Educational and Research Centre in Transport Mgr. Lenka Čermáková. Educational and Research Centre in Transport. Operational Program Research and Development for Innovations Project reg. number: CZ.1.05/4.1.00/04.0137. Jan Perner Transport Faculty, University of Pardubice. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Educational and Research Centre in Transport

Mgr. Lenka Čermáková

Page 2: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Educational and Research Centre in Transport

Operational Program Research and Development for Innovations

Project reg. number: CZ.1.05/4.1.00/04.0137

Page 3: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Jan Perner Transport Faculty, University of Pardubice

• established in 1993• bears the name of Jan Perner – an outstanding 19th century railway

engineer• related to number of students, it is the second biggest faculty at university• 7 departments DFJP Profile: o strong technical character - focuses on transport engineering

and telecommunicationso connection of education and research which has direct impact on increase

to quality of human resources in Pardubice‘s region and the whole CR o The multidisciplinary character of Jan Perner Transport Faculty reflects

the complexity of problems occurring in transport and telecommunications

Page 4: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

History- reasons to build ERCT

1) to strengthen and improve education of doctoral study programmes in the field of transport means and transport infrastructure

2) to change existing heavy laboratories to laboratories with light operation or to new standard classrooms

3) to ensure the higher connectivity between education and experimental research

Page 5: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Preparation period 1/2009 – 1/2011

• spring of 2009 project team was established for preparation stage

• searching a place to build

• Plans of a building - “How big and what to include“

• Preparation of project application - Final resolution on allocation of dotation to ERCT project was given by the Ministry of Education, Youth and Sports in January 2011.

• Technical documentation, necessary permits were given (April 2010)

• Preparation of tender for building contractor

Page 6: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

History- previous heavy laboratories

Jan Perner Transport Faculty

Heavy laboratories

Page 7: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

History- finding a place to build

• Location:

• University technology area

• in Doubravice city part

Page 8: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Technical documentation and contract

• After receiving necessary permits- works on technical documentation had started

• After that tender documentation was prepared

• Draft contract for construction company

• - what was specified (total cost of the building, penalties, working schedule, communications, definition of building site, definition of technical documentation, bill of quantities, technical specifications of structure details and so on)

• Prepared by professional commercial company

Page 9: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Building of ERCTImportant data:Settled area: 2 321.92 m2 Length: 87.05 mUseful area: 3 417.55 m2 Width: 24.6 m Enclosure size: 24 133.50 m3 High: 9.25 m

Page 10: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

REALISATION 2/2011 – 04/2014

• main construction contractor tender• signature of contract• setting project team for ralisation period• tenders for all technologies, furniture, moving of

previous laboratory equipment• monitoring reports each 3 months• publicity • originally project end was 12/2013

Page 11: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Construction Contract and plan

• spring and summer 2011 tender on main constructing contractor proceeded

• 12 competitors applied such as Metrostav, Syner, Unistav, IMOS, Gemo, Hochtief.

• The winner was Zlínstav Inc. and contract was signed on 29th August 2011.

• The total cost of the building (without technology) is 97,9 mil CZK. Building works started the 1st September 2011

“milestones” of construction:• 01.09.2011 handover/takeover of building site (building commencement)

• 13.04.2012 completion of concrete structures under - 0,200

• 15.07.2012 completion of framework

• 15.08.2012 completion of cladding

• 15.10.2012 roof completion

• 15.01.2013 building preparedness for technology installation

• 09.07.2013 building acceptation

• 20.09.2013 final handover/takeover of building

Page 13: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Pictures of ERCT construction- Opening ceremony

Page 14: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

ERCT in operation

Page 15: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Budget85% 15%

the EU CZ State Budget

Previous budget- total costs estimated: CZK 266, 7 mil

Changed budget- total costs estimated: CZK 198, 1 mil

Page 16: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Project team

• 19 team members during realization phase

• 4 persons in the core realization team (sharing documents, regular and irregular meetings, in contact list for communication with the

Ministry), others were heads of departments and their assistants

• only 2 personal changes during realization phase

• in reality more time spent working on project than official work load of project team was

• cooperation with different departments of the institution

• Importance of information sharing

Page 17: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Project team scheme

Page 18: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Monitoring • monitoring period each 3 months

• monitoring reports prepared in electronic system called „Benefit“ with many supplements and copies of all documents in paper and also electronic form on CD have to be delivered personally to the Ministry in Prague

• financial manager and project manager from the Ministry are assigned to check the project

• remarks and inquiries must be answered within deadline given by the Ministry

• final report has to be delivered until the end of June 2014

Page 19: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Monitoring- comments

• in big project with many invoices 3 months monitoring period can be an advantage

• thousands of printed papers- hopefully- future change to electronic delivery only and electronic signing only

• in 3 years of project realization - 6 personal changes in project and financial managers of the Ministry- continuous explaining of history

• late approval of previous report from the Ministry-

e.g. minimum time to prepare new report in the „Benefit“

system online

• dozens of trips to Prague

Page 20: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Project publicity• regulations and rules given by the Ministry for project´s

publicity

• website- construction progress and basic project information

• a few press releases

• opening ceremony 10/2013- TV report in a news

• information brochure

• Facebook- started after opening of the Centre

• Planned: conferences, cooperation on international projects, video animation about purpose of laboratories, Researchers' night for public

Page 21: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Stickers to mark objects acquired from the project.

Page 22: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Changes in the project• A few informative, non important changes

• 4 official applications to the Ministry for substantial changes

1. Change of the budget (cause of very low price for building after tender), using part of saved money for technologies - APPROVED

2. Decrease in number of monitoring indicators- students (constant decreasing number of students at Universities within whole Czech republic)- APPROVED

3. Project prolongation and usage of saved money for new technologies- Denied REFUSED

4. Project prolongation until 04/2014 (to finish running tenders) APPROVED

Page 23: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Challenges and changes “Foresee unforeseeable, expect unexpected“

• Challenges during project realization we experienced Change of The Act Public Procurement Act (since 4/2012 rules have tightened up)

Significant change in Euro exchange rate

in 04/2014- 1€=27,45CZK

in 02/2011- 1 €= 24,1 CZK

Change of VAT (since 1/2013 VAT has raised from 20% to 21%)

Company providing construction supervision turned into being wounded up, they went bankrupt

Page 24: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Lessons to be learnt from the ERCT project

• Think positively

• Choose a hard working and long lasting project team

• Inform people in rest of the organization

• Start tenders as early as you can

• Learn from mistakes and success of other projects

• Good building surveyor is necessary while constructing

• Do not place memorial plaque on the building

before official end of the project

• Always think about your target

Page 25: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

…from an idea to reality in 5 years…

Page 26: Educational and Research Centre  in Transport Mgr. Lenka Čermáková

Thank you for your attention!

Contact details:

Mgr. Lenka Čermáková

[email protected]

+420 466 038 506

http://www.upce.cz/dfjp/vvcd.html

https://www.facebook.com/vvcd.upce