E. Talero - 11- 11-04 IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior E-Government Consultant - The World Bank (Retired) Nairobi, November 11, 2004

Upload: horatio-mclaughlin

Post on 02-Jan-2016

227 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 1

IFMIS Implementation Workshop

Effective IFMIS Procurement and Management of Consultants

Eduardo TaleroSenior E-Government Consultant - The World Bank

(Retired)

Nairobi, November 11, 2004

Page 2: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 2

9-15 months 6 months

Develop Functional/Technical Specifications

Advertise and receive bids

Prepare Bidding documents

Evaluate bids

Award contract

4-5 months 2 months 21-28 months

3-5 months 3 months3-4 months 2 months 11-14 months

Best case

Possible?

IFMIS PROCUREMENT IN AFRICA

Page 3: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 3

OVERVIEW

How to be effective in IS procurement (and minimize headaches)

How to get maximum value from consultants

How to deal with the World Bank to prevent delays

Page 4: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 4

Effective Procurement (or how to minimize headaches)

Acknowledge complexity Find the right skills & organize the

work Develop a sound strategy Manage timetable effectively Follow sound bid evaluation method Develop a smart, fair contract

Page 5: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 5

The procurement process is difficult because

It is a heavily regulated, competitive process

It has antagonistic stakeholders It is complex and deals with high

stakes. It is corruption prone. It often has conflicting objectives.

Page 6: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 6

Competitive Procurement

TRANSPA-RENCY

Potentially conflictive objectives in competitive procurement

ECONOMY

Page 7: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 7

Competitive Procurement

TRANSPA-RENCY

Potentially conflictive objectives in competitive procurement

EFFICIENCY

Page 8: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 8

IS Procurement is even more difficult because of:

Diverse, complex technical content Interdependency with organizational

& social dynamics Value from the whole, not the parts Mix of intellectual services & supply

of goods. High failure rate of IS Projects

Page 9: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 9

Technology. (Goods)

Intellectual Services (Consultants)

Working Systems (IFMIS)

“DESIGN” RISK Supplier Client Shared

CSFs Tech. Specs Logistics

Prof. Expertise Communications

Prof. Expertise Process Mgmt.

QUALFICATION CRITERIA

Ability to supply

Fin. strength

Credentials Track record

Financial /operational capabilities

Track record Credentials

EVALUATION CRITERIA

Price Quality of

M&S

Quality of Proposal

Expertise Price

Quality of Proposal Expertise Price

PAYMENT TRIGGER

Delivery Work done

Acceptance of Deliveries

Procurement profiles

Page 10: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 10

Acknowledge complexity Find the right skills & organize the

work Design a sound strategy Manage timetable effectively Follow sound bid evaluation method Develop a smart, fair contract

Effective procurement (or how to minimize headaches

Page 11: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 11

Find the right skills & organize the work

Skill requirements: Domain knowledge: public accounting,

budgeting and treasury management. Expertise in management of IS projects Information technology knowledge Contracting knowledge Procurement knowledge

Effective procurement requires organized teamwork: authorities, responsibilities, schedule, resources.

Page 12: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 12

Effective Procurement (or how to minimize headaches)

Acknowledge complexity Find the right skills & organize the

work Develop a sound strategy Establish feasible timetable Follow sound bid evaluation method Develop a smart, fair contract

Page 13: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 13

Develop a sound strategy

Understand the solution market Consult with peer network Choose a packaging option Choose a process option Set a timetable

Page 14: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 14

Supply & Maintenance of Technology

System Engineering/ Integration

Independent Audits

RFI & Pre-Qualification

Phase IIProject Strategy &

System Requirements

Phase I

System Engineering

Phase III

Implementation

Phase IV

Maintenance

Phase V

System Specification & Project Mgmt.

PROJECT PHASE

PROCUR. TRACK

Key: Competitive Bidding Packaging Option

Conflict of Interest

Consulting Services Supply &Maintenance System Engineering

Ponder packaging options carefully (1)

Page 15: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 15

Supply & Maintenance of Technology

System Engineering/ Integration

Independent Audits

RFI & Pre-Qualification

Phase IIProject Strategy &

System Requirements

Phase I

System Engineering

Phase III

Implementation

Phase IV

Maintenance

Phase V

System Specification & Project Mgmt.

PROJECT PHASE

PROCUR. TRACK

Key: Competitive Bidding Packaging Option

Conflict of Interest

Consulting Services

Integration

Ponder packaging options carefully (2)

Page 16: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 16

Choose between single and 2-stage process

Single stage when: Possible solutions are well known Outsourcing is not an option Procurement complexity and risk are moderate

Two stage when: Possible solutions are poorly known Outsourcing of operation or ownership is an

option Large scope or complexity pose excessive risks

Page 17: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 17

Effective Procurement (or how to minimize headaches)

Acknowledge complexity Find the right skills & organize the

work Develop a sound strategy Establish feasible timetable Follow sound bid evaluation method Develop a smart, fair contract

Page 18: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 18

At least a monthTime

Engineer system

Document System

Deliver test Hw/OS

Acceptance End rollout

Train users

Run Acceptance Tests

Deliver rollout Hw/OS

Begin Testing

Establish feasible timetable

Deliver pilot Hw/OS

Conduct pilot

Rollout system

End Pilot

Page 19: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 19

Effective Procurement (or how to minimize headaches)

Acknowledge complexity Find the right skills & organize the

work Develop a sound strategy Manage timetable effectively Follow sound bid evaluation method Develop a smart, fair contract

Page 20: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 20

Follow sound bid evaluation method (1)

Assemble a team beyond reproach Decide what features to evaluate Beware of evaluation tradeoffs Focus on features with high

discerning value Leave room for exercise of

judgment

Page 21: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 21

Follow sound bid evaluation method (2)

Define & test the point/weight scheme

Plan effective system demonstrations

Carry out & document evaluation Keep evaluators to what they know Iterate evaluation rounds to achieve

consistency

Page 22: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 22

Decide what features to evaluate

Known Un-known

Needed Unacceptable

Desirable

Undesirable

M

M

S +E

S +E

E

E

E

E

Page 23: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 23

Beware of tradeoffs in quality evaluation

Importance of Quality Evaluation

Level of competition

Range of solutions considered

Precision of qualification requirements

Precision of Technical Specifications

Page 24: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 24

Illustrative Top Level Scoring Table

Note: See IT Procurement Technical Note 10 at www.worldbank.org, procurement

Criterion Criterion1 Criterion 2 Criterion 3 Criterion 4 Total (Maximum)

Weight 40 20 20 20 100 Scores and Weight points [1] -10 -5 -5 -5

[2] 0 0 0 0

[3] 20 10 10 10

[4] 40 20 20 20 100

Page 25: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 25

Evaluation Criteria

1: Quality of proposed solution

2: Bidder's expertise, performance record, business risk profile.

3: Quality of implementation plan and knowledge transfer strategy

40%

4: Quality of proposed technical environment. - Technical Risk Profile

Weight 

20%

30%

10%

Illustrative Evaluation Criteria for IFMIS Contract

Note: See IT Procurement technical note 10 at www.worldbank.org, procurement

Page 26: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 26

Follow sound bid evaluation method (2)

Define & test the point/weight scheme Plan effective system demonstrations Carry out & document evaluation Keep evaluators to what they know Iterate evaluation rounds to achieve

consistency Evaluate lifecycle costs

Page 27: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 27

Plan effective system demonstrations

Choose one of two objectives: Evaluate attributes of proposed solution Build and evaluate a prototype solution

Predefine standard protocol Require PM to lead demonstration Watch for presentation order bias Iterate to ensure evaluation consistency Lower compliance cost to bidders

Page 28: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 28

Follow sound bid evaluation method (2)

Define & test the point/weight scheme Plan effective system demonstrations Carry out & document evaluation Keep evaluators to what they know Iterate evaluation rounds to achieve

consistency Evaluate lifecycle costs

Page 29: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 29

Effective Procurement (or how to minimize headaches)

Acknowledge complexity Find the right skills & organize the

work Develop a sound strategy Manage timetable effectively Follow sound bid evaluation method Develop a smart, fair contract

Page 30: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 30

Develop a smart, fair contract (1)

Make contractor responsible for solving your business problem despite specification error or omission

Spell out client’s obligations and fulfill them.

Require formal work methodology Pay against intermediate deliverables

Page 31: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 31

Develop a smart, fair contract (2)

Define the acceptance test protocol Test all the human/data/process

aspects before acceptance Do system stress tests Define the rollout protocol Define rollout readiness indicators

Page 32: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 32

Develop a smart, fair contract (3)

Leave flexibility in rollout schedule Demand industry-standard

documentation

Page 33: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 33

Develop a smart, fair contract (4)

Retain host computer flexibility Guard against default expiration of

licenses Consider concurrent user licenses Forbid cross-licensing conditions Disallow unilateral revocation of SLA,

disabling or impairment of system operation.

Software License Agreements (1)

Page 34: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 34

Develop a smart, fair contract (5)

Require manufacturer’s authorization and concurrence on supplier’s SW licensing obligations.

Supplier must support an old version 24 months after new one is received by client.

If a new version causes problems, supplier must support the prior version until problems are solved.

Software License Agreements (2)

Page 35: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 35

Develop a smart, fair contract (6)

Develop good M & S contract:

Ask for proof of local capability Commit M & S supplier for 5+ years Keep client’s right to exit after 1 year Block effectiveness of supply contract

until M&S contract is signed Retain performance security until

delivery capacity is verified.

Page 36: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 36

OVERVIEW

How to be effective in IS procurement (and minimize headaches)

How to get maximum value from consultants

How to deal with the World Bank to prevent delays

Page 37: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 37

Consultants: How to get maximum value (1)

Rely on peer network to: Identify skill / experience requirements Develop TOR. Develop candidate shortlist

Expect bias and neutralize through TOR

Watch out for conflict of interest rules

Page 38: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 38

Supply & Maintenance of Technology

System Engineering/ Integration

Independent Audits

RFI & Pre-Qualification

Phase IIProject Strategy &

System Requirements

Phase I

System Engineering

Phase III

Implementation

Phase IV

Maintenance

Phase V

System Specification & Project Mgmt.

PROJECT PHASE

PROCUR. TRACK

Key: Competitive Bidding Packaging Option

Conflict of Interest

Possible Contractor Continuation

Consulting Services Supply &Maintenance System Engineering

Complex IS Procurement – Specify and Engineer Option

Page 39: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 39

Consultants: How to get maximum value (2)

Define time and residence requirements for key personnel

Define knowledge transfer indicators Evaluate communication, social skills Use contract management

instruments consistently and forcefully

Control staff replacements

Page 40: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 40

Consultants: How to get maximum value (3)

Brief/induct consultants thoroughly Control incidental costs separately Pay attention to fairness Do not expect fire fighting miracles Pay on time Manage client-side obligations

Page 41: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 41

Dealing with the World Bank (1)

WB not staffed for major technical reviews Fiduciary responsibility imposes

constraints. Key recommendation: avoid triggering

reviews. Consequently, engage expert procurement

advice during process. You are the client. Do not hesitate to

complain.

Page 42: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 42

Dealing with the World Bank (2)

Do not hesitate to ask for reasonable, well justified exceptions. Better evaluation formula Relief from COI provisions for pilot

consultants Justified sole sourcing decisions

Page 43: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 43

Possible World Bank support

To develop and nurture IFMIS network

To develop baseline system requirement specifications

To analyze and compare technology licensing terms

Page 44: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 44

9-15 months 6 months

Develop Functional/Technical Specifications

Advertise and receive bids

Prepare Bidding documents

Evaluate bids

Award contract

4-5 months 2 months 21-28 months

3-5 months 3 months3-4 months 2 months 11-14 months

Best case

Possible?

IFMIS PROCUREMENT IN AFRICA

Page 45: E. Talero - 11-11-04IFMIS Workshop - Nairobi 1 IFMIS Implementation Workshop Effective IFMIS Procurement and Management of Consultants Eduardo Talero Senior

E. Talero - 11-11-04 IFMIS Workshop - Nairobi 45

THANK YOU