![Page 1: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/1.jpg)
EAST DON TRAIL ENVIRONMENTAL ASSESSMENT
Public Meeting #3/3June 24, 20145:30 to 8:30 pmVictoria Park Hub
![Page 2: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/2.jpg)
Questions and Answers
East Don Trail Environment Assessment
We want to hear from you…
• Write down your questions• One question per sheet • Please print clearly
Following the presentation, staff will provide answers to as many on-topic questions as possible.
![Page 3: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/3.jpg)
Existing East Don Trail
Gatineau Corridor Trail
Don Trail Systems
Project PurposeProject Update
Facilities separated from the roadway, which support a number of non-motorized uses such as walking, running, cycling, inline skating, wheelchair users, and dog walking, amongst others.
The proposed East Don Trail will be an asphalt surface at 3.5 to 4 meters wide
Multi-use Trails
Gap in multi-use trail network
Problem/Opportunity
![Page 4: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/4.jpg)
Existing East Don Trail
Gatineau Corridor Trail
Don Trail Systems
Alternative Trail Alignments
Problem/Opportunity
Area 1
Area 2
Area 3
Alternative Trail Alignments
Project Update
Solutions
![Page 5: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/5.jpg)
East Don Trail Environment Assessment
• Alignments were evaluated and presented at Public Meeting #2o Majority of respondents agreed
with the evaluation as presented
• 3 revised Alignments were developed based on public and landowner input: o Forest Trail C – Area 1o Hillside Trail – Area 2o Corridor Trail – Area 2
Corridor Trail
Hillside Trail
Area 1
Area 2
Area 3
Forest Trail C
Alternative Trail AlignmentsProject Update
![Page 6: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/6.jpg)
Preferred Alignment:• Area 1: Forest Trail A
Area 1
Area 2
Area 3
Forest Trail A
Hillside Trail
Access Route B
Input was received from the Technical Advisory Committee and Community Liaison Committee to select a preferred alignment
Preferred Alternative Trail AlignmentsProject Update
• Area 3: Access Route B
• Area 2: Hillside– River Walk B ranked the highest
however as the land is not currently available moving forward with second highest ranking Hillside
![Page 7: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/7.jpg)
Preferred Alternative Trail Alignment being moved forward to next project phase Design Concepts
Preferred Alternative Trail AlignmentsProject Update
![Page 8: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/8.jpg)
East Don Trail Environment Assessment
Technical Constraints: Topography, Flooding and Trees
FloodingTopography Trees
Guiding Principles : • Accessibility requirements• Grades less than 5%• User needs • Trail outside of the 2 year floodline• Minimize impacts to the physical and natural environment• Needs of maintenance vehicles
Constraints and Guiding PrinciplesDesign Concepts
![Page 9: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/9.jpg)
Design ConceptsDevelopment How Design Concepts were Developed: 1. The preferred Alignment was divided into segments 2. Existing informal trails guided the placement of the concepts 3. Detailed topography and tree surveys 4. A range of viable Design Concepts were created and evaluated
1:Segments 2:Existing Informal Trails
3:Surveys 4:Design Concepts
![Page 10: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/10.jpg)
Alternative Design ConceptsDesign Concepts
Preliminary preferred Design Concept route “Outcome” based on
evaluation as presented on the panels
Alternative Design Concepts
Preliminary Preferred Design Concepts
Evaluation
![Page 11: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/11.jpg)
Example OutcomeDesign Concepts
The following slides will walk through of a few examples of design concept outcomes. Examples selected
represent some of the different situation within
the corridor.
![Page 12: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/12.jpg)
Example OutcomeDesign Concepts
N
Location of rail line
crossing north of
Eglinton Ave
Tunnel location – west & east of rail line
Meadow area with trees towards rail line and river
![Page 13: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/13.jpg)
Example OutcomeDesign Concepts
![Page 14: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/14.jpg)
Example OutcomesDesign Concepts
Low-lying wet area along forest
N
Low-lying wet area at base of slope, south of Eglinton
Existing informal trail
along a forested slope
![Page 15: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/15.jpg)
Example OutcomeDesign Concepts
![Page 16: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/16.jpg)
Example OutcomeDesign Concepts
Existing maintenance level crossing
An example of a level crossing with controls
*Note: level crossing to undergo safety assessment and all rail crossings subject to approval by Metrolinx.
Gatineau crossing location also subject to approval by Hydro One
N
Steep forest area east of rail line
Flat area just south of existing maintenance crossing
Example trail with ramp and bridge
Example switchback
![Page 17: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/17.jpg)
Example OutcomeDesign Concepts
![Page 18: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/18.jpg)
Example OutcomeDesign Concepts
N
Low west bank and erosion along east river bank
Existing informal
trail along the river
bank
Potential bridge location & example bridge on the Don
![Page 19: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/19.jpg)
Design Concept Options
Black lines = preferred segments
Map – “Birds eye view”
Profiles – “On the ground view”
Trail location
Existing Ground
How to read the panels – Maps and ProfilesDesign Concepts
![Page 20: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/20.jpg)
How to read the panels - EvaluationDesign Concepts
Option 1• Steeper grades throughout (5 to 9%) • Lower operating/maintenance costOption 2• Fewer steep grades (5 to 9%)• Greater variety of views and landscapes• Higher operating/maintenance cost
Option 2 Scored Higher than Option 1
Maps and profiles by segment above evaluation
Evaluation focuses on differences
between the options
Preliminary preferred design concept indicated at bottom
in colour of option
![Page 21: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/21.jpg)
East Don Trail Environment Assessment
Next StepsEast Don Trail Environmental Assessment
• Review public input on the recommended Design Concept
• Fill out a questionnaire today or mail one in by July 11, 2014
• Prepare Consultation Report for the third public event
• Select a Preferred Design Concept• File Environmental Study Report with Ministry of
Environment for 30 day public review• Detailed design and implementation**pending approval of the Environmental Assessment
![Page 22: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/22.jpg)
East Don Trail Environment Assessment
Feedback and InputEast Don Trail Environmental Assessment
We’d like your input at this key stage of the EA process!• Do you agree with the evaluation of the design
concepts as presented on the panels?• Do you agree with the overall preliminary
preferred design concept?
As we move into detailed design, what do you value the most: Protection of natural environment, user experience & aesthetics, cost, or maintenance requirements?
Please fill out a questionnaire
![Page 23: EAST DON TRAIL - Amazon Web Services...on-topic questions as possible. Existing East Don Trail Gatineau Corridor Trail Don Trail Systems Project Purpose Project Update Facilities separated](https://reader031.vdocuments.mx/reader031/viewer/2022013021/5f0cb45a7e708231d436b90e/html5/thumbnails/23.jpg)
Questions?
East Don Trail Environment Assessment
We want to hear from you…
• Write down your questions• One question per sheet • Please print clearly
Following the presentation, staff will provide answers to as many on-topic questions as possible.