP Kotamobagu 3 dan 4 2 x 20 PLN SULAWESI Sulawesi Utara

5 GeoPP Sembalun 2 x 10 PLN NUSA TENGGARA Nusa Tenggara Barat

6 GeoPP Tulehu 2 x 10 PLN MALUKU Maluku

7 HEPP Pump Storage Upper Cisokan 4 x 260 PLN JAWA Jawa Barat

8 HEPP Asahan 3 2 x 87 PLN SUMATERA Sumatera Utara

9 HEPP Masang 2 55 (Total) PLN SUMATERA Sumatera Barat

10 CFPP Indramayu 1 x 1.000 PLN JAWA - BALI Jawa Barat

11 CGPP Sabang 8 (Total) PLN SUMATERA Nanggroe Aceh Darussalam

12 CFPP Pangkalan Susu 3 dan 4 2 x 200 PLN SUMATERA Sumatera Utara

13 CFPP Melak 2 x 7 PLN KALIMANTAN Kalimantan Timur

14 CFPP Parit Baru 2 x 50 PLN KALIMANTAN Kalimantan Barat

15 CFPP Ketapang 2 x 10 PLN KALIMANTAN Kalimantan Barat

16 CFPP Takalar 2 x 100 PLN SULAWESI Sulawesi Selatan

17 CFPP Bau-Bau 2 x 10 PLN SULAWESI Sulawesi Tenggara

18 CFPP Lombok 2 x 25 PLN NUSA TENGGARA Nusa Tenggara Barat

19 GTPP Bangkanai 280 (Total) PLN KALIMANTAN Kalimantan Tengah

20 CGPP Tanjung Batu 8 (Total) PLN SUMATERA Kepulauan Riau

21 CGPP Putussibau 8 (Total) PLN KALIMANTAN Kalimantan Barat

22 CGPP Tahuna 8 (Total) PLN SULAWESI Sulawesi Utara

23 CGPP Selayar 8 (Total) PLN SULAWESI Sulawesi Selatan

24 CGPP Larantuka 8 (Total) PLN NUSA TENGGARA Nusa Tenggara Timur

25 CGPP Tobelo 8 (Total) PLN MALUKU Maluku Utara

26 CGPP Tual 8 (Total) PLN MALUKU Maluku

PROVINCECAPACITY (MW)NO. OWNER ISLANDPROJECT

30 days Yes

permission

Minister IUPL Holders

meet the requirements

application

No

Permit Requirements:

1. copy of the electricity

supply license;

2. initial agreement sale of

electricity;

3. balance of power in its region

4. electricity supply business plan for 5 (five) years

POWER SALES PERMIT CROSS-BOARDER

30 days Yes

permission

Minister IUPL Holders

meet the requirements

application

No

Permit Requirements:

1. copy of the electricity supply

license;

2. initial power purchase

agreement;

3. balance of power in its region;

4. electricity supply business

plan for 5 (five) years; and

5. copy of the importer identification

number obtained in accordance

with the provisions of the

legislation

POWER PURCHASE PERMIT CROSS-BOARDER