eerc gathering pipeline study status

18
© 2015 University of North Dakota Energy & Environmental Research Center. EERC Gathering Pipeline Study Status Briefing to the NDPC Annual Meeting Fargo, North Dakota Tuesday, September 22, 2015 Jay C. Almlie Senior Research Manager

Upload: others

Post on 14-Nov-2021

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EERC Gathering Pipeline Study Status

© 2015 University of North Dakota Energy & Environmental Research Center.

EERC Gathering Pipeline Study Status

Briefing to the NDPC Annual Meeting

Fargo, North Dakota

Tuesday, September 22, 2015

Jay C. Almlie

Senior Research Manager

Page 2: EERC Gathering Pipeline Study Status

HB 1358 Prescribed Focus

• Project is focused on conducting analysis of crude oil

and produced water (gathering) pipelines including:

– Construction standards

– Depths

– Pressures

– Monitoring systems

– Maintenance

– Types of materials used in the pipeline backfill.

– Analysis of the ratio of spills and leaks occurring in this state

in comparison to other large oil and gas-producing states

with substantial volumes of produced water

Page 3: EERC Gathering Pipeline Study Status

HB 1358 Goals & Objectives

• Project is focused on conducting analysis of crude oil and produced water (gathering) pipelines

– Phase I -- Study♦ Analyze the existing regulations on construction and

monitoring of crude oil and produced water pipelines

♦ Determine the feasibility and cost-effectiveness of requiring leak detection and monitoring technology on new and existing pipeline systems

♦ Provide a report with recommendations to the NDIC and the EDTC by December 1

– Phase II -- Demonstration♦ Pilot project to evaluate a pipeline leak detection and

monitoring system

Page 4: EERC Gathering Pipeline Study Status

Pipeline Study Topics Covered

Page 5: EERC Gathering Pipeline Study Status

Progress Report

• Work began in May, NDIC contracting complete July 1

• Work status:

– Discovery work complete

– Stakeholder meetings hosted

– Data collection, conference calls, site visits

– Evaluation of economics of leak detection applied to gathering lines complete

• Draft report ready for internal review by state and industry stakeholders October 1

– Stakeholders and DMR will review and comment on draft report before report submittal on December 1

• We have begun recruiting demonstration partners, and have formulated preliminary demonstration plans

Page 6: EERC Gathering Pipeline Study Status

Stakeholder Input

• The EERC has solicited input from:

– ND Department of Mineral Resources

– ND Public Service Commission

– ND Pipeline Authority

– Northwest Landowners Association

– Three Affiliated Tribes

– Industry

– Office of the Governor

Page 7: EERC Gathering Pipeline Study Status

Project Schedule – Two Phases

• Project Kickoff

• Discovery work

• Economic analysis

• Due date for study final report

• Ongoing support to State

• Demonstration project

• Final report on demonstration

• May 2015

• May-August 2015

• September 2015

• December 1, 2015

• All of 2016

• Q1 - Q3 2016

• December 2016

All Schedule Dates Driven by January 2017 Legislature Start

Page 8: EERC Gathering Pipeline Study Status

Gathering Systems Are Large,

Dynamic, and Complex

Page 9: EERC Gathering Pipeline Study Status

Overview of Produced Fluid

TransportStudy Focus: Pipelines that transport liquids (crude oil, produced water, or mixtures)

from a wellsite to aggregation points such as a crude oil refinery or

pipeline terminal or water treatment/disposal sites.

Page 10: EERC Gathering Pipeline Study Status

Gathering Pipeline Infrastructure

Statistics

Miles of Pipe by Fluid Type and Pipe Material ‒ DMR Database

Steel HDPE Reinforced Fiberglass Total

Crude Oil 2344 1 73 19 2436

Brine 2 841 332 0 1176

Mixed Fluid 56 13 140 0 209

Freshwater 5 247 28 0 281

• More than 23,000 miles of gathering pipeline installed in North Dakota• 4,000 miles of liquids gathering lines installed since Aug2011 in DMR database

Page 11: EERC Gathering Pipeline Study Status

Roll of Gathering Pipelines

• The focus of this study is to inform the State on

opportunities to improve the safety and reliability of

gathering pipelines carrying crude oil and produced

water.

• The challenges of pipelines need to be evaluated within

context

– Pipelines reduce truck traffic and associated road

congestion, road dust, and traffic-related accidents.

– Incidents such as leaks and spills are less frequent (on

an incident/volume basis) from pipelines than from

trucks.

Page 12: EERC Gathering Pipeline Study Status

Early Conclusions

• Overall: industry has made significant strides in past 2-3

years

– Many pipeline spills stem from rushed work done

during peak of Bakken activity (2007-2014)

– Most operators are moving from manual monitoring to

SCADA without regulation … improvement in-progress

• Leak detection (vs. system monitoring) on complex

gathering line systems is not a mature science or market

– Report will discuss what it takes to evolve SCADA to

active leak detection

Page 13: EERC Gathering Pipeline Study Status

Early Conclusions (Cont’d)

• Report will discuss ND spill statistics vs. other states, and

offer some reasons why those numbers differ

• Report will balance recommendations on how the state

can improve oversight with how industry can improve

installation and monitoring

• Report will contain recommendations for both industry

and state entities

• Report will not prescribe best pipeline materials

– Will emphasize that all are likely satisfactory, IF AND

ONLY IF very rigid adherence to prescribed installation

procedures and inspections is executed

Page 14: EERC Gathering Pipeline Study Status

Pipeline Spill Statistics (2001–2014)

Source: NDDH and DMR.

0

50

100

150

200

250

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

Tota

l Pip

elin

e S

pill

Inci

de

nts

Year

Total Pipeline Spill Incidents

Page 15: EERC Gathering Pipeline Study Status

0

100

200

300

400

500

600

700

800

900

2008 2009 2010 2011 2012 2013 2014

Bar

rels

Sp

illed

per

Mill

ion

Bar

rels

Pro

du

ced

Year

Alaska California North Dakota New Mexico

Brine Spill Volume, bbl/Oil Production, MMbbl

Page 16: EERC Gathering Pipeline Study Status

20

01

200

2

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Vo

lum

e (b

bl)

Oil Produced

Oil Spilled

Overall Spill Statistics (2001–2014)

In 2014, approximately 396,000,000 bbl of oil produced; 20,000 bbl of oil spilled (0.005%).

In 2014, approximately 432,000,000 bbl of brine

produced; 71,000 bbl of brine spilled (0.01%).

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Vo

lum

e (b

bl)

Brine Produced

Brine Spilled

Source: NDDH and DMR.

Page 17: EERC Gathering Pipeline Study Status

Looking Forward …

• Upon completion and submittal of study report, work will

begin on demonstration project planning

• Demonstration project will validate conclusions of study

– Demonstrate applicability of leak detection to gathering

pipelines (or not)

– Demonstrate expected costs of installation and

operation of leak detection on gathering pipelines

• Multiple partners likely

Page 18: EERC Gathering Pipeline Study Status

Contact Information

Energy & Environmental Research Center

University of North Dakota

15 North 23rd Street, Stop 9018

Grand Forks, ND 58202-9018

www.undeerc.org

John Harju, Associate Director for

Strategic Partnerships

Jay Almlie, Senior Research

Manager

(701) 777-5157 (701) 777-5260

[email protected] [email protected]