earned value project management - mit opencourseware · 2 objective to introduce and discuss the...

17
1 Earned Value Project Management Colonel John Keesee Colonel John Keesee

Upload: truongtruc

Post on 05-Apr-2018

219 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

1

Earned Value Project Management

Colonel John KeeseeColonel John Keesee

Page 2: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

2

Objective

To introduce and discuss the fundamentals To introduce and discuss the fundamentals of earned value project managementof earned value project management

Work Breakdown StructuresWork Breakdown StructuresProgram plans and schedulesProgram plans and schedulesEarned value management systemsEarned value management systemsCost and schedule variancesCost and schedule variancesEstimates at completionEstimates at completion

Page 3: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

3

Scenario

You have been tasked to be the project You have been tasked to be the project manager for an important projectmanager for an important project

You have been directed to use an earned You have been directed to use an earned value management systemvalue management systemTime to market is critical for this Time to market is critical for this developmentdevelopment

Page 4: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

4

Work Breakdown Structure

Identifies 100 % of the work to be Identifies 100 % of the work to be accomplishedaccomplishedWBS dictionary breaks the scope into WBS dictionary breaks the scope into measurable tasksmeasurable tasks

Each with an estimated valueEach with an estimated valueResponsibility for each task assigned to Responsibility for each task assigned to individuals or work teamsindividuals or work teams

Page 5: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

5

Work Breakdown Structure

Launch Vehicle

Payload Spacecraft Reentry vehicle Integration, Assembly,Test and Checkout

Space Vehicle Ground Command,Control, Communicationsand Mission Equipment

Space System

Page 6: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

6

Project Master Schedule

Detailed plan and scheduleDetailed plan and scheduleIdentified dependencies between tasksIdentified dependencies between tasks

18 months18 monthsEstimated resources for each taskEstimated resources for each task

10 units at $150K each10 units at $150K each

Page 7: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

7

Project Master ScheduleTask/Event Jan - Jun Jul - Dec Jan - JunAward ^Design ^Buy specifications ^Vendor quotes ^ Purchase orders ^Receive materials ^Factory plans ^Tool design ^Tool fabrication ^Parts fabrication ^Assembly: sub and final ^Test & checkout ^

Page 8: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

8

Project Performance Display

0

200000

400000

600000

800000

1000000

1200000

1400000

1600000

Jan

April

July

Octobe

rJa

nuary Apri

l

July

BCWSBCWPACWP

Page 9: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

9

Plan Review Before Go-Ahead

CEO:CEO:“Time to market is critical. You have 12 “Time to market is critical. You have 12 months.”months.”“This looks gold“This looks gold--plated at $1.5M. You plated at $1.5M. You have $1.0M.”have $1.0M.”“Go ahead, but come back to me with “Go ahead, but come back to me with your progress in three months.”your progress in three months.”

Page 10: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

10

The Three Month Review

Three units scheduled for completionThree units scheduled for completionTwo units actually completedTwo units actually completed$300,000 budgeted at this point$300,000 budgeted at this point$300,000 actually spent$300,000 actually spentOptimist PM: “A little behind schedule but Optimist PM: “A little behind schedule but right on the cost plan.”right on the cost plan.”

Page 11: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

11

Earned Value System

Requires a detailed, bottomsRequires a detailed, bottoms--up up performance planperformance planPerformance measured against the planPerformance measured against the planProvides forecast of final expected results Provides forecast of final expected results based on databased on data

Page 12: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

12

Earned Value Measurements

1.1. Work scheduledWork scheduled2.2. Budgeted cost of work scheduled (BCWS)Budgeted cost of work scheduled (BCWS)3.3. Work performedWork performed4.4. Budgeted cost of work performed (BCWP)Budgeted cost of work performed (BCWP)5.5. Actual cost of work performed (ACWP)Actual cost of work performed (ACWP)6.6. Schedule variance (SV) = BCWP Schedule variance (SV) = BCWP -- BCWSBCWS7.7. Cost Variance (CV) = BCWP Cost Variance (CV) = BCWP -- ACWPACWP

Page 13: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

13

New Project Performance Display

0

200000

400000

600000

800000

1000000

1200000

Janu

ary April

July

Octobe

rDec

embe

rBCWSBCWPACWP

Page 14: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

14

Estimate at Completion

Cost efficiency CPI = BCWP/ACWPCost efficiency CPI = BCWP/ACWPSchedule efficiency SPI = BCWP/BCWSSchedule efficiency SPI = BCWP/BCWSEstimate at completionEstimate at completion

CPIBACEAC =1

SPICPIBCWPBACACWPEAC

*2

−+=

Page 15: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

15

Management Reserve

Budgeted to provide the ability to adjust for Budgeted to provide the ability to adjust for uncertaintyuncertaintyAlways accounted at the total project levelAlways accounted at the total project levelNormally retained and controlled at the total Normally retained and controlled at the total project levelproject levelMust not be eliminated by negotiationsMust not be eliminated by negotiations

Page 16: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

16

Summary

Earned value management system provides Earned value management system provides a key link between the cost, schedule, and a key link between the cost, schedule, and technical aspects of a projecttechnical aspects of a projectProvides an early and reliable prediction of Provides an early and reliable prediction of future performancefuture performance

Page 17: Earned Value Project Management - MIT OpenCourseWare · 2 Objective To introduce and discuss the fundamentals of earned value project management Work Breakdown Structures Program

17

References

Fleming, Quentin W. and Joel M. Fleming, Quentin W. and Joel M. KoppelmanKoppelman, , Earned Value Project Earned Value Project Management, Management, PMI, Newtown Square, PA PMI, Newtown Square, PA 20002000Lewis, James P., Lewis, James P., Fundamentals of Project Fundamentals of Project ManagementManagement, AMACOM, NY 2002, AMACOM, NY 2002