S P P 2 0 1 5 T P L - 0 0 1 - 4

S h o r t C i r c u i t P l a n n i n g A s s e s s m e n t f o r U p p e r M i s s o u r i Z o n e E n t i t i e s

12/30/2015

SPP Engineering

Page 2: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Revision History

SPP 2015 TPL-001-4 Short Circuit Planning Assessment for Selected UMZ Entities 2

Revision History

Date Author Change Description

12/23/2015 SPP staff Initial Draft

12/30/2015 SPP staff Final Draft

Page 3: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Table of Contents

SPP 2015 TPL-001-4 Short Circuit Planning Assessment For Selected UMZ Entities 3

Table of Contents

REVISION HISTORY ........................................................................................................................................................................................................... 2 TABLE OF CONTENTS ....................................................................................................................................................................................................... 3 LIST OF TABLES................................................................................................................................................................................................................. 4

PURPOSE ....................................................................................................................................................................................................... 5 MODELS ........................................................................................................................................................................................................ 6 STUDIES ........................................................................................................................................................................................................ 7

3.1: TPL-001-4 Short Circuit Study ............................................................................................................................................................... 7 3.2: Simulation ........................................................................................................................................................................................................ 7 3.3: Corrective Action Plans and Member Review ................................................................................................................................. 7

ENTITIES INVOLVED ................................................................................................................................................................................... 8 RESULTS........................................................................................................................................................................................................ 9

5.1: TPL-001-4 Short Circuit Study ............................................................................................................................................................... 9 5.2: Totals by Modeling Area ............................................................................................................................................................................ 9

SUMMARY .................................................................................................................................................................................................. 11 2015 TPL SHORT CIRCUIT SCOPE ....................................................................................................................................................... 12

Page 4: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. List of Tables

SPP 2015 TPL-001-4 Short Circuit Planning Assessment for Selected UMZ Entities 4

List of Tables

Table 2.1: Models used in TPL-001-4 short circuit studies ............................................................................................................................ 6 Table 4.1: Entities included in the TPL-001-4 Short Circuit study ............................................................................................................. 8 Table 5.1: TPL-001-4 Potential Violations ............................................................................................................................................................. 9 Table 5.2: Potential Violation Totals by Model Area ...................................................................................................................................... 10

Page 5: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 1: Purpose

SPP 2015 TPL-001-4 Short Circuit Planning Assessment For Selected UMZ Entities 5

Purpose

The objective of the 2015 TPL-001-4 Short Circuit Assessment (assessment) is to report findings from

the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in

support of SPP’s compliance, as a Planning Coordinator (PC), with the NERC TPL-001-4 Reliability

Standard.

The goals of this assessment are:

1. Determine whether circuit breakers have interrupting capability for Faults that they will be

expected to interrupt. (R2.3)

2. Report Corrective Action Plans (CAPs) to address the Equipment Rating violations. (R2.8)

This assessment focuses on certain transmission facilities in the SPP footprint of Corn Belt Electric

Cooperative (Corn Belt), Missouri Basin Municipal Power Agency (MRES), and Heartland Consumers

Power District (Heartland), collectively known as the Upper Missouri Zone Entities (UMZ Entities), and

summarizes potential criteria violations and the associated CAPs developed by the affected entities and

the SPP PC.

Page 6: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 2: Models

SPP 2015 TPL-001-4 Short Circuit Planning Assessment for Selected UMZ Entities 6

Models

The 2015 SPP Model Development Working Group (MDWG) short circuit models reflect system

conditions for the Near-Term Transmission Planning Horizon. These models are updated by TPs to

reflect the most current information using the Model On Demand (MOD) program. The SPP 2015 Series

MDWG Final Short Circuit Maximum Fault Models were used in the 2015 TPL planning studies as

reflected in Table 2.1.

Table 2.1: Models used in TPL-001-4 short circuit studies

Model Scope

Seasonal Assessment

Model Used Model Released Assessment Completed

Near

Term

2016 Summer

Peak

2015MDWGFINALSC_Cl

assical_MAX_FAULT-16S April 2015 November 2015

Page 7: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 3: Studies

SPP 2015 TPL-001-4 Short Circuit Planning Assessment For Selected UMZ Entities 7

Studies

3.1: TPL-001-4 Short Circuit Study

Analysis results on the SPP 2015 MDWG Final Short Circuit Maximum Fault models used for the PC

assessment were provided to the UMZ Entities. The UMZ Entities were also provided the option to

perform their own short circuit analysis in lieu of the PC provided results.

3.2: Simulation

Fault current values were determined for each bus modeled in SPP model areas using Power System

Simulation for Engineering (PSS/E) activities Automatic Sequencing Fault Calculation (ASCC) and

ANSI fault current calculation (ANSI) for Single Line to Ground and Three Phase faults. Results from

both activities included system intact faults and activity ASCC also included Line Out faults.

3.3: Corrective Action Plans and Member Review

The UMZ Entities evaluated the applicable results and provided CAPs to the PC, if necessary. If

necessary, the PC verified validity of the submitted CAPs.

Page 8: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 4: Entities Involved

SPP 2015 TPL-001-4 Short Circuit Planning Assessment for Selected UMZ Entities 8

Entities Involved

The following entities registered with the Midwest Reliability Organization (MRO) Regional Entity

were included in this TPL Short Circuit Analysis.

Entity Name Registered Function

Corn Belt Electric Cooperative (Corn Belt) DP, RP, TO, TOP, TP

Heartland Consumers Power District (Heartland) RP, TO

Missouri Basin Municipal Power Agency (MRES) GO, GOP, RP, TO

Table 4.1: Entities included in the TPL-001-4 Short Circuit study

DP : Distribution Provider RP: Resource Planner

GO : Generation Owner TO: Transmission Owner

GOP: Generator Operator TOP: Transmission Operator

TP: Transmission Planner

Page 9: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 5: Results

SPP 2015 TPL-001-4 Short Circuit Planning Assessment For Selected UMZ Entities 9

Results

CAPs to address potential violations consisted of the following:

No CAPs were required.

5.1: TPL-001-4 Short Circuit Study

The SPP 2015 MDWG Final Short Circuit Maximum Fault models used for the short circuit study did

not result in potential violations. Table 5.1 lists a summary of these potential violations.

Season Total

Violations Mitigated Findings

Remaining Violations

2016 Summer 0 0 0

Table 5.1: TPL-001-4 Potential Violations

5.2: Totals by Modeling Area

Table 5.2 below summarizes the potential violations by modeling area. Note that the UMZ Entities do

not have unique modeling areas as their transmission facilities are embedded within other SPP modeling

areas, specifically Area 652, WAPA.

Page 10: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 5: Results

SPP 2015 TPL-001-4 Short Circuit Planning Assessment for Selected UMZ Entities 10

Transmission Planner

Area Number

Total Violations

Mitigated Findings

Remaining Violations

Corn Belt Electric

Cooperative 652 0 0 0

Heartland Consumers

Power District 652 0 0 0

Missouri River

Energy Services 652 0 0 0

Table 5.2: Potential Violation Totals by Model Area

Page 11: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 6: Summary

SPP 2015 TPL-001-4 Short Circuit Planning Assessment For Selected UMZ Entities 11

Summary

The MDWG models developed by the SPP RTO and its Members represent the power system for the

SPP PC. These models did not identify potential equipment rating violations for the UMZ Entities

transmission systems. No CAPs were required as a result of the analysis.

Page 12: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

SPP 2015 TPL-001-4 Short Circuit Planning Assessment for Selected UMZ Entities 12

2015 TPL Short Circuit Scope

Page 13: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,
Page 14: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment

2015 TPL

Short Circuit Scope

Engineering

TWG approved on 3/18/2015

Page 15: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 15

Revision History

Date or Version

Number

Author Change Description Comments

12/30/2014 SPP Staff Initial Draft

2/10/2015 SPP Staff Update based on the February

TPLTF meetings

3/6/2015 SPP Staff Update based on member

feedback

3/9/2015 SPP Staff Update based on the March 9th

TPLTF meeting

Page 16: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 16

Table of Contents

REVISION HISTORY ......................................................................................................................................... 15

OVERVIEW .......................................................................................................................................................... 17

DATA INPUTS .................................................................................................................................................... 18 MODELING DATA ............................................................................................................................................................... 18 DATA REQUIRED BY THE PC ............................................................................................................................................ 19

Initial Data request ............................................................................................................................................. 19 Subsequent Data request ................................................................................................................................. 19

SHORT CIRCUIT SIMULATION ..................................................................................................................... 20 ANALYSIS ........................................................................................................................................................................... 20 SOFTWARE PARAMETERS ................................................................................................................................................. 20

DELIVERABLES.................................................................................................................................................. 22

ASSESSMENT DISTRIBUTION ....................................................................................................................... 23

SCHEDULE ........................................................................................................................................................... 24

CHANGES IN PROCESS AND ASSUMPTIONS ............................................................................................. 26

Page 17: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 17

Overview

This document presents the scope and schedule of work for the NERC TPL-001-4 Short Circuit

Assessment. This document will be reviewed by the Transmission Planning Task Force (TPLTF),

Transmission Working Group (TWG), and the applicable functional entities as described in NERC TPL-

001-4, A.4.1. SPP, as the Planning Coordinator (PC1), will coordinate with the Transmission Planners

(TP) to exchange data. The assessment begins in January 2015 and is a 12-month study scheduled to be

finalized by December 2015.

1 In this document, SPP does not represent a TP.

Page 18: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 18

Data inputs

Modeling data

Modeling data required in the TPL Steady State study is incorporated through the annual SPP MDWG

model building process. The SPP MDWG model building process is performed in accordance with the

applicable NERC Modeling, Data, and Analysis (MOD) Standards. In order to meet the R1

requirements, the models must represent the following:

Existing Facilities

Known outage(s) of generation or Transmission Facility(ies) with a duration of at least six

months

New planned Facilities and changes to existing Facilities

Real and reactive Load forecasts

Known commitments for Firm Transmission Service and Interchange

Resources (supply or demand side) required for Load

However, these requirements are not applicable in determining the interrupting capability of circuit

breakers required for Faults for all system conditions. The System short circuit model with all planned

generation and Transmission Facilities in service is represented with the following additional

requirements:

Place all available facilities in-service:

o Generation

o Transmission lines (Out for maintenance)

o Transformers

o Buses

Flat – classical fault analysis conditions

The model set in the table below establishes category P0 as the normal System condition in TPL-001-4

Table 1, and defines the models that will be used for the 2015 TPL short circuit analyses. These models

were chosen to comply with requirement R2.3

Requirement Description Study case

R2.3 Year 1 Maximum Fault Short Circuit MDWG 2016S

Page 19: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 19

Data required by the PC

Initial Data request

There is not an initial data request for ASCC results, because the PC will run a short circuit analysis on

all buses in the short circuit model within the PC footprint.

For TPs that require ANSI Fault Current calculation, each TP will provide to the PC the following ANSI

Fault Current Calculation parameters to be used for each bus within the TP area:

Divisors

o For branches in positive sequence

o For machines in positive sequence

o For branches in zero sequence

o For machines in zero sequence

Fault multiplying factors

o DC decrement only or AC and DC decrement

Max operating voltage, in PU

Contact parting times, in seconds

Subsequent Data request

Corrective Action Plans for instances where the short circuit current interrupting duty exceeds the

equipment rating.2 Use of Activity ANSI requires a second step involving line-out cases if the full bus-

fault current exceeds the interrupting capability of the breaker under review. The TP will provide a

listing of each bus number for which a line-out analysis is required for Activity ANSI to be performed

by the PC.

2 R2.8

Page 20: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 20

Short Circuit Simulation

Analysis

The PC will send out the total Bus fault current study results for SLG and 3 phase faults to the TPs.

Full bus-fault current and line-out results using ASCC

Full bus-fault current using ANSI

o Line-out results for buses provided in subsequent request

The TPs can perform their own short circuit analysis in lieu of the PC provided results. The TP will

evaluate the results and respond to the PC with necessary Corrective Action Plans (CAPs) based upon

TP analysis/feedback and subsequent data request for the required ANSI line-out results. The PC will

verify the validity of the TP submitted CAPs.

Software parameters

PSS/E settings:

Run activity FLAT

o Set classical Short Circuit Assumptions (activity FLAT,CL)

Set Tap Ratios to unity (1.0)

Set Charging to zero (0.0)

Set Shunts to zero (0.0) in all sequences3

Use Automatic Sequence Fault Calculation (ASCC) function

o Three phase fault

o Line to Ground (LG) fault

o Line Out (LOUT) fault

o Impose flat conditions

o I”k contributions to “N” levels away

N=0

Use ANSI Fault Current Calculation (with defaults below unless alternate provided by TP)

o Divisors

For branches in positive sequence = 40.0

For machines in positive sequence = 80.0

For branches in zero sequence = 40.0

For machines in zero sequence = 80.0

o Fault multiplying factors = DC decrement only

o Output Format = Summary output using ANSI R and X

o Max operating voltage, in PU = 1.05

o Contact parting times, in seconds = 0.033

Short Circuit Output = Physical

Short Circuit Coordinates = Polar

3 Set line shunts to 0.0 in the positive (and hence negative) sequence, and fixed and switched shunts to 0.0 in all three sequence networks.

Page 21: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 21

Short Circuit Parameters = 3 Phase

Page 22: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 22

Deliverables

Initial submittal of total Bus Fault Currents from PC to TPs in an Excel format

o Full bus-fault current and line-out results using ASCC

o Full bus-fault current using ANSI

Subsequent submittal of line-out Bus Fault Currents using ANSI from PC to TPs in an Excel

format

Draft TPL-001-4 Short Circuit Assessment

Final Comprehensive TPL-001-4 Assessment

Page 23: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 23

Assessment Distribution

Each Planning Coordinator and Transmission Planner shall distribute its Planning Assessment results to

adjacent Planning Coordinators and adjacent Transmission Planners within 90 calendar days of

completing its Planning Assessment, and to any functional entity that has a reliability related need and

submits a written request for the information within 30 days of such a request. 4

If a recipient of the Planning Assessment results provides documented comments on the results, the

respective Planning Coordinator or Transmission Planner shall provide a documented response to that

recipient within 90 calendar days of receipt of those comments.5

SPP Adjacent Transmission Planner PSS/E Area Number Contact email Cleco Corporation 502 TBD

Entergy 351, 327 TBD

Ameren Services Company 356 [email protected]

Saskatchewan Power Corporation 672 [email protected]

Otter Tail Power Company 620 TBD

Minnkota Power Corporation TBD TBD

MidAmerican Energy Corporation 635 TBD

Great River Energy 615 TBD

City of Ames Electric Services TBD TBD

Central Iowa Power Cooperatives TBD TBD

Xcel Energy 600 TBD

Alliant Energy West 627 TBD

DPC 680 TBD

Montana-Dakota Utilities 661 TBD

SPP Adjacent Planning Coordinator Contact email Associated Electric Cooperatives, Inc. (AECI) [email protected]

Mid-Continent Area Power Pool (MAPP) [email protected]

Midcontinent Independent System Operator

(MISO)

[email protected]

[email protected]

4 R8

5 R8.1

Page 24: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 24

Schedule

Owner Study Scheduled Activities Dates

PC SS Steady State Scope Development Thu , January 1

PC ST Stability Scope Development Thu , January 1

PC SC Short Circuit Scope Development Thu , January 1

MDWG SS Contingency data request Fri , February 27

MDWG SS 2015 MDWG Powerflow model set approval Mon , March 2

MDWG SC 2015 MDWG Short circuit model set approval Mon , March 2

PC SS Generate basecase 'P0' potential violations Tue , March 3

PC SS Send TPs basecase 'P0' potential violations Fri , March 13

PC SS BES inclusion list and spare equipment data request Mon , March 16

TWG SS,SC,ST TWG Scope Approvals Wed , March 18

TP SS Deadline for providing ‘P0’ basecase CAPs Thu , March 26

TP SS Deadline for providing Contingency data (P1) Fri , March 27

PC SS Deadline for applying basecase CAPs Mon , March 30

TP SS Deadline for providing BES inclusion list, spare equipment Mon , March 30

PC SC Perform SC simulation Wed , April 1

MDWG ST Contingency data request Wed , April 1

TP SS Deadline for providing Contingency data (P2,P4,P5,P7, EE) Mon, April 27

PC SS Perform POM-OPM ACCC runs Tue , April 28

PC SS Organize POM-OPM ACCC results Wed , May 27

PC SS Send initial potential violations to TPs and request CAPs Tue , June 30

PC SS Verify TP submitted CAPs upon reception Wed, July 1

PC SC Send Short Circuit results to TPs and request CAPs Wed , July 1

TP SS Begin Stakeholder meetings to shed NCLL Mon , July 13

TP SS Deadline for providing Protection Scheme Contingencies Fri , July 31

TP SC Deadline for providing listing of buses for line-out results

using activity ANSI

Mon , August 3

PC SS Send additional potential violations to TPs and request CAPs Fri , August 7

TP SS Deadline for providing CAPs Fri , August 14

MDWG ST 2015 MDWG Dynamic model set approval Thu , August 20

TP SC Deadline for providing CAPs Mon , August 31

PC ST Complete Fast Fault Scans for Dynamics Mon , August 31

PC SC Send Short Circuit simulation results for line-out results using

activity ANSI to TPs and request additional CAPs

Mon , August 31

TP SS End Stakeholder meetings to shed NCLL Wed , September 16

TP SC Deadline for providing additional CAPs for Short Circuit

simulation results for line-out results using activity ANSI

Wed , September 16

TP ST Deadline for providing Contingency data Mon , September 21

Page 25: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 25

Owner Study Scheduled Activities Dates

PC SC Complete verification of TP submitted Short Circuit CAPs Thu , October 15

PC SS Complete verification of TP submitted Steady State CAPs Thu , October 15

PC ST Complete Dynamics Stability Analysis Wed , October 21

PC SS Begin Drafting Steady State TPL Assessment Fri , October 16

PC SC Begin Drafting Short Circuit TPL Assessment Fri , October 16

PC ST Begin Drafting Stability TPL Assessment Fri , October 16

PC SS,SC,ST Post Draft TPL Comprehensive Assessment to TWG Tue , November 10

TWG SS,SC,ST TWG approval of 2015 Comprehensive TPL Assessment Wed, December 9

Page 26: SPP 2015 TPL-001-4 2015 tpl... · 30.12.2015  · the 2015 TPL-001-4 short circuit studies along with an associated evaluation of the study results in support of SPP’s compliance,

Southwest Power Pool, Inc. Section 7: 2015 TPL Short Circuit Scope

2015 SPP TPL-001-4 Short Circuit Assessment 26

Changes in Process and Assumptions

In order to protect against changes in process and assumptions that could present a significant risk to the

completion of the TPL study, any such changes must be vetted. If TWG votes on any process steps or

assumptions to be used in the study, those assumptions will be used for the 2015 TPL study. Changes to

process or assumptions recommended by stakeholders must be approved by the TWG. This process will

allow for changes if they are deemed necessary and critical to the TPL study, while also ensuring that

changes, and the risks and benefits of those changes, will be fully vetted and discussed.