Questions
You have reached the end of design phase of your project. Youdecide to call a "phase end review" for obtaining authorization toclose the design phase and initiate the next phase (i.e. execution
phase) of your project.Your manager disagrees with your suggestion. He wants a "kill point"
to formally end the design phase of the project. In this context, youshould:
A. Disagree with your manager because you know that phase endreviews should be used at the end of each phase of the project
B. Agree with your managerC. Escalate this issue to the project sponsor
D. Take advise from a senior project manager about what shouldactually be done at the end of each phase of the project
-
7/27/2019 Questions - Risk,Procurement
2/47
Questions
Youre managing a project to build a new accounting system. One ofthe accountants in another department really likes the currentsystem and is refusing to be trained on the new one. What isthe BEST way to handle this situation?
A. Refuse to work with him because hes being difficultB. Appeal to the accountants manager and ask to have him
required to take trainingC. Get a special dispensation so that the accountant doesnt have to
go to the trainingD. Work with him to understand his concerns and do what you can
to help alleviate them without compromising your project
-
7/27/2019 Questions - Risk,Procurement
3/47
Questions
One of the initial project documents, issued by seniormanagement, which outlines the authority of the
project manager, is called Project charter. As a seller,what other document can be used in this place:
A. Work breakdown structure
B.Project scope
C.ContractD.Internal memo
-
7/27/2019 Questions - Risk,Procurement
4/47
Each item of the Work Breakdown Structure isassigned a unique identifier. What is the name of
this identifier?A. Product ID number
B. Code of accounts
C. Quality inspection identifier
D. Project activity code
Questions
-
7/27/2019 Questions - Risk,Procurement
5/47
Questions
Which of the following is NOT a characteristic of aproject?
A. Constrained by limited resources
B. Planned, executed, and controlled
C. Creates a unique product or serviceD. Ongoing and repetitive
-
7/27/2019 Questions - Risk,Procurement
6/47
Youre managing a project, when your client tells you that anexternal problem happened, and now you have to meet an earlierdeadline. Your supervisor heard that in a situation like this, you canuse schedule compression by either crashing or fast-tracking theschedule, but hes not sure which is which. What do you tell him?
A Crashing the project adds risk, while fast-tracking adds cost
B When you crash a project, it always shortens the total duration of theproject
C. Crashing the project adds cost, while fast-tracking adds riskD. When you fast-track a project, it always shortens the total duration
of the project
Questions
-
7/27/2019 Questions - Risk,Procurement
7/47
Questions
What is the ES & LF of activity FA. 13 , 16B. 10, 10C. 13 , 10
D. 10,14
-
7/27/2019 Questions - Risk,Procurement
8/47
You are working on a project with a PV of $56,733 and an SPI of 1.2.Whats the Earned Value of your project?
A. $68,079.60
B. $47,277.50
C. $68,733
D. 0.72
Questions
-
7/27/2019 Questions - Risk,Procurement
9/47
Project A has a NPV of $75,000, with an internal rate of return of1.5% and an initial investment of $15,000. Project B has a NPV of$60,000 with a BCR of 2:1. Project C has a NPV of $80,000, which
includes an opportunity cost of $35,000. Based on these projects,which is the BEST one to select:
A. Project A
B. Project B
C. Project CD. Not enough information
Questions
-
7/27/2019 Questions - Risk,Procurement
10/47
You are working on a project with an SPI of .72 and a CPI of 1.1.Which of the following BEST describes your project?
A. Your project is ahead of schedule and under budget
B. Your project is behind schedule and over budget
C.Your project is behind schedule and under budget
D.Your project is ahead of schedule and over budget
Questions
-
7/27/2019 Questions - Risk,Procurement
11/47
Three members of your project team want to pad theirestimates because they believe there are certain risks that
might materialize. What is the BEST way to handle thissituation?
A. Estimate the activities honestly, and then use a contingencyreserve to cover any unexpected costs
B. Allow more time for the work by adding a buffer to every
activity in the scheduleC. Tell the team members not to worry about it, and if the
schedule is wrong its okay for the project to be late
D.Crash the schedule
Questions
-
7/27/2019 Questions - Risk,Procurement
12/47
1. Which tool or technique is used to analyze trends?
A. Scatter chart
B. Run chart
C. Checklist
D. Flow chart
Questions
-
7/27/2019 Questions - Risk,Procurement
13/47
1. When is inspection performed?
A. At the beginning of the project
B. Any time a project deliverable is produced
C. Just before the final product is delivered
D. At the end of the project
Questions
-
7/27/2019 Questions - Risk,Procurement
14/47
Youre managing a project to deliver 10,000 unitsof custom parts to a manufacturer that uses Just
In Time management. Which of the followingconstraints is most important to your client?
A. The parts must be delivered on time
B. The parts must be delivered in a specific order
C. The parts must conform to ISO specifications
D. The parts must be packaged separately
Questions
-
7/27/2019 Questions - Risk,Procurement
15/47
Which of the following is NOT a human resourceprocess?
A. Develop Human Resource Plan
B. Acquire Project Team
C. Report Team Performance
D. Develop Project Team
Questions
-
7/27/2019 Questions - Risk,Procurement
16/47
Your company is constructing a new just in time manufacturingfacility in Puerto Rico. This facility will be producing 3,000 bicyclesevery day. The raw materials are delivered to the facility on standardpallets, each taking up 1m2 (one square meter) of space. Every day
approximately 500 pallets will be delivered to the facility. You haveasked four local companies to submit their offers for constructingthis new manufacturing facility. If you had to pick a vendor basedon just the following information, which one would you choose?
A.) Company A: 8,000 m2 of production space and 500 m2 of palletstorage
B.) Company B: 8,000 m2 of production space and 350 m2 of palletstorage
C.) Company C: 8,000 m2 of production space and 250 m2 of palletstorage
D.) Company D: 8,000 m2 of production space and 0 m2 of palletstorage
Questions
-
7/27/2019 Questions - Risk,Procurement
17/47
Your designer has given his resignation. This means thatyou will be losing him and your team size (includingyourself ) will go from 12 to 11 people. How many fewer
communication channels do you personally have on yourproject?
A.) 1
B.) 10
C.) 11
D.) 12
Questions
-
7/27/2019 Questions - Risk,Procurement
18/47
The project manager for a construction project discovers that thelocal city council may change the building code to allow adjoiningproperties to combine their sewage systems. She knows that acompetitor is about to break ground in the adjacent lot and contactshim to discuss the possibility of having both projects save costs bybuilding a sewage system for the two projects.
This is an example of which strategy?
A. Mitigate
B. Share
C. Accept
D. Exploit
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
19/47
Which of the following is NOT a risk response technique?
A. Exploit
B. Transfer
C. MitigateD. Confront
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
20/47
You are using an RBS to manage your risk categories. What processare you performing?
A. Risk Planning
B. Risk IdentificationC. Qualitative Analysis
D. Quantitative Analysis
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
21/47
Which of the following is used to monitor low priority risks?
A. Triggers
B. Watch lists
C. Probability and Impact MatrixD. Monte Carlo analysis
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
22/47
Youre managing a construction project. Theres a 30% chance thatweather will cause a three-day delay, costing $12,000. Theres also a20% chance that the price of your building materials will drop,which will save $5,000. Whats the total EMV for both of these?
A. $3,600
B. $1,000
C. $2,600
D. $4,600
The expected monetary value (or EMV) of the weather risk is the probability(30%) times the cost ($12,000), but dont forget that since its a risk, thatnumber should be negative. So its EMV is 30% x -$12,000 = -$3,600.
The building materials opportunity has an EMV of 20% x $5,000 = $1,000.Add them up and you get -$3,600 + $1,000 = -$2,600.
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
23/47
Joe is the project manager of a large software project. When itstime to identify risks on his project, he contacts a team of expertsand has them all come up with a list and send it in anonymously.What technique is Joe using?
A. SWOT
B. Ishikawa diagramming
C. Delphi
D. Brainstorming
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
24/47
Susan is project manager on a construction project. When she hearsthat her project has run into a snag due to weeks of bad weather onthe job site, she says No problem, we have insurance that coverscost overruns due to weather. What risk response strategy did sheuse?
A. Exploit
B. Transfer
C. Mitigate
D. Avoid
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
25/47
Youre performing risk identification on a software project. Twoof your team members have spent half of the meeting arguingabout whether or not a particular risk is likely to happen on the
project. You decide to table the discussion, but youre concernedthat your teams motivation is at risk. The next item on theagenda is an discussion of a potential opportunity on the projectin which you may be able to purchase a component for muchless than it would cost to build.Which of the following is NOT avalid way to respond to an opportunity?
A. Exploit
B. Transfer
C. Share
D. Enhance
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
26/47
Risks that are caused by the response to another risk are called
A. Residual risks
B. Secondary risks
C. Cumulative risksD. Mitigated risks
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
27/47
Whats the main output of the Risk Management processes?
A. The Risk Management Plan
B. The Risk Breakdown Structure
C. Work Performance InformationD. The Risk Register
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
28/47
Tom is a project manager for an accounting project. Hiscompany wants to streamline its payroll system. The project isintended to reduce errors in the accounts payable system and
has a 70% chance of saving the company $200,000 over the nextyear. It has a 30% chance of costing the company$100,000.Whats the projects EMV?
A. $170,000
B. $110,000
C. $200,000D. $100,000
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
29/47
Whats the difference between management reserves andcontingency reserves?
A. Management reserves are used to handle known unknowns,
while contingency reserves are used to handle unknownunknowns.
B. Management reserves are used to handle unknown unknowns,while contingency reserves are used to handle knownunknowns.
C. Management reserves are used to handle high-priority risks,while contingency reserves are used to handle low-priorityrisks.
D. Management reserves are used to handle low-priority risks,while contingency reserves are used to handle high-priorityrisks.
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
30/47
How often should a project manager discuss risks with theteam?
A. At every milestone
B. Every dayC. Twice
D. At every status meeting
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
31/47
Which of the following should NOT be in the risk register?
A. Watchlists of low-priority risks
B. Relative ranking of project risksC. Root causes of each risk
D. Probability and impact matrix
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
32/47
Which of the following is NOT true about risk management?
A. The project manager is the only person responsible for
identifying risksB. All known risks should be added to the risk register
C. Risks should be discussed at every team meeting
D. Risks should be analyzed for impact and priority
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
33/47
Youre managing a project to remodel a kitchen. You find outfrom your supplier that theres a 50% chance that the model ofoven that you planned to use may be discontinued, and youll
have to go with one that costs $650 more. Whats the EMV ofthat risk?
A. $650
B. $650
C. $325
D. $325
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
34/47
Which risk analysis tool is used to model your risks by runningsimulations that calculate random outcomes and probabilities?
A. Monte Carlo analysis
B. Sensitivity analysisC. EMV analysis
D. Delphi technique
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
35/47
A construction project manager has a meeting with the teamforeman, who tells him that theres a good chance that a generalstrike will delay the project. They brainstorm to try to find a way
to handle it, but in the end decide that if theres a strike, there isno useful way to minimize the impact to the project. This is anexample of which risk response strategy?
A. Mitigate
B. Avoid
C. TransferD. Accept
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
36/47
Youre managing a project to fulfill a military contract. Yourproject team is assembled, and work has begun. Yourgovernment project officer informs you that a supplier that you
depend on has lost the contract to supply a critical part. Youconsult your risk register and discover that you did not plan forthis. Whats the BEST way to handle this situation?
A. Consult the probability and impact matrix
B. Perform quantitative and qualitative risk analysis
C. Recommend preventive actionsD. Look for a new supplier for the part
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
37/47
Which of the following BEST describes risk audits?
A. The project manager reviews each risk on the risk register withthe team
B. A senior manager audits your work and decides whether youredoing a good job
C. An external auditor reviews the risk response strategies foreach risk
D. An external auditor reviews the project work to make sure the
team isnt introducing new risk
Questions - Risk
-
7/27/2019 Questions - Risk,Procurement
38/47
Tom is a project manager for a software company. He iscontracting a long-term software project with an externalcompany. That company charges him $20/hour per employee
and $300 overhead per month. What kind of contract is heusing?
A. FP
B. CPPC
C. CR
D. T&M
Questions Procurement
-
7/27/2019 Questions - Risk,Procurement
39/47
Which of the following is NOT true about bidder conferences?
All potential sellers should meet separately with the buyer
Potential sellers should ask questions in an open forum so other
sellers can hear the answers Bidder conferences are a good way to make sure sellers are
treated fairly
All sellers are given the same procurement documents
Questions - Procurement
-
7/27/2019 Questions - Risk,Procurement
40/47
Youre managing a project that might have to contract out work,and youre comparing the relative advantages and disadvantagesof finding a seller versus having your company do the work itself.
Which process are you in? Plan Purchases
Plan Contracting
Select Sellers
Request Seller Responses
Questions - Procurement
-
7/27/2019 Questions - Risk,Procurement
41/47
Youre working on creating a qualified sellers list. Which processare you in?
A. Plan Purchases and Acquisitions
B. Plan ContractingC. Select Sellers
D. Request Seller Responses
Questions - Procurement
-
7/27/2019 Questions - Risk,Procurement
42/47
Youre managing a project that is difficult to estimate, so youdont have a good idea of when the project will end. Which of thefollowing contracts is BEST?
A. FPB. CPPC
C. CPIF
D. T&M
Questions - Procurement
-
7/27/2019 Questions - Risk,Procurement
43/47
Youre looking for a seller to do work for your project. When doyou send out an RFP?
A. After you create the procurement documents, but before you
select the sellerB. Before you plan contracting, but after you plan purchases and
acquisitions
C. After the bidder conference, but before you select the seller
D. During contract administration
Questions - Procurement
-
7/27/2019 Questions - Risk,Procurement
44/47
ABC Consultancy is getting 200 computers installed from avendor. The vendor will be paid the cost involved and a 10%incentive. Which contract will be used in this case?
A. CPPC B. CPIF
C. CPFF
D. Fixed Cost
Questions - Procurement
-
7/27/2019 Questions - Risk,Procurement
45/47
Monika is a Project Manager. She is coordinating a bidderconference to allow vendors to get clarification on the work thatneeds to be performed. Which phase of Project Management is
in progress? A. Conduct Procurements
B. Plan Procurements
C. Control Procurements
D. Close Procurements
Questions - Procurement
-
7/27/2019 Questions - Risk,Procurement
46/47
Makeorbuy analysis is a tool used in which process?
A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements D. Analyze Procurements
Questions - Procurement
-
7/27/2019 Questions - Risk,Procurement
47/47
ABC Consultancy has a large internal project to be initiated. Tostaff this project, ABC Consultancy is working with PeopleConsultancy to provide three resources for six months. Theresources will be part of the team managed by ABCConsultancy for six months. Which contract type should beused?
A. Purchase Order
B. Cost plus Fee
C. Fixed cost D. Time and Material
Questions - Procurement