Transcript

Location

Between

Downtown and

the Airport

Mission:

Inspire people to grow

through immersion in a world

of natural outdoor wonder to

nourish mind, body and spirit.

Timeline:

1988 - Began with a vision for a world-class public garden

1998 – Signed 99-year renewable lease with Allegheny County

2003 - MTR Landscape Architects completes Master Plan

History

Timeline:

2004 - AMD from abandoned coal mines identified, then exacerbated by Hurricane Ivan flooding

2005 - “Daylighting” best reclamation option

2010 - Reclamation work began

2004 - 2006

2013 - Construction of award-winning passive

limestone AMD treatment system

Before After

Pond Overview

Removing wall forms for

the drainable limestone bed

In Progress

Between

Downtown and

the Airport

Tank filled with limestone

Pond with aluminum

Settling basin

In Progress

Between

Downtown and

the Airport

Iris and Water Lilies

In Progress

• Trout, bass and bluegills

Between

Downtown and

the Airport

2014

Yoga at the Garden on the hashiyasu boardwalk, 2015

Reclamation site, 2011

Sally Jewell and OSMRE inspecting daylighting site, 2014

Pond 6 – An E & S Pond which becomes an irrigation pond and lies above a 400,000 gallon cistern

Revegetation of Reclamation area: first three acres

In partnership with TreeVitalize of the Western Pennsylvania Conservancy, 1,500 saplings were planted in May on the first three acres of the “daylighting” site.

The planting template was provided by the Appalachian Regional Reforestation Initiative and this is the first use of such template in Western PA.

Planting Volunteers

May 9, 2015

Kentucky Hollow

Mining Camp remains

Water Monitoring Crew

Wetland & Stream

1870s Barn

Settlers Cabin Maintenance, 2013

Ada and George Davidson Center 2014

1870s Barn

Upper level entrance view, 2013 2015 upper entrance view

1870s barn/Bayer Welcome Center

2013 2015

1870s barn/Bayer Welcome Center

Upper entrance in 2013 Upper entrance in 2015