earned value in five easy pieces

20
Earned Value in Five Easy Pieces Not that Earned Value can be made that easy, but this is the start of getting our mind around the concepts of project performance measurement 1

Upload: glen-alleman

Post on 15-Jan-2015

3.371 views

Category:

Technology


2 download

DESCRIPTION

A simple introduction to the principles of Earned Value Management

TRANSCRIPT

Page 1: Earned value in five easy pieces

Earned Value in

Five Easy Pieces

Not that Earned Value can be

made that easy, but this is the start of getting our mind

around the concepts of project performance

measurement

1

Page 2: Earned value in five easy pieces

1. Using a credible schedule, define the planned value of the work 2. Measure the Physical % Complete for each period of performance 3. Calculate Earned Value = Planned Value x Physical % Complete 4. Using the Earned Value variables ,calculate the performance indices 5. With the performance indices take corrective actions

2

Page 3: Earned value in five easy pieces

Using a credible schedule, define

the planned value of the work

3

1

Page 4: Earned value in five easy pieces

Create Work Packages for the

activities that produce physical

outcomes

I

1

4

Page 5: Earned value in five easy pieces

Define the planned value (PV)(BCWS) spreads for each

Work Package

I

1

5

Page 6: Earned value in five easy pieces

Measure Physical Percent Complete of Work

Package Outcomes

2 6

Page 7: Earned value in five easy pieces

Define 0/100 or

50/50 activities

within each Work

Package.

You’re either

done or not done.

There is no

“partial” done for

a Work Package.

2 7

Page 8: Earned value in five easy pieces

Define Apportioned

Milestones that

describe the

incremental

progress of the Work

Package in units

meaningful to the

customer

II

2

8

Page 9: Earned value in five easy pieces

Use evidentiary materials

for each measurement.

These are the only

measures of progress.

Not the passage of time

or the consumption of

resources.

“Show Me the

Outcomes”

II 9

2

Page 10: Earned value in five easy pieces

Calculate the Earned Value 3

10

Page 11: Earned value in five easy pieces

11

The Value that is Earned - the Earned Value - is the percent of the Planned Value that was delivered at the end of the period of performance.

The percentage assessment is always measured by some physical assessment, some evidence that this percentage was actually achieved

EV= PV Physical Percent Complete

3

Page 12: Earned value in five easy pieces

Using the Earned Value variables (BCWS, BCWP, ACWP), calculate Performance Indices

4 12

Page 13: Earned value in five easy pieces

The To Complete Performance Index (TCPI)

13

EAC

BAC BCWPTCPI

EAC ACWP

4

Page 14: Earned value in five easy pieces

The Independent Estimate At Completion (IEAC)

14

1

2

3

4 1 2

5 ( )

cum cum

cum cum

cum cum

cum cum period

EAC BAC CPI

EAC ACWP BAC BCWP SPI

EAC ACWP BAC BCWP SPI CPI

EAC ACWP BAC BCWP wt SPI wt CPI

EAC ACWP BAC BCWP CPI

Probably as Good

as it Gets

Probably as Bad

as it Gets

4

Page 15: Earned value in five easy pieces

V

With the performance indices‘, take

corrective action for remaining

work

15

5

Page 16: Earned value in five easy pieces

16

Earned Value must measure work

performance within a pre-defined

period of time – the period of

performance

At the end of a project, the Earned Value

always equals the Planned Value – since all

the work has been done.

What is different is how long it took and how

much money is cost.

Earned Value bounds the time period to the

Planned period

IV

Page 17: Earned value in five easy pieces

17

Inattention to budgetary responsibilities Work authorization not always followed Budget and data reconciliation issues Lack of integrated management systems Baseline fluctuations and frequent

replanting Current period and retroactive changes Improper use of management reserve Earned Value techniques not reflecting

actual accomplishments Untimely and unrealistic Latest Revised

Estimates (LRE)

Progress not monitored in a regular and consistent manner

Lack of vertical and horizontal traceability (critical path)

Not capturing and using cost and schedule data for corrective action

Lack of predictive variance analysis Lack of internal surveillance and controls Managerial actions not demonstrated

using Earned Value

Failing to us discipline and

rigor can put you on the

beach. So remember…

A ship on the beach is a

lighthouse to the sea

– Dutch Proverb

Page 18: Earned value in five easy pieces

Are You Doing Earned Value?

Do we know the value of

the planned work? Have we bounded the

period of performance for each work element?

Do we know how to measure Physical Percent Complete?

18 www.jack-nicholson.info

Page 19: Earned value in five easy pieces

Earned Value is

fundamentally a

planning tool.

It will not “fix”

problems with

projects.

But it will make the

performance

problems visible in

analytical ways.

19 www.jack-nicholson.info

Page 20: Earned value in five easy pieces

Glen B. Alleman

Niwot Ridge Consulting

4347 Pebble Beach Drive

Niwot, Colorado 80503

303.241.9633

[email protected]

Performance Based Management(sm)

Integrated Master Plan

Integrated Master Schedule

Earned Value Management Systems

Risk Management

Proposal Support Services

20/58 Glen B. Alleman, Copyright © 2012