eastland woolen mill background information...
TRANSCRIPT
1
Eastland Woolen MillSuperfund Site
Eastland Woolen MillBackground Information
Textile Mill25 miles northwest of Bangor, MaineWool products
Fabric finishing and dyingDye-aid
Chlorobenzene, Dichlorobenzene (1,2; 1,3, and 1,4), and Trichlorobenzene (1,2,4 and 1,2,3)
Operations began in 1912Eastland Woolen Mill acquired mill in 1936Major employer for Town
Eastland Woolen MillBackground Information
Mill closes in 1996Stores began to closeSewer system and water system dependent upon MillMajor hit to tax base
Maine DEP initiates cleanup to remove solid and liquid waste from mill in 1996Town considers options for next steps 1996-1998
Eastland Woolen MillBackground Information
Town of Corinna deliberated whether to seek a Brownfield grant or request Superfund designation
BrownfieldsGrant to deal with investigation
Cleanup resources would need to come from another source
Local controlRedevelopment focus
Superfund PerceptionLose control to federal governmentCannot control outcomeCleanup focusCan Town be liable?
They took Mill property due to unpaid taxes
Requires support from Governor prior to placement on National Priorities List (NPL)Must complete the Hazard Ranking Process and exceed a score of 28.5
2
Eastland Woolen MillBackground Information
Town Officials and local citizens met with EPA in 1998Discussion focused on Brownfields vs Superfund NPLEPA explained its commitment to local input and consideration of re-use as part of “revitalized” Superfund programEPA also agreed to consider a dual track “SACM” model for the site
Determine if initial removal action is appropriate while completing the overall investigation program
EPA initiates removal evaluation in December 1998EPA signs Action Memorandum to initiate a Non-Time-Critical Removal Action (NTCRA) in July 1999EPA adds site to NPL in July 1999
Eastland Woolen MillSite Cleanup
Two components of cleanupStakeholder involvement
Local inputRe-use focus
Planning and implementation of cleanup
Critical area of overlap was the design phase
Integrate local and other stakeholders input Resolve divergent interests in a timely manner
Eastland Woolen MillSite Cleanup
How was it done?EPA provided Redevelopment grant for the development of a re-use planEPA provided a Technical Assistance GrantEPA met regularly with stakeholders and provided input to re-use planState Agencies were fully involved and invested in re-useEPA’s design consultants and implementation contractors were also committed to these themes
Eastland Woolen MillSite Cleanup
Examples of reuse integration into cleanupHistoric resources
Odd Fellows Building
Road re-alignment and bridge replacementRiver restorationSite grading and restorationGroundwater cleanup
3
Eastland Woolen MillSite Cleanup
Historic resourcesOdd Fellows Building
Eligible for National Register of Historic PlacesFoundation over riverTown wanted to saveCleanup plan required excavation beneath structure
EPA, State Historic Preservation Office, Town of Corinna
Town offered a new lotEPA could move once
Moving Odd Fellows HallMoving Odd Fellows Hall
Eastland Woolen MillSite Cleanup
Road re-alignment and bridge replacement
EPA needed to relocate the road and remove bridgeTown and State wanted a permanent re-alignmentEPA redevelop grant helped provide vision and frameworkTown and Maine DOT acquired property and resolve logistical issuesEPA only had to move road and bridge once rather than twice
Road ReRoad Re--AlignmentAlignment
4
Eastland Woolen MillSite Cleanup
River restorationDam beneath mill and shallow pond behind damEPA had to remove damTown, State of Maine (DOT, DOC, IFW, DEP), and EPA evaluated options
Return to unrestricted flowNo dam maintenanceFish passageCommunity Resource
River RestorationRiver Restoration
River RestorationRiver RestorationTown boardwalk trail along restored riverTown boardwalk trail along restored river
Eastland Woolen MillSite Cleanup
Site grading and restoration
EPA considered the original Town re-development planDeveloped revised figure based on updated subdivision and re-use planDeveloping grading plan to match re-use planTown installed utilities and roads in conjunction with EPA workCompleted back section of site early to allow for construction of Senior Housing
5
Eastland Woolen MillSite Cleanup Eastland Woolen Mill
Site CleanupGroundwater Cleanup
EPA cleanup included long-term pump and treat system
Permanent facility in downtown – middle of re-use areaTown and re-use committee requested that EPA re-considerTechnical information from design and early implementation indicated that system need only be temporaryEPA changed remedy in September 2006
Eastland Woolen MillEastland Woolen MillSite CleanupSite Cleanup
Cleanup involved innovation and innovative technology
Treatment systemSite CharacterizationIn-situ Remediation
Eastland Woolen MillEastland Woolen MillSite CleanupSite Cleanup
Treatment SystemDesign to have minimal stand-by costsLow-temperature thermal steam strippingAdapt to phased fundingPre-excavated and screened soil stockpile
6
Soil Treatment SystemSoil Treatment SystemSoil Treatment SystemSoil Treatment System
Soil Treatment Results
2.82.8(3.9)(3.9)
9.69.6(12.3)(12.3)
1.11.1(1.4)(1.4)
12.912.9(17.1)(17.1)
72.272.2(92.1)(92.1)
Avg. Pre-treatment
Contaminant Concentrations (mg/kg)
93%93%0.170.17(0.19)(0.19)
33ChlorobenzeneChlorobenzene
93%93%0.660.66(0.68)(0.68)
331,41,4--DichlorobenzeneDichlorobenzene
66%66%0.280.28(0.28)(0.28)
661,31,3--DichlorobenzeneDichlorobenzene
94%94%0.740.74(0.77)(0.77)
661,21,2--DichlorobenzeneDichlorobenzene
92%92%5.65.6(5.8)(5.8)
15151,2,41,2,4--TrichlorobenzeneTrichlorobenzene
Average Post-
Treatment
TreatmentGoal
Percent Contaminant Removal Based on
Average Pre- and Post-Concentrations
Contaminant of Concern
Note: Post-treatment results based on 4,200 samples. Number in () is the 95% upper confidencelevel
Eastland Woolen MillEastland Woolen Mill
Use of 3Use of 3--D graphics to present information and refine D graphics to present information and refine conceptual modelconceptual model
Rock ChipResults
7
Eastland Woolen MillEastland Woolen Mill
2-D representation of conceptual model
33--D Representation of Tracer Test D Representation of Tracer Test Tomography Tomography -- AnimationAnimation
In-situ Chemical Oxidation(ISCO)
ISCO selected to address groundwater and remaining source contaminationIron catalyzed PersulfateDeep overburden, shallow bedrock, and deep bedrock
ISCOISCO
8
PRE-ISCO GROUNDWATER CONTAMINATION POST-ISCO GROUNDWATER CONTAMINATION
PRE-ISCO GROUNDWATER CONTAMINATION
POST-ISCO GROUNDWATER CONTAMINATION
9
Groundwater Plume Reduction
BUILDING 14 / UST AREA
AREA 1
Eastland Woolen MillEastland Woolen MillSummarySummary
The local students painted murals on the abandoned mill in 1998 –the year EPA, the State of Maine, and the Town of Corinna along with hard working members of the community decided to do something about the mill and attempt to revitalize the abandoned downtown
Eastland Woolen MillEastland Woolen MillSummary Summary –– Mill area before Mill area before
Eastland Woolen MillSummary – Mill Area Today
10
Eastland Woolen MillEastland Woolen MillSummarySummary
Local input and re-use are critical elements of Superfund project managementObtaining early and substantial stakeholder involvement can greatly increase value of cleanup to communityProject Team must integrate re-use and other local input with main focus – cleanup
Not just the federal and state agencies: Investigation, design, and implementation consultants and contractors are a vital part of the team
Be prepared to adapt to funding, schedule, and other changes