Effective practices for geotechnical and foundation engineering in
design-build
Dan Brown, Dan Brown & Assoc.
Steven Saye, Kiewit Infrastructure Engineers
1
![Page 2: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/2.jpg)
Key Topics
• Pre-bid geotechnical data
• Risks & differing site conditions
• Alternative Technical Concepts (ATC’s)
• Performance based specifications
• Case studies 2
![Page 3: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/3.jpg)
NCHRP 429 – Geotechnical Information Practices in Design-Build
Describes effective practices in geotechnical procurement, design, and quality management
• Qualifications & experience of D-B geotechnical team is key to quality
• Use over-the-shoulder reviews to expedite schedule
• Weight geotechnical factors appropriately to the importance for project success
• Use ATC’s to allow bidders to reduce risk 3
![Page 4: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/4.jpg)
Pre-bid geotechnical data
• Forms the basis of the D-B Team’s design, schedule and bid
• May be < 25% of the quantity of information required for final design
• D-B Team must address the limitations in the provided information at bid time
4
![Page 5: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/5.jpg)
Pre-bid geotechnical data
• Quality and timeliness of basic information is critical
– Stratigraphy and coverage
– Emphasis on basic soil and rock material properties
– Limitations of pre-bid foundation tests
5
![Page 6: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/6.jpg)
Stratigraphy and Coverage
• Need thorough program of borings or soundings for pre-bid estimating
– More routine borings with cpt soundings preferred over few borings with sophisticated testing
– Provide surveyed information for 3D modeling
– Televiewer data with rock coreholes
– Provide core samples for examination by bidders
6
![Page 7: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/7.jpg)
Example: CPT Soundings
7
![Page 8: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/8.jpg)
Example: ATV Logs of Rock Core Borings
8
![Page 9: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/9.jpg)
Need basic material properties
• SPT hammer energy measurements
• Groundwater levels
• Pavement section data
• Electronic files for CPTu, or GINT logs
• Borings to sufficient depth
• Lab tests on “Undisturbed” samples
• Follow Agency’s Geotechnical Manual 9
![Page 10: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/10.jpg)
Limitations of pre-bid load tests
• Expensive for Owner and may be of little value to bidder
• Tied to Owner’s concept
• Subject to low-bidders means and methods
• May yield more ?’s than answers
• May invite claims
10
![Page 11: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/11.jpg)
Timing of pre-bid geotechnical data
• Late data is of very limited usefulness!
• Causes confusion & inefficient design!
• Estimators throw money into the bid for last minute surprises!
11
![Page 12: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/12.jpg)
Importance of high-quality pre-bid geotechnical data
Typical Problems:
• No SPT hammer energy measurements
• No groundwater level data
• No pavement section data
• Geotechnical data input into Gint format but electronic files not provided to D-B Teams
• CPTu electronic files not provided
• Investigation does not extend deep enough 12
![Page 13: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/13.jpg)
Risks & differing site conditions (DSC)
• DSC provisions contribute to a fair and equitable allocation of risk on design-build projects
• Provides a means to address risks and reduce contingency costs
• Usually (but not always) included on public works D-B projects
13
![Page 14: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/14.jpg)
Risks and DSC
Agency should:
• Provide all available geotechnical information in a data report
• Describe background geology and known conditions
• Avoid exculpatory language and overly broad descriptions
14
![Page 15: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/15.jpg)
Risks and DSC
D-B team should:
• Document the basis for design and construction (escrow)
• Evaluate the impact of reasonable variations in ground conditions
• Develop contingency provisions in construction plans and schedule
15
![Page 16: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/16.jpg)
Risks and DSC: Geotechnical Baseline Reports (GBR)
• Defines basis for bid and allocates risks
• ASCE guidance in “Geotechnical Baseline Reports for Construction Suggested Guidelines” Essex (2007)
– The Technical Committee on Geotechnical Reports of the Underground Technology Research Council
16
![Page 17: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/17.jpg)
Differing site conditions and application of baseline geo reports
• Baseline does not eliminate DSC but more clearly defines when DSC occurs
• Example baselines: rock elevations, thickness of soft alluvium, groundwater elevations
• Approach to some high risk items may be prescriptively defined; for example landslide stabilization measures or contaminated soil
17
![Page 18: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/18.jpg)
Alternative Technical Concept (ATC)
• Fosters innovation from D-B process
• Potential to lower costs/improve schedule
• May represent unfamiliar technology to owner agency
• Potential challenge with performance verification
18
![Page 19: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/19.jpg)
Alternative Technical Concept (ATC)
Agency should:
• Maintain confidentiality
• Talk early and often. Talk one-on-one
• Require performance testing of concepts; demonstrate effectiveness prior to construction
19
![Page 20: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/20.jpg)
Alternative Technical Concept (ATC)
D-B team should:
• Consider risks and allocation
• Provide examples and experience
• Plan for performance testing of concepts; demonstrate effectiveness prior to construction
20
![Page 21: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/21.jpg)
Alternative Technical Concept (ATC)
Examples:
• Base grouting of drilled shafts to enhance capacity
• Reliance on long term pile setup
• Use of equipment that is not covered in specifications
• Innovative ground improvement techniques 21
![Page 22: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/22.jpg)
Performance based specifications
Owner describes the expected outcome without prescribing a specific approach or design
• Fosters innovation
– Allow the Contractor to select means and methods
• Reduces potential claims
• Requires performance verification
22
![Page 23: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/23.jpg)
Performance based specifications
• Geotechnical Investigations
– Set the minimum requirements for extent of exploration
– All the D-B Team to determine the type of investigation (borings, in situ tests, laboratory study)
– Reference the State Manual of Instruction
23
![Page 24: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/24.jpg)
Performance based specifications
• Foundation load testing – verification of both design and construction methods
– O-cell or Statnamic on drilled shafts
– Static and/or Dynamic testing on driven piles
• QC/QA and integrity testing for production
– Crosshole sonic or other
– Dynamic monitoring 24
![Page 25: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/25.jpg)
Performance based specifications
• Embankment settlements
– UDOT example: 4 inches allowable settlement in 5 years (after project completion) w/ < ¼ inch differential within 12 ft horizontal distance
• Liquefaction mitigation
• Vibration monitoring
25
![Page 26: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/26.jpg)
Performance based specifications
Agency should:
• Set realistic expectations; overly stringent performance requirements cost time and money that will be reflected in the bid cost
• Clearly define performance measurement requirements
• Use best value selection for optional items 26
![Page 27: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/27.jpg)
Performance based specifications
D-B team should:
• Plan to achieve performance requirements with robust contingency plans
• Budget adequately to satisfy performance measurement requirements with qualified subconsultants
• Approach best value selection for optional items strategically 27
![Page 28: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/28.jpg)
Selected Case Histories
• Honolulu Transit, Hawaii
• Biloxi Bay Bridge, Mississippi
• Hastings Bridge, Minnesota
28
![Page 29: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/29.jpg)
Honolulu Transit Project
29
![Page 30: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/30.jpg)
Complex Geology – GBR Provided
30
![Page 31: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/31.jpg)
31
![Page 32: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/32.jpg)
Basalt Characteristics
32
![Page 33: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/33.jpg)
Cobbles & Boulders in Alluvium
33
![Page 34: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/34.jpg)
GBR for Honolulu Transit • Owner’s defined purpose “to help define the
contractual ground rules of the bidding process in regards to allocation and definition of geotechnical risks”
• “baselines are developed which will serve as a contractual basis for comparison with actual conditions encountered during foundation construction”
• “The Contractor may rely on these baselines in preparing his Price Proposal”
34
![Page 35: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/35.jpg)
Farrington guideway case Honolulu, HI
• Key components to the baseline report
– Geologic setting
– Site and subsurface conditions
– Previous construction experience
– Baselines for stratigraphy and ground characterization
– Design considerations
– Construction considerations 35
![Page 36: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/36.jpg)
Farrington guideway case Honolulu, HI
• Baselines developed for:
– Application of baselines to the contract price
– Geologic profile (fill, recent alluvium, coraline deposits, older alluvium, basalt, cobbles and boulders, clinker zones and voids)
– Groundwater
– Ground characterization
– Contamination 36
![Page 37: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/37.jpg)
Farrington guideway case Honolulu, HI
• Construction considerations:
– Anticipated ground behavior
– Groundwater control and management
– Ground support (casing) requirements
– Obstructions
– Rock excavation
37
![Page 38: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/38.jpg)
Performance Verification
• Base grouting ATC used in gravel zone within alluvium – load tests verify performance
• Load tests with different geologic conditions, construction methodology
• Testing for Basalt with clinker zones below tip
• Testing for Tuff with alluvium below tip
38
![Page 39: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/39.jpg)
Base Grouting Operations
Oscillator Drilling Equipment
39
![Page 40: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/40.jpg)
Keys for Honolulu Transit
• Robust pre-bid design to accommodate wide range of conditions
• GBR to limit risks to bidders
• ATC approach to mitigate deep soft alluvium
• Extensive performance verification with method shafts O-cell tests prior to production shafts
40
![Page 41: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/41.jpg)
Case History – Biloxi Bay Bridge
• US 90 Bridge over Biloxi Bay destroyed by Hurricane Katrina on August 29, 2005.
• Design-Build contract awarded June 7, 2006
• Project cost: $338.6 million
• Schedule date open to traffic: March 28, 2008
41
![Page 42: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/42.jpg)
Biloxi After Katrina
42
![Page 43: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/43.jpg)
Test Pile Program • 21 test and indicator piles, 19 on main bridge
• Verify drivability, hammer, cushions, etc.
• Multiple restrikes w/ PDA/CAPWAP
• Static, statnamic, lateral load tests
43
![Page 44: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/44.jpg)
Keys for Biloxi • Established long term setup with test piles
– Avoid restrikes, reduce schedule risk
• Axial resistance w/ limited reliance on end bearing
– Avoid variable pile lengths
• Hammer sufficient to drive to tip w/ minimal risk of refusal or damage
• Owner buy-in on approach to testing 44
![Page 45: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/45.jpg)
October 26, 2007 Biloxi Bay Bridge Opens Two Weeks Ahead of
Schedule
45
![Page 46: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/46.jpg)
Example: Hastings Bridge, MN
• Best value selection process
–price / technical score
• Key Issues:
–Verification of high capacity pipe piles
–North abutment settlement issue
46
![Page 47: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/47.jpg)
Hastings, MN Steel Pipe Piles
• 42” dia x 1” x 150’
• PDA used to monitor driving stress so pile can be driven hard
• Statnamic axial for verification 47
![Page 48: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/48.jpg)
Hastings, MN Steel Pipe Piles
48
![Page 49: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/49.jpg)
Pile Supported Embankment
Pile raft thru soft clay at north embankment 49
![Page 50: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/50.jpg)
50
![Page 51: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/51.jpg)
Photo from the Star-Tribune
51
![Page 52: Effective practices for geotechnical and foundation ......Performance Verification •Base grouting ATC used in gravel zone within alluvium – load tests verify performance •Load](https://reader036.vdocuments.mx/reader036/viewer/2022081620/610bf6b90f35257c11545aca/html5/thumbnails/52.jpg)
Summary
• Need high quality, timely pre-bid geotechnical data
• Risks & differing site conditions should be addressed appropriately
• Use ATC’s to obtain value from D-B