Transcript
Page 1: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

ECONOMIC VIABILITY OF DIESEL-PV-HYBRID

SYSTEMS USING THE “100% PEAK

PENETRATION TECHNOLOGY”

GIZ, 5 JULY 2016

Page 2: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

INTRODUCTION

Page 3: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

3

Economic and financial viability of hybridising existing – so called

brownfield – diesel grids with a “100% peak PV penetration”

technology;

Impact of hybridisation on the levelised cost of electricity (LCOE);

determining key cost drivers of diesel and hybrid power generation;

Consideration of two different ownership and financing structures on

LCOE:

“Private sector” return expectations – project finance structure, IPP;

“Public sector” return expectations – financing on balance-sheet of

state-owned utility, concessional debt terms;

Sensitivity analysis for diesel prices, equipment costs, PV penetration

levels, and (customer) demand growth;

Analysis of investing, operating and financing cash flows.

HYBRID POWER PLANTS Research focus areas

Page 4: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

4

Bequia

St. Vincent

Owner: VINLEC (Public)

Size: 4.12 MW

Customer

s:

~2,300

HYBRID POWER PLANTS Selected sites

Las Terrenas

Dominican

Republic

Owner: Private company

Size: 9.50 MW

Customer

s:

~9,000

Puerto Leguizamo

Colombia

Owner: IPSE, CEDENAR

(Public)

Size: 4.20 MW

Customer

s:

~3,000

Hola

Kenya

Owner: KPLC (Public)

Size: 0.80 MW

Customer

s:

~1,700

Mango

Togo

Owner: CEET (Public)

Size: 1.60 MW

Customer

s:

~1,900

Basse Santa Su

Gambia

Owner: NAWEC (Public)

Size: 1.30 MW

Customer

s:

~3,700

Busuanga Island

Philippines

Owner: NPC (Public)

Size: 3.58 MW

Customer

s:

~12,000

Nusa Penida

Indonesia

Owner: PLN (Public)

Size: 3.65 MW

Customer

s:

~13,000

Page 5: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

APPROACH

AND

FINANCIAL

ASSUMPTIONS

Page 6: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

6

APPROACH Technical and financial modeling

Input

- Current plant layout

- Load data

- Diesel consumption

- RE resource

availability

- CAPEX and OPEX

assumptions for

diesel, PV, hybrid

HOMER* output

- Sizing of hybrid

system and

individual technical

components

- Diesel/PV split

Financial Model

output

- Economic viability

analysis

- Financial viability

analysis

- Sensitivity analysis

- Growth scenarios

- Cash flow analysis

*The HOMER software determines how variable RE resources can be optimally integrated into hybrid

systems. However, it applies simplified financial assumptions. Only a constant discount rate can be

assumed to calculate the NPVs of the different technical layouts. Also, HOMER does not properly consider

fluctuating diesel price forecasts, revenue streams, tax effects, or changes of the financing structure over

the 20-year lifetime of the project. The financial analysis is hence based on a fully-fledged financial model

that builds upon HOMER output and other input data.

Page 7: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

7

FINANCIAL ASSUMPTIONS Private sector case / Project finance terms

Component Assumption

Transaction cost (legal

documentation, due diligence, set-

up of SPVs etc.)

2% of total initial CAPEX

Contingencies (buffer for changes

in equipment costs) 5% of total initial CAPEX

Interest 8% on debt, 2% on cash (nominal cost)

Equity IRR 15% (nominal cost)

Debt/equity split Debt capacity to meet DSCR of 1.2, based on net operating cash

flow, capped at max. debt portion of 70%

Debt tenor 12 years + 1 year grace period

DSRA 6 months debt service

Inflation, cost escalation

2% assumed inflation on revenues and cost components

(including cost of carbon), similar to inflation in the US since the

whole model is based on USD

Project lifetime 20 years

Currency All values are based in USD, to avoid unnecessary currency

mismatches and make different sites comparable

Page 8: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

8

OIL PRICE ASSUMPTIONS Example of Nusa Penida, Indonesia

Page 9: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

HYBRIDISATION:

POTENTIAL AND

BENEFITS

Page 10: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

10

DAILY AVERAGE LOAD vs. POSSIBLE PV

OUTPUT

Example of Nusa Penida, Indonesia

PV output from 3 MW

installed capacity

Page 11: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

11

DIESEL/PV SPLIT (CAPACITY AND OUTPUT) Example of Nusa Penida, Indonesia

Page 12: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

12

ENERGY DEMAND, PV SHARE & POSSIBLE

SAVINGS

Comparison of sites

* Depending on oil price projection

Page 13: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

ECONOMIC

VIABILITY

ASSESSMENT

PRIVATE vs. PUBLIC

SECTOR FINANCE

Page 14: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

14

LCOE COMPOSITION Example of Nusa Penida, Indonesia

Page 15: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

15

LCOE BREAKDOWN – PRIVATE SECTOR

FINANCE Comparison of sites

Page 16: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

16

BREAK EVEN WACC – PRIVATE SECTOR CASE Comparison of Nusa Penida, Indonesia and Hola, Kenya

Nusa Penida, Indonesia Hola, Kenya

WACC: 12.74%

LCOE: 0.404

WACC: 8.03%

LCOE: 0.503

Page 17: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

17

LCOE – PRIVATE vs. PUBLIC SECTOR

FINANCE Example of Nusa Penida, Indonesia

Private Sector Case Public Sector Case

Page 18: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

18

RELATION OF COST ADVANTAGE AND… …PV size, solar radiation, local diesel price premium

PV size Solar radiation Local diesel price

premium

The two sites where hybridisation could result in a cost increase (Hola and Basse Santa Su) have by far the smallest

generation capacity; even relatively high local diesel prices and solar radiation cannot compensate the missing scale;

The cost advantage at the largest site (Las Terrenas) is limited by relatively low diesel prices and solar radiation;

The most viable case for hybridisation is Nusa Penida, a mid-sized plant with the highest local diesel price premium

and relatively high solar radiation.

Page 19: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

CONCLUSIONS

Page 20: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

20

CONCLUSIONS Financing

Hybridisation can reduce avg. generation costs and exposure to diesel price volatility;

Financing costs are a major cost driver and, amongst other things, depend on

ownership structure (project finance vs. balance sheet; commercial vs. concessional

terms):

Private sector case (IPP, project finance, commercial terms, WACC from 8.4

to 8.7 percent depending on local tax shield): LCOE reduction at five of

seven sites, but not significant except Nusa Penida (-7.6 percent) if assuming

EIA reference oil price projection;

Public sector case (balance sheet of utility, concessional finance, WACC flat

at 5 percent): Cost savings at all sites (-12 to -15 percent) under EIA

reference scenario;

Appetite of private-sector lenders is likely limited by the small investment volume,

which translates in high transaction costs relative to anticipated revenues

Concessional financing probably required to leverage private investments – at

least until more experience is gained, risks are better understood, and private

financing costs decline.

Page 21: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

21

CONCLUSIONS Determinants

Plant size, on-site diesel costs and solar radiation are the main determinants

for the economic/financial viability of a hybrid project:

Larger plants can achieve economies of scale by distributing fixed cost of the hybrid

system (like automation tool) over more units of generated electricity The two

sites where hybridisation could result in a cost increase (Hola and Basse Santa Su)

have by far the smallest generation capacity, and even relatively high local diesel

prices (in 2013) and solar radiation cannot compensate the missing scale;

High diesel prices result in high cost savings and allow hybrid systems to offer

partial insurance against the risk of rising fuels costs Crude oil price decline

from 115 USD/barrel (06/2014) to less than 50 USD/barrel (02/2015) jeopardizes

viability of hybrid project; it remains to be seen when prices will increase

again, and where trend will go;

Higher solar radiation allows each unit of PV capacity to produce more (cheaper)

electricity Difficult to manage load in a way that demand curve matches better the

PV output.

Page 22: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

22

CONCLUSIONS Implementation considerations and challenges

Operation and optimisation of isolated grids is not necessarily at the top of the

agenda of national utilities, as they are often too small to receive much attention in

the national context;

A more thorough cost analysis needs to take into account all site-specific details like

current diesel generation costs and financing conditions – to be disclosed by the

utilities; however, local contacts (on-site at the grid) often lack access to data, and

managers at utility headquarters are rarely aware of optimisation potential on site;

Another hybrid configuration, other RE sources and/or connection to the main grid

might be more cost efficient than hybridisation with the “100% peak PV penetration”;

Level of familiarity with hybrid technologies among stakeholders – in particular in

environments dominated by residential consumption – is often limited;

Transparency and fair communication – especially regarding technology selection,

diesel cost savings and financing assumptions – is necessary to create mutual trust.

Page 23: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

APPENDICES

Page 24: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

24

CAPEX / OPEX Hybrid Diesel only*

Initial CapEx (USD)

Diesel gen-sets 1.47m 1.47m

PV panels 6.12m

Balance of system (converter, battery, automation

solution) 1.99m

Replacement CapEx (USD)

Diesel gen-sets 0.73m (yr 10), 0.37m (yr 12) 0.7m (yr 7), 0.37m (yr 12)

Balance of system (converter, battery, inverter) 1.99m (yr 10)

O&M costs p.a. (USD)

Diesel gen-sets 501,673 707,443

PV system 81,600

Balance of system (converter, battery) 15,776

Diesel consumption (Liter/MWh) 282

Current diesel price (USD/Liter) 1.16

* Since existing diesel generators are already quite old, and in order to ensure a comparative analysis of the diesel and

hybrid cases over the entire investment lifetime, it was assumed that initial investments are required in diesel capacity.

CAPEX AND OPEX ASSUMPTIONS (USD) Example of Nusa Penida, Indonesia

Page 25: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

25

HYBRID INVESTMENT COSTS (USD) Example of Nusa Penida, Indonesia

Components Initial Costs Replacement

Costs Year 10

Replacement

Costs Year 12

Diesel Gen-Sets 1,475,600 734,400 367,200

PV-Panels 6,120,000

Balance of system (converter, battery, automation

tool) 1,999,200 1,985,600

Capital Investment 9,594,800 2,720,000 367,200

Contingencies (5%) 479,740

Transaction Costs (2%) 191,896

Total Initial Investment 10,266,436

Page 26: ECONOMIC VIABILITY OF DIESEL-PV-HYBRID SYSTEMS USING … · ECONOMIC VIABILITY OF DIESEL-PV-HYBRID ... Consideration of two different ownership and financing structures on ... hybrid

26

Frankfurt School – UNEP Collaborating

Centre

http://fs-unep-centre.org

[email protected]


Top Related