EirGrid – Gate 3 Liaison Group
Aidan Corcoran, Grid25 Programme Manager
Presentation to Gate 3 Liaison Group, 21st September 2010
![Page 2: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/2.jpg)
Previous Update
• Grid25/Challenge
• Implementation and Work Streams
– Reorganisation
– Planning/Environmental Policy
– Stakeholder/Strategic Consultation
– Ongoing Projects
– Major New Regional Projects
![Page 3: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/3.jpg)
EirGrid Organisational Change
• Programme Management Office
– Coordinate the delivery of the Grid 25
Programme
– Monitoring and reporting
– Specialist support and training
– Stakeholder Interaction
• Three Regional Groups
![Page 4: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/4.jpg)
Planning Environmental Policy
•Strategic Infrastructure Act
•Regional Planning Guidelines
•County Development Plans
•Habitats Guidelines
•Strategic Environmental Assessment
•An Bord Pleanala
![Page 5: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/5.jpg)
Stakeholder/Public Engagement
• National Forum
– Dublin
• Regional Forums
– Killarney
– Castlebar, Carlow, Waterford
• Open Days
– Millstreet
– Macroom
– Tarbert
– Portlaoise
– Kilkenny
– Listowel
![Page 6: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/6.jpg)
Strategy Prior to Public Consultation on a
scheme
•Continue to Build Awareness
•Continue strategic input to Policy
•Complete SEA Process
•National Stakeholder Forum
oDevelop National/EirGrid Policy Guidelines
•Regional Stakeholder Forum
•Regional Consultation
•Commence Consultation of Schemes
![Page 7: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/7.jpg)
•September 10
Transmission Projects Under Analysis for
Price Review 3 ( 2011-2015)
400 kV / 220 kV/ 110 kV
No. of New Stations 13
Overhead Line 1200 km
Underground Cable 100 km
No. of New
Transformers
30
No. of New
Capacitor Banks
14
Uprates 1900 km
![Page 8: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/8.jpg)
•September 10
Transmission Projects in Progress
400 kV / 220 kV/ 110 kV
No. of New Stations 16
Overhead Line 610 km
Underground Cable 33.1 km
No. of New Transformers 17
No. of New Capacitor Banks 12
Uprates 665 km
![Page 9: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/9.jpg)
•September 10
• Tarbert - Moneypoint
Cable Project
•Planned Transmission System
•400kV, 220kV & 110 kV
•Planning
![Page 10: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/10.jpg)
•September 10
Tarbert - Moneypoint Cable Project•Project Driver:
•Provide export capacity for wind in the South West,
•allow connection of ShannonLNG and retire Tarbert
•110kV Station.
•Project Details:
•3km of 220kV Subsea Cable
•1 new 220kV/110kV station at Kilpaddoge
•2 new cable bays in Moneypoint
•10km of underground cable
•Project Value: €51m
•Planning Permission:
•One foreshore licence application,
•Submitted Q1 2010
•Estimated completion date: July 2013
•ation
•March 2010
![Page 11: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/11.jpg)
•September 10
• North Kerry 220kV Project -New 220kV Station including Shallow
Connection for Athea phase II, Dromada, &
Cloghboola
•Planned Transmission System
•400kV, 220kV & 110 kV
•Generator Connection Projects
•Planning
![Page 12: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/12.jpg)
•September 10
North Kerry 220kV Project - New 220kV Station
•March 2010
•Project Driver:
•Non Contestable Generator Connection Project
•Shallow connection for Gate 2
•Project Details:
•220kV bays: 5 (2 bays are for a coupler)
•220/110kV trafo: 1
•110kV bays: 7 (2 bays are for a coupler)
•OHL: circa 5.5km
•Project Value:€47.4m
•Planning Status:
•Planning Lodgement: Q1 2011
•Estimated completion date: Q2 2014
![Page 13: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/13.jpg)
•September 10
• Millstreet 220/110
kV station
•Planned Transmission System
•400kV, 220kV & 110kV
•Generator Connection Projects
•Planning
![Page 14: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/14.jpg)
Millstreet 220/110 kV station
•March 2010
•Project Driver:
•Non Contestable Generator Connection Project.
•Shallow connection for Gate 2.
•Project Details:
•In Ballyvouskill:
•220kV bays: 5 (2 bays are for a coupler)
•220/110kV trafo: 1
•110kV bays: 5 (2 bays are for a coupler)
• Also in Garrow:
•110kV bays: 6 (2 bays are for a coupler)
•OHL: circa 12km
•Project Value:€25m
•Planning Status:
•Estimated Planning Lodgement: Q1 2011
•Estimated completion date: Q4 2014
![Page 15: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/15.jpg)
September 10
• Srananagh
220kV Station
and Line
•Planned Transmission System
•400kV, 220kV & 110 kV
•Construction
![Page 16: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/16.jpg)
September 10
Srananagh 220kV Station and Line•Project Drivers:
•Reinforcement of the network in the north west area
•Project Details:
•220kV Station:1
•250 MVA Trafo:1
•220kV bays:3
•220 kV Overhead Line: 56 km
•110 kV Overhead Line: 49 km
•Project Value:€66m
•Project Construction Status:
•220 kV Overhead Line: 75%
•110 kV Overhead Line: 100%
•Project Wayleave Status:
•80% Waylweaves cleared
•Estimated Completion date: December 2011
•March 2010
![Page 17: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/17.jpg)
September 10
• Tarbert-Tralee No.2
110kV New Line
•Planned Transmission System
•400kV, 220kV & 110kV
•Construction
![Page 18: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/18.jpg)
September 10
Tarbert-Tralee No.2 110kV New Line
•March 2010
•Project Driver:
•This is needed to overcome 110 kV line overloads
and voltage collapse in the Tralee area.
•Project Details:
•110 kV bays: 2110 kV line: 47km
•Project Value: €28.3
•Construction Status:
•Construction due to start in the coming weeks.
•Wayleave Status:
•100% Wayleaves complete
•Estimated completion date: November 2011
![Page 19: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/19.jpg)
September 10
Meath – Tyrone 400kV
Interconnector
•Planned Transmission System
•400kV, 220kV & 110 kV
•Planning
![Page 20: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/20.jpg)
September 10
Meath – Tyrone 400kV Project
•Project Drivers:
•-Interconnection with Northern Ireland
•-Security of supply to North East
•-Integration of renewables
•Project Details:
•400kV Overhead Line:140km
•New 400/220 kV AIS/GIS Substation at Moyhill, Co. Meath.
•Project Value: €180m
•Planning Permission
•-Planning application submitted18th December 2009.
•-Statutory Consultation completed 12th March 2010.
•-Approx 800 submissions received.
•-Oral Hearing held by An Bord Pleanála in April –June 2010.
•-Application withdrawn.
•Estimated completion date: 2014
•March 2010
![Page 21: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/21.jpg)
September 10
• Loughteeog
400kV Station –
New Station
•Planned Transmission System
•400kV, 220kV & 110kV
•Planning
![Page 22: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/22.jpg)
Loughteeog 400kV Station – New Station
•March 2010
•Project Driver:•Reinforcement will deal with voltage problems in the Carlow, Kilkenny and Laois areas
•Project Details:•400 kV Station
•400 kV bays: 5
•400 kV busbar
•110 kV Station:
•110 kV bays: 7
•110 kV busbar
•In other 110 kV stations
•110 kV bays: 5
•110 kV OHL: 30km
•Project Value:€70.4m
•Planning Status:
•Planning Permission submission target: Q1 2011
•Construction start target: 2012
•Estimated completion date: 2014
![Page 23: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/23.jpg)
Ploughing Championship
![Page 24: EirGrid Gate 3 Liaison Group · –Coordinate the delivery of the Grid 25 Programme –Monitoring and reporting –Specialist support and training –Stakeholder Interaction •Three](https://reader034.vdocuments.mx/reader034/viewer/2022042115/5e926c882d61556e0633bff3/html5/thumbnails/24.jpg)
• Questions?