ehealth workgroup meeting january 9, 2008 department of public health public health information...
TRANSCRIPT
eHealth Workgroup MeetingJanuary 9, 2008
Department of Public HealthPublic Health Information Network
Department of Public HealthPublic Health Information Network
DPH IT Management
• Lois Bryant– Oversees PHIN related activities and PHIN
team. PHIN IT applications hosted at DOIT.
• Vanessa Kapral– Oversees DPH located infrastructure and
development/application activities and teams and applications hosted at DPH.
DPH PHIN Platform
• Established under MOU December 2004.– Unix/Oracle and Windows/SQL platforms in place.
• CT Electronic Disease Surveillance System first on Oracle platform, followed by CT Immunization Registry.
• PHIN Messaging System first on Windows/SQL platform.
• DPH mandated to “upgrade” surveillance applications to meet new Centers for Disease Control and Prevention (CDC) and other federal requirements.
• DPH-DOIT PHIN IT Working Group in place.
SDM at DPH• Governance procedures presented to
DPH Executive Leadership Team (ELT) May 3, 2007.
– Included IT Strategic Plan (Lois Bryant).– Governance example by Len Smith (DCF).– Assessment of current applications (criticality,
EWTA compliance, IT support).
• Overview of SDM presented to DPH Executive Leadership Team on November 29, 2008 by Lois and Vanessa.
• DPH PHIN is using “pure” SDM for large projects; modified for smaller.
Status of PHIN Applications Business
Issue Defd
Business
Reqs Defd
Design Construction Testing Implementation Post Implement
CT EDSS
(pre-SDM)
X X
Jan 2008 (RFQ
New Vendor)Winter-Spring
2008Winter-Spring
Due August 2008
CT EPHTN X X Jan 2008 (RFQ to CT
EDSS Vendor)
Winter-Spring 2008
Winter-Spring
Due August 2008
CIRTS
(pre-SDM)
X X X X Ongoing Jan-Feb 2008
eHARS (CDC developed)
X X X X X October 2007
PHIN MS X X X X X August 2007
Lab LIMS (pending contract;
COTS)
X X X Winter 2008 2008-2009
2008-2009
Status of PHIN Applications, cont. Business
Issue Defd
Business
Reqs Defd
Design Construction Testing Implementation Post Implemen
t
SDWIS (EPA developed)
X X X X X Winter-Spring 2008
EMS/Trauma (pre-SDM)
X X X X Winter-Spring 2008
Spring-Summer 2008
EVRS (SDM) X
Winter 2008 (RFP out by
Spring)
Licensure (SDM)
X May 2008 (RFP by July)
HIE Technology
Plan
X December 2007 (RFP)
HAN X February 2008 (RFP)
DPH PHIN Process
• Project Management– MS Project– Best practices including strategic planning and
procedures
• Acquisition of IBM Rational Suite– Business Requirements capture– Traceability– Stress Testing– Version control– Change management
Applications pending PHIN platform migration
• EVVE = Electronic Verification of Vital Events– NAPHSIS required– Pending call with vendor (NAPHSIS contracted)
• Childhood Lead Poisoning– Current system at DPH unsupported– To be built into CT EDSS/CT EPHTN system
• Newborn Screening– Split system: DOIT piece unsupported as of 9/08; DPH
piece needs updating– To be built into CT EDSS/CT EPHTN system
• CYSHCN = Children and Youth with Special Health Care Needs– Assessment pending; functionality overlaps with Child
Health Profile
Communication
• ELT to receive monthly updates on PHIN IT projects.
• Format to include SDM information, timelines, etc.
• First update January 2008.