dranesville - capital project summary report foundation design revision to ... the utilities design...
TRANSCRIPT
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 400-C40001
Project Number/SubProject Number TF-000017-001 0
Project Name Fairfax Connector – Reston-Herndon Operating Facility
Project Description The project includes renovations to the existing building and upgrades to the site at the existing Reston-Herndon Bus Operating Facility located at 268 Spring Street, Herndon, VA 20170.
12,000 Total Project Estimate ($k)
Future Funding ($k)
Construction Current Status
5/6/2016 (A) Construction Award
Spring - 2018 Project Complete
Remarks Phase 2 interior renovation substantial completion was given on 03/30/18. With the added scope of concrete pavement for the site, the overall
completion date for the project extends through late spring 2018.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 400-C40061
Project Number/SubProject Number CC-000015-001 0
Project Name McLean Community Center Improvements
Project Description Expansion and renovation of McLean Community Center's Ingleside Avenue facility.
8,474 Total Project Estimate ($k)
Future Funding ($k)
Construction Current Status
2/15/2017 (A) Construction Award
Fall - 2018 Project Complete
Remarks The building slab was placed in March/April 2018. The plumbing rough-in for the courtyard and duct fabrication throughout the building are complete. The new roof system has been installed except for gravel wearing layer. Framing for exterior soffits is underway, and drywall installation and glazing installation are scheduled for April 2018.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 400-C40013
Project Number/SubProject Number TF-000027-001- 0
Project Name Innovation Center Station Parking Garage
Project Description An approximately 2,072-space parking structure with bus bays, a Kiss & Ride, and a pedestrian connection for Metro Silver Line-Phase 2. Located at 2345 Innovation Center, Herndon, VA.
52,000 Total Project Estimate ($k)
Future Funding ($k)
Construction Current Status
3/7/2017 (A) Construction Award
Spring - 2019 Project Complete
Remarks The installation of garage foundation piers is nearly complete, and Stair A foundations are in progress. Pre-cast installation began on 4/9/18 and a temporary closure on Magna Way was coordinated with the community for phase 1 installation. Dominion Virginia Power coordination for installation of utility ductbank is ongoing. The construction is approximately 37% complete.
Coordination on the Common Infrastructure continues on construction activities and the resolution of costs and infrastructure construction agreement issues.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 400-C40101
Project Number/SubProject Number SD-000031-174 0
Project Name Stream & Water Quality Improvements
Salt Storage Facilities
Project Description The following three sites are being developed for salt storage facilities to meet MS4 requirements: Lake Fairfax Park, Central Material Facility, and Dulles Material Facility.
5,850 Total Project Estimate ($k) 5,850 Future Funding ($k)
Design Current Status
TBD Construction Award
Project Complete TBD
Remarks Gauthier, Alvarado & Associates was authorized to proceed with Phase II A/E services on 2/23/18. A meeting was held on 3/5/18, with zoning
and a 2232 submission is required for the three project sites. Site plan submissions and 50% Construction Documents are scheduled for 5/18,
for the CMF and DMF sites. MSMD is continuing to review the Lake Fairfax project site.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 300-C30010
Project Number/SubProject Number HS-000011-001 0
Project Name Lewinsville Redevelopment
Project Description A new 32,000 SF Intergenerational Center, located at 1611 Great Falls Street, McLean, which includes a senior center, adult daycare center and two child care centers.
18,900 Total Project Estimate ($k)
Future Funding ($k)
Construction Current Status
8/1/2017 (A) Construction Award
Summer - 2019 Project Complete
Remarks The construction of the project is 40% complete. Foundations, slab on grade, and under slab utilities are in place. Exterior wood framing and
sheathing are complete. Roof truss installation is 95% complete. Roof shingle installation is currently underway and is scheduled to be
completed by 4/30/18. Interior partition framing is currently underway. M/E/P rough-in is ongoing.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 400-C40101
Project Number/SubProject Number SD-000031-043 0
Project Name Storm Drainage Outfalls 10030 Colvin Run Road- Robinson, PCL 19 Outfall Improvement @ Pond 0723DP (DF82-0003)
Project Description Restore ~260 lf of outfall for improved water quality and rehabilitate 73 lf of road culvert and endwall.
Total Project Estimate ($k) 745
Future Funding ($k)
Construction Current Status
11/1/2017 (A) Construction Award
Spring - 2018 Project Complete
Remarks Notice-to-proceed was issued to Environmental Quality Resources, LLC on 11/1/17. Work began 12/6/18 and construction is approximately 75% complete.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 400-C40101
Project Number/SubProject Number SD-000031-100 0
Project Name Stream & Water Quality Improvements
Dead Run Stream Restoration Segment 2/3
Project Description Restore ~3,200 lf of stream using natural channel design principles and riparian corridor enhancements for improved water quality.
Total Project Estimate ($k) 3,346
Future Funding ($k)
Current Status Construction
Construction Award 1/15/2018 (A)
Project Complete Winter - 2019
Remarks Notice-to-proceed was issued to Meadville Land Service, Inc. on 2/6/18. Construction is 10% complete.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 400-C40101
Project Number/SubProject Number SD-000031-131 0
Project Name Stream & Water Quality Improvements
Bull Neck Run at Springhill Rec. Center
Project Description Restore ~1,350 lf of stream channel using natural channel design for improved water quality.
2,904 Total Project Estimate ($k)
Future Funding ($k)
Construction Current Status
5/3/2018 (A) Construction Award
Spring - 2019 Project Complete
Remarks Final design plans prepared by Stantec Consulting Services, Inc. have been authorized for construction. The contract was awarded to Resource Environmental Solutions, LLC.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
400-C40101 Fund
SD-000031-155 0Project Number/SubProject Number
Stream & Water Quality Leigh Meadow & Towlston Basin (0584DP/0103DP Project Name Improvements
Project Description Retrofit two basins and restore ~1,600 lf of stream channel using natural channel design for improved water quality.
2,768 Total Project Estimate ($k) 2,208 Future Funding ($k)
Design Current Status
TBD Construction Award
Project Complete TBD
Remarks Staff received a revised concept of Towlston Meadow basin from Stantec Consulting Services, Inc. on 3/22/18. Staff is reviewing design with
comments due on 4/20/18. The 65% design is due 6/8/18.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
400-C40101 Fund
SD-000031-183 0Project Number/SubProject Number
Stream & Water Quality Piney Run@Lake Werowance (DF82-0017/FM0030) Project Name Improvements
Project Description Restore ~4,385 lf of stream using natural channel design and riparian corridor enhancements for improved water quality.
4,250 Total Project Estimate ($k) 3,700 Future Funding ($k)
Design Current Status
TBD Construction Award
Project Complete TBD
Remarks Task order for concept design was authorized with Stantec Consulting Services, Inc. on 2/7/18. Stantec is scheduled to submit the pre-design plan by 8/3/18.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 400-C40101
Project Number/SubProject Number SD-000034-036 0
Project Name Major Storm Drainage Maintenance Scotts Run Tributary @ Windy Hill Road (SC82-0001)
Project Description Stabilize/restore 650 lf of stream using natural stream channel design to improve downstream stormwater infrastructure and water quality.
1,318 Total Project Estimate ($k)
Future Funding ($k)
Design Current Status
Spring - 2018 Construction Award
Fall - 2018 Project Complete
Remarks Acquisition of land rights was completed on 12/1/17. Rinker Design Associate submitted the final design on 4/9/18. Final construction package
will be transmitted to the Utilities Design and Construction Division by 5/6/18.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
690-C69300 Fund
WW-000001-01 0Project Number/SubProject Number
Pumping Stations CIA PS Rehab Project Name
Project Description Rehabilitation of Central Intelligence Agency Pump Station.
1,700 Total Project Estimate ($k) 1,700 Future Funding ($k)
Pre-Design Current Status
TBD Construction Award
Project Complete TBD
Remarks Project is currently in scope development.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 690-C69300
Project Number/SubProject Number WW-000007-01 0
Project Name Collection System Replacement and Rehabilitation
Sluice Gate Rehab/Odor Control
Project Description Replacement of sluice gates, installation of active odor control system at Carderock site, and installation of passive odor control system at Scotts Run site.
3,269 Total Project Estimate ($k) 2,969 Future Funding ($k)
Construction Current Status
1/25/2017 (A) Construction Award
Fall - 2018 Project Complete
Remarks CDM is utilizing Booth & Associates to prepare the plan & specs for the Carderock overhead power line repairs. The National Park Service
reviewed a rendering of a proposed open enclosure for the Carderock Odor Control. Site work for Scotts Run Odor Control began the week of
4/9/18. Project schedule is being adjusted based on Wastewater Collection Divisions requested changes to scope.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 690-C69300
Project Number/SubProject Number WW-000008-00 0
Project Name Force Main Rehabilitation Langley School FM Rehabilitation
Project Description Rehabilitation of a 2,200 LF 6" diameter sanitary sewer force main will involve a cured in place pipe liner.
Total Project Estimate ($k) 700
Future Funding ($k)
Design Current Status
TBD Construction Award
Project Complete TBD
Remarks Homeowner and Board of Supervisors notifications were sent out 2/8/18. Survey and SAM field work is complete as of 4/13/18. Negotiations are underway with Rummel, Klepper & Kahl, LLP for the design.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT April 2018
Dranesville
Fund 690-C69300
Project Number/SubProject Number WW-000008-00 0
Project Name Force Main Rehabilitation Merrywood FM Rehabilitation
Project Description Rehabilitation of a 1,080 LF 6" diameter sanitary sewer force main located in The Merrywood on the Potomac Community in McLean, Virginia.
Total Project Estimate ($k) 700
Future Funding ($k)
Construction Current Status
2/23/2018 (A) Construction Award
Fall - 2018 Project Complete
Remarks Flippo started construction on 4/10/18 and they are at around 30% complete by the end of the April. The construction should be completed in June 2018.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December
DPWES CAPITAL PROJECT SUMMARY REPORT
April 2018
Dranesville
Fund 690-C69300
Project Number/SubProject Number WW-000026-00 0
Project Name Large Diameter Pipe Rehabilitation & Replacement
Carderock Gravity Sanitary Sewer Interceptor Rehab
Project Description A study of the Carderock Gravity sewer including flow monitoring, modeling, condition assessment, and evaluation with improvement alternatives.
2,000 Total Project Estimate ($k) 1,810 Future Funding ($k)
Pre-Design Current Status
TBD Construction Award
Project Complete TBD
Remarks Video inspection work has been completed. Flow meter installation will be completed in early May 2018. Potential rehabilitation methods are being discussed for the purposes of developing alternatives for the final report.
(A) Actual Winter - January, February, March Spring - April, May, June Summer - July, August, September Fall - October, November, December