eglinton crosstown update
TRANSCRIPT
1
Crosstown Update
Allen Road and Eglinton Avenue June 19, 2013
Welcome
2
What is the Crosstown?
The Eglinton Crosstown is a 19 kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section
The line will connect Mount Dennis in the west to Kennedy Road in the east
The new service will be up to 60% faster than bus service today
3
Project Schedule 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Sheppard
Finch
Eglinton
Scarborough RT
SRT / Sheppard Maintenance
Facility
Note: Timeline reflects initiation of major construction activities
RFQ Issued RFP Issued
Financial Close Timeline
2021
4
5
Eglinton Crosstown LRT Project $4.9 B (2010$), funded by the Province of Ontario 19 kilometres east-west LRT from Kennedy to
Jane/Black Creek, including 10 kilometres of tunnel Connections to Yonge-University-Spadina Subway,
Scarborough RT and GO Stouffville Up to 26 stations
6
Tunnelling Update
The tunnel contract was awarded September 11, 2012 The winning consortium is comprised of Kenny
Construction Co., Kenaidan Contracting Ltd., Obayashi Canada Ltd. and Technicore Underground Inc.
Assembly of the first Tunnel Boring Machine (TBM) at the West Launch pit at Eglinton and Black Creek is complete and tunnelling is underway
A twin machine is being assembled
7
Assembly of Tunnel Boring Machines
8
Assembly and Launch Tunnel Boring Machine
9
Sequence of Tunnel Drive
10
Tunnel Drive Works 2013-Current Status
The majority of the works in 2013 will take place between Black Creek Drive and the vicinity of Allen Road
Crews are starting the construction of headwalls at future station sites along Eglinton Avenue West
Work zones are set up at Keele and Caledonia
11
Tunnel Drive Works 2013-Current Status
12
Tunnel Drive Works 2013
Headwalls: Temporary support walls for future excavation of the LRT stations
Made of concrete and installed to the depth of the future track level
Two methods of installation used: Secant Pile Walls, Jet Grout
Machinery including drill rigs, grout tanks, diggers and other equipment
Tunnelling from Black Creek to Caledonia expected by end of year
13
Tunnel Drive Works 2013
Secant pile wall: formed by intersecting concrete piles
Jet grout wall: uses engineered grout to form wall in situ
14
TBM Extraction- Vicinity of Allen Road and Eglinton
Extraction Shaft: a deep excavation located just west of Allen Road where the first two tunnel boring machines will be removed from the ground
Utility relocation will occur before excavation begins Concrete temporary support walls will form the foundation
of the shaft Work will start on the north side of Eglinton Avenue. Traffic
will be shifted according to phases of the work
15
Excavation Shaft West of Allen Road
16
Launch shaft: deep excavation just east of Allen Road Two more tunnel boring machines will be assembled and
launched for the second phase of tunnelling to Yonge Street
The site will be active for the delivery of tunnel liners and the hauling of spoils northbound on Allen Road for 12 months
Sound barrier will be erected on north side of east commuter parking lot
Existing subway service will remain operational
TBM Launch Shaft-Vicinity of Allen Road and Eglinton
17
TBM Launch-Vicinity of Allen Road and Eglinton
18
Timeline At future station locations underground structures
(emergency exits, cross passages) utility relocation and headwall installation is expected to last approximately six months on average
The deep excavations at Allen Road that provide egress and access points for TBMs are expected to take up to 24 months to construct
Tunnelling activities for the second phase of tunnelling to Yonge are expected to take 12 months
Following the completion of tunnelling works, the site will be turned over to the Metrolinx station contractor
19
Utility Relocations Construction of the headwalls and shafts requires that
some utilities be moved safely out of the way Depending on site conditions: gas, hydro, water mains,
sewers, lighting and telephone and cable lines may be relocated to allow for construction
In the vicinity of the launch and extraction shafts Metrolinx is co-ordinating with Bell, Enbridge, Toronto Water and Toronto Hydro, Cogeco regarding required relocations
In most cases utility relocations will be undertaken by Metrolinx contractor
Enbridge will coordinate works with Metrolinx
20
Approach to Traffic Management
Maintain a minimum of one lane eastbound and westbound on Eglinton in construction work zones
Buses and general traffic will share this lane Additional lanes will be provided if space allows Metrolinx will work with City of Toronto Transportation, local
elected officials and neighbours to monitor local traffic Signal timing may be modified and turning restrictions may
be added or relaxed
21
Traffic Lane Reductions
22
Anticipated Side Street Closures
In order to safely move utilities out of the way and to install underground structures, some local streets off of Eglinton Avenue will be closed during construction phases: Strathearn Rd Flanders Rd Winnett Ave Everden Rd
Atlas Ave Park Hill Rd Old Park Rd
23
Allen Road Access
Metrolinx is no longer pursuing the full year-long closure of Allen Road for an extended period
Temporary, short-term closures to on and off ramps will be required during different phases of construction
We will provide as much notice as possible in advance of those closures
Advance warning signs will be placed in the vicinity of the corridor including electronic changeable message signs and static signs
24
Transit Services during Tunnel Construction
Pedestrian and bus access to Eglinton West Station will remain open
Both eastbound and westbound TTC stops in the affected area may be shifted and relocated for the safety of transit riders. Watch for TTC posted signs indicating the adjusted stop locations
25
Parking Currently, 3 hour paid parking is available on Eglinton
Avenue during off-peak hours In order to provide space for construction work, street
parking on Eglinton in the work zone will not be permitted In order to off-set street parking losses for users of the
shops and services along Eglinton, Metrolinx is proposing that one-hour parking on some local roads be extended to 3 hours while construction is impacting parking availability
The provision of additional all-day parking is not within the scope of Crosstown works
26
Proposed Parking Alternatives
The following streets have been proposed to allow 3 hour parking while construction is impacting on-street parking availability:
Glenarden Road: Between Eglinton Avenue & Old Forest Hill Road WEST SIDE ONLY
Westover Hill Road: Between Eglinton Avenue & Dewbourne Avenue EAST SIDE ONLY
Wembley Road: Between west end point & Hilltop Road SOUTH SIDE ONLY
27
Pedestrians In the construction zone for temporary sidewalks or existing
sidewalks the goal is to maintain 1.5 metre sidewalk widths wherever possible
Access to properties from sidewalks should be maintained Some sections of sidewalk may be closed and crossings will
be available at traffic signals Please take care when travelling near construction. Watch
for additional signage directing pedestrians
28
Pedestrian Detours
29 29
Please get in touch with us Franca Di Giovanni Nicole Di Carlo Mark Iogna Denise Jayawardene Grace Lau E-mail: [email protected] Online: www.thecrosstown.ca Tel: 416-782-8118
Community Office 1848 Eglinton Avenue West Monday, Wednesday, Friday: 9:00 a.m. – 5:00 p.m. Tuesday & Thursday: by appointment
Crosstown Community Relations Team