Transcript
Page 1: Gartner Best Practices in Business Continuity Planning Report
Page 2: Gartner Best Practices in Business Continuity Planning Report
Page 3: Gartner Best Practices in Business Continuity Planning Report

Human Error/

Operations Risk

Content/Application Links to Third Parties

Outsourced

Service Providers

Performance/Capacity

Security Incidents

Planned/Unplanned

Downtime

New E-Commerce Risks

Page 4: Gartner Best Practices in Business Continuity Planning Report

• IT and business process management are integrated —

no longer solo views

• Production costs increase — no separate budget for BCP

• Risk identification and management take on a matrix

management focus, e.g., technology, financial, trading,

operations

• Problems are public — IT and business problem

management must be integrated; root cause analysis

• Only as strong as your weakest link — good

application/bad operations

• Contingency plans become critical when automation isn’t

there — every component of the business process now

must have a plan

E-Commerce BC: New Rules/New Realities

Page 5: Gartner Best Practices in Business Continuity Planning Report

Disaster

Recovery

Business

Recovery

Business

Resumption

Contingency

Planning

Objective Mission-critical

applications

Mission- critical

business

processing

(workspace)

Business process

workarounds

External event

Focus Site or component

outage (external)

Site outage

(external)

Application outage

(internal)

External behavior

forcing change to

internal

Deliverable Disaster recovery

plan

Business

recovery plan

Alternate

processing plan

Business

contingency plan

Sample

Event(s)

Fire at the data

center; critical

server failure

Electrical outage

in the building

Credit

authorization

system down

Main supplier

cannot ship due to

its own problem

Sample

Solution

Recovery site in a

different location

Recovery site in

a different power

grid

Manual procedure 25% backup of

vital products;

backup supplier

Crisis Management

BC Components

Page 6: Gartner Best Practices in Business Continuity Planning Report

Creating Business Continuity Plans

Business Impact Analysis

Risk Analysis

Recovery Strategy

Group Plans

and Procedures

Business Continuity Planning Initiation

Risk

ReductionImplement

Standby Facilities

Create Planning Organization

Testing

PROCESS

Change Management Education Testing Review

Policy ScopeResourcesOrganization

Ongoing

Process

Project

Page 7: Gartner Best Practices in Business Continuity Planning Report

Awareness Programs Fiduciary Responsibility

BIA & Risk AssessmentCatalysts

Obtaining Management Commitment

Page 8: Gartner Best Practices in Business Continuity Planning Report

Security Incident Detection & Response

Prevention/Planning

Detection

Incident Response

InvestigationEvidence

Legal Action

Page 9: Gartner Best Practices in Business Continuity Planning Report

Business Req.

SystemArchitecture

SystemDesign

Construct Test ImplementPost

Imple-ment

• Identify

technology

and

business

continuity

risks from a

business

perspective

– BIA/ risk

analysis

RTO/RPO

• Ensure

complete

cost

estimate

• Ensure

appropriatel

y protected

end product

• Assess risks

of new

technology

products

• Identify secure

infrastructure

requirements

• Identify secure

administrative

requirements

• Establish

security

responsibilities

and service-

level

regulations

• Identify

BC/DR

strategies

• Establish

security test

strategy

• Translate

security

architecture to

detailed security

infrastructure

design

• Develop security

baselines for

new

technologies/

products

• Develop

detailed security

admin. design

• Develop

detailed

BCP/DR

design/

strategy

• Develop draft

SLAs

• Develop security

test plan

• Build/code

security

infrastructure

environment

and processes

• Build/code

security

admin.

environment,

roles/profiles

and processes

• Build

BCP/DR

environment,

plans and

processes

• Build/code

security test

plan,

processes,

scripts and

test

environment

• Train secure

administrati

ve,

operations,

business

unit, staff...

• Identify

security

noncomplia

nce issues

• Identify new

security

exposures

• Test

BCP/DR

plans to

ensure that

RTO/RPO

is

attainable

• Turn over

secure

application

infrastructure

to production

• Implement

secure

administrative

roles/profiles

• Implement

business/

continuity

DR

environment

Project Life Cycle

• Identify

changes to

tested env.

• Finalize secure

admin. env.

and processes

• Finalize

security

infrastructure

environment

and processes

• Finalize

BCP/DR env.,

plans and

processes

• Assess SLA

accuracy

• Finalize risk

acceptance

with business

• Ensure that

info. security

policies are

current

Page 10: Gartner Best Practices in Business Continuity Planning Report

Business Process Owner

Architecture and

Standards Application and

Tech Design

Business

ContinuityOperations

Architecture and

Design

IT Operations

Problem, Change,

Performance, DR

Risk Management (Financial, Technology, Operations)

Information

Security

Recovery/continuity strategy/

design

IT Recovery management

E-Biz Project Manager

Business Manager

Risk Manager

Business Continuity Mgr.

Audit

IT

Information Security

Business Operations

Legal/Compliance

HR / Public Relations

E-Biz Recovery Team

Business continuity

strategy/design

Audit — Financial and EDP

OSPs/

Business Partners

E-Commerce BC — Integrated Processes

Rules and tools

Security Incident

identification/response

design

Page 11: Gartner Best Practices in Business Continuity Planning Report

Problem Identification

and Impact Assessment

Problem Status/

Communication

Problem

Prevention and

Planning

Problem

Resolution

Root Cause Analysis

Problem Management Life Cycle

Problem Mgmt Team

Business Process Owner

Customer/Partner

Relationship Owner

Risk Management

Business Continuity

Information Security

IT Technical Support

IT Applications Support

Vendors/OSPs/Third Parties

Legal/Compliance

Public Relations

Page 12: Gartner Best Practices in Business Continuity Planning Report

BCP PhaseAccounts

Payable

Accounts

Receivable

Cash

Mmgt.R&D Prod. Eng.

Order

Fulfillment

Impact Analysis

Risk Analysis

Strategy

Resources

Committed

Last Tested

Change Mgmt.

Last Major Review

Workable Solution

Audit

Location, Business Process or Department

Management Reporting is Critical

Too Much Testing and Reporting Is Never Enough

Page 13: Gartner Best Practices in Business Continuity Planning Report

Revenue

Know your downtime

costs per hour, day, two

days...

Productivity

• Number of

employees impacted

X hours out X

burdened hourly rate

Damaged Reputation

• Customers

• Suppliers

• Financial markets

• Banks

• Business partners

• ...

Financial Performance

• Revenue recognition

• Cash flow

• Lost discounts (A/P)

• Payment guarantees

• Credit rating

• Stock price

Other Expenses

Temporary employees, equipment rental, overtime costs,

extra shipping costs, travel expenses...

What Is Your Cost of Downtime?

• Direct loss

• Compensatory payments

• Lost future revenue

• Billing losses

• Investment losses

Page 14: Gartner Best Practices in Business Continuity Planning Report

Cost

Disaster Recovery Times

24 hours

48 hours

72 hours

Minutes12 hrs.

StandardRecovery

Elec.Vaulting

ElectronicJournaling

Shadowing

Mirroring

Database and/or fileand/or object backup

Log/journal transfer(continuous or periodic)

Database and/or file and/or object replication

Assumes mirroring or shadowing plusa complete application environment

net $host $disk $tape $

net $tape $

net $-$$+host $$+disk $$$$+

net $$$+host $$+disk $$$$+

net $$$+host $$$+disk $$$$+appl. $+

Hot Standby orLoad-Balanced

Applying High Availability to Disaster Recovery

Page 15: Gartner Best Practices in Business Continuity Planning Report

Standby or Active

Geographic Load BalancerSite Load Balancer

Database Clusters

Application Server Clusters

Site Load Balancer

Web Server Clusters

Database Clusters

Database Replication

Transaction Replication

Designing E-Commerce Applications for No Single-Point-of-Failure

Page 16: Gartner Best Practices in Business Continuity Planning Report

Database

ClustersDatabase

Clusters

Host-based

Disk-based

Replication Methods Examples

Disk-to-Disk mirroring EMC SRDF, Compaq DRM, IBM PPRC

and XRC, HDS HARC and HRC

Log-based DBMS

replication

Quest Shareplex, Oracle Standby

Database, ENET RRDF, SQL

Server 2000

Server-based block or file

replication

Legato Octopus, NSI Doubletake,

Veritas SRVM

Application-based

replication

Typically implemented with

message-queuing middleware

Data Replication for Continuous Availability

Page 17: Gartner Best Practices in Business Continuity Planning Report

Emerging Technologies/Services

• Capacity on demand/emergency back-up

• Wide-area clusters

– HP Continental Clusters

– IBM Geographically Dispersed Parallel Sysplex

• Cascading data replication

Disks

Host

Operational

Site

High Bandwidth (fiber)

Disks

Host

Metropolitan/Regional

Recovery Facility

Tape Backup/Archival

Disks

Host

Primary Recovery

Site

Page 18: Gartner Best Practices in Business Continuity Planning Report

High-

Availability-

Based Service

2000 2004

Warm Site and

Mobile Recovery

Quick Ship

Warm Site and

Mobile Recovery

Quick Ship

Load-Balanced (2+Sites)

Disaster Recovery: Market Dynamics

Page 19: Gartner Best Practices in Business Continuity Planning Report

External

(dedicated)

External (shared)Internal

•You have an

alternative facility (50

km distant)

•BC vendors have

insufficient capacity

•BC is a recognized

and respected

discipline

•You cannot

economically benefit

from syndication

•You do not have an

alternate facility

•You desire multisite

continuous

availability or hot

standby support

•RTOs/RPOs are

very short

•You want to focus

on core competencies

•Getting management

sign-off for dedicated

capital is difficult

•Experience of

supporting an

invocation is

important

•Your planning

scenarios include

loss of technical

staff

Resource Internally or Externally

Page 20: Gartner Best Practices in Business Continuity Planning Report

• Comdisco Recovery Services and Web Availability Services• IBM Business Continuity Recovery Services and Outsourcing Services• SunGard Recovery Services and E-Sourcing

• Professional services

• Planning software

• Hot/warm/cold standby

• Mobile/static facilities

• Mainframe/midrange/desktop

• Quick ship

Business Continuity and Internet Services

• Peripherals

• Networks

• Work area

• Specialized ancillary services

such as check processing and

data recovery

What’s new — Full-service Web-hosting with BC ―designed

in,‖ multisite infrastructures for continuous availability, Web

site and network ―throttling‖ for performance

North AmericanBusiness Continuity Market

Full-Service Providers

Page 21: Gartner Best Practices in Business Continuity Planning Report

Cost

Always use competitive

tendering, even at renewal

Keep contracts to three years

Unbundle contract costs

Understand upgrade costs

Specify test time and additional

fees

Declaration fees are negotiable

For unsyndicated equipment,

check cost of self-acquisition

Annual cap fees

Contract Terms

Include early-termination conditions

Miscellaneous

Understand the right of access: ―first

come, first served‖ or shared

Check syndication levels, risk

exposures and exclusion zones

Touch the equipment. Visit the

recovery center

Agree to a buy-out schedule

Specify occupancy/comm. fees

Negotiating a Favorable BC Contract —Balance Risk With Economies of Scale

Page 22: Gartner Best Practices in Business Continuity Planning Report

Top Related