Program Governance1. What the Program Governance ensures?
It ensures Decision making and delivery management activities are focused on achieving program goals in a consistentmanner, addressing appropriate risks and fulfilling stakeholder requirements
2. What the Program Governance really needs for conducting its activities through all phases of the Program Life Cycle?
Organizations to establish and enforce policies that address the following
Common Procedures for all components within the program Appropriate controls to ensure consistent application of procedures
Approach for developing and documenting program assumptions and decisions
Approach for managing program change
Quantifiable measures for evaluating the success of individual projects and the program
Common Practices for capturing risks, issues, benefits measurements and lessons learned
3. The Program Governance Team member has taught how to handle any escalations from customer to one of my Component Team,when they brought a recent bad news of customer dissatisfaction to his knowledge. Team did address the customers concerns andachieved customer satisfaction accordingly. The component team was happy for the given support by Program Governance teammember but myself and Progra12m Board were not. Guess why?
Governance must be proactive and not performed afterwards
4. The Governance Structure ensures Programs _______ and _______ are aligned with the _______ goals and objectives of the______________s
Goals, Objectives, Strategic, Enterprises
5. ___________ by their nature may overlap with number of enterprises, with one or more being ________, performing organizations,stakeholders or suppliers
Programs, customers
6. The _______ _______ ensures that important interfaces are managed carefully to minimize the program and inter-componentconflicts
Governance Framework
7. Effective Governance ensures the following:
The strategic alignment and the ________ that has been promised is _________ and ________delivered
Value, Realized, Benefits All stakeholders are appropriately communicated with the kept aware of _________ and __________
Progress, Issues
The appropriate ________ and _________ are used in the program
Processes, Tools
The _______ are being made rationally and with Justification
Decisions
The ___________ and accountabilities are clearly defined and applied
Responsibilities
All of above is done with the ________ and _________of the partner organizations and is measured to ensure compliance
Policies and Standards
-
7/29/2019 Program Governance - Notes Q&A Approach
3/20
14 Feb 2013 3
Program Governance
8. What are the responsibilities of below roles of Program Governance Structure
Executive Sponsor
Program Board
Program Manager
Project Managers
Program Management Office
Project Team and Team Members
9. When benefits becomes value?
When benefits are utilized by the organization, community or other program or project beneficiaries
10. The benefits realization plan identifies _________ and ________ these benefits to be realized and may specify _________s that
should be in place to ensure that the benefits are fully realized over time.
When, How, Mechanisms
11. What subsidiary plans of Program Management Plan you may use to plan and establish program governance structure.
Program Charter, Program Business Case, Sponsor and stakeholder requirements (to find minimum acceptance criteria)
12. What the Benefits Realization Measurement Analysis requires? Linking benefits to expenditures (Not just financial), Measurement Criteria, Measurement and Review Points
13. What are the three outcomes of Plan and Establish Governance Structure
Governance Plan, Issue Escalation Process and Audit Plan
14. What the Governance Plan is comprised with?
Program Governance Goals, Program Governance Structure and Composition, Program Governance Role and Responsibilities, High
level governance plan and meeting schedules , Gate Review Requirements, Component Initiation Criteria and Periodic Health checks
15. What the governance board usually do after creating Program Governance Goals?
Communicates to Program and Component Teams
16. What a component manager should do once he receives the Program Governance Goals?
He/She should prioritize his/her goals and include them in Project Charter and Project Management Plan and advice how these goals need
to be met
17. What the program governance structure and composition section of Governance Plan describes?
How Program Governance will be implemented, Roles and Responsibilities, Stage Gate Review Requirements, and execution
18. What is the most important activity of program governance?
To ensure the program components are being managed effectively
19. What the phase gate review requirements should address?
What is to be gated?, How is it gated (Process), Who is responsible?, What are the measurement criterions?
-
7/29/2019 Program Governance - Notes Q&A Approach
4/20
14 Feb 2013 4
-
7/29/2019 Program Governance - Notes Q&A Approach
5/20
14 Feb 2013 5
Program Governance
20. What is the Primary Criteria for Component Initiation?
Right components are initiated at right time
21. Periodic Health Checks are substitute to Phase-gate reviews. True or False?
False
22. Phase-gate reviews assess performance against expected outcomes and against the need to realize and sustain program benefitsinto the long term. True or False?
False. This applies to Periodic Health Checks
23. What are the objectives of Periodic Health Checks?
24. How many levels of escalations are in Program Management
Between Program Management Team and Component Teams and Program Management and Organizational Executive Management or
other stakeholders
25. Where do you find the Audit objectives and schedule in Program Artifacts?
Audit Plan
-
7/29/2019 Program Governance - Notes Q&A Approach
6/20
14 Feb 2013 6
-
7/29/2019 Program Governance - Notes Q&A Approach
7/20
14 Feb 2013 7
Program Governance
26. How a Program Manager should be prepared for audits?
27. In what phases the audits usually performed?
During Program Execution or at end of Program Completion
28. Where the audit results would be recorded?
Each audit results should be recorded in Audit Plan with feedback to Governance Planning function28. The majority of the Quality Planning, Assurance and Control occur at the Program Level . True or False?
False
29. Program Quality is primarily defined by____________ __________ ________
Successful Benefits Realization
30. What is really enables a Program manager to define appropriate quality standards and measures?
Complete understanding on Scope and nature of the benefits
31. What you must consider when you plan on how much quality you need to achieve?
Cost/Benefit Tradeoffs
32. What is the primary benefit of meeting quality requirements?
Less Rework i.e. Higher Productivity, Less Costs and increased Stakeholders Satisfaction
33. What is the better tool for developing Quality System to ensure any items are not missed ?
Checklists
34. How checklists helps Quality Management Planning
Reduce the development time of the same
34. How do you measure the cost of quality?
Prevention Costs (total cost of all efforts to achieve product or service quality)
Appraisal Costs (total cost of all efforts to ensure conformance to quality requirements)
Failure Costs: (total cost of all efforts resulting from internal and external non-conformance)
-
7/29/2019 Program Governance - Notes Q&A Approach
8/20
14 Feb 2013 8
-
7/29/2019 Program Governance - Notes Q&A Approach
9/20
14 Feb 2013 9
Program Governance35. What the Quality Management Plan should include?
Minimal quality standards for Components
Minimal Testing Requirements for Components
Minimal Quality Planning, Quality Assurance and Quality Control for components
Any Program level Quality Assurance or Quality Control activities required
Roles and Responsibilities to perform Program level Quality Assurance and Quality Control activities required36. In what are the phases of Program Life Cycle the Approve Component Initiation can occur?
During any phase except closing
37. Which plan controls the timing of component initiation?
Program management plan provides overall guidance for Initiating Components
38. What elements of Program management plan use the Approve Program Initiation process ?
Program Charter including Program Scope Statement guide individual component charter through Define various dailyoperational components and identify when they become part of program
Program Strategic Plan : Companys strategic plan should be the defining document for program and should be reflected inProgram charter. The Program and Component Plans should support company strategic plan
39. What the Approve Component Initiation Process takes care at Program Level?
40. What the Program Manager may delegate with other Program Manager during Approve Component Initiation?
When any with-in component manager unable or unwilling to release the resources for the new component resourcerequirements
41. What may triggers by Approve Component Initiation Process?
Redeployment of human and other Resources from one component to other
-
7/29/2019 Program Governance - Notes Q&A Approach
10/20
14 Feb 2013 10
-
7/29/2019 Program Governance - Notes Q&A Approach
11/20
14 Feb 2013 11
Program Governance
42. What each component really requires before begin their work?
Approved COMPONENT Charter.
43. What evaluates the COMPONENT against the organizations approved selection criteria to make a decision onwhether component should be initiated?
Component Initiation Request44. Where you should define the criteria for approval of component initiation?
Program Governance Plan
45. Who would review and approve the Component Change Requests?
Program Governance Board
46. Define Governance!
Process of developing, communicating, implementing, monitoring and assuring the POLICIES,PROCEDURES, ORGANIZATIONAL STRUCTURES, and PRACTICES associated with the givenprogram. The simplest definition is OVERSIGHT and CONTROL.
47. What request you would raise at end of phase completion or when you found an issue or when you receive anew proposal from customer or when you find a risk?
Governance Decision Request along with Support Documentation
48. When you notice a Program change, which process you must follow before you approach Governance Boardfor a FINAL DECISION?
Monitor and Control Program Changes
49. Audit Reports from planned and unplanned audits are an example of external viewpoints that can be used as a___________ and ___________opinion for the governance boards decision process
Check, Balance
50. Changes that do not affect the _________ _______ _____will USUALLY not require governance board review.
Overall programs performance51. What really enhance the effectiveness of the governance process?
Regularly Scheduled Meetings, Well Planned Agendas and Documented Decision Records
52. The Decisions are documented formally using ________ ______, ______ ______ ____ or other forms ofdecision records.
Meeting Minutes and Action Items Logs
-
7/29/2019 Program Governance - Notes Q&A Approach
12/20
14 Feb 2013 12
-
7/29/2019 Program Governance - Notes Q&A Approach
13/20
14 Feb 2013 13
Program Governance
53. The Program Closure Recommendation would typically be proposed to the_____ for the final closure decision
Programs Sponsor
54. What Manage Program Benefits ensures?
A set of reports or metrics reported to PMO, Program Stakeholders, Governance Committee and/or Sponsors that helps them
to assess the health of the program and take necessary actions for successful benefits delivery
55. How Program Management Plan helps for managing program benefits?
When the identified Benefit Realization Events are scheduled? And those events are included in PHASE GATE reviews and
are the decisions emanating from these PHASE GATE reviews
56. Program Components need to review the ________ ________to derive planned benefits.
Program Charter
57. What are the artifacts you keep review for managing the program benefits?
Program Management Plan, Program Charter, Program Performance Reports, Governance Plan
58. Benefits should be described in an effective manner, explaining how they add value. If benefits are notpresented in a coherent fashion, then the value may not be understood. If you can ensure this, your facilitation
of ________ very effective.
Review
59. What is the difference between usual Program Risk Management and Risk Management during Benefits
Realization Analysis?
Risks to benefits realization is managed in the enterprise than management of specific risks
60. What do you focus on Risk Management of Benefits Realization Analysis?
Ensure Senior Enterprise officers aware of the risks, Understand the enterprise RISK TOLERENCES, Manage the Inter-component and enterprise-level risks
61. Why do you have to consider Strategic Alignment as one factor during Benefits Realization Analysis?
To understand the linkage between How Enterprise Operations Manager and Program Manager defines, maintain and
validate the program value proposition.
62. What you focus while you analyzing the benefits realization from strategic alignment perspective?
How will the realization of benefits affect the flow of operations? How negative effectives can be minimized? How organization
is going to manage the inbuilt disruptions in components ?
-
7/29/2019 Program Governance - Notes Q&A Approach
14/20
14 Feb 2013 14
-
7/29/2019 Program Governance - Notes Q&A Approach
15/20
14 Feb 2013 15
Program Governance
63. Share any thing you know about how benefits get translate into value!
Service Level Agreements, Achieving the results (e.g. increasing market share),
64. What do you focus while analyzing the benefits realization from VALUE DELIVERY perspective?
Time Window of Opportunity and Investments for a benefit to be turned into value
65. What do you focus while analyzing the benefits realization from Resource Management perspective? Ensuring that the appropriate resources are made available to components and returned
to the enterprise at the appropriate time for optimal utilization
66. What do you focus while analyzing the benefits realization from Performance Measurementperspective?
Tracking and Monitoring the Strategy Implementation, Component Completion, ComponentDeliverables, Resource Usage, Process Performance,
Establishing or Influence the Service Level Agreements
Monitor each Component Performance impacts other components to ensure ability to deliverbenefits is not compromised
67. How do you measure the benefits realization?
Dimensions of the benefit (e.g. the date when realization must start)
Quantification of the benefit (e.g. Hours save, Profits Increased, Market Share increased)
68. Which artifact measures each component against the benefits realization plan?
Benefits Realization Report
69. You just rejoined office after a vacation. One of your Governance Board Team member saidinformally that he heard one of the benefits realization was compromised? What do you do next?
Verify the same in Benefit Realization Report and identify the required actions in Decisions Log If true, consult Monitor and Control Program Benefits and Report Program Performance
before reporting PROGRAM PERFORMANCE to corresponding Enterprise Executives with asuggestion that the impacted component need to be realigned or terminated
Ensure a change request was raised and approved. Update Develop Program Requirementsaccordingly
Verify that any changes required to Governance Process, Governance Plan, Governance Rolesand Responsibilities and Governance Structure. Update GOVERNANCE PLAN accordingly.
-
7/29/2019 Program Governance - Notes Q&A Approach
16/20
14 Feb 2013 16
-
7/29/2019 Program Governance - Notes Q&A Approach
17/20
14 Feb 2013 17
Program Governance
70. Who makes decisions regarding the proposed changes to the Program Management Plan? Program Governance
71. A Component Manager has sent one line email to you that a CR# was opened for yourapproval? Whom you represent? What are your next steps.
The Program Governance/Change Control Board/Appropriate Authority As per Integrated Change Control Process, analyze the CR (#) from the Change Request Log and
review the Program Management Plan to ensure that proposed changes are consistent with thecurrent direction of the program
Conduct Reviews to ensure the delivery of any benefits were not compromised by decisions made duringthe execution of the program and its components
Conduct Impact Analysis and explore the effect of the proposed changes on any specific component andoverall program, identifies RISKS and BENEFITS to the component arising from the change if it were tobe accepted.
Change decisions are made with an understanding of the documented program benefits and would be
consistent with the current program benefits. Change Request Log updated and Stakeholders are communicated, after any change
approval/rejection/modified for further consideration,
Incase change approval, ensures the changes are communicated to components for implementation andactions.
72. As part of closure, what are the dual requirements that components must confirm? Program Component Closure Requirements as well as Component Closure Requirements that defined
by Program Management Plan and Governance Processes
73. What the last gate-review ensures?
Validation of component-level closure was occurred appropriately and component has achieved itsobjectives relative to the overall program
Program Component Closure Requirements as well as Component Closure Requirements that definedby Program Management Plan and Governance Processes
Non-project components must be approved for transition or termination as appropriate
The resources that become available may be reallocated to other components
Communication to a larger or different set of stakeholders may be necessary
74. Recommendation to close the PROGRAM is part of which process? Program Governance Oversight
-
7/29/2019 Program Governance - Notes Q&A Approach
18/20
14 Feb 2013 18
-
7/29/2019 Program Governance - Notes Q&A Approach
19/20
14 Feb 2013 19
Program Governance
75. Who makes Component Closure Request? Component Manager/Team
76. Who makes component closure decisions?
Program Governance Board arising from normal project completion or fromterminations
77. What may effect component, result in termination? Program Scope Changemay influence the component termination
Cost Controlsmay influence the component termination
Component failure to provide the benefits outlines in Benefits Realization Planmay influence the component termination
78. Where do you find the documented decisions of transitioning or closureof components?
Project Transition/closure certificate
79. What do you do when you find documented decisions of transitioning orclosure of components?
Inform Stakeholders and Component Personnel
Store the decision documents in archives, and in accordance withregulations, laws and organizational requirements
Update the benefits realization report to summarize how component hasdelivered the desired benefits
Capture Lessons Learned throughout the life cycle of the program and project
Following component closure, Update Program Management Plan andDecision Log and create Project Transition/Closure certificate
-