Power Transformers
Al-Khobar, Kingdom of Saudi ArabiaRiesa, GermanyHeidenau, GermanyIreland
Case Studies:
![Page 2: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/2.jpg)
2
Diagnosis Measurements on Power Transformer in Al-Khobar, Kingdom of Saudi Arabia
Part 1 – GT 14Part 2 – GT 4Part 3 – GT 2
1. Partial Discharge Measurement
2. Dielectric Loss Analysis (DLA)
3. Sweep Frequency Response Analysis (SFRA)
![Page 3: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/3.jpg)
3
1. Setup of the PDM system incl. the UHF-PD-sensor
2. Frequency analysis for determination of the measuring frequency (Zero-span-mode measurement)
3. Instrument Performance Check
4. Recording of the measuring signals for the measuring cycle of 120 second
5. Evaluation of the measuring recordings by using the LDS-6/UHF Analysis software: PRPD Pattern Recognition and Replay-Mode for signal evaluation
1. PD Measurement in Al-Khobar, Kingdom of Saudi Arabia (Part 1 & 2)
![Page 4: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/4.jpg)
4
The main constituent parts of the PD measurement system are the inductive loop as non-conventional sensor, the handheld detector LDP-5, at least of the measurement instrument LDS-6 as used for the phase resolved PD pattern recognition.
Fig. 2: Sensor placement for the acoustic transformer inspection
Fig. 1: Schematic diagram of the PD measuring setup (non-conventional; inductive decoupling)
1. PD Measurement in Al-Khobar, Kingdom of Saudi Arabia (Part 3)
A) Inductive Decoupling at the earth lead
1. Calibration of the PDM System as reduced charge
2. Recording of the measuring signals for the measuring cycle of 120 second
3. Evaluation of the measuring recordings by using the LDS-6 Analysis software: PRPD Pattern Recognition and Replay-Mode for signal evaluation
B) Acoustic Decoupling at transformer tank
Acoustic inspection of the transformer at four positions of the tank each transformer side
![Page 5: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/5.jpg)
5
2. DLA Measurement in Al-Khobar, Kingdom of Saudi Arabia
1. De-Energization of the Power Transformer and isolation from the power system completely.
2. Connection & configuration of the measuring system.
3. Performing the test in different configuration (GST, GUARD, UST).
4. Restoring the electrical connections of the power transformer to the network for the service operation.
5. Energization of the Power Transformer.
![Page 6: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/6.jpg)
6
3. SFRA Measurement in Al-Khobar, Kingdom of Saudi Arabia
1. De-Energization of the Power Transformer and isolation from the power system completely.
2. Connecting & configuration of the measuring system.
3. Performing the test in different configurations. Fingerprints-Recording in the different measuring configurations (Fig. 4) for open and short-circuit (LV) winding.
4. Restoring the electrical connections of the power transformer to the network for the service operation
5. Energization of the Power Transformer
![Page 7: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/7.jpg)
7
Part 1 – GT 14
1. Partial Discharge Measurement
2. Dielectric Loss Analysis (DLA)
3. Sweep Frequency Response Analysis (SFRA)
![Page 8: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/8.jpg)
Part 1: Results of the PD Measurement
![Page 9: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/9.jpg)
9
Part 1: Results of the DLA Measurement
19020,6319020,9619022,6919017,3219016,02
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
7828,41 7830,57 7831,17 7830,28 7830,86
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
11182,39 11184,32 11184,75 11186,22 11186,09
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
15228,215228,3215226,7215223,6315225,28
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
4040,83 4040,12 4040,14 4040,82 4040,46
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
11183,47 11184,22 11184,46 11186,28 11186,09
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
CH+CHL CH CHL
CLCL+CHL CHL
![Page 10: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/10.jpg)
Part 1: Results of the SFRA Measurement
![Page 11: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/11.jpg)
11
Part1: Results of the SFRA Measurement
Fingerprints all phases overlapped: Open Circuit H1-H0, H1-H0, H3-H0; (h1/h2/h3 open)
Fingerprints all phases overlapped: Short Circuit H1-H0, H1-H0, H3-H0; (h1/h2/h3 shorted)
The SFRA Measurement at the power transformer GT14 has been performed as base line fingerprint to compare measurements in future.
This initial measurement of SFRA is based on a subjective comparison of the traces.
The traces are analyzed for changes between responses of the three investigated phases of the same transformer.
The responses, short circuit measurement, as well as open circuit measurement, for all three phases are nearly similar.
Measurements in future should be compared with these base lines to check the mechanical integrity of the investigated power transformer.
![Page 12: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/12.jpg)
12
Part 2 – GT 4
1. Partial Discharge Measurement
2. Dielectric Loss Analysis (DLA)
3. Sweep Frequency Response Analysis (SFRA)
![Page 13: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/13.jpg)
Part 2: Results of the PD Measurement
![Page 14: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/14.jpg)
Part 2: Results of the DLA Measurement I
CH+CHL CH CHL
CLCL+CHL CHL
13549,38 13549,19 13551,17 13552,18 13551,56
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
20288,6 20291,72 20296,89 20292,43 20293,43
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
3079,293079,53079,513079,873080,71
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
9819,249818,19818,59817,249816,98
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
10471,9110469,9710469,8410469,4210468,18
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
10472,8810470,4110469,3710468,6210467,86
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
![Page 15: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/15.jpg)
Part 2: Results of the DLA Measurement II
CH+CHL CH CHL
CLCL+CHL CHL
0,7490,7470,7470,7480,746
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
0,779 0,779 0,778 0,781 0,784
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
0,910,9090,9090,9080,94
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
0,8470,8450,8440,8440,842
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
0,6970,6960,6970,6950,693
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
0,7110,710,710,7080,706
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
![Page 16: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/16.jpg)
16
Part 2: Results of the DLA Measurement
I) The recorded PF values are increased.
The insulation PF values more than 0.5%, between 0.7% and 0.8%.
Tendency the insulation values are increasing slightly more then 0.9 %.
Data should be analyzed on basis of prior tests on the same unit.
II) The results of the capacitance readings have to be compared with previously
measurements.
Capacitance is a function of winding geometry, and is expected to be stable with
temperature and age.
Change of capacitance is an indication of winding movement such as might occur
as a result of a through fault.
![Page 17: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/17.jpg)
Part 2: Results of the SFRA Measurement
![Page 18: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/18.jpg)
18
Part2: Results of the SFRA Measurement
Fingerprints all phases overlapped: Short Circuit H1-H0, H1-H0, H3-H0; (h1/h2/h3 shorted)
Fingerprints all phases overlapped: Open Circuit H1-H0, H1-H0, H3-H0; (h1/h2/h3 open)
1) The SFRA Measurement at the power transformer GT4 has been performed as base line fingerprint to compare measurements in future.
This initial measurement of SFRA is based on a subjective comparison of the traces. The traces are analyzed for changes between responses of the three investigated phases of the same transformer.
2) The responses, short circuit measurement, as well as open circuit measurement, for all three phases differ. All measurements of the phases differ considerable starting from 100 kHz.
The recorded fingerprints have to be compared with previously measurements at the power transformer if they are performed. Phase B, the open circuit measurement differ from both other phases over the complete recorded frequency range.
![Page 19: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/19.jpg)
19
Part 3 – GT 2
1. Partial Discharge Measurement
2. Dielectric Loss Analysis (DLA)
3. Sweep Frequency Response Analysis (SFRA)
![Page 20: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/20.jpg)
Part 3: Results of the PD Measurement
PD Reading – Reduced Charge: QR = 68 pC
![Page 21: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/21.jpg)
Part 3: Results of the DLA Measurement I
CH+CHL CH CHL
CLCL+CHL CHL
0,904 0,901 0,899 0,904 0,902
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
0,7760,7750,7730,770,763
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
0,535 0,536 0,538 0,534 0,536
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]Lo
ss F
acto
r
0,4140,4150,4140,4120,417
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
0,991,010,97
1,051,01
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
1,1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
1,0451,0451,0461,0371,013
0
0,1
0,2
0,3
0,4
0,50,6
0,7
0,8
0,9
1
1,1
0 2 4 6 8 10 12
Voltage [kV]
Loss
Fac
tor
![Page 22: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/22.jpg)
Part 3: Results of the DLA Measurement II
CH+CHL CH CHL
CLCL+CHL CHL
14930,5214929,1414930,9214927,8614931,15
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
2573,16 2573,24 2572,86 2572,65 2571,79
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
12357,68 12355,99 12356,73 12356,65 12357,21
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Capa
city
[pF]
21183,91 21188,39 21194,63 21193,16 21195,6
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
8826,51 8829,2 8829,43 8830,17 8830,24
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
12357,64 12356,51 12357,85 12360,14 12361,22
0
2500
5000
7500
10000
12500
15000
17500
20000
22500
25000
0 2 4 6 8 10 12
Voltage [kV]
Cap
acity
[pF]
![Page 23: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/23.jpg)
23
Part 3: Results of the DLA Measurement
1) The recorded PF values are high increased, more than 0.9%.
Older power transformer may have insulation PF values in excess of 0.5%.
Data should be analyzed on basis of prior tests on the same unit too.
2) The results of the capacitance readings have to be compared with previously measurements.
Capacitance is a function of winding geometry, and is expected to be stable with temperature and age.
Change of capacitance is an indication of winding movement such as might occur as a result of a through fault.
![Page 24: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/24.jpg)
Part 3: Results of the SFRA Measurement
![Page 25: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/25.jpg)
Part3: Results of the SFRA Measurement
Fingerprints all phases overlapped: Short Circuit H1-H0, H1-H0, H3-H0; (h1/h2/h3 shorted)
Fingerprints all phases overlapped: Open Circuit H1-H0, H1-H0, H3-H0; (h1/h2/h3 open)
The SFRA Measurement at the power transformer GT2 has been performed as base line fingerprint to compare measurements in future.
This initial measurement of SFRA is based on a subjective comparison of the traces.
The traces are analyzed for changes between responses of the three investigated phases of the same transformer.
The responses, short circuit measurement, as well as open circuit measurement, for all three phases have minimal deviation. Phase B, short circuit measurement, the curve differed at 2-3 kHz.
![Page 26: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/26.jpg)
26
UHF PD measurement in Riesa, Germany
![Page 27: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/27.jpg)
27
UHF PD measurement in Riesa, Germany
Transformer
Drain valve
UHF PD probe DN80
Output
Input
Pre-amplifier
High-pass filter
Measuring results at 690 MHz
Installed UHF PD probe DN80
Application benefit:
• PD measurement with the UHF probe DN 80 on the drain valve of a 110 kV transformer
• Installation of the PD measurement equipment online• Based on receiving electromagnetic fields transmitted by the
PD source• The UHF probe used at online and on-site PD measurements• High noise reduction level, because the probe is located in the
inner transformer tank in a shielded area
![Page 28: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/28.jpg)
28
UHF PD measurement in Heidenau, Germany
![Page 29: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/29.jpg)
29
on a 3-phase 40 MVA Power Transformer
Application benefit:
customer wanted to verify the electric PD monitoring results
full in-service UHF sensor application, performance check and measurement
Strong noises clearly identifiable
UHF noise; amplified Performance Check; >300MHz
UHF PD measurement in Heidenau, Germany
![Page 30: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/30.jpg)
30
UHF PD measurement in Ireland
![Page 31: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/31.jpg)
31
UHF PD measurement in Ireland
Application benefit:
• Tested measurements have been performed using non-conventional decoupling methods taking advantage of electromagnetic field coupling
• PD measurements on the power transformers have been functioned on the drain valves of the three phase power transformers with the help of the UHF probe DN 50
• Three transformers with minor PD activity, one transformer with clear PD
Location:
• Louth (T2101; T2103)
• Dublin (T102)
• Ardnacrusha (T142)
• Cashla (T2101, T2102)
![Page 32: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/32.jpg)
32
Drain Valve
Applied UHF Drain Valve Sensor
Mounting of the UHF Probe DN50 (with Adapter DN50/DN80)
Measuring System LDS-6/UHF
Measuring Instrument:
• PD Measuring System LDS-6/UHF• UHF Probe DN50 (with Adapter DN50/DN80)• UHF Calibrator LDC-6/UHF• Pre Amplifier LDA-5/GIS
UHF PD measurements in Ireland
![Page 33: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/33.jpg)
33
UHF PD measurement in Louth, Dublin, Ardnacrusha, Cashla (Ireland)
V ≈ 550 mV at measuring frequency 560 MHzV ≈ 238 mV at measuring frequency 560 MHz
V ≈ 139 mV at measuring frequency 560 MHz V ≈ 128 mV at measuring frequency 520 MHz
![Page 34: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/34.jpg)
34
UHF PD measurement in Jizan, Saudi Arabia
![Page 35: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/35.jpg)
35
UHF PD measurement in Jizan, Saudi Arabia
Drain Valve Power Transformer
on 33/13,8 KV Power Transformers GT14 and GT4
Measuring Instrument:
• UHF Probe DN50
• Calibrator LDC-6/UHF
• PD measurement instrument LDS-6/UHF
![Page 36: Power Transformers Case Studies](https://reader033.vdocuments.mx/reader033/viewer/2022042514/563db79a550346aa9a8c9793/html5/thumbnails/36.jpg)
36
UHF PD measurement in Jizan, Saudi Arabia
PRPD Pattern at the measuring frequency of 400 MHz V = 177 mV
PRPD Pattern at the measuring frequency of 400 MHz V = 288 mV