E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

Upload: roderick-ray

Post on 29-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

E906 Spectrometer Upgrade Overview

Paul E. Reimer

Magnet Concept

Design

Estimates (Money & Time)

Page 2: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

211 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

Magnet Concept

Use pieces from existing (but dismantled) SM12 Magnet– This was the large dipole used by E866 and predecessors

Design coils to minimize the need to cut existing iron Decrease nonBend aperture

– to match downstream acceptance– Save on Amp-Turns

Tapered pole pieces

Copper Beam dump (either modified from E866/SM12 or new)

Graded hadron absorber within aperture of magnet (Copper, Carbon, Polyethylene)

Page 3: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

311 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

66”

198”

50’ (9 blocks long)

2£17”

SM12 Removal

Page 4: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

411 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

M1 Magnet

New coils Reuse whole pieces of SM12 magnet yoke (1/3 or total SM12 yoke) Beam dump either modified to fit or new (from Fermilab) Coil Design Team

– Jack Jagger—Engineering (PHY-STA)

– Ken Thompson—Field, power calculations, etc (APS)

– Tom O’Connor and Kevin Bailey—design and drafting (PHY)

Page 5: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

511 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

M1 Magnet

Parameter Parameter

Length 189 in Cooling Water

Width (Vert. Bend)

95 in Temp Rise 25^\circ C

Height 198 in Flow rate 90 g/min

Aperture Weight

Bend 48 in Pole Inserts

9.5 t

Non-Bend 26 in Coils 19 t

Current 2,400 A Yoke 420 t

Voltage 240 V Total 450 t

Power 0.58 MW

Page 6: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

611 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

Budgetary Estimates: Aluminum conductor

Conductor Properties– Al 1350 Alloy– 1.6 £ 1.6 inch – 0.700 inch diameter hole for cooling

Estimate From Alconex, Fort Wayne, IN– Will vary with base metal price– Investigating additional possible

vendors

Item Cost

Base Metal ($1.25/lb) $59,400

Fabrication $186,700

Testing $13,700

Misc. (die, ship, etc.) $7,500

Total $267,300

× 1.2 (contingency)

× 1.1 (Overhead)

× 1.03 (inflation) $363,000

Page 7: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

711 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

Budgetary Estimate: Coil Fabrication

Contacted 5 possible vendors in Fall 2004 for budgetary estimates based on preliminary designs—4 vendors responded by January 2005

Revisited estimates with 3 of 4 vendors for this review (Oct-Nov 2006)

Conductor Tooling and setup

Coil Fabr. Ship. Total

Everson Tesla

Nazareth, PA

Included $160k $703k $7k $870k

Sigma Phi

France

$267k

(our est.)530 euro × 1.30 $/euro

$689

$20k

(our est.)

$976k

Alpha Magnetics

Hayward, CA

$267k

(our est.)

$74k $429k $9k $779k

For budget, estimate is based on Sigma Phi total, but will use lowest bidder in which there is confidence

× 1.2 (contingency) × 1.1 (Overhead) × 1.03 (inflation)

Page 8: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

811 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

M1 Magnet Coil Fabrication Budget

Cost dominated by cost of conductor and coil ($1.3M of $1.6M)

Tab. III of review document

Page 9: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

911 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

Coils: Fabrication time

Schedule based on longest lead-time vendor: – Sigma Phi: 10 Months with conductor available 4 months before Sigma Phi: 10 Months with conductor available 4 months before

deliverydelivery– Everson Tesla: 18-22 week (5 months)– Alpha Magnetics: no estimate

Requested Budget—purchase coils over two years:– FY2007:

• Bid and contract for coils• Purchase tooling

– FY2008 (starting in Jan 2008)—this is delay is the critical path itemthis is delay is the critical path item:• Purchase conductor• Fabrication of coils

Page 10: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

1011 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

Magnet Timeline

Al Conductor delayed to FY08

Coil Fabrication delayed to FY08

Page 11: E906 Spectrometer Upgrade Overview Paul E. Reimer Magnet Concept Design Estimates (Money & Time)

1111 December 2006 Paul Reimer E906 Sepctrometer Upgrade Overview

Conclusions

Design of magnet is underway Sufficiently advanced enough to obtain reasonable budgetary

estimates on coil fabrication from vendors Both budget and time line are based on conservative estimates